This document summarizes common defects in Portland cement concrete pavement (PCCP) and their probable causes and recommendations. Major defects include scaling caused by insufficient cement paste or improper mixing/curing; transverse cracks from settling base or unfavorable weather without contraction joints; longitudinal cracks from narrow road widths; and multiple cracks from failed bases. Recommendations are to follow proper mix designs and procedures, attain fully compacted bases, add contraction joints before 24 hours, and replace failed pavement. The workshop aims to control materials quality in infrastructure projects through identifying defects, determining root causes, and prescribing preventative measures.

Uploaded by

emljr
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
240 views2 pages

PCCP

This document summarizes common defects in Portland cement concrete pavement (PCCP) and their probable causes and recommendations. Major defects include scaling caused by insufficient cement paste or improper mixing/curing; transverse cracks from settling base or unfavorable weather without contraction joints; longitudinal cracks from narrow road widths; and multiple cracks from failed bases. Recommendations are to follow proper mix designs and procedures, attain fully compacted bases, add contraction joints before 24 hours, and replace failed pavement. The workshop aims to control materials quality in infrastructure projects through identifying defects, determining root causes, and prescribing preventative measures.

Uploaded by

emljr
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

TRAINING WORKSHOP ON MATERIALS QUALITY CONTROL IN PROJECT IMPLEMENTATION

GROUP -2 ( MACON )

PCCP

Defects/Deficiencies Probable Cause/s Recommendation/s


1 Major Scaling
insufficient cement paste have adequate
on concrete mix concrete mix
improper procedure of follow the right
work design mix and
weather condition procedure of
improper curing concreting
too much water apply glass weld
poor quality of cement facilitate proper
curing

2 Transverse crack
within the middle settlement of base and sub Base of concrete
third base due to inadequate must attain 100%
compaction compaction
Concrete mixture
must attained its
workability and
durability
3 Transverse crack
outside the middle Due to unfavorable Provide contraction
third weather condition joint or weakened
Contraction of expansion plane joint before it
of concrete passes to 24 hours
after pouring

4 Longitudinal crack
Insufficient prepared road Maintain the full
width road width
preparation

5 Multiple/criss-
cross/series cracks Total base failure Remove and replace
the damage PCCP
and prepare the sub
base to its maximum
compaction
TRAINING WORKSHOP ON MATERIALS QUALITY CONTROL IN PROJECT IMPLEMENTATION

GROUP -2 ( MACON )

PCCP

6 Corner crack Low shoulder Provide enough


Improper removal of forms shoulder
Insufficient sealant on joint Provide enough
sealant