Testing and Commissioning
DOMESTIC WATER SYSTEM
Project :
System : Domestic water Date :
a- General :
1- System : Domestic Water System
2- Location :
3- Serial Number :
4- Model Number :
5- Type :
6- Voltage :
7- Amperage :
Pump No. 1
8- Suction Pressure, psi :
9- Discharge pressure, psi :
Design Actual
10- Head ,ft : 0
11- Water flow, gpm :
Pump No. 2
12- Suction Pressure, psi :
13- Discharge pressure, psi :
Design Actual
14- Head ,ft : 0
15- Water flow, gpm :
Pump No. 3
16- Suction Pressure, psi :
17- Discharge pressure, psi :
Design Actual
18- Head ,ft : 0
19- Water flow, gpm :
NOTES :
Name Signature
RED SEA MALL - JEDDAH General 1
Technical Specification
1 Split Type Central Air Conditioning Units
- shall comprise of air cooled condensing unit and Air Handling Unit
- refrigerant based on R407C/R134A or equivalent refregirant
1.1 - Air Cooled Condensing ok
The entire unit must be mounted on antivibration pad with 32mm thick
- shear rubber made up of layers of grid pattern rubber with galvanized
sheets inserts between each layer ok
3 - Alignment and Levelling good
4 - Strainer and gate valve installation at suction side found
5 - Check valve & gate valve installation at discharge side found
6 - Flexible connection at suction and discharge sides found
7 - Pipes connection good
8 - Pipes identifications found
9 - Supporting system good
10 - Valves tagging found
11 - Pressure gauge installation at discharge side found
12 - Control panel installation ok
13 - Dry running protection found
14 - Wires installation inside liquid tight conduits ok
15 - Connection to BMS done
16 - Pressure vessel installation with drain found
17 - Multi media filter installation found
18 - Circulating pumps installation with all accessories found
19 - Sensors installation found
20 - Hypochlorinator installation with feeding pump found
21 - Softner installation with brine tank found
22 - Pressure switches installation for each pump found
23 Pipes are properly cleaned and flushed done
24 Pipes are properly disinfected done
25 - Alternation unit installation inside control panel found
26 - Changeover unit installation inside control panel found
27 - Connection to MCC panel done
28 - Union fitting is provided beside each valve done
NOTES :
Name Signature Date
RED SEA MALL - JEDDAH Checklist 2
RED SEA MALL - JEDDAH Checklist 3
not ok
not ok
bad
not found
not found
not found
bad
not found
bad
not found
not found
not ok
not found
not ok
not done
not found
not found
not found
not found
not found
not found
not found
not done
not done
not found
not found
not done
not done
RED SEA MALL - JEDDAH Checklist 4
c- Electrical Checklist
Pumps are connected to MCC No. :
Voltage :
Amperage :
1 - Control panel installation good bad
2 - Indication lamps found not found
3 - Phase failure unit protection found not found
4 - Overload protection found not found
5 - Wires are tightly connected good bad
6 - Aternation unit installation found not found
7 - Changeover unit installation found not found
d- Control Checklist
Pumps are connected to DDC No. :
Pressure switch settings :
ON OFF
Lead
Lag 1
Lag 2
1 - System pressure connection to DDC panel ok not ok
2 - Flow switch connection to DDC panel ok not ok
3 - Command and signal status ok not ok
4 - Water level indicator in water tank ok not ok
NOTES :
Name Signature Date
RED SEA MALL - JEDDAH Electrical&Control 5
Testing and Commissioning
HOT WATER SYSTEM
Project :
System : Domestic water - Hot water Date :
a- General :
1- System : Domestic water - Hot water
2- Location :
3- Serial Number :
4- Model Number :
5- Capacity :
6- Voltage :
7- Amperage :
HWCP - No.1
8- Serial Number :
9- Model Number :
10- Voltage :
11- Amperage :
12- Suction Pressure, psi :
13- Discharge pressure, psi :
Design Actual
14- Head ,ft : 0
15- Water flow, gpm :
HWCP - No.2
16- Serial Number :
17- Model Number :
18- Voltage :
19- Amperage :
20- Suction Pressure, psi :
21- Discharge pressure, psi :
Design Actual
22- Head ,ft : 0
23- Water flow, gpm :
NOTES :
Name Signature
RED SEA MALL - JEDDAH HW_genral 6
RED SEA MALL - JEDDAH HW_genral 7
b- Check List :
1 - EWH are installed on concrete pad ok not ok
2 - Relief pipe connection ok not ok
3 - Drain pipe connection ok not ok
4 - Gate valve installation at hot water side found not found
5 - Check valve, gate valve installation at cold water side found not found
6 - Pipes connection good bad
7 - Pipes identifications found not found
8 - Supporting system good bad
9 - Valves tagging found not found
### - Pressure gauge installation at discharge side found not found
11 - Temperature gauge installation at discharge side found not found
### - Connection to MCC panel done not done
### - Wires installation inside liquid tight conduits ok not ok
### - Connection to BMS (signal status) done not done
### - Circulating pumps installation with all accessories found not found
### - Control panel for HWCP with timer control found not found
### - Changeover unit installation inside control panel found not found
### - Pipes are properly cleaned and flushed done not done
### - Pipes are properly disinfected done not done
### - Union fitting is provided beside each valve done not done
### - Check valve installed at CW pipe before HWR pipe found not found
NOTES :
Name Signature Date
RED SEA MALL - JEDDAH HW_checklist 8
RED SEA MALL - JEDDAH HW_checklist 9