Project Management

The document outlines the various phases and steps involved in a construction project from pre-construction through post-construction. In the pre-construction phase, key steps include site selection, surveys, design, and tendering. The construction phase involves preparing the site layout, excavation, foundation, plinth and columns, walls, floors, and other works. Post-construction involves collecting drawings, manuals, bills, certificates, and handing over the completed building.

Uploaded by

SatyamTiwari
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
85 views3 pages

Project Management

The document outlines the various phases and steps involved in a construction project from pre-construction through post-construction. In the pre-construction phase, key steps include site selection, surveys, design, and tendering. The construction phase involves preparing the site layout, excavation, foundation, plinth and columns, walls, floors, and other works. Post-construction involves collecting drawings, manuals, bills, certificates, and handing over the completed building.

Uploaded by

SatyamTiwari
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Pre-construction Phase:

A. Site Selection/ Land acquisition [1-4 weeks]


B. Site preparation/ Clearing of site [2-4 days]
C. Site Surveying [1 week]
o C1. Site boundary/ area
o C2. Grading/ Profile of site
o C3. Soil testing
o C4. Verifying the surveys
D. Selection of architect/architectural firms [3-4 days]
E. Design Process [6-8 weeks]
o E1. Input of Requirements from client
o E2. Data collection/ Site analysis
o E3. Spatial zoning
o E4. Approximate estimation
o E5. Design Conceptualisation
o E6. Client discussions
o E7. Finalization of design & Final estimate
o E8. Preparation of working drawings & specifications
o E9. Sanction Drawings
o E10. Approval of drawings from City Development Authority.
F. Tendering Process [2-3 weeks]
o F1. Identification of the type of the tender
o F2. Request preparation
o F3. Tender invitation
o F4. Respond from suppliers
o F5. Evaluation & selection
o F6. Notification and debriefing
o F7. Contract establishment & management

Construction Phase:
G. Preparation of site layout as per drawing. [up to 2 weeks]
o G1. Marking of Boundaries
o G2. Approach Roads
o G3. Site Office
o G4. Construction of material store
o G5. Material storage
o G6. Open Stack
o G7. Labour Huts
o G8. Water Supply and Electricity
o G9. Sanitary Arrangement
H. Excavation [up to 3 weeks]
o H1. Marking of centreline & foundation points
o H2. Checking a datum level
o H3. Digging of hole for foundation with an extra space for someone to work
within
o H4. Cleaning of the excavated hole
o H5. Preliminary plumbing or heating installation
o H6. Construction of trenches
I. Construction of Foundation [up to 2 weeks]
o I1. Filling of aggregates at the bottom and leveling
o I2. Filling of PCC Bed
o I3. Formation & Placement of reinforced steel framework
o I4. Pouring of concrete
o I5. Damp-proofing of the foundation
o I6. Fixation of drain tile
o I7. construction of the sewer & water tank
o I8. Backfilling & grading of Soil
J. Construction of Plinth beam [up to 2 weeks]
o J1. Marking of plinth beam
o J2. Filling of columns up to plinth level
o J3. Soil filling in trenches and compaction till ground level
o J4. Laying & filling of RCC beams
o J5. Curing of Concrete and removing of formwork
o J6. Plinth construction & DPC
K. Construction of Columns & slab [up to 10 weeks]
o K1. Marking of Column Layout
o K2. Filling of columns up to lintel level
o K3. Construction of lintels
o K4. Filling of columns up to roof level
o K5. Soil filling and compaction till plinth level wherever required
o K6. Laying & filling of RCC beams
o K7. Setting up the shoring/scaffolding for slab support
o K8. Setting up the steel framework for the slab
o K9. Electrical installations if any
o K10. Construction and curing of the roof slab
L. Constructions of walls [up to 6 weeks]
o L1. Construction of brickwork till lintel level
o L2. Curing of brickwork
o L3. Fixation of door and window frames
o L4. Construction of brickwork till slab level
o L5. Curing of brickwork
o L6. Ducts for electrical, heating & plumbing fittings
o L7. Plastering of walls
o L8. Curing of plastered walls
M. Laying of plumbing lines inside and outside of the building (manholes) [up to 4
days]
N. Construction of flooring [up to 2 weeks]
o N1. Filling of the base till the desired floor level
o N2. Compaction of the base soil
o N3. Laying of the flooring/tiling
o N4. Filling the cracks & fixing the skirting
O. Other works [up to 6 weeks]
o O1. Filling the electrical wirings
o O2. Fixation of electrical & water supply points
o O3. Fixation of door & window shutters with necessary fittings
o O4. Painting & wall finishes
o O5. Grinding & polishing of the floor
o O6. Fix all electric fixtures like AC, Fans and light point
o O7. Fix all the bib cocks and other fixtures
o O8. Construction of approaching pathways and parking spaces
o O9. Pavement of the exterior spaces
o O10. Landscaping if required
o O11. Final inspection & walkthrough

Post-construction Phase:
P. Collection of all built drawings from consultants and approved by architect.
Q. Collection of warranty & maintenance manuals
R. Certifying all vendor bills.
S. Preparation of Completion certificate based on all documents & Drawings.
T. Assist in finding suitable facility Manager & introduce him basics about the building.
U. Final handing over to the client