Formwork Quantity Take Off 2

This document provides a quantity take-off of formwork for the ground floor, basement, and foundation of a building. For the ground floor, it lists the areas of beams, slabs, and columns totaling 31.784 square meters. For the basement, it lists the areas of beams, slabs, shear walls, internal column sides, and columns totaling 35.236 and 32.750 square meters respectively. For the foundation, it lists the areas of footings, column bases, slabs, and columns totaling 21.71 square meters. It also provides rules for estimating the quantities of spacers and rebar chairs needed for formwork based on the types and dimensions of structural elements.

Uploaded by

kian hong
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
569 views4 pages

Formwork Quantity Take Off 2

This document provides a quantity take-off of formwork for the ground floor, basement, and foundation of a building. For the ground floor, it lists the areas of beams, slabs, and columns totaling 31.784 square meters. For the basement, it lists the areas of beams, slabs, shear walls, internal column sides, and columns totaling 35.236 and 32.750 square meters respectively. For the foundation, it lists the areas of footings, column bases, slabs, and columns totaling 21.71 square meters. It also provides rules for estimating the quantities of spacers and rebar chairs needed for formwork based on the types and dimensions of structural elements.

Uploaded by

kian hong
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Formwork quantity take-off of ground floor

Beams Slabs m2
3,80 x 5,00 4 x 0,40 x 0,10 + 2 x
S1: = 20,136
3,60 x 0,18
2 x 5,00 x 0,50 + 2 x (5,00-2 x 0,40) x
b1,b2: 0,32 +
+ 2 x 4,20 x 0.30 = 10,208
Columns(joints 4 x 0,40 x 0,50 + 4 x 0,40 x 0,32 + 4 x
= 1,440
areas): 0,10 x 0,32
Total = 31,784
Columns:
4 x (0,40 x 0,40 x 2,50) = 16,000
Formwork quantity take-off of basement
Beams Slabs m2
S1: 4,50 x 3,90 - 4 x (0,15 x 0,15) = 17,460
2 x [5,00 x 0,50 +4,20 x 0,32]
b1,b2: = 9,788
+4,20 x 0,25
4,40 x 0,50 + 3,60 x 0,32 +3,60
b3: = 4,252
x 0,25
Shear wall sw5: 4,40 x 0,50 + 3,60 x 0,32 = 3,352
internal columnsides: 4 x 2 x 0,15 x 0,32) = 0,384
Total = 35,236

4 x (0,40 x 0,40 x 2,50)


Columns: = 14,750
2 x (0,25 x 2,50)
Shear wall sw5: 2 x (3,60 x 2,50) = 18,000
Total = 32,750
Formwork quantity take-off of foundation
m2
FootingsF3,4,5: 0,50 x [5,00 + 2 x 1,00 + 0,30 x 2] = 5,85
2 x [0,70 x0,10 + 4,30 x 0,60
+0,30 x 0,30]
Cb1,2: = 10,04
2 x [0,30 x0,10 + 3,60 x 0,60
+0,30 x 0,30]
(3,80 + 4,40) x 0,30 + (3,60 +
Sf4: = 4,86
4,40) x 0,30
2 x 2 [0,10 x 0,30 +0,10 x 0,10] +
Columns: = 0,96
+(4,40+3,60 ) x 0,10
Total = 21,71
Spacers quantity take-off
RULES FOR ESTIMATING THE QUANTITTIES OF SPACERS AND REBAR CHAIRS
Superstructure and foundation beams: (2 m of linear spacers + 2 pieces of point support) in
every meter of clear beam length
Columns: (8 pieces of point support) per column
Shear walls: 2 m of linear spacers in every meter of the shear walls length
Foundation slabs and footings: (1.25 m of linear spacers) in every square meter of clear slab
area
Slabs free edges: (1 m of linear spacers + 1m of rebar chairs + 1 piece of point support) in
every edge meter
Slabs supports: 1 m of rebar chairs per meter of every slab support