0% found this document useful (0 votes)
751 views3 pages

Sample Procedure Flow

This document outlines the procedure for receipt inspection at a manufacturing facility. It defines responsibilities, describes the inspection process, and lists relevant records and references. The receipt inspection process involves verifying approved suppliers and documentation, tagging incoming materials, performing random sampling and inspections, updating records based on acceptance or rejection, and notifying relevant parties. The goal is to verify that incoming goods meet specified requirements.

Uploaded by

vyly1723
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
751 views3 pages

Sample Procedure Flow

This document outlines the procedure for receipt inspection at a manufacturing facility. It defines responsibilities, describes the inspection process, and lists relevant records and references. The receipt inspection process involves verifying approved suppliers and documentation, tagging incoming materials, performing random sampling and inspections, updating records based on acceptance or rejection, and notifying relevant parties. The goal is to verify that incoming goods meet specified requirements.

Uploaded by

vyly1723
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

SYSTEM PROCEDURE DOC NO: QA-BPF-01

RECEIPT INSPECTION PAGE: 1 OF 3

REVISION RECORD SHEET


REV. DESCRIPTION OF AMMENDMENT DATE OF REASON FOR
NO. AMMENDMENT AMMENDMENT
00 Stated as per QS 9000: 1998 requirement 16.08.1999 QS9000:1998
updation
01 Responsibilities in column 3 re-defined & 25.10.1999 Observations during
changed to AM-QA. Preparation, Review Pre Assessment
& approval, Issuance & functional audit
deleted. Control plan for receipt/final
inspection added. Frequency of dock
audit changed. Separate register(QA-R-
11) used for dock audit
02 Responsibility of Layout Inspection 25.07.01 Observation during
changed to Exec. Tool Room from Exec Audit
QA. And register TLR-R-07 replaces QA-
R-08 for the same.
03 • Clause 4.1, resp. changed to Exec. 18.11.03 QS 9000 System
QS ipo AM-QA Review & Updation
• Clause 4.2& 4.3 merged.
• Clause 4.5, responsibility changed to
Executive store in place of Sr.
manager QA.
• Clause 4.8, provision added for
temporary process parameter
deviation to fulfill the requirement of
product.
• Clause 4.11, generation of inspection
standard added with responsibility
• Performance testing / initial testing
added
• Layout inspection re-defined
04 • Procedure changed from Simple Text 15.05.2004 System review due
to Flow Chart to switching to
• Title changed from Inspection & ISO/TS 16949
Testing to Receipt Inspection, only
• No. changed from QA-P-01 to QA-
BPF-01
• New Header & Footer added

DISTRIBUTED TO :
S.NO. DESIGNATION SIGNATURE OF THE RECEIVER
1. ASST. MANAGER (QA)
2. MANAGER (PRODUCTION)
3. MANAGER (PURCHASE)
4. MANAGER (ENGG.)

Prep. By: Reviewed & Appd. by: Issued by: REV. NO: 04

HOD-QA CEO / MR Exec-MIS DATE : 15.05.04


SYSTEM PROCEDURE DOC NO: QA-BPF-01

RECEIPT INSPECTION PAGE: 2 OF 3

1.0 Purpose:
To establish and maintain a system for inspection and testing in order to verify that the specified
requirements for the product are met
2.0 Scope :
All incoming goods including goods for job work.
3.0 Responsibility :
Asstt. Manager (QA)
4.0 Definition :
---
5.0 Description:

S. Input Process / Activity Resp. & Control Doc. / Output


No Interaction Check Point

5.1 MRR (STR-F- Store I/C Material Identification ---


03) MRR receipt from store QA-Exec tag (QA-F-01)
RGP (STR-F-10) Supplier Test
certificate /
Insp. Report
Reject & return
MRR to store

5.2 Check A.S.L. Pur-Exec Approved supplier Verification


Not OK QA-Exec List (PUR-D-01) of
& All related
doc. approved
supplier

OK
5.3 Tagged QA-Exec Quality Plan Incoming
material Store I/C (QA-Q-XXX) Inspection
Sampling Plan Report
Not OK Random (QA-D-04) (QA-F-02)
sample Calibrated
selection & instrument
Inspection

OK
5.4 Inspected QA-Exec Identification / Inspected
Material Tear off accepted / rejected QA-HOD Inspection Tag material
portion as applicable Store I/C (QA-F-01) Approved
MRR by
QA
5.5 -- QA-Exec Vendor history card Entry in
Update supplier history (QA-F-05) vendor
card history
card

Prep. By: Reviewed & Appd. by: Issued by: REV. NO: 04

HOD-QA CEO / MR Exec-MIS DATE : 15.05.04


SYSTEM PROCEDURE DOC NO: QA-BPF-01

RECEIPT INSPECTION PAGE: 3 OF 3

PERFORMANCE INDICATORS:
Efficiency: Line rejections trend
Effectiveness: Incoming %age Acceptance

6.0 Records:

6.1 QA-F-01 Identification Tag


6.2 QA-F-02 Incoming Inspection Report
6.3 QA-F-05 Vendor History Card
6.4 STR-F-03 Material Receipt cum Inspection Report
6.5 STR-F-10 Returnable Gate Pass / Receipt Report / Insp. Report – Job Work only

7.0 References:

7.1 QA-Q-XXX Relevant Quality Plans


7.2 QA-W-01 Work Instruction for Incoming Inspection
7.3 QA-D-04 Single Sampling Plan
7.4 PUR-D-01 Approved Supplier List
7.4 QA-D-05 List of Major / Minor Defects

Prep. By: Reviewed & Appd. by: Issued by: REV. NO: 04