ARA - For Emergency Diesel Generator

The document summarizes a risk assessment for emergency diesel generator work. It identifies 5 specific tasks: 1) permit to work, 2) continuity and resistance testing, 3) no load testing, 4) risk assessment training, and 5) risk assessment preparation. For each task, it identifies potential hazards, consequences, likelihood of occurrence, and initial risk rating. It then lists control measures to reduce the risks and residual ratings. The highest remaining residual risk is low.

Uploaded by

Shaikh Aftab
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
441 views4 pages

ARA - For Emergency Diesel Generator

The document summarizes a risk assessment for emergency diesel generator work. It identifies 5 specific tasks: 1) permit to work, 2) continuity and resistance testing, 3) no load testing, 4) risk assessment training, and 5) risk assessment preparation. For each task, it identifies potential hazards, consequences, likelihood of occurrence, and initial risk rating. It then lists control measures to reduce the risks and residual ratings. The highest remaining residual risk is low.

Uploaded by

Shaikh Aftab
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Project Name: Sagar Samrat Conversion Project

Project/ Task Risk Assessment for Emergency Diesel Gener


Description:

RISK RANKING

CONSEQUENCE
Ref SPECIFIC TASK/ ACTIVITY STEPS IDENTIFY POTENTIAL HAZARDS
No.

Permit to work Contractor, client co-ordination fails

1 2

Continuity & Resistance Testing Electrocution


2 4

Injury to personnel 5
No Load Testing

Damage to equipment 4
Risk Assessment trained
Risk Assessment person:
Prepared by:
Other participant names:

Approved by

RISK MATRIX
CONSEQUENCE
Insignificant (1) Minor (2) Moderate (3) Major (4) Catastrophic
(5)
LIKELIHOOD
Almost Certain (5) M H E E E

Likely (4) M H H E E
Possible (3) L M H E E
Unlikely (2) L L M H E
Rare (1) L L M M H
System SSCP-1381-GPC-COM-05 Date: 25.04.2017

for Emergency Diesel Generator

RISK RANKING RESIDUAL RISK

ACTIONER/ INITIALS
RESIDUAL RATING
RISK CONTROL MEASURES CONSEQUENCE
RISK RATING

Hierarchy of Control Elimination,


LIKELIHOOD

LIKELIHOOD
Substitution, Isolation, Engineering,
Administration, Personal Protection.
Additional information can be attached.

Supervisor to ensure that the


permit to work is valid for the date,
and that the work will start only 1 2 L
after getting a valid permit.
2 M
Communicate properly in Tool Box
Talk 1 1 L
2 M
Ensure electrically competent
persons are engaged in work 2 L
3 E
Only inspected, calibrated and
4 E approved test equipment to be 1 3 L
used
Ensure only authorised persons are
3 E allowed in the test area. 1 1 L

Ensure appropriate tools are used


3 E and inspected before use 1 2 L

Ensure all Personnel are wearing


4 E correct PPE at all times. 1 1 L
Highest Remaining Residual Risk L