Noveco EPM 3 0 Planning and Forecasting by Purchase Order

This document discusses SAP solutions for project management, including project cost forecasting, planning, execution, monitoring, and forecasting. It describes how SAP can be used to create projects, plan costs using Easy Cost Planning, create purchase orders, post payments and goods receipts, perform forecasts, and plan remaining purchase order values by period. The SAP project management solutions allow tracking of actual costs, commitments, and forecasting of estimated costs to complete.

Uploaded by

RITA SILABAN
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
121 views24 pages

Noveco EPM 3 0 Planning and Forecasting by Purchase Order

This document discusses SAP solutions for project management, including project cost forecasting, planning, execution, monitoring, and forecasting. It describes how SAP can be used to create projects, plan costs using Easy Cost Planning, create purchase orders, post payments and goods receipts, perform forecasts, and plan remaining purchase order values by period. The SAP project management solutions allow tracking of actual costs, commitments, and forecasting of estimated costs to complete.

Uploaded by

RITA SILABAN
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 24

SAP Project Cost Forecast,

SAP Project Cost Forecasting,


SAP Project Forecast,
SAP Project Forecasting,
SAP Project System,
SAP PS,
SAP Project Management,
SAP Project Management solutions,
SAP Project Planning,
SAP Project Cost Planning,
SAP Project Cost Plan,
SAP Project Cost To Complete,
SAP Project Remaining Cost To Complete,
SAP Project CTC,
SAP Project Estimate At Completion,
SAP Project EAC,
SAP Project Progress Analysis,
SAP Project Earned Value,
SAP Project Estimation,
SAP Project Cost Estimation,
SAP Project Cost Estimate,
SAP Project Cost Estimating,
SAP Project Estimate,
SAP Project Estimating,
SAP Project Margin Forecasting
SAP Project Revenue Forecasting
SAP Solutions for Engineering and Construction,
SAP Solutions for Construction projects,

Noveco ePM 3.0 : SAP Solutions for Construction industry,


SAP Solutions for Capital projects,
SAP Solutions for Capital and Maintenance projects,
SAP Solutions for Maintenance projects,
SAP Solutions for CAPEX projects,

Planning and Forecasting by SAP solutions for Manufacturing projects,


SAP solutions for Project Manufacturing,
SAP Solutions for Shipbuilding projects,
SAP Solutions for Engineering Projects
SAP Solutions for Professional Services,

Purchase Order SAP Solutions for EPCM


SAP Project Variation Management,
SAP Project Change Management,
SAP Project Change Control,
SAP Project Risk Management,
SAP Project Contingency,
SAP Project Risk Management,
SAP Project System enhancements,
SAP Project Portal,
SAP Project Portfolio Report,
SAP Project Portfolio Reporting,
SAP Project Portfolio Planning,
SAP Project Portfolio Management,
SAP PPM,
SAP Commercial Project Management,
SAP CPM,
SAP Easy Cost Planning,
SAP ECP,
SAP CJ9L,
SAP Project Builder
SAP Project Editor
SAP Project Scheduling,
SAP Project Schedule,
SAP Project Gantt Chart,
SAP Project Report,
SAP Project Cash Flow,
SAP Project Cashflow,
SAP Project Cash Management,
SAP Project Resource Forecasting,
SAP Project Resource Planning,
SAP Project Resource Management
SAP Project KPI,
SAP Project Key Performance Indicators,
SAP Project S-curves reports,
SAP Project Reporting,
SAP Project Report,
Process Flow

Monitoring
Planning and
Execution and
Estimating
Forecasting

• Create Purchase • Perform Project


• Create Project
Orders Forecasts
• Plan Costs using
• Post Down Payments • Detail forecast by
Easy Cost Planning
Purchase Order
• Post GR/IR for
Purchase Orders • Plan Purchase Order
remaining value by
period
Create Project

In this example we use project with WBS


only
Project with WBS and Network Activities
will work the same way
Plan Costs using Easy Cost Planning

We use cost type ‘V’ (variable), but we can


use ‘M’ material or ‘N’ service

If we use ‘M’ or ‘N’ we must enter material


or service number, we can also use Vendor
Name, Purchasing Info Record etc.
Open Project in Noveco Project Manager Workbench

• Original Estimate
derived from Easy Cost
Planning
• Cost To Complete initially
generated from Original
Estimate
Noveco Project Manager Workbench

Estimated at Completion = Actual Costs + Commitments +


Costs To Complete

NOTE:
- In “Forecast” tab cost plan is summarized by Cost Element, Resource Name and Value Category
Noveco Project Manager Workbench

Select Costing item and choose “Detail Forecasting”


Noveco Project Manager Workbench

When run for the first time, costing line items are copied from
Easy Cost Planning
Process Flow

Monitoring
Planning and
Execution and
Estimating
Forecasting

• Create Purchase • Perform Project


• Create Project
Orders Forecasts
• Plan Costs using Easy
• Post Down • Detail forecast by
Cost Planning
Payments Purchase Order

• Post GR/IR for • Plan Purchase Order


Purchase Orders remaining value by
period
Post Time Sheets

Down Payment
Noveco demo: Plan By PO 4500009115 / 10

“Engineering:
Noveco demo: Plan By PO Electrical”
Goods receipt
Engineering

Design 4500009116 / 10
Goods receipt
“Engineering:
Mechanical”

Down Payment
4500009117 / 10

“Engineering:
Structural”

Goods receipt
Process Flow

Monitoring
Planning and
Execution and
Estimating
Forecasting

• Create Purchase • Perform Project


• Create Project
Orders Forecasts
• Plan Costs using Easy
• Post Down Payments • Detail forecast by
Cost Planning
Purchase Order
• Post GR/IR for
Purchase Orders • Plan Purchase Order
remaining value by
period
Project Manager Workbench

Exclamation mark indicates that forecast


cost to complete must be recalculated

Actual Costs and PO Commitments are


displayed

PO List is displayed
for selected WBS
hierarchy
Project Manager Workbench
Click “Refresh” to automatically
recalculate Cost To Complete and adjust
Estimated at Completion (if necessary)

Cost and Work To Complete reduced from


actual costs and purchase commitments
Switch to Change mode
Select Costing item and choose “Detail Forecasting”
Detailed Forecasting by Purchase Order

When run for the first time, the system copies plan cost
items from ECP.
Delete them if they are no longer required
Detailed Planning by Purchase Order

PO Value of Work Done = Value of Work


Done as % * ( PO Plan Value + PO Cost To
Complete)

PO Progress calculated
as %: PO Actual Cost / PO Actual Costs PO Down Current total
PO Plan Value and Remaining Payment amount PO Plan Value
Committed value
Detailed Planning by Purchase Order

Enter PO Cost To Complete amount System recalculates PO Estimated at Completion =


PO Plan Value + PO Cost To Complete
Detailed Planning by Purchase Order

Enter % of Value of Work Done by PO item System recalculates PO Value Of Work Done =
% of Value of Work Done * PO Estimated at Completion
Detailed Planning by Purchase Order

System recalculates PO Accrued Value = Value of


Work Done – Actual Costs – Down Payment
Detailed Planning by Purchase Order

System recalculates PO Remaining Value = Value of


Work Done – Actual Costs – Down Payment
Plan by Period PO Remaining value
Select Purchase Order item (or multiple items) and click
on “Plan By Period”
Plan by Period PO Remaining value
When Completed click “Confirm” to copy new Cost To
Complete to “Forecast” tab
Update Project Forecast from Detailed Forecasting

Exception indicator turns red because


project Estimated Cost at Completion
is higher than its Budget

Estimated at Completion is updated Cost To Complete are updated


and it is now over Budget by from the Detailed Forecasting
$30000.0 or by 10.0% screen
For more information visit Noveco Systems on
www.novecosystems.com