The document outlines the activities and sequence for constructing a building organized by: demolition, site clearance, earth work including grading, excavation of footings and trenches, foundation including layout of footings, installation of reinforcement, and pouring of concrete. Subsequent activities include backfilling, installation of reinforcement and concrete for columns, slabs, beams, staircases for the ground floor and first floor. Finishing activities are listed for the second floor including reinforcement, formwork, pouring of concrete, plastering, tile installation, and doors/windows.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
125 views2 pages
Organization of The Work:: Activities
The document outlines the activities and sequence for constructing a building organized by: demolition, site clearance, earth work including grading, excavation of footings and trenches, foundation including layout of footings, installation of reinforcement, and pouring of concrete. Subsequent activities include backfilling, installation of reinforcement and concrete for columns, slabs, beams, staircases for the ground floor and first floor. Finishing activities are listed for the second floor including reinforcement, formwork, pouring of concrete, plastering, tile installation, and doors/windows.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2
Organization of the work:
NO ACTIVITIES Symbol Predecessor duration
1 demolition A ------------------- 15 2 Site clearance B A 9 Earth work Grading / leveling C AB 2 Excavation of footing D C Excavation of trench and E C Foundation Layout footing F D Install reinforcement G F Pouring footing H FG Construction of rubble masonry I E Ground Back filling and compaction J HI floor Lean concrete K J Column Installation of reinforcement L K Electric mesh M L Formwork preparation N LM Pouring of concrete O N Slab and beam Formwork preparation P O Installation of reinforcement Q P Electric mesh R PQ Pouring of concrete S R Staircase Formwork preparation T PQ Installation of reinforcement U T Pouring of concrete V TU Column Installation of reinforcement W S Electric mesh X W First Formwork preparation Y WX floor Pouring of concrete Z Y Slab and beam Formwork preparation A1 Z Installation of reinforcement B1 A1 Electric mesh C1 A1B1 Pouring of concrete E1 A1B1C1 Staircase Formwork preparation F1 E1 Installation of reinforcement G1 F1 Pouring of concrete K1 F1,G1 Column Installation of reinforcement L1 E1 second Electric mesh M1 L1 floor Formwork preparation N1 L1,M1 Pouring of concrete O1 N1 Slab and beam Formwork preparation P1 O1 Installation of reinforcement Q1 P1 Electric mesh R1 P1,Q1 Pouring of concrete S1 P1,Q1,R1 finishing Break work T1 S1 plastering U1 T1 Base tiles installation V1 T1 toilet accessories W1 U1 White washing & painting X1 U1 Windows & doors installation Z1 T1 Stair room A2 S1