T&C Manual

This document provides test procedures for current transformers (CTs). It outlines 10 tests to be performed: 1. Insulation resistance measurement to check insulation of primary and secondary circuits. 2. Continuity test to check for open circuits in primary and secondary windings. 3. Secondary winding resistance test to check winding resistance matches factory values. 4. Polarity test to check primary and secondary polarity matches scheme requirements. 5. Tan delta and capacitance test to check bushings' capacitance and tan delta values match factory data. It gives equipment needed, test procedures, and safety precautions for each test. Test report formats are in annexures. The goal is to systematically

Uploaded by

Karthikeyan S
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (3 votes)
685 views65 pages

T&C Manual

This document provides test procedures for current transformers (CTs). It outlines 10 tests to be performed: 1. Insulation resistance measurement to check insulation of primary and secondary circuits. 2. Continuity test to check for open circuits in primary and secondary windings. 3. Secondary winding resistance test to check winding resistance matches factory values. 4. Polarity test to check primary and secondary polarity matches scheme requirements. 5. Tan delta and capacitance test to check bushings' capacitance and tan delta values match factory data. It gives equipment needed, test procedures, and safety precautions for each test. Test report formats are in annexures. The goal is to systematically

Uploaded by

Karthikeyan S
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 65

LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:

Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 1 of 65

PRE COMMISSIONING TEST PROCEDURE FOR CURRENT TRANSFORMERS

1.0 SCOPE
This procedure covers the Pre commissioning Test for current Transformers and the test
report format covers CT’s which is having 5 cores on its secondary.

2.0 PURPOSE
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 2 of 65

This procedure is prepared to carry out various pre- commissioning tests to be conducted in
systematic manner for Current Transformers to ensure the healthiness of the equipment.

3.0 PRE-REQUISITES
SYSTEM REQUIREMENTS
1. Relevant Drawings and layouts.
2. 415 V AC, 3 Ph power supply is available for Testing.
3. All Cables pertaining to current transformers were laid & terminated.
4. Make sure that the equipment erected is as per approved drawings & Layouts.
5. Check the Name Plate & Rating Plate Of the equipment Erected.

4.0 REQUIREMENTS OF TESTING KITS

S.No Test Kit Range


1 Tan Delta Test Kit with test leads 0 – 12kV
2 Primary Injection Kit with test leads 0-2000A / 5V (AIS)
0-3000 / 5V (GIS)
3 High Voltage Transformer with test leads 0 -5kV
4 Contact Resistance Kit with test leads 0-2000 milliohm
5 Secondary injection kit with test leads 0 – 100A

5.0 REQUIREMENT OF TESTING INSTRUMENTS


1. Digital Multi meter.
2. 500 V, 5000 V Insulation Tester
3. Polarity Tester.
4. Clamp Meters (200mA – 2000A)
5. 3 Ph- A.C Supply Extension Board with MCB Protection.

6.0 HAZARDS AND PRECAUTIONS


1. Unauthorized persons should not be allowed to enter Testing Area.
2. Barricade the Testing Area With Warning Tape
3. There should not be any temporary (hooking of supply) arrangement for Testing. Proper A.C
Supply extension board should be used
4. Ensure protection MCB is provided in the circuit of AC supply used for testing
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 3 of 65

5. Ensure Proper Tools & Tackles are Available for carrying out Tests.
6. Ensure Proper PPE ( Personal Protective Equipments) are used
7. Ensure the Healthiness of the test leads (Check for any insulation Damages).
8. Competent Authority to maintain shutdown & Work permit system in existing Live Bay
works.
9. Any conducting element should be carried horizontally at waist level in the area used for
pre-commissioning tests.

7.0 POST INSTALLATION CHECKS


Post installation check list should be done according to the annexure enclosed.

8.0 TESTS TO BE CONDUCTED


1. Insulation Resistance measurement Test.
2. Continuity Test.
3. Secondary Winding Resistance Test.
4. Polarity Test.
5. Tan Delta & Capacitance Test.
6. Primary Injection Test.
7. Magnetizing Current Characteristic Test (Knee Point Voltage Test).
8. Contact Resistance Measurement Test for Connectors.
9. Secondary Injection Test.
8.1 INSULATION RESISTANCE MEASUREMENT TEST
Aim:
To ensure the insulation healthiness of the primary and secondary circuits by measuring
insulation resistances.
Equipment Required:
The major equipment required for performing IR measurement test is,
i) 0-10kV Meggar.
ii) Test Leads.
Test Procedure:
The above test to be conducted at following points,
a) Primary to Earth
b) Primary to Secondary
c) Secondary to Earth
d) Between Secondary Cores
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 4 of 65

Note: a) Remove the connected earthing to system involving CT under test


b) Disconnect the connected terminals of CT M. Box.
c) Permissible values for 400 kV > 400 MΩ and for 220 kV > 200 MΩ

a. Primary to earth
1) Connect the line terminal of the Meggar (5000V) to either P1 (or) P2 of the Current
Transformers
2) Connect the Earth terminal of the Meggar to the earth stud provided at the equipment
3) Switch on the Meggar
4) Take down the readings (It should be in Mega Ohms).

b. Primary to Secondary
1) Connect the line terminal of the Meggar(5000V) to either P1 (or) P2 of the Current
transformers
2) Connect the Earth terminal of the Meggar to the S1 (or) S2 of the Current transformers
3) Switch on the Meggar

4) Take down the readings( It should be in Mega Ohms)

c. Secondary to Earth
1) Connect the line terminal of the Meggar(500V) to either S1 (or) S2 of the Current
transformers
2) Connect the Earth terminal of the Meggar to the earth stud provided at the equipment
3) Switch on the Meggar.

4) Take down the readings (It should be in Mega Ohms).

d. Between Secondary cores


1) Connect the line terminal of the Meggar(500V) to either S1 (or) S2 of one core of the Current
transformers
2) Connect the Earth terminal of the Meggar(500V) to either S1 (or) S2 of the other cores of
the Current transformers
3) Switch on the Meggar
4) Take down the readings (It should be in Mega Ohms).
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 5 of 65

Fig 1 : Insulation Resistance Measurement Setup


Test Format For the above test is enclosed in Annexure –III, IV & V.

8.2 CONTINUITY TEST


Aim:
To show that there is a continuity of supply in primary and secondary winding without any
open circuit in the current path.
Equipments Required:
The equipments required for performing continuity test are,
i) Digital Multimeter.
ii) Test Leads.
Test Procedure:
a) Select the Multi meter in continuity Mode.
b) Connect the Multi meter across the secondary terminals of various cores.
c) Check for the ‘Beep’ sound.
Test Format For the above test are enclosed in Annexure –VI
8.3 SECONDARY WINDING RESISTANCE TEST
Aim:
To check for the winding resistance on the secondary side value, so that the value matches
with the factory test values.
Equipments Required:
The Secondary winding resistance test can be performed with the following equipments,
i) Milli ohm meter.
ii) Test Leads.
Test Procedure:
a) Select the Multi meter in Resistance Mode.
b) Connect the Multi meter across the secondary terminals of various cores.
c) Note down the readings
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 6 of 65

d) Compare the test results with Factory Test Report (If available)
Test Format For the above test are enclosed in Annexure –VII

8.4 POLARITY TEST

Aim:
To check for the correct sequence of polarity on the primary and secondary side of the
current transformer. (For eg. When P1 is positive w.r.t. P2, then S1 also must be positive w.r.t S2,
according to the scheme requirement).
Equipments Required:
The equipments required for polarity tests are as follows,
i) Battery of suitable rating or Polarity tester.
ii) Analog Multimeter / Galvanometer.
iii) Connecting leads.
Test Procedure:

i) Connect battery + Ve to P1(Primary) Terminal of CT


ii) Connect battery - Ve to P2 (Primary) Terminal of CT
iii) Connect Multi meter (Analog) + Ve to S1 (Secondary) Terminal of CT
iv) Connect Multi meter (Analog) - Ve to S2 (Secondary) Terminal of CT
v) Momentarily apply the D.C Voltage across the Primary terminals of CT
If the meter deflects forward then the polarity is O.K.

Fig 2: Polarity Test Setup

Test Format For the above test are enclosed in Annexure – VIII

8.5 TAN DELTA & CAPACITANCE TEST


Aim:
To check the capacitances and tan delta value of the CT bushings and ensure that it
corresponds to the equipment data value given during the time of factory test.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 7 of 65

Equipments Required:
The equipments required for carrying out Tan Delta Capacitance test are as follows,
i) Tan Delta Test Kit.
ii) Connecting cables.
Test Procedure:
Note: When the CT’s are provided with taps then the measurement of capacitance can be done
between the tests taps, else the capacitance should be measured from one terminal to grounded
terminal. (As per the connections shown in the diagram).
a) Connect the kit across the test terminals provided in the equipment for Tan Delta
Measurement.
b) Initially apply 2 KV and note down the readings
c) Then apply 10 KV and note down the readings
d) Compare with the test results obtained at the manufacturer test report (If Available)
For CT’s With Test Taps:

For CT’s Without Test Taps:

Fig 3: Tan Delta Measurement


Test Format For the above test are enclosed in Annexure –IX

8.6 PRIMARY INJECTION (RATIO) TEST


Aim:
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 8 of 65

To check the ratio of the primary turns to the secondary turns and compare it with the given
rated values.
Equipments Required:
The equipments required for primary injection test or ratio test are as follows,
i) Primary injection test kit / Loading Transformer.
ii) Clamp Meter.
iii) Connecting cables.
Test Procedure:
a) Connect the Primary injection kit across the primary terminals (P1, P2)
b) Initially apply 20% of rated current
c) Then Raise the current to 40%, 60% and 80%
d) Note down the corresponding Secondary current at various cores.
e) Repeat the test for all the ratios mentioned in the rating plate

Fig 4 : Typical Primary Injection Test Setup


Test Format For the above test are enclosed in Annexure – X
8.7 MAGNETIZING CURRENT CHARACTERISTIC (KNEE POINT VOLTAGE) TEST
Aim:
To prove that the CT cores do not saturate during the application of peak voltage and ensure
that the saturation of the core is avoided at knee point voltage.
Equipments required:
The following are the equipments required for performing magnetizing current characteristics,
i) High Voltage Transformer test kit.
ii) Digital Multimeter.
iii) Clamp Meter.
iv) Connecting cables.
Test Procedure:
Note: a) CT should not saturate at 110% of KVp
b) If knee point voltage is not mentioned the knee point current may be taken into
consideration
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 9 of 65

c) Magnetization of Metering core should not been done.


i) Connect the Hi-voltage Transformer across the secondary terminals of PS Class core
ii) Apply 25% of Knee point Voltage mentioned in rating plate
iii) Then Raise the voltage to 50%, 75%, 100% and 110%
iv) Note down the Magnetizing Current.
v)Repeat the test for all PS class cores.

Fig 5: Magnetization Current Measurement Setup

Fig 6: Typical Magnetization curve


Test Format For the above test are enclosed in Annexure – XI

8.8 CONTACT RESISTANCE MEASUREMENT TEST FOR CONNECTORS


Aim:
To check the CT terminals has least value of resistance which ultimately ensures the tightness
of the joints and connectors.
Equipments Required:
The equipments required for performing test are,
i) CRM test kit.
ii) Connecting leads.
Test Procedure:
a) Connect the Micro Ohm Meter leads on the connectors of CT primary terminals
b) Switch ‘ON’ the test kit & apply the current up to 100Amps
c) Take Down the Readings.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 10 of 65

d) It should be in Micro Ohms


Test Format For the above test are enclosed in Annexure – XII

8.9 SECONDARY INJECTION TEST


Aim:
To check the values of current injected to the secondary matches approximately with the
current measured at the C&R panel terminal point, without much deviation and ensures proper supply
of current to CR panel for controlling.
Equipments required:
The equipments required for performing secondary injection test are as follows,
i) Secondary injection test kit.
ii) Clamp Meter.
iii) Connecting leads.
Test Procedure:
a) Connect the secondary injection kit across the secondary terminals
b) Apply 0.5 Amps current.
c) Measure the current across the protective relay point & Metering point in the C & R panel (or)
In BCU.
d) Repeat Test for all the cores

Fig : Secondary Injection Test Setup


Test Format For the above test are enclosed in Annexure – XIII

ANNEXURE – I
DATA OF EQUIPMENT (Rating Plate)

Make :
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 11 of 65

Type: :

Sl. No. : R-Phase: Y-Phase: B-Phase:

Year of manufacture: R-Phase: Y-Phase: B-Phase:

Feeder /Bay Name :

V. Rated data and duty:

Core Ratio Class Burden KVp Protection / Metering

Winding I

Winding II

Winding III

Winding IV

Winding V

KVp: Knee point voltage in volts

ANNEXURE – II
Post Installation check list
S. No. Description Status Remarks, Record
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 12 of 65

Yes No discrepancies, if any


1. Equipment is cleaned and free from dust /
dirt, foreign materials etc.
2. Equipment is free from all visible defects on
physical inspection
3. Check CT tank has been provided with
double earthing
4. Check that CT junction box is earthed
5. All nuts and bolts are tightened correctly as
per specified torque
6. Check tightness of terminal connector
7. All fitting as per out line general
arrangement drawing
8. Leveling and alignment of structure and base
frame checked
9. Erection completion certificate along with
list of outstanding activities reviewed
10. Any paint removed / scratched in transit has
been touched up
11. Check primary polarity of CT erected as per
relevant drawing
12. Check hermetically sealing is intact
13. Check the oil level and leakage through any
joint / secondary terminals
14. Check oil drain valve is properly closed and
locked
15. Check oil level, nitrogen pressure and oil
sampling
16. Oil level in top chamber gauge glass
17. Check nitrogen pressure at Schrader valve
18. BDV of oil sample taken from tank bottom
drain valve (Only if nitrogen pressure
measured zero)
19. All the cable identification tags provided and
all cores are provided identification ferrules
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 13 of 65

at MB
20. Check secondary cable end box is properly
fixed and ensure cable entry at the bottom
and unused holes sealed.
21. Ensure interpose cabling is completed and
check the continuity
22.. Check the IR value of secondary cables
23. Check external cabling from junction box to
relay / control panel completed
24. Ensure unused secondary cores, if any, has
been shorted
25. Check star point has been formed properly
and grounded at one end only
26. Check spark gap setting in P1 terminal
27. Check permanent pole labelling and
identification marking made

ANNEXURE – III
Insulation Resistance Measurement test
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 14 of 65

Primary to Earth/ Secondary

Core Phase

R- Phase Y- Phase B-Phase

Primary – Core – I

Primary – Core – II

Primary – Core – III


Primary – Core – IV

Primary – Core – V

Primary – Earth

Primary – Tan Delta Point

ANNEXURE – IV
Insulation Resistance Measurement test
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 15 of 65

Secondary to Earth
Permissible value for 1kV is 1Mohm.
Phase
Core
R- Phase Y- Phase B-Phase

Secondary Core I - Earth

Secondary Core II - Earth

Secondary Core III - Earth

Secondary Core IV - Earth


Secondary Core V - Earth

ANNEXURE – V
Insulation Resistance Measurement test
Between Secondary Cores
Permissible value for 400 kV > 400 M Ω and for 220 kV > 220 M Ω

Core Phase
R- Phase Y- Phase B-Phase
Core I- Core II
Core I – Core III
Core I – Core IV
Core I – Core V
Core II – Core III
Core II – Core IV
Core II – Core V
Core III – Core IV
Core III – Core IV
Core IV – Core V

ANNEXURE – VI
Continuity Test
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 16 of 65

Core Between Phase


Terminal R- Phase Y- Phase B-Phase

1S1 – 1S2
Core I

1S1 – 1S3

1S1 – 1S4

2S1 – 2S2
Core II

2S1 – 2S3

2S1 – 2S4

3S1 – 3S2
Core III

3S1 – 3S3

3S1 – 3S4

4S1 – 4S2
Core IV

4S1 – 4S3

4S1 – 4S4

5S1 – 5S2
Core V

5S1 – 5S3

5S1 – 5S4

ANNEXURE – VII
Secondary Winding Resistance Test
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 17 of 65

Secondary winding resistance (In Ohms):

Core Terminal R- Phase Y- Phase B- Phase


Factory Site Factory Site Factory Site

1S1 – 1S2
Core I
1S1 – 1S3

1S1 – 1S4

2S1 – 2S2
Core II
2S1 – 2S3

2S1 – 2S4

3S1 – 3S2
Core III
3S1 – 3S3

3S1 – 3S4

4S1 – 4S2
Core IV
4S1 – 4S3

4S1 – 4S4

5S1 – 5S2
Core V
5S1 – 5S3

5S1 – 5S4

ANNEXURE – VIII
Polarity Test
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 18 of 65

Polarity Test: (With 1.5 Volt DC supply)


Connect + ve at P1 and –ve at P2
Core Between Phase
R-Phase Y-Phase B-Phase

1S1 (+ve) 1S2 (-ve)

Core I 1S1 (+ve) 1S3 (-ve)

1S1 (+ve) 1S4 (-ve)

2S1 (+ve) 2S2 (-ve)

Core II 2S1 (+ve) 2S3 (-ve)

2S1 (+ve) 2S4 (-ve)

3S1 (+ve) 3S2 (-ve)

Core III 3S1 (+ve) 3S3 (-ve)

3S1 (+ve) 3S4 (-ve)

4S1 (+ve) 4S2 (-ve)

Core IV 4S1 (+ve) 4S3 (-ve)

4S1 (+ve) 4S4 (-ve)

5S1 (+ve) 5S2 (-ve)

Core V 5S1 (+ve) 5S3 (-ve)

5S1 (+ve) 5S4 (-ve)

ANNEXURE – IX
Tan Delta & Capacitance Test
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 19 of 65

A.

Capacitance (Measured Value)


Y-Phase B-Phase
Voltage R -Phase Remarks
Site Factory Site Factory Site Factory

5 kV

10 kV

B.
Remarks
Voltage Tan Delta (Measured Value)
Y-Phase B-Phase
R -Phase
Site Factory Site Factory Site Factory

5 kV

10 kV

ANNEXURE – X
Primary Injection Test
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 20 of 65

CORE PRIMARY CURRENT SECONDARY THEORETICAL ACTUAL % OF


S1 - S2 % ACTUAL CURRENT RATIO RATIO ERROR
CORE I 20%

(1S1 - 1S2) 40%

60%

80%

CORE II 20%

(2S1 - 2S2) 40%

60%

80%

CORE III 20%

(3S1 - 3S2) 40%

60%

80%

CORE IV 20%

(4S1 - 4S2) 40%

60%

80%

CORE V 20%

(5S1 - 5S2) 40%

60%

80%

CORE I 20%

(1S1 - 1S3) 40%

60%

80%

CORE II 20%

(2S1 - 2S3) 40%

60%

80%

CORE III 20%

(3S1 - 3S3) 40%

60%

80%
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 21 of 65

CORE IV 20%

(4S1 - 4S3) 40%

60%

80%

CORE V 20%

(5S1 - 5S3) 40%

60%

80%

CORE I 20%

(1S1-1S4) 40%

60%

80%

CORE II 20%

(2S1 - 2S4) 40%

60%

80%

CORE III 20%

(3S1 - 3S4) 40%

60%

80%

CORE IV 20%

(4S1 - 4S4) 40%

60%

80%

CORE V 20%

(5S1 - 5S4) 40%

60%

80%

ANNEXURE – XI
Magnetizing Current Characteristic (Knee Point Voltage) Test
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 22 of 65

R – Phase
Voltage Current Measurement
To be applied Actual Value Core - I Core II Core IV Core V
1S1 – 1S2 2S1 – 2S2 4S1 – 4S2 5S1 – 5S2
0.25 X KVp
0.50 X KVp
0.75 X KVp
1.00 X KVp
1.10 X KVp

Y- Phase
Voltage Current Measurement
To be applied Actual Value Core - I Core II Core IV Core V
1S1 – 1S2 2S1 – 2S2 4S1 – 4S2 5S1 – 5S2
0.25 X KVp
0.50 X KVp
0.75 X KVp
1.00 X KVp
1.10 X KVp

B-Phase
Voltage Current Measurement
To be applied Actual Value Core - I Core II Core IV Core V
1S1 – 1S2 2S1 – 2S2 4S1 – 4S2 5S1 – 5S2
0.25 X KVp
0.50 X KVp
0.75 X KVp
1.00 X KVp
1.10 X KVp

ANNEXURE – XII
Contact Resistance Measurement (For Connectors) Test
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 23 of 65

Contact Resistance R-Phase Y-Phase B-Phase


Micro
Across terminal P1 Ω
Micro
Across terminal P2 Ω
The value of contact resistance should not be more than 5 micro Ω per joint per connector

ANNEXURE – XIII
Secondary Injection Test

Core Terminal R- Phase Y- Phase B- Phase


Current Current Current Current Current Current
Injected Measured Injected Measured Injected Measured

1S1 – 1S2
Core I
1S1 – 1S3

1S1 – 1S4

2S1 – 2S2
Core II
2S1 – 2S3

2S1 – 2S4

3S1 – 3S2
Core III
3S1 – 3S3

3S1 – 3S4

4S1 – 4S2
Core IV
4S1 – 4S3

4S1 – 4S4
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 24 of 65

5S1 – 5S2
Core V

5S1 – 5S3

5S1 – 5S4

ANNEXURE – XIV
Calibration Status Table
TEST INSTRUMENT DETAILS:
Sr no Instrument description Range Calibration status
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 25 of 65

PRE COMMISSIONING TEST PROCEDURE FOR VOLTAGE TRANSFORMERS

1.0 SCOPE
This procedure covers the Pre commissioning Test for Voltage Transformers

2.0 PURPOSE
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 26 of 65

This procedure is prepared to carry out various pre- commissioning tests to be conducted in
systematic manner for Voltage Transformers to ensure the healthiness and performance of
the equipment.

3.0 PRE-REQUISITES
SYSTEM REQUIREMENTS
1. Relevant Drawings and layouts.
2. 415 V AC, 3 Ph power supply is available for Testing.
3. All Cables pertaining to Voltage transformers were laid & terminated.
4. Make sure that the equipment erected is as per approved drawings & Layouts.
5. Check the Name Plate & Rating Plate Of the equipment Erected.

4.0 REQUIREMENTS OF TESTING KITS


S.No Test Kit Range
1 Tan Delta Test Kit with test leads 0 – 12kV
2 High voltage test kit with test leads 0-10kV (AIS)
3 Variac with test leads 0 -230V
4 Contact Resistance Kit with test leads 0-2000 milliohm

5.0 REQUIREMENT OF TESTING INSTRUMENTS


1. Digital Multi meter.
2. 500 V, 5000 V Insulation Tester
3. Polarity Tester.
4. 3 Ph- A.C Supply Extension Board with MCB Protection.

6.0 HAZARDS AND PRECAUTIONS


1. Unauthorized persons should not be allowed to enter Testing Area.
2. Barricade the Testing Area With Warning Tape
3. There should not be any temporary (hooking of supply) arrangement for Testing. Proper A.C
Supply extension board should be used
4. Ensure protection MCB is provided in the circuit of AC supply used for testing
5. Ensure Proper Tools & Tackles are Available for carrying out Tests.
6. Ensure Proper PPE ( Personal Protective Equipments) are used
7. Ensure the Healthiness of the test leads (Check for any insulation Damages).
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 27 of 65

8. Competent Authority to maintain shutdown & Work permit system in existing Live Bay works.
9. Any conducting element should be carried horizontally at waist level in the area used for pre-
commissioning tests.

7.0 POST INSTALLATION CHECKS


Post installation checks should be done according to the annexure enclosed.

8.0 TESTS TO BE CONDUCTED


1. Insulation Resistance measurement Test.
2. Continuity Test
3. Secondary Winding Resistance Test.
4. Polarity Test.
5. Tan Delta & Capacitance Test.
6. Ratio Test
7. Contact Resistance Measurement Test for Connectors.
8. Secondary Injection / Annunciation Test.
8.1 INSULATION RESISTANCE MEASUREMENT TEST
Aim :
To ensure the insulation healthiness of the primary and secondary windings by measuring the
insulation resistance value.
Equipment Required:
o Insulation Tester.
o Test leads.
Test Procedure:
The Above test to be conducted at following points
e) Primary to Earth
f) Primary to Secondary
g) Secondary to Earth
h) Between Secondary Cores
Note: a) Remove the connected earthing to system involving CVT/PT under test
b) Disconnect the connected terminals of CVT/PT M. Box.
c) Permissible values for 400 kV > 400 MΩ and for 220 kV > 200 MΩ
a. Primary to earth
1) Connect the line terminal of the Meggar(5000V) to either P1 (or) P2 of the Voltage
Transformers
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 28 of 65

2) Connect the Earth terminal of the Meggar to the earth stud provided at the equipment
3) Switch on the Meggar
4) Take down the readings (It should be in Mega Ohms).

b. Primary to Secondary
1. Connect the line terminal of the Meggar(5000V) to either P1 (or) P2 of the Voltage
transformers
2. Connect the Earth terminal of the Meggar to the a (or) n of the Voltage transformers
3. Switch on the Meggar
4. Take down the readings( It should be in Mega Ohms)

c. Secondary to Earth
1. Connect the line terminal of the Meggar(500V) to either a (or) n of the Voltage transformers
2. Connect the Earth terminal of the Meggar to the earth stud provided at the equipment
3. Switch on the Meggar
4. Take down the readings( It should be in Mega Ohms)

d. Between Secondary cores


1. Connect the line terminal of the Meggar(500V) to either a (or) n of one core of the Voltage
transformers
2. Connect the Earth terminal of the Meggar(500V) to either a (or) n of the other cores of the
Voltage transformers
3. Switch on the Meggar
4. Take down the readings( It should be in Mega Ohm
Test Format For the above test are enclosed in Annexure –III, IV & V

Fig 1: Insulation Resistance Measurement

8.2 CONTINUITY TEST


Aim:
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 29 of 65

This test is done in order to ensure that the flow of power is not interrupted in between due
to damages. This test assures that the flow of power is continuous.
Equipments Required:
o Multimeter.
o Test Leads.
Test Procedure:
a) Select the Multi meter in continuity Mode.
b) Connect the Multi meter across the secondary terminals of various cores.
c) Check for the ‘Beep’ sound
Test Format For the above test is enclosed in Annexure –VI.

8.3 SECONDARY WINDING RESISTANCE TEST


Aim:
This test is mainly done in order to calculate the winding resistance value and compare it with
the factory test report and approve if the values are found satisfactory.
Equipments Required:
o Multimeter.
o Test Leads.
Test Procedure:
a) Select the Multi meter in Resistance Mode.
b) Connect the Multi meter across the secondary terminals of various cores.
c) Note down the readings
d) Compare the test results with Factory Test Report (If available)
Test Format For the above test is enclosed in Annexure –VII.
8.4 POLARITY TEST
Aim:
To find the polarity of the terminals. This ensures that the terminals are marked with correct
polarity as manufactured.
Equipments Required:
o Battery supply.
o Multimeter.
o Test Leads.
Test Procedure:
i) Connect battery + Ve to S2 (Secondary) Terminal of CVT/PT
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 30 of 65

ii) Connect battery - Ve to S1 (Secondary) Terminal of CVT/PT

iii) Connect Multi meter (Analog) + Ve to ‘P1’ (Primary) Terminal of CVT/PT

iv) Connect Multi meter (Analog) - Ve to ‘P2’ (Primary) Terminal of CVT/PT

v) Momentarily apply the D.C Voltage across the Secondary terminals of CVT

If the meter deflects forward then the polarity is O.K.


Test Format For the above test are enclosed in Annexure – VIII

Fig 2: Polarity Test

8.5 TAN DELTA & CAPACITANCE TEST


Aim:
To calculate the value of capacitance and tangent delta angle and find the values to be
satisfactory in comparison with the factory test reports.
Equipments Required:
o Tandelta test kit.
o Trolley.
o Test Leads.
Test Procedure:
a) Connect the kit across the test terminals provided in the equipment for Tan Delta
Measurement.
b) Initially apply 2 KV and note down the readings
c) Then apply 10 KV and note down the readings
d) Compare with the test results obtained at the manufacturer test report (If Available)
Test Format For the above test are enclosed in Annexure –IX
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 31 of 65

Fig 3: Tan Delta Test Setup

8.6 RATIO TEST


Aim:
To calculate the value of the turns ratio and compare it with the name plate details and
approve it, if the values are found to be satisfactory.
Equipments Required:
o Ratio test kit.
o Test Leads.
Test Procedure:
a) Connect the Ratio Test kit across the primary terminals (P1, P2)
b) Apply 2000V (For220 KV), 4000V (For 400 KV)
c) Note down the corresponding Secondary Voltage at various cores.
d) Compare the ratio with Factory Test Reports (If available)

Fig 4 : Ratio Test


Test Format For the above test are enclosed in Annexure-X

8.7 CONTACT RESISTANCE MEASUREMENT TEST FOR CONNECTORS


Aim:
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 32 of 65

To calculate the value of the contact resistances and compare it with the factory test report
and find the values to be in acceptable limits.
Equipments Required:
o Micro ohm meter.
o Test Leads.
Test Procedure:
a) Connect the Micro Ohm Meter leads on the connectors of CVT/PT primary terminals
b) Switch ‘ON’ the test kit & apply the current up to 100Amps
c) Take Down the Readings.
d) It should be in Micro Ohms
Test Format For the above test is enclosed in Annexure – XI.

8.8 SECONDARY INJECTION TEST


Aim:
To find that the continuity of supply from the secondary to the load end do not very much in
order to ensure that the protection and metering is done accurately.
Equipments Required:
o Single phase variac.
o Test Leads.
o Multimeter.
Test Procedure:
a) Connect the Variac across the secondary terminals
b) Apply 110V A.C Supply.
c) Measure the Voltage across the protective relay point & Metering point in the C & R panel
(or)
In BCU.
d) Remove the Fuses and check for the annunciations.

Fig 5 : Secondary Injection Test


Test Format For the above test are enclosed in Annexure – XII.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 33 of 65

ANNEXURE – I

DATA OF EQUIPMENT (Rating Plate)

Make :

Type: :

Sl. No. : R-Phase: Y-Phase: B-Phase:

Year of manufacture: R-Phase: Y-Phase: B-Phase:

Feeder /Bay Name :

V. Rated data and duty:

Core Ratio Class Burden Protection / Metering

Winding I

Winding II

Winding III

ANNEXURE – II
Post Installation check list

S. No. Description Status Remarks, Record


Yes No discrepancies, if any
1. Equipment is cleaned and free from dust / dirt,
foreign materials etc.
2. Equipment is free from all visible defects on
physical inspection
3. Check CVT/PT tank has been provided with
double earthing
4. Check that CVT/PT junction box is earthed
5. All nuts and bolts are tightened correctly as per
specified torque
6. Check tightness of terminal connector
7. All fitting as per out line general arrangement
drawing
8. Leveling and alignment of structure and base
frame checked
9. Labelling and identification marking is carried out

10. Erection completion certificate along with list of


outstanding activities reviewed
11. Any paint removed / scratched in transit has been
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 34 of 65

touched up
12. Sl. No. of HV capacitor identical to the Sl. No.
mentioned on rating plate
13. Ensure brass vent plug between stacks of CVT is
removed.
14. Check the oil level and leakage through any joints
/ terminals
15. Check oil drain valve is properly closed and
locked
16. Oil level in top chamber gauge glass
17. BDV of oil sample taken from tank bottom drain
valve
18. Check secondary cable end box is properly fixed
and ensure cable entry at the bottom.
19. Ensure HF terminal of unused phases has been
earthed and no load on HF terminal bushing.
20. Check rating / healthiness of fuses at CVT MB and
CVT terminal box.
21. Check rating / healthiness of fuses at CVT MB and
CVT terminal box.
22. Check that the neutral point is earthed.
23. Check the IR value of secondary cables> 1M Ω for
outdoor cables and>10 M Ω for indoor cables.
24. Check external cabling from junction box to relay /
control panel completed
25. All the cable identification tags provided and all
cores are provided with identification ferrules at
MB

ANNEXURE – III

Insulation Resistance Measurement test

Primary to Earth/ Secondary

Core Phase
R- Phase Y- Phase B-Phase

Primary – Core – I MΩ

Primary – Core – II MΩ

Primary – Core – III MΩ

Primary – Earth MΩ
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 35 of 65

ANNEXURE – IV

Insulation Resistance Measurement test


Secondary to Earth

Permissible value for 1kV is 1 M Ω

Phase
Core
R- Phase Y- Phase B-Phase

Secondary Core I - Earth

Secondary Core II - Earth

Secondary Core III - Earth

ANNEXURE – V

Insulation Resistance Measurement test

Between Secondary Cores

Permissible value for 400 kV > 400 M Ω and for 220 kV > 220 M Ω

Core Phase
R- Phase Y- Phase B-Phase

Core I- Core II

Core I – Core III

Core II – Core III

ANNEXURE – VI

Continuity Test

Core Between Phase


Terminal R- Phase Y- Phase B-Phase
Core I 1a – 1n
Core II 2a – 2n
Core III 3a – 3n
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 36 of 65

ANNEXURE – VII

Secondary Winding Resistance Test

Secondary winding resistance (In Ohms):

Core Terminal R- Phase Y- Phase B- Phase


Factory Site Factory Site Factory Site

Core I 1a – 1n

Core II 2a – 2n

Core III 3a – 3n

ANNEXURE – VIII

Polarity Test

Polarity Test: (With 1.5 Volt DC supply)

Connect + ve at P1 and –ve at P2

Core Between Phase


R-Phase Y-Phase B-Phase

Core I 1a (+ve) 1n (-ve)

Core II 2a (+ve) 2n (-ve)

Core III 3a (+ve) 3n (-ve)


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 37 of 65

ANNEXURE – IX
Tan Delta & Capacitance Test

Capacitance (Measured Value)


Y-Phase B-Phase
Voltage Across R -Phase Remarks
Site Factory Site Factory Site Factory

2 KV C1
10KV C1
2 KV C2
10KV C2
2 KV C3
10KV C3
2 KV C1+C2+C3
10KV C1+C2+C3

B.

Tan Delta(Measured Value)


Y-Phase B-Phase
Voltage Across R -Phase Remarks
Site Factory Site Factory Site Factory

2 KV C1
10KV C1
2 KV C2
10KV C2
2 KV C3
10KV C3
2 KV C1+C2+C3
10KV C1+C2+C3

ANNEXURE – X
Ratio Test

Phas e Primary Se condary Voltage The ore tical Actual ratio % Error
Voltage Be twe e n Value ratio Factory Site
R 1a-1n
R 2a-2n
R 3a-3n
Y 1a-1n
Y 2a-2n
Y 3a-3n
B 1a-1n
B 2a-2n
B 3a-3n
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 38 of 65

ANNEXURE – XI
Contact Resistance Measurement (For Connectors) Test

Contact Resistance R-Phase Y-Phase B-Phase


Micro
Across terminal P1 Ω

The value of contact resistance should not be more than 5 micro Ω per joint per connector

ANNEXURE – XII
Secondary Injection Test

S.No. Description of the Source of initiation Window Result Remarks


test Description OK / Not
OK
A Remove all the fuse Apply 110 v AC through
in R, Y, B Phase in 3 Phase variac in the
CVT secondary CVT secondary circuit
junction box towards C & R Panels
(i) Remove R – Phase CR Panel CVT Fuse CVT Fuse failure
fuse in the control
panel
(ii) Remove Y – Phase CR Panel CVT Fuse CVT Fuse failure
fuse in the control
panel
(iii) Remove B – Phase CR Panel CVT Fuse CVT Fuse failure
fuse in the control
panel

ANNEXURE – XIII
Calibration Status Table
TEST INSTRUMENT DETAILS:
Sr no Instrument description Range Calibration status
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 39 of 65

PRE COMMISSIONING TEST PROCEDURE FOR TRANSFORMERS

1.0 SCOPE
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 40 of 65

This procedure covers the Pre commissioning Test for Transformers.

2.0 PURPOSE
This procedure is prepared to carry out various pre- commissioning tests to be conducted in
systematic manner for Transformers to ensure the healthiness and performance of the
equipment.

3.0 PRE-REQUISITES
3.1 SYSTEM REQUIREMENTS
1. Relevant Drawings and layouts.
2. 415 V AC, 3 Ph power supply is available for Testing.
3. All Cables pertaining to Transformers were laid & terminated.
4. Make sure that the equipment erected is as per approved drawings & Layouts.
5. Check the Name Plate & Rating Plate of the equipment Erected.

4.0 REQUIREMENTS OF TESTING KITS


S.No Testing Kit Range
1 Tan Delta Test kit with test leads 0-12kV
2 Primary injection test kit with test leads 0 – 2000A
3 High voltage transformer with test leads 0 -5kV
4 Contact resistance test kit with test leads 0 – 2000milliohm
5 Secondary injection test kit with test leads 0 -100A
6 Transformer winding resistance kit with test leads 0 – 100milliohm
7 Transformer ratio kit with test leads 0 – 2000 turns
8 Sweep frequency analyzer kit with test leads 1kHz – 1MHz (-90dB min)

5.0 REQUIREMENT OF TESTING INSTRUMENTS


1. Digital Multi meter.
2. 500 V, 5000 V Insulation Tester
3. Polarity Tester.
4. Clamp Meters (200mA – 2000A)
5. 3 Ph- A.C Supply Extension Board with MCB Protection.

6.0 HAZARDS AND PRECAUTIONS:


1. Unauthorized persons should not be allowed to enter Testing Area.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 41 of 65

2. Barricade the Testing Area With Warning Tape


3. There should not be any temporary (hooking of supply) arrangement for Testing. Proper A.C
Supply extension board should be used
4. Ensure protection MCB is provided in the circuit of AC supply used for testing
5. Ensure Proper Tools & Tackles are Available for carrying out Tests.
6. Ensure Proper PPE ( Personal Protective Equipments) are used
7. Ensure the Healthiness of the test leads (Check for any insulation Damages).
8. Competent Authority to maintain shutdown & Work permit system in existing Live Bay works.
9. Any conducting element should be carried horizontally at waist level in the area used for pre-
commissioning tests.

7.0 POST INSTALLATION CHECKS


Post installation checks should be done according to the annexure enclosed.

8.0 TESTS TO BE CONDUCTED


1. Polarization Index Test (Insulation Resistance measurement Test).
2. Core Insulation Test.
3. Magnetic Balance Test.
4. Floating Neutral Point Test
5. Winding Resistance Test.
6. Turns Ratio Test.
7. Tan Delta & Capacitance Test for Bushings & Windings.
8. Vector Group Test.
9. Magnetizing Current Measurement.
10. Short Circuit Impedance measurement Test.
11. Sweep Frequency Analysis Test.(ONLY FOR 220kV AND ABOVE)
12. Pre-Commissioning Test on Bushing CT’s.
13. Contact Resistance Measurement Test for Connectors.
14. Operational Checks on OLTC.
15. Operational Checks on Protection System.

8.1 POLARIZATION INDEX TEST (INSULATION RESISTANCE MEASUREMENT TEST)


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 42 of 65

Aim:
To find the value of insulation resistance and ensure that the insulation resistance value is
within the acceptable limit.
Equipments Required:
o Insulation Tester.
o Test leads.
Test Procedure:
The Polarization Index is nothing but the Ratio of Insulation Resistance Measured at 10 Minutes
to the 1 Minute. The above test is to be conducted at following points.
a) Windings of Transformer to Earth.
b) Between HV and LV winding.
a. Windings to earth
1) Connect the line terminal of the Meggar (5000V) to winding (s) of the Transformer.
2) Connect the Earth terminal of the Meggar to the earth stud provided at the equipment.
3) Switch on the Meggar.
4) Take down the readings (It should be in Mega Ohms).

b. Between Windings
1) Connect the line terminal of the Meggar (5000V) to one winding of the Transformer.
2) Connect the Earth terminal of the Meggar to the other winding of Transformer
3) Switch on the Meggar.
4) Take down the readings (It should be in Mega Ohms).

Fig 1: Insulation Resistance Measurement Setup

Test Format For the above test are enclosed in Annexure –III

8.2 CORE INSULATION TEST


Aim:
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 43 of 65

To ensure that the insulation resistance value between the core and tank is in acceptable
limits.
Equipments Required:
Insulation Tester.
Test leads.
Test Procedure:
a) Apply 2 KV D.C between Core and Frame/Tank. Take down the IR value.
b) Apply 2 KV D.C between Frame and Core/Tank. Take down the IR value.
Test Format For the above test are enclosed in Annexure –IV

8.3 MAGNETIC BALANCE TEST


Aim:
To ensure that the transformer is balanced magnetically so that there is no net flow of
unbalance current under normal operation.
Equipments Required:
o Multimeter.
o Test leads.
Test Procedure:
a) Keep The Tap in Normal Position.
b) Apply single phase A.C supply across one phase of the windings.
c) Measure the Voltage on the other two phases of the winding.
d) Measure the Voltage on the voltage induced on the other windings.

Fig 2 : Magnetic Balance Test


Test Format For the above test are enclosed in Annexure – V

8.4 FLOATING NEUTRAL POINT TEST.


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 44 of 65

Aim:
To ensure that the voltages when applied to the winding are always balanced and there is
only negligible voltage at neutral.
Equipments Required:
o Multimeter.
o Test Leads.
Test Procedure:
a) Remove the Ground/Earth connection From Neutral Point of Transformer.
b) Apply three Phase A.C Supply across HV windings / IV windings.
c) Measure the voltage between Neutral and Ground. It should be Zero (or) Very Negligible.
Test Format For the above test are enclosed in Annexure – VI

8.5 WINDING RESISTANCE TEST


Aim:
To find the value of the winding resistance and ensure that the values are similar to the
factory test reports.
Equipments Required:
o Transformer winding resistance meter.
o Test leads.
Test Procedure:
a) Connect the kit across the one phase of the HV windings. Measure the resistance.
b) Then connect the kit across the other phase of HV windings. Measure the resistance.
c) Repeat the test for all taps provided in the transformer.
d) Connect the Kit across one Phase of the IV Windings. (only for autotransformer)
e) Connect the kit across the other phases of the IV windings.
F) Repeat the Test for LV Windings also.
Compare with the test results obtained at the manufacturer test report (If Available)
Test Format For the above test are enclosed in Annexure – VII

8.6 TURNS RATIO TEST


Aim:
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 45 of 65

To calculate the value of the turn’s ratio and compare it with the factory test reports and
ensure the correctness of the values obtained.
Equipments Required:
o Transformer turns ratio meter.
o Test leads.
Test Procedure:
a) Connect the ratio kit across the HV and IV winding of the transformer at 1 st Tap.
b) Measure the turn’s ratio obtained.
c) Repeat the test at all Taps.
d) Repeat the Test between HV and LV windings also.
Compare the results obtained with actual ratios.

Fig 3: Turns Ratio Test


Test Format For the above test are enclosed in Annexure – VIII

8.7 CAPACITANCE & TAN DELATA TEST ON BUSHINGS & WINDINGS.


Aim:
To measure the capacitance and tan delta value and ensure that the values are within the
acceptable limits.
Equipments Required:
o Tan delta Test Kit
o Test Leads.
Test Procedure:
Bushings
a) Short all the bushings together. Remove earth connection from Neutral.
b) Connect HV Lead to the one bushing of Transformer & LV lead to the Test tap provided
in the bushings. This Value will be recorded as C1.
c) Connect the HV lead to the Test tap of Bushing and LV lead to the Ground. This will be
recorded as C2.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 46 of 65

Windings
a) Connect the HV & LV test lead of the kit across the windings in one phase.
b) Repeat the test for other phases of the windings.
c) Repeat the test between windings & Earth.

Fig 4: Tan Delta Measurement


Test Format For the above test are enclosed in Annexure – IX

8.8 VECTOR GROUP TEST


Aim:
To ensure that the windings in the transformer are of same vector group as that mentioned
in the name plate.

Equipments Required:
o Multimeter.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 47 of 65

o Test leads.
Test Procedure:
This test is to confirm the Vector group of Transformer. This more crucial in sub-station where
transformers are paralleled together.
The vector group test for Yd11 Transformer (Widely used in all sub-stations)

1B1 – N > 3B1 -N


1Y1 –N > 3Y1 –N

1R1 –N = 3R1 -N
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 48 of 65

Fig 5: Vector Group Representation


Test Format For the above test are enclosed in Annexure – X

8.9 MAGNETIZING CURRENT TEST


Aim:
To calculate the value of the magnetizing current flow in each phase and compare the value with
the factory results.
Equipments Required:
o Milliammeter.
o Test leads.
Test Procedure:
a) Apply single phase 5KV (or) 10 KV across one phase of the HV winding. Take down Magnetizing
current.
b) Repeat the test for other phases of the HV windings & other (IV & LV) windings of the
transformers.
c) The readings to be similar for all the phases of the windings.
Test Format For the above test are enclosed in Annexure – XI

8.10 SHORT CIRCUIT IMPEDENCE TEST


Aim:
To ensure that the percentage impedance given in the factory test report is similar to that
measured value.
Equipments Required:
o Multimeter.
o Clamp meter.
o Test leads.
Test Procedure:
a) Apply Single Phase voltage across one phase of HV windings. Short the IV side winding of
that phase. Measure the Current at IV side. Note down the voltage applied.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 49 of 65

b) Apply Single Phase voltage across one phase of IV windings. Short the LV side winding of
that phase. Measure the Current at LV side. Note down the voltage applied.
c) Apply Single Phase voltage across one phase of HV windings. Short the LV side winding of
that phase. Measure the Current at LV side. Note down the voltage applied.
This Test should be done at Nominal Tap, Minimum & Maximum Tap positions

The test format for the above test are enclosed in Annexure - XII

8.11 SWEEP FREQUENCY RESPONSE ANALYSIS TEST


Aim:
Frequency response analysis (FRA) is conducted to assess the mechanical integrity of the
transformer which may get disturbed due to transportation shocks or short circuit forces experienced in
service. FRA signatures will be taken after assembly and oil filling and compared with factory testing’s to
ensure the healthiness of core/coil assembly during transportation. These signatures will be benchmark
for future reference. The FRA signatures should be analyzed in conjunction with impact recorder
readings. Report of impact recorder readings is to be obtained from manufacturer.
Equipments Required:
o SFRA Test kit.
o Test leads.
Test Procedure:
It is recommended to follow the standard procedure for the SFRA measurement as per
the Table-1. It should be done on maximum, normal and minimum tap.

Table-1
TEST TYPE TEST 3 – PHASE 1-PHASE
Test 1 H! – X1
Series winding (OC)
Test 2 H2 – X2 H1-X1
All other terminals floating
Test 3 H3 –X3
Test 4 X1 – H0X0
Common winding (OC)
Test 5 X2 – H0X0 X1 – H0X0
All other terminals floating
Test 6 X3 – H0X0
Test 7 Y1 – Y3
Tertiary winding (OC) Y1 – Y2
Test 8 Y2 – Y1
All other terminals floating (Y1 – Y0)
Test 9 Y3 – Y2
Short circuit (SC) Test 10 H1-H0X0
H1-H0X0
High (H) to Low (L) Test 11 H2-H0X0
Short (X1-H0X0)
Short (X1-X2-X3) Test 12 H3-H0X0
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 50 of 65

Short Circuit (SC) Test 13 H1-H0X0


H1-H0X0
High (H) to Tertiary (Y) Test 14 H2-H0X0
Short (Y1-Y2)
Short (Y1-Y2-Y3) Test 15 H3-H0X0
Short Circuit (SC) Test 16 X1-H0X0
X1-H0X0
Low (L) to Tertiary (Y) Test 17 X2-H0X0
Short (Y1-Y2)
Short (Y1-Y2-Y3) Test 18 X3-H0X0

8.12 TESTS ON OIL SAMPLE

Dissolved gas analysis (DGA) is a powerful diagnostic tool to detect any incipient fault
developing inside the oil-filled equipment. The oil sample is to be taken after oil filling (before
commissioning) as a benchmark and there after 24hrs of charging, 7 days, 15 days, one month
and three months after charging to monitor the gas build up if any. The oil samples are to be sent
to CIOTL/IOTL/STL for DGA and first two samples for oil parameter testing also.

The test format for the above test are enclosed in Annexure - XIII

8.13 OPERATIONAL CHECKS ON PROTECTION SYSTEM

a. Operational checks on breathers ( Conventional Silcagel or Drycol as supplied with the


transformers)
b. Visual check of MOG of Main Conservator.
c. Marshalling box & kiosk checks.
d. Valve operational checks.
1. Checks in cooling fans-rotation, speed & control (Manual/temp/load) setting checks.
2. Checks on cooling pumps-rotation, vibration/noise, oil flow direction.
e. Checks on temperature gauges (OTI/WTI-calibration and cooler control, alarm & trip setting
tests).
f. Checks on gas actuated (SPRs/PRDs/Buchholz) relays – Operational checks by simulation as well
as shorting the respective contacts as applicable.
g. Checks on tightness of terminal connectors – micro-ohm measurement of each connection.
h. Checks on transformer/Reactor protection (differential, REF, Over-current & stability tests etc.)

8.14 OPERATIONAL CHECKS ON OLTC

Following checks should be carried out during pre-commissioning:


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 51 of 65

Before applying voltage to the transformer, the mechanical operation of tap changer and motor
drive for step by step operation to be checked as follows:
a) Manual operation: The tap changer has to be run manually by the hand crank through the total
operating cycle. In each operating position, the position indicators of motor drive and tap
changer (On TC head) show the same position.
b) Motor drive for step by step tap changing operation: Push button to be kept pressed till the
motor stops i.e. driving motor should be automatically switched off when the tap changer has
performed one switching operation.

(Note: At the time of change over selector operation (i.e. 9b to 10 & vice-versa), higher
torque is required. Tap changer end position should be checked that the same is not overrun to
avoid any failure during operation. Same can be seen through the inspection glass in the tap
changer head cover.
With the tap-changer fully assembled on the transformer the following sequence of
operations shall be performed:
a) With the transformer un-energized, one complete cycles of operations (a cycle of operation
goes from one end of the tapping range to the other, and bach again). Check continuity of
winding during this test. Ensure that the voltmeter does not deflect to Zero.
b) With the transformer un-energized, and with the auxiliary voltage reduced to 85% of its
rated valve, one complete cycle of operation.
c) With the transformer energized at rated voltage and frequency at no load, one complete
cycle of operation.

The following additional check points/guide lines for OLTC is recommended in consultation
with OLTC manufacturer to ensure the absence of problems and proper operation:
a) Function of control switches.
b) OLTC stopping on position.
c) Fastener tightness.
d) Signs of moisture such as rusting, oxidation or free standing water and leakages.
e) Mechanical clearances as specified by manufacturer’s instruction booklet.
f) Operation and condition of tap selector, changeover selector and arcing transfer switches.
g) Drive mechanism operation.
h) Counter operation, position indicator operation and its co-ordination with mechanism and tap
selector positions.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 52 of 65

i) Limit switch operation.


j) Mechanical block integrity.
k) Proper operation of hand-crank and its interlock switch.
l) Physical condition of tap selector.
m) Freedom of movement of external shaft assembly.
n) Extent of arc erosion on stationary and moveable arcing contacts.
o) Inspect barrier board for tracking and cracking.
p) After filling with oil, manually crank throughout entire range.
q) Oil BDV and moisture content (PPM) to be measured and recorded (Min BDV should be 60kV
and moisture content should be less than 10 PPM).

The test format for the above test are enclosed in Annexure - XIV

ANNEXURE – I
DETAILS OF EQUIPMENT

Make :

Type:

Rating :

SL No :

Voltage Ratio :

Cooling Type :

Type of Neutral Grounding :

Year of Manufacture :

Oil Quantity :

Quantity of Main Tank :


Quantity of Radiator :

Oil Make &Type :


Specify oil type inhibited/uninhibited/standard

ANNEXURE – II
Post Installation check list

S. No. Description Status Remarks, Record


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 53 of 65

Yes No discrepancies, if any


1. ICT and its auxiliaries are free from visible
defects on physical inspection.
2. All fittings as per out line general arrangement
drawings.
3. Check main tank has been provided with double
earthing.
4. Check neutral is grounded through separate
connections. Ensure metallic requirements as per
specification (e.g. Cu.) in earthing strips used.
5. Check that marshaling box, T/C driving gear,
diverter, radiator bank pump & fan motor ETC
has been earthed.
6. All nuts and bolts are tightened correctly as per
specified torque (as per manufactures
recommendation).
7. Check tightness of terminal connectors.
8. Check leveling of transformer and its accessories.
9. Erection completion certificate along with list of
outstanding activities reviewed.
10. Any paint removed/scratched in transit has been
touched up.
11. Bushings are clean and free from physical
damages.
12. Oil level is correct on all bushings.
13. Check hermetically sealing is intact in all
bushings.
14. Check oil leakage through any joints/valves etc.
15. Check oil drain valves are properly closed and
locked.
16. Check oil level in MAIN/OLTC conservator tank.
17. Check oil level at conservator matches with oil
temperature of transformer.
18. Check gear box oil level in OLTC.
19. Check OTI and WTI pockets and replenish the
oil, if required.
21. Check the color of breather silica gel (blue when
dry).
22.. Check availability of oil in the breather cup.
23. Check all rollers are locked and tack welded with
rails (wherever applicable).
24. Check bushings test tap is grounded.
25. Check no debris, loose T & P and oil strains on
and around the transformer.
26. Check that pressure relief valve is correctly
mounted.
27. Check that pressure relief valve is correctly
mounted.
28. Ensure unused secondary cores of bushing CT’s,
if any, has been shorted.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 54 of 65

29. Check star point has been formed properly and


grounded at one end only as per scheme.
30. Check that permanent and adequate lighting
arrangements are ready.
31. Check that labeling and identification is
permanent and satisfactory.
32. Check that bushels relay is correctly mounted
with arrow pointing towards conservator.
33. Check cables are properly fixed and ensure cable
entry at the bottom.
34. Ensure all power and control cable terminals are
tightened.
35. Check all cables and ferrules are provided with
number as per cable schedule (cross feruling to be
checked).
36. Check that all cables are correctly glanded.
37. Check external cabling from junction box to
relay/control panel completed.
38. Check that air has been released from the
radiators and their HEADERS/OLTC
BUCHHOLZ RELAY/MAIN
TANK/TANK/BUSHING TURRETS ETC.
39. Check fire protection system & emulsifier system
is adequate & ready.
40. Check that CC-CL&G are shorted.
41. Check that all radiator bank valves on top and
bottom headers are open.
42. Change over operation of AC supply from
source-I to source-II checked.
43. Check the flanges of bushings & OLTC for any
crack after fixing

ANNEXURE – III
Insulation Resistance Measurement: Using _____________ Megger

Make: Range: Sl.No: Calib due date:


IR Value
Main Winding Temperature
15 Sec 60 Sec 600 Sec PI
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 55 of 65

HV/E + LV
IV/E+HV+LV
LV/E+HV+IV
HV/LV

IV/LV

HV/LV

ANNEXURE – IV
Core Insulation test

APPLY 1.0 KV DC BETWEEN CL & CC+G

INSULATION VALUE
BETWEEN CC-G
BETWEEN CL-G
BETWEEN CC-CL

RECOMMENDED VALUE > 10 Mohm

ANNEXURE – V
Magnetic Balance Test
(Using Equipment Details)
Equipment: Make: Range: Sl.No: Calib due date:

HV Side at Normal Tap

Applied Voltage Measured Voltage


1R-N 1Y-N 1B-N 1R-N 1Y-N 1B-N

IV Side at Normal Tap (only for autotransformer)

Applied Voltage Measured Voltage


2R-N 2Y-N 2B-N 2R-N 2Y-N 2B-N

LV Side at Normal Tap

Applied Voltage Measured Voltage


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 56 of 65

3R-N 3Y-N 3B-N 3R-N 3Y-N 3B-N

ANNEXURE – VI
FLOATING NEUTRAL VOLTAGE MEASUREMENT

Note: Disconnect the transformer neutral from the ground. Apply 3 Phase 415 Volts to the high voltage
winding and make the measurement in the IV winding with respect to neutral point to ground.

PRIMARY VOLTAGE IV VOLTAGE REMARKS, IF


TAP
WINDING APPLIED WINDING MEASURED ANY

Apply 3 Phase 415Volts to the intermediate voltage winding and make the measurement in the tertiary
winding with respect to neutral and neutral point to ground.

PRIMARY VOLTAGE IV VOLTAGE REMARKS, IF


TAP
WINDING APPLIED WINDING MEASURED ANY

ANNEXURE – VII
MEASURMENT OF WINDING RESISTANCE (IN OHM)
Testing Instrument details : _______________________________
Testing Equipment Calibration Valid or not : _______________________________
Ambient temperature at the time of test : _______________________________
Temperature of oil : _______________________________
WTI reading : _______________________________

Winding Resistance (HV-N)


Tap Resistance 75 deg C Factory Value
Remarks
Position
1R1-2R1 1Y1- 1B1-2B1 R Y B R Y B
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 57 of 65

2Y1
1
2
3
4
5
6
7
8
9b
10
11
12
13
14
15
16
17
Reverse order
Tap No
Tap No
Tap No
Tap No
Tap No
Tap No
Factory Test Report Ref No: ________________________________
B INTERMEDIATE VOLTAGE SIDE
Between Resistance Resistance at 75 deg C
Remark
Winding Site Value Factory Site
2R1-N
2Y1-N
2B1-N

C LOW VOLTAGE SIDE


Between Resistance Resistance at 75 deg C
Remark
Winding Site Value Factory Site
3R1-3B1
3Y1-3R1
3B1-3Y1

NOTE: LV winding resistance at factory measured without formation of delta. However measurements
carried out at site are after formation of delta. Hence a correction factor of 1.5 times to be applied in site
results.

ANNEXURE – VIII
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 58 of 65

VOLTAGE RATIO TEST

Testing Instrument Details : ___________________________________


Testing Equipment Calibration Valid or not : ___________________________________
Ambient temperature at the time of test : ___________________________________
Temperature at the time of test : ___________________________________

a) RATIO : HV/IV

Tap Voltage Applied Voltage Measures Ratio Factory ratio


Position 1R-N 1Y-N 1B-N 2R-N 2Y-N 2B-N R Y B R Y B

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16

REVERSE SIDE:

Tap
Voltage Applied Voltage Measures Ratio Factory ratio
Position
Tap Posi

Tap Posi
Tap Posi

Tap Posi

Remarks if any: ___________________________________________________________

b) Ratio: HV/LV

Tap Voltage Applied Voltage Measures Ratio Factory ratio


Position 1R-N 1Y-N 1B-N 3R-3Y 3Y-3B 3R-3B R Y B R Y B
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 59 of 65

Lowest

Normal
Highest

Remarks if any: ___________________________________________________________

c) Ratio: IV/LV (only for autotransformer)

Tap Voltage Applied Voltage Measures Ratio Factory ratio


Position 2R-N 2Y-N 2B-N 3R-3Y 3Y-3B 3R-3B R Y B R Y B

Remarks if any: ___________________________________________________________

ANNEXURE – IX
TAN DELTA & CAPACITANCE MEASUREMENT OF BUSHING

Testing Instrument details : _________________________________


Testing Equipment calibration valid or not : _________________________________
Ambient temperature at the time of test : _________________________________
Temperature of Oil : _________________________________

a) High Voltage Side


Capacitance (Measured Value) Remarks
Voltage R Phase Y Phase B Phase
Site Factory Site Factory Site Factory
Measurement of C1 Capacitance
2 kV
10kV
Measurement of C2 Capacitance
1kV

Tan Delta (Measured Value) Remarks


Voltage R Phase Y Phase B Phase
Site Factory Site Factory Site Factory
Measurement of C1 Capacitance
2 kV
10kV
Measurement of C2 Capacitance
1kV
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 60 of 65

b) Intermediate Voltage Side


Capacitance (Measured Value) Remarks
Voltage R Phase Y Phase B Phase
Site Factory Site Factory Site Factory
Measurement of C1 Capacitance
2 kV
10kV
Measurement of C2 Capacitance
1kV

Tan Delta (Measured Value) Remarks


Voltage R Phase Y Phase B Phase
Site Factory Site Factory Site Factory
Measurement of C1 Capacitance
2 kV
10kV
Measurement of C2 Capacitance
1kV

c) Low Voltage Side

Capacitance (Measured Value) Remarks


Voltage R Phase Y Phase B Phase
Site Factory Site Factory Site Factory
Measurement of C1 Capacitance
2 kV
10kV
Measurement of C2 Capacitance
1kV

Tan Delta (Measured Value) Remarks


Voltage R Phase Y Phase B Phase
Site Factory Site Factory Site Factory
Measurement of C1 Capacitance
2 kV
10kV
Measurement of C2 Capacitance
1kV

Factory Test Report Ref No: _________________________________


** Note: C2 Values shall be only for record purpose.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 61 of 65

ANNEXURE – X
VECTOR GROUP TEST & POLARITY CHECKING

Connect neutral point with earth.


Join 1R1 & 3R1 terminals.
-Apply 415V, 3-Phase supply to HV terminals.

Terminals Voltage Measured Remarks

ANNEXURE – XI
MAGNETISATION CURRENT TEST

Testing Instrument details : _________________________________


Testing Equipment calibration valid or not : _________________________________
Ambient temperature at the time of test : _________________________________
Temperature of Oil : _________________________________

a) Apply 1-Phase AC Supply on HV terminals and keep IV & LV Open

Tap Position Voltage Applied Current Measured Remarks


R-N V R-Ph m AMP
Lowest ( ) Y-N V Y-Ph m AMP
B-N V B-Ph m AMP
R-N V R-Ph m AMP
Normal ( ) Y-N V Y-Ph m AMP
B-N V B-Ph m AMP
R-N V R-Ph m AMP
Highest( )
Y-N V Y-Ph m AMP
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 62 of 65

B-N V B-Ph m AMP

b) Apply 1-Phase AC Supply on IV terminals and keep HV & LV Open

Tap Position Voltage Applied Current measured ( in LV side)


Between volts
2R-N Volts R – PH m AMP
Normal ( )
2Y-N Volts Y – PH m AMP
2B-N Volts B – PH m AMP

ANNEXURE – XII
SHORT CIRCUIT IMPEDANCE TEST
Testing Instrument details : _________________________________
Testing Equipment calibration valid or not : _________________________________
Ambient temperature at the time of test : _________________________________
Temperature of Oil : _________________________________

a. MV to LV
Tap 1U1 ( R ) 1V1 ( Y ) 1W1 ( B )
Number (IV of R Ph & N shorted, LV (IV of Y Ph & N shorted, (IV of B Ph & N shorted,
Open) LV Open) LV Open)
Voltage Current Voltage Current Voltage Current

b. IV to LV
Supply Short all 3 LV bushing, Short all 3 LV bushing, Short all 3 LV bushing, HV
HV open HV open open

c. HV to LV
Tap No: ______

Supply Short all 3 LV bushing, IV Short all 3 LV bushing, IV Short all 3 LV bushing, IV
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 63 of 65

open open open

Tap No: ______

Supply Short all 3 LV bushing, IV Short all 3 LV bushing, IV Short all 3 LV bushing, IV
open open open

ANNEXURE – XIII
DISSOLVE GAS ANALYSIS

Oil Sample Schedule


Dissolve Just 15 days 01 month 03 months
24 Hrs after 7 days after
Gases before after after after
charging charging
charging charging charging charging
Total Gas
(%)
H2
CH4
C2H4
C2H6
C2H2
CO
CO2
O2
N2

ANNEXURE – XIV
TEST ON OLTC

Status Remarks
S. No Description
OK NOT OK
1 Visual inspection of equipment
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 64 of 65

Manual operation on all taps (local) with


2 confirmation of the No. of revolutions and
locking at extreme taps.
3 Over load device of driving motor.
4 Local operation (Electrical)
5 Remote operation (Electrical)
6 Tap position indicator
Check operation with master follower
7
scheme (parallel operation)
8 Out of step relay.
9 Step by step relay
10 Limit switch
11 Winding resistance at all taps
Continuity test of winding during one
12
complete cycle of operation

ANNEXURE – XV
OPERATIONAL TEST ON OTHER
EQUIPMENTS OK NOT OK
i) Rotation direction of Pumps

ii) Rotation direction of Fans OK NOT OK

Eqpmt Setting Valve Pickup Valve Single Phasing Prevention


Fan no Check
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Pump
No
1
2
3
4
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING MANUAL Page 65 of 65

ANNEXURE – XVI
OIL CHARACTERISTICS

MOISTURE TAN DELTA RESISTIVITY INTERFACIAL


OIL B.D.V
(MAX) (MAX) 90 (MIN) OHM- TENSION AT 27 REMARKS
SAMPLE (MIN) KV
PPM deg C CM deg (MIN) N/m

ANNEXURE – XVII

Calibration Status Table


TEST INSTRUMENT DETAILS:
Sr Instrument description Range Calibration status
no