T&C Manual
T&C Manual
1.0 SCOPE
This procedure covers the Pre commissioning Test for current Transformers and the test
report format covers CT’s which is having 5 cores on its secondary.
2.0 PURPOSE
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
This procedure is prepared to carry out various pre- commissioning tests to be conducted in
systematic manner for Current Transformers to ensure the healthiness of the equipment.
3.0 PRE-REQUISITES
SYSTEM REQUIREMENTS
1. Relevant Drawings and layouts.
2. 415 V AC, 3 Ph power supply is available for Testing.
3. All Cables pertaining to current transformers were laid & terminated.
4. Make sure that the equipment erected is as per approved drawings & Layouts.
5. Check the Name Plate & Rating Plate Of the equipment Erected.
5. Ensure Proper Tools & Tackles are Available for carrying out Tests.
6. Ensure Proper PPE ( Personal Protective Equipments) are used
7. Ensure the Healthiness of the test leads (Check for any insulation Damages).
8. Competent Authority to maintain shutdown & Work permit system in existing Live Bay
works.
9. Any conducting element should be carried horizontally at waist level in the area used for
pre-commissioning tests.
a. Primary to earth
1) Connect the line terminal of the Meggar (5000V) to either P1 (or) P2 of the Current
Transformers
2) Connect the Earth terminal of the Meggar to the earth stud provided at the equipment
3) Switch on the Meggar
4) Take down the readings (It should be in Mega Ohms).
b. Primary to Secondary
1) Connect the line terminal of the Meggar(5000V) to either P1 (or) P2 of the Current
transformers
2) Connect the Earth terminal of the Meggar to the S1 (or) S2 of the Current transformers
3) Switch on the Meggar
c. Secondary to Earth
1) Connect the line terminal of the Meggar(500V) to either S1 (or) S2 of the Current
transformers
2) Connect the Earth terminal of the Meggar to the earth stud provided at the equipment
3) Switch on the Meggar.
d) Compare the test results with Factory Test Report (If available)
Test Format For the above test are enclosed in Annexure –VII
Aim:
To check for the correct sequence of polarity on the primary and secondary side of the
current transformer. (For eg. When P1 is positive w.r.t. P2, then S1 also must be positive w.r.t S2,
according to the scheme requirement).
Equipments Required:
The equipments required for polarity tests are as follows,
i) Battery of suitable rating or Polarity tester.
ii) Analog Multimeter / Galvanometer.
iii) Connecting leads.
Test Procedure:
Test Format For the above test are enclosed in Annexure – VIII
Equipments Required:
The equipments required for carrying out Tan Delta Capacitance test are as follows,
i) Tan Delta Test Kit.
ii) Connecting cables.
Test Procedure:
Note: When the CT’s are provided with taps then the measurement of capacitance can be done
between the tests taps, else the capacitance should be measured from one terminal to grounded
terminal. (As per the connections shown in the diagram).
a) Connect the kit across the test terminals provided in the equipment for Tan Delta
Measurement.
b) Initially apply 2 KV and note down the readings
c) Then apply 10 KV and note down the readings
d) Compare with the test results obtained at the manufacturer test report (If Available)
For CT’s With Test Taps:
To check the ratio of the primary turns to the secondary turns and compare it with the given
rated values.
Equipments Required:
The equipments required for primary injection test or ratio test are as follows,
i) Primary injection test kit / Loading Transformer.
ii) Clamp Meter.
iii) Connecting cables.
Test Procedure:
a) Connect the Primary injection kit across the primary terminals (P1, P2)
b) Initially apply 20% of rated current
c) Then Raise the current to 40%, 60% and 80%
d) Note down the corresponding Secondary current at various cores.
e) Repeat the test for all the ratios mentioned in the rating plate
ANNEXURE – I
DATA OF EQUIPMENT (Rating Plate)
Make :
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
Type: :
Winding I
Winding II
Winding III
Winding IV
Winding V
ANNEXURE – II
Post Installation check list
S. No. Description Status Remarks, Record
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
at MB
20. Check secondary cable end box is properly
fixed and ensure cable entry at the bottom
and unused holes sealed.
21. Ensure interpose cabling is completed and
check the continuity
22.. Check the IR value of secondary cables
23. Check external cabling from junction box to
relay / control panel completed
24. Ensure unused secondary cores, if any, has
been shorted
25. Check star point has been formed properly
and grounded at one end only
26. Check spark gap setting in P1 terminal
27. Check permanent pole labelling and
identification marking made
ANNEXURE – III
Insulation Resistance Measurement test
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
Core Phase
Primary – Core – I
MΩ
Primary – Core – II
MΩ
Primary – Core – IV
MΩ
Primary – Core – V
Primary – Earth
ANNEXURE – IV
Insulation Resistance Measurement test
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
Secondary to Earth
Permissible value for 1kV is 1Mohm.
Phase
Core
R- Phase Y- Phase B-Phase
ANNEXURE – V
Insulation Resistance Measurement test
Between Secondary Cores
Permissible value for 400 kV > 400 M Ω and for 220 kV > 220 M Ω
Core Phase
R- Phase Y- Phase B-Phase
Core I- Core II
Core I – Core III
Core I – Core IV
Core I – Core V
Core II – Core III
Core II – Core IV
Core II – Core V
Core III – Core IV
Core III – Core IV
Core IV – Core V
ANNEXURE – VI
Continuity Test
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
1S1 – 1S2
Core I
1S1 – 1S3
1S1 – 1S4
2S1 – 2S2
Core II
2S1 – 2S3
2S1 – 2S4
3S1 – 3S2
Core III
3S1 – 3S3
3S1 – 3S4
4S1 – 4S2
Core IV
4S1 – 4S3
4S1 – 4S4
5S1 – 5S2
Core V
5S1 – 5S3
5S1 – 5S4
ANNEXURE – VII
Secondary Winding Resistance Test
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
1S1 – 1S2
Core I
1S1 – 1S3
1S1 – 1S4
2S1 – 2S2
Core II
2S1 – 2S3
2S1 – 2S4
3S1 – 3S2
Core III
3S1 – 3S3
3S1 – 3S4
4S1 – 4S2
Core IV
4S1 – 4S3
4S1 – 4S4
5S1 – 5S2
Core V
5S1 – 5S3
5S1 – 5S4
ANNEXURE – VIII
Polarity Test
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
ANNEXURE – IX
Tan Delta & Capacitance Test
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
A.
5 kV
10 kV
B.
Remarks
Voltage Tan Delta (Measured Value)
Y-Phase B-Phase
R -Phase
Site Factory Site Factory Site Factory
5 kV
10 kV
ANNEXURE – X
Primary Injection Test
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
60%
80%
CORE II 20%
60%
80%
60%
80%
CORE IV 20%
60%
80%
CORE V 20%
60%
80%
CORE I 20%
60%
80%
CORE II 20%
60%
80%
60%
80%
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
CORE IV 20%
60%
80%
CORE V 20%
60%
80%
CORE I 20%
(1S1-1S4) 40%
60%
80%
CORE II 20%
60%
80%
60%
80%
CORE IV 20%
60%
80%
CORE V 20%
60%
80%
ANNEXURE – XI
Magnetizing Current Characteristic (Knee Point Voltage) Test
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
R – Phase
Voltage Current Measurement
To be applied Actual Value Core - I Core II Core IV Core V
1S1 – 1S2 2S1 – 2S2 4S1 – 4S2 5S1 – 5S2
0.25 X KVp
0.50 X KVp
0.75 X KVp
1.00 X KVp
1.10 X KVp
Y- Phase
Voltage Current Measurement
To be applied Actual Value Core - I Core II Core IV Core V
1S1 – 1S2 2S1 – 2S2 4S1 – 4S2 5S1 – 5S2
0.25 X KVp
0.50 X KVp
0.75 X KVp
1.00 X KVp
1.10 X KVp
B-Phase
Voltage Current Measurement
To be applied Actual Value Core - I Core II Core IV Core V
1S1 – 1S2 2S1 – 2S2 4S1 – 4S2 5S1 – 5S2
0.25 X KVp
0.50 X KVp
0.75 X KVp
1.00 X KVp
1.10 X KVp
ANNEXURE – XII
Contact Resistance Measurement (For Connectors) Test
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
ANNEXURE – XIII
Secondary Injection Test
1S1 – 1S2
Core I
1S1 – 1S3
1S1 – 1S4
2S1 – 2S2
Core II
2S1 – 2S3
2S1 – 2S4
3S1 – 3S2
Core III
3S1 – 3S3
3S1 – 3S4
4S1 – 4S2
Core IV
4S1 – 4S3
4S1 – 4S4
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
5S1 – 5S2
Core V
5S1 – 5S3
5S1 – 5S4
ANNEXURE – XIV
Calibration Status Table
TEST INSTRUMENT DETAILS:
Sr no Instrument description Range Calibration status
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
1.0 SCOPE
This procedure covers the Pre commissioning Test for Voltage Transformers
2.0 PURPOSE
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
This procedure is prepared to carry out various pre- commissioning tests to be conducted in
systematic manner for Voltage Transformers to ensure the healthiness and performance of
the equipment.
3.0 PRE-REQUISITES
SYSTEM REQUIREMENTS
1. Relevant Drawings and layouts.
2. 415 V AC, 3 Ph power supply is available for Testing.
3. All Cables pertaining to Voltage transformers were laid & terminated.
4. Make sure that the equipment erected is as per approved drawings & Layouts.
5. Check the Name Plate & Rating Plate Of the equipment Erected.
8. Competent Authority to maintain shutdown & Work permit system in existing Live Bay works.
9. Any conducting element should be carried horizontally at waist level in the area used for pre-
commissioning tests.
2) Connect the Earth terminal of the Meggar to the earth stud provided at the equipment
3) Switch on the Meggar
4) Take down the readings (It should be in Mega Ohms).
b. Primary to Secondary
1. Connect the line terminal of the Meggar(5000V) to either P1 (or) P2 of the Voltage
transformers
2. Connect the Earth terminal of the Meggar to the a (or) n of the Voltage transformers
3. Switch on the Meggar
4. Take down the readings( It should be in Mega Ohms)
c. Secondary to Earth
1. Connect the line terminal of the Meggar(500V) to either a (or) n of the Voltage transformers
2. Connect the Earth terminal of the Meggar to the earth stud provided at the equipment
3. Switch on the Meggar
4. Take down the readings( It should be in Mega Ohms)
This test is done in order to ensure that the flow of power is not interrupted in between due
to damages. This test assures that the flow of power is continuous.
Equipments Required:
o Multimeter.
o Test Leads.
Test Procedure:
a) Select the Multi meter in continuity Mode.
b) Connect the Multi meter across the secondary terminals of various cores.
c) Check for the ‘Beep’ sound
Test Format For the above test is enclosed in Annexure –VI.
v) Momentarily apply the D.C Voltage across the Secondary terminals of CVT
To calculate the value of the contact resistances and compare it with the factory test report
and find the values to be in acceptable limits.
Equipments Required:
o Micro ohm meter.
o Test Leads.
Test Procedure:
a) Connect the Micro Ohm Meter leads on the connectors of CVT/PT primary terminals
b) Switch ‘ON’ the test kit & apply the current up to 100Amps
c) Take Down the Readings.
d) It should be in Micro Ohms
Test Format For the above test is enclosed in Annexure – XI.
ANNEXURE – I
Make :
Type: :
Winding I
Winding II
Winding III
ANNEXURE – II
Post Installation check list
touched up
12. Sl. No. of HV capacitor identical to the Sl. No.
mentioned on rating plate
13. Ensure brass vent plug between stacks of CVT is
removed.
14. Check the oil level and leakage through any joints
/ terminals
15. Check oil drain valve is properly closed and
locked
16. Oil level in top chamber gauge glass
17. BDV of oil sample taken from tank bottom drain
valve
18. Check secondary cable end box is properly fixed
and ensure cable entry at the bottom.
19. Ensure HF terminal of unused phases has been
earthed and no load on HF terminal bushing.
20. Check rating / healthiness of fuses at CVT MB and
CVT terminal box.
21. Check rating / healthiness of fuses at CVT MB and
CVT terminal box.
22. Check that the neutral point is earthed.
23. Check the IR value of secondary cables> 1M Ω for
outdoor cables and>10 M Ω for indoor cables.
24. Check external cabling from junction box to relay /
control panel completed
25. All the cable identification tags provided and all
cores are provided with identification ferrules at
MB
ANNEXURE – III
Core Phase
R- Phase Y- Phase B-Phase
Primary – Core – I MΩ
Primary – Core – II MΩ
Primary – Earth MΩ
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
ANNEXURE – IV
Phase
Core
R- Phase Y- Phase B-Phase
ANNEXURE – V
Permissible value for 400 kV > 400 M Ω and for 220 kV > 220 M Ω
Core Phase
R- Phase Y- Phase B-Phase
Core I- Core II
ANNEXURE – VI
Continuity Test
ANNEXURE – VII
Core I 1a – 1n
Core II 2a – 2n
Core III 3a – 3n
ANNEXURE – VIII
Polarity Test
ANNEXURE – IX
Tan Delta & Capacitance Test
2 KV C1
10KV C1
2 KV C2
10KV C2
2 KV C3
10KV C3
2 KV C1+C2+C3
10KV C1+C2+C3
B.
2 KV C1
10KV C1
2 KV C2
10KV C2
2 KV C3
10KV C3
2 KV C1+C2+C3
10KV C1+C2+C3
ANNEXURE – X
Ratio Test
Phas e Primary Se condary Voltage The ore tical Actual ratio % Error
Voltage Be twe e n Value ratio Factory Site
R 1a-1n
R 2a-2n
R 3a-3n
Y 1a-1n
Y 2a-2n
Y 3a-3n
B 1a-1n
B 2a-2n
B 3a-3n
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
ANNEXURE – XI
Contact Resistance Measurement (For Connectors) Test
The value of contact resistance should not be more than 5 micro Ω per joint per connector
ANNEXURE – XII
Secondary Injection Test
ANNEXURE – XIII
Calibration Status Table
TEST INSTRUMENT DETAILS:
Sr no Instrument description Range Calibration status
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
1.0 SCOPE
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
2.0 PURPOSE
This procedure is prepared to carry out various pre- commissioning tests to be conducted in
systematic manner for Transformers to ensure the healthiness and performance of the
equipment.
3.0 PRE-REQUISITES
3.1 SYSTEM REQUIREMENTS
1. Relevant Drawings and layouts.
2. 415 V AC, 3 Ph power supply is available for Testing.
3. All Cables pertaining to Transformers were laid & terminated.
4. Make sure that the equipment erected is as per approved drawings & Layouts.
5. Check the Name Plate & Rating Plate of the equipment Erected.
Aim:
To find the value of insulation resistance and ensure that the insulation resistance value is
within the acceptable limit.
Equipments Required:
o Insulation Tester.
o Test leads.
Test Procedure:
The Polarization Index is nothing but the Ratio of Insulation Resistance Measured at 10 Minutes
to the 1 Minute. The above test is to be conducted at following points.
a) Windings of Transformer to Earth.
b) Between HV and LV winding.
a. Windings to earth
1) Connect the line terminal of the Meggar (5000V) to winding (s) of the Transformer.
2) Connect the Earth terminal of the Meggar to the earth stud provided at the equipment.
3) Switch on the Meggar.
4) Take down the readings (It should be in Mega Ohms).
b. Between Windings
1) Connect the line terminal of the Meggar (5000V) to one winding of the Transformer.
2) Connect the Earth terminal of the Meggar to the other winding of Transformer
3) Switch on the Meggar.
4) Take down the readings (It should be in Mega Ohms).
Test Format For the above test are enclosed in Annexure –III
To ensure that the insulation resistance value between the core and tank is in acceptable
limits.
Equipments Required:
Insulation Tester.
Test leads.
Test Procedure:
a) Apply 2 KV D.C between Core and Frame/Tank. Take down the IR value.
b) Apply 2 KV D.C between Frame and Core/Tank. Take down the IR value.
Test Format For the above test are enclosed in Annexure –IV
Aim:
To ensure that the voltages when applied to the winding are always balanced and there is
only negligible voltage at neutral.
Equipments Required:
o Multimeter.
o Test Leads.
Test Procedure:
a) Remove the Ground/Earth connection From Neutral Point of Transformer.
b) Apply three Phase A.C Supply across HV windings / IV windings.
c) Measure the voltage between Neutral and Ground. It should be Zero (or) Very Negligible.
Test Format For the above test are enclosed in Annexure – VI
To calculate the value of the turn’s ratio and compare it with the factory test reports and
ensure the correctness of the values obtained.
Equipments Required:
o Transformer turns ratio meter.
o Test leads.
Test Procedure:
a) Connect the ratio kit across the HV and IV winding of the transformer at 1 st Tap.
b) Measure the turn’s ratio obtained.
c) Repeat the test at all Taps.
d) Repeat the Test between HV and LV windings also.
Compare the results obtained with actual ratios.
Windings
a) Connect the HV & LV test lead of the kit across the windings in one phase.
b) Repeat the test for other phases of the windings.
c) Repeat the test between windings & Earth.
Equipments Required:
o Multimeter.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
o Test leads.
Test Procedure:
This test is to confirm the Vector group of Transformer. This more crucial in sub-station where
transformers are paralleled together.
The vector group test for Yd11 Transformer (Widely used in all sub-stations)
1R1 –N = 3R1 -N
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
b) Apply Single Phase voltage across one phase of IV windings. Short the LV side winding of
that phase. Measure the Current at LV side. Note down the voltage applied.
c) Apply Single Phase voltage across one phase of HV windings. Short the LV side winding of
that phase. Measure the Current at LV side. Note down the voltage applied.
This Test should be done at Nominal Tap, Minimum & Maximum Tap positions
The test format for the above test are enclosed in Annexure - XII
Table-1
TEST TYPE TEST 3 – PHASE 1-PHASE
Test 1 H! – X1
Series winding (OC)
Test 2 H2 – X2 H1-X1
All other terminals floating
Test 3 H3 –X3
Test 4 X1 – H0X0
Common winding (OC)
Test 5 X2 – H0X0 X1 – H0X0
All other terminals floating
Test 6 X3 – H0X0
Test 7 Y1 – Y3
Tertiary winding (OC) Y1 – Y2
Test 8 Y2 – Y1
All other terminals floating (Y1 – Y0)
Test 9 Y3 – Y2
Short circuit (SC) Test 10 H1-H0X0
H1-H0X0
High (H) to Low (L) Test 11 H2-H0X0
Short (X1-H0X0)
Short (X1-X2-X3) Test 12 H3-H0X0
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
Dissolved gas analysis (DGA) is a powerful diagnostic tool to detect any incipient fault
developing inside the oil-filled equipment. The oil sample is to be taken after oil filling (before
commissioning) as a benchmark and there after 24hrs of charging, 7 days, 15 days, one month
and three months after charging to monitor the gas build up if any. The oil samples are to be sent
to CIOTL/IOTL/STL for DGA and first two samples for oil parameter testing also.
The test format for the above test are enclosed in Annexure - XIII
Before applying voltage to the transformer, the mechanical operation of tap changer and motor
drive for step by step operation to be checked as follows:
a) Manual operation: The tap changer has to be run manually by the hand crank through the total
operating cycle. In each operating position, the position indicators of motor drive and tap
changer (On TC head) show the same position.
b) Motor drive for step by step tap changing operation: Push button to be kept pressed till the
motor stops i.e. driving motor should be automatically switched off when the tap changer has
performed one switching operation.
(Note: At the time of change over selector operation (i.e. 9b to 10 & vice-versa), higher
torque is required. Tap changer end position should be checked that the same is not overrun to
avoid any failure during operation. Same can be seen through the inspection glass in the tap
changer head cover.
With the tap-changer fully assembled on the transformer the following sequence of
operations shall be performed:
a) With the transformer un-energized, one complete cycles of operations (a cycle of operation
goes from one end of the tapping range to the other, and bach again). Check continuity of
winding during this test. Ensure that the voltmeter does not deflect to Zero.
b) With the transformer un-energized, and with the auxiliary voltage reduced to 85% of its
rated valve, one complete cycle of operation.
c) With the transformer energized at rated voltage and frequency at no load, one complete
cycle of operation.
The following additional check points/guide lines for OLTC is recommended in consultation
with OLTC manufacturer to ensure the absence of problems and proper operation:
a) Function of control switches.
b) OLTC stopping on position.
c) Fastener tightness.
d) Signs of moisture such as rusting, oxidation or free standing water and leakages.
e) Mechanical clearances as specified by manufacturer’s instruction booklet.
f) Operation and condition of tap selector, changeover selector and arcing transfer switches.
g) Drive mechanism operation.
h) Counter operation, position indicator operation and its co-ordination with mechanism and tap
selector positions.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
The test format for the above test are enclosed in Annexure - XIV
ANNEXURE – I
DETAILS OF EQUIPMENT
Make :
Type:
Rating :
SL No :
Voltage Ratio :
Cooling Type :
Year of Manufacture :
Oil Quantity :
ANNEXURE – II
Post Installation check list
ANNEXURE – III
Insulation Resistance Measurement: Using _____________ Megger
HV/E + LV
IV/E+HV+LV
LV/E+HV+IV
HV/LV
IV/LV
HV/LV
ANNEXURE – IV
Core Insulation test
INSULATION VALUE
BETWEEN CC-G
BETWEEN CL-G
BETWEEN CC-CL
ANNEXURE – V
Magnetic Balance Test
(Using Equipment Details)
Equipment: Make: Range: Sl.No: Calib due date:
ANNEXURE – VI
FLOATING NEUTRAL VOLTAGE MEASUREMENT
Note: Disconnect the transformer neutral from the ground. Apply 3 Phase 415 Volts to the high voltage
winding and make the measurement in the IV winding with respect to neutral point to ground.
Apply 3 Phase 415Volts to the intermediate voltage winding and make the measurement in the tertiary
winding with respect to neutral and neutral point to ground.
ANNEXURE – VII
MEASURMENT OF WINDING RESISTANCE (IN OHM)
Testing Instrument details : _______________________________
Testing Equipment Calibration Valid or not : _______________________________
Ambient temperature at the time of test : _______________________________
Temperature of oil : _______________________________
WTI reading : _______________________________
2Y1
1
2
3
4
5
6
7
8
9b
10
11
12
13
14
15
16
17
Reverse order
Tap No
Tap No
Tap No
Tap No
Tap No
Tap No
Factory Test Report Ref No: ________________________________
B INTERMEDIATE VOLTAGE SIDE
Between Resistance Resistance at 75 deg C
Remark
Winding Site Value Factory Site
2R1-N
2Y1-N
2B1-N
NOTE: LV winding resistance at factory measured without formation of delta. However measurements
carried out at site are after formation of delta. Hence a correction factor of 1.5 times to be applied in site
results.
ANNEXURE – VIII
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
a) RATIO : HV/IV
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
REVERSE SIDE:
Tap
Voltage Applied Voltage Measures Ratio Factory ratio
Position
Tap Posi
Tap Posi
Tap Posi
Tap Posi
b) Ratio: HV/LV
Lowest
Normal
Highest
ANNEXURE – IX
TAN DELTA & CAPACITANCE MEASUREMENT OF BUSHING
ANNEXURE – X
VECTOR GROUP TEST & POLARITY CHECKING
ANNEXURE – XI
MAGNETISATION CURRENT TEST
ANNEXURE – XII
SHORT CIRCUIT IMPEDANCE TEST
Testing Instrument details : _________________________________
Testing Equipment calibration valid or not : _________________________________
Ambient temperature at the time of test : _________________________________
Temperature of Oil : _________________________________
a. MV to LV
Tap 1U1 ( R ) 1V1 ( Y ) 1W1 ( B )
Number (IV of R Ph & N shorted, LV (IV of Y Ph & N shorted, (IV of B Ph & N shorted,
Open) LV Open) LV Open)
Voltage Current Voltage Current Voltage Current
b. IV to LV
Supply Short all 3 LV bushing, Short all 3 LV bushing, Short all 3 LV bushing, HV
HV open HV open open
c. HV to LV
Tap No: ______
Supply Short all 3 LV bushing, IV Short all 3 LV bushing, IV Short all 3 LV bushing, IV
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
Supply Short all 3 LV bushing, IV Short all 3 LV bushing, IV Short all 3 LV bushing, IV
open open open
ANNEXURE – XIII
DISSOLVE GAS ANALYSIS
ANNEXURE – XIV
TEST ON OLTC
Status Remarks
S. No Description
OK NOT OK
1 Visual inspection of equipment
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001
ANNEXURE – XV
OPERATIONAL TEST ON OTHER
EQUIPMENTS OK NOT OK
i) Rotation direction of Pumps
ANNEXURE – XVI
OIL CHARACTERISTICS
ANNEXURE – XVII