Manhole Achievement

The document outlines progress towards targets for completing stretches of drainage works of various sizes by June 2017, listing the target length, progress to date, number of settings remaining to complete, days left to finish, and daily distance needed to meet targets. Several targets are on track to be completed by the deadline, while others require faster daily progress to finish the remaining distance in time. The total target length is 1312 meters, with some sizes still having the full amount left to complete.

Uploaded by

RaxKit
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
112 views7 pages

Manhole Achievement

The document outlines progress towards targets for completing stretches of drainage works of various sizes by June 2017, listing the target length, progress to date, number of settings remaining to complete, days left to finish, and daily distance needed to meet targets. Several targets are on track to be completed by the deadline, while others require faster daily progress to finish the remaining distance in time. The total target length is 1312 meters, with some sizes still having the full amount left to complete.

Uploaded by

RaxKit
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 7

WARAS MEGAH BACKCHARGE

MH Timber (pcs) Steelmould Sheetpile (pcs) Per piece Unit x Price Waler Price Tot. RM/Day Status Day Total Base:
5/3 68 RM 1.50 RM 102.00 RM 58.14 RM 160.14 SSP future 365 - RM 2.50 for 12m Sheetpile/piece
5/4 97 RM 1.50 RM 145.50 RM 82.94 RM 228.44 155 RM 35,407.43 - 165% timber price from Sheetpile
5/5 68 RM 1.50 RM 102.00 RM 58.14 RM 160.14 95 RM 15,213.30
5/6 7.98 ton 95
5/7 55 RM 1.50 RM 82.50 RM 47.03 RM 129.53 126 RM 16,320.15
5/8 77 RM 1.50 RM 115.50 RM 65.84 RM 181.34 92 RM 16,682.82
5/9 58 RM 1.50 RM 87.00 RM 49.59 RM 136.59 105 RM 14,341.95
5/10 75 RM 1.50 RM 112.50 RM 64.13 RM 176.63 86 RM 15,189.75
5/11 58 RM 1.50 RM 87.00 RM 49.59 RM 136.59 126 RM 17,210.34 Prorates:
5/20 12.89 ton 13.4 tapper 143
5/21 40 RM 3.13 RM 125.20 RM 30.05 RM 155.25 I-Beam 76 timber RM 16.50
5/39 48 RM 2.50 RM 120.00 RM 28.80 RM 148.80 93 RM 13,838.40 sheetpile RM 10.00
5/40 41 RM 3.13 RM 128.33 RM 30.80 RM 159.13 75 RM 11,934.69 difference 1.65
5/45 56 RM 3.13 RM 175.28 RM 42.07 RM 217.35 Pipe Rec 52
5/46 62 RM 2.50 RM 155.00 RM 37.20 RM 192.20 168 RM 32,289.60
5/47 77 RM 3.13 RM 241.01 RM 57.84 RM 298.85 153 RM 45,724.42 waler RM 11,721.72 RM 34,721.28 RM 26,402.64 RM 41,231.52 RM 22,687.20 RM 25,153.20 RM 32,945.76
5/48 68 RM 3.13 RM 212.84 RM 51.08 RM 263.92 115 RM 30,350.98 sheetpile RM 46,872.00 RM 139,708.80 RM 103,017.60 RM 160,637.40 RM 98,532.00 RM 111,812.40 RM 145,189.80
5/49 58 RM 2.50 RM 145.00 RM 34.80 RM 179.80 11.7 pipe.rec difference 0.25 0.25 0.26 0.26 0.23 0.22 0.23
5/50 69 RM 3.13 RM 215.97 RM 51.83 RM 267.80 167 RM 44,723.07
5/54 63 RM 3.13 RM 197.19 RM 47.33 RM 244.52 176 RM 43,034.75 waler RM 16,801.68 RM 4,971.46 RM 4,142.88 RM 4,524.29
5/55 56 RM 3.13 RM 175.28 RM 42.07 RM 217.35 Pipe Rec 146 timber RM 30,045.17 RM 8,388.92 RM 7,372.08 RM 7,807.87
5/58 61 RM 3.13 RM 190.93 RM 45.82 RM 236.75 209 RM 49,481.42 difference 0.56 0.59 0.56 0.58
5/59 53 RM 3.13 RM 165.89 RM 39.81 RM 205.70 Pipe Rec 32
5/60 60 RM 3.13 RM 187.80 RM 45.07 RM 232.87 STP 62 RM 14,438.06
RM 416,181.12
TARGET JUNE 2017

TODAY REPORT :- 25-May-17 red (no changes from yesterday) blue (progressing) green (completed)

JUNE 2017
DISTANCE NEEDED
SIZE 1st Stretch 2nd Stretch 3rd Stretch TOTAL SETTING 1 SETTING 2 SETTING 3 DAYS LEFT DISTANCE LEFT PER DAY
MH12/05 MH12/04
375mm Target
73.2 73.2 8 27 73.2 2.7
Completion 0 0
MH12/03 MH12/02
375mm (2) Target
67.3 67.3 10 25 67.3 2.7
Completion 0 0
MH14/11-3 MH14/11-2 MH14/11-1 MH14/11-2
525mm Target
82.6 83.6 166.2 8 7 20 166.2 8.3
Completion 0 0 0
MH12/14 MH12/15 MH12/11 MH12/10
600mm Target
84.7 83.6 168.3 2 7 26 168.3 6.5
Completion 0 0 0
MH6/24 MH6/23 MH6/22 MH6/23
750mm Target
61.6 89.59 151.19 3 7 25 151.19 6
Completion 0 0 0
MH12/22 MH12/21
900mm(1) Target
39.3 39.3 12 23 39.3 1.7 23
Completion 0 0 67.16
MH12/20 MH12/21 MH12/20 MH12/19 67.16
900mm (2) Target
48 88 136 12 7 16 136 8.5
Completion 0 0 0
MH05/30 MH05/31 MH5/30 MH5/29
1050mm(1) Target
101.68 48.48 150.16 11 7 17 150.16 8.8
Completion 0 0 0
MH6/49 MH6/48
1050mm (2) Target
134.31 134.31 14 21 134.31 6.4
Completion 0 0
MH12/30 MH12/31 MH12/30 MH12/29
1200mm(1) Target
76.04 0 76.04 14 21 76.04 3.6
Completion 0 0 0
MH12/32 MH12/31
1200mm(2) Target
150 150 9 26 150 5.8
Completion 0 0
TARGET TOTAL 1312
COMPLETION TOTAL 0

MANHOLE TARGET JUNE 2017

TODAY REPORT :- 25-May-17 progress by WARAS progress by MH Subcon

Large Diameter Manhole Precast


Base Pipe Tappertop Make-up Piece Cast IronTop
& Concrete
Manhole Excavation Concreting Jointing Alumina 2nd Wall & Top Coal Tar Chamber Concreting Coverslab Remarks
1st Wall Haunching Concreting
Cement Slab Epoxy
MH5/20 29-Mar 29-Mar 31-Mar N/A 4-Apr 5-Apr N/A N/A 11-Apr 13-Apr Day 42 TARGET 9/5 WM to complete backfill
MH5/21 20-Apr 22-Apr 28-Apr N/A 3-May Day 22 N/A N/A TARGET I-Beam obstruction
MH5/22 5-Apr 6-Apr 11-Apr N/A 14-Apr 19-Apr N/A N/A 29-Apr 3-May Day 22 TARGET 14/5 WM to complete backfill
MH5/23 30-Mar 31-Mar 5-Apr N/A 10-Apr 18-Apr N/A N/A 20-Apr 21-Apr Day 34 TARGET 19/5 WM to cmplete backfill
MH5/34 TARGET
MH5/45 TARGET
MH5/46 Done 28-Nov Done 5-Jan 19-Jan Done 13-Feb 14-Mar 24-Feb 17-Apr Day 38 TARGET Vibro to mob-in 11/5
MH5/47 Done 30-Dec Done 10-Feb 21-Jan Done 21-Feb 18-Mar 17-Apr 21-Apr Day 34 TARGET Vibro to mob-in 13/5
MH5/48 Done 30-Dec Done 14-Jan 19-Jan Done 13-Feb 13-Mar 24-Feb 17-Apr Day 38 TARGET WM to fill crusherrun 5/5
MH5/49 Done 20-Jan TARGET Pipe Rec to Propose
MH5/50 Done 8-Mar 11-Mar 18-Mar 18-Mar 23-Mar 30-Mar 19-Apr 21-Apr 22-Apr Day 33 TARGET Vibro to mob-in 15/5
MH5/53 TARGET WM rectification cmpleted
MH5/54 9-Apr 10-Apr 15-Apr 27-Apr 27-Apr Day 28 19-May TARGET Alumina to arrive 5/5
MH5/55 Pipe rec to propose
MH5/56 28-Apr Day 27 Pipe Rec to Propose
MH5/57 Day 15 Pipe rec to start 17/5. Shtpile
MH5/58 30-Mar 31-Mar 20-Apr 25-May Day 0 formwork
MH5/59 Day 26 TARGET Pipe Rec to Propose
MH5/4-59 TARGET
MH12/8 24-Apr 25-Apr 26-Apr N/A 25-May N/A N/A 25-May 225 VCP
MH12/12 21-Apr 21-Apr 24-Apr N/A 27-Apr 4-May N/A N/A 4-May 5-May
MH12/13 TARGET N/A N/A
MH12/27 22-May N/A N/A
MH12/28 TARGET

compressor air brekaer


1 2
submerse robin
4 of 6 5

PIT TARGET JUNE 2017

TODAY REPORT :- 25-May-17

Concrete
Pit Depth Progress Sheetpiling Bracing Base Remarks

MH5/30 8.7 6.5 75% 75% TARGET steelplate driven


MH5/29 9.52 TARGET

MH6/21 6.64 TARGET


MH6/22 7.46 TARGET
MH6/23 9.3 7.5 81% 81% TARGET pending plate for caisson
MH6/49 8 2 25% 25% TARGET pend. drain diversion CBB
MH6/50 5.93 TARGET

MH12/10 4.9 TARGET


MH12/18 TARGET
MH12/19 TARGET
MH12/20 TARGET
MH12/21 TARGET
MH12/22 6.6 5 76% 76% TARGET in progress
MH12/23 6.82 TARGET piloting confirmed
MH12/32 9 7 78% 78% TARGET in progress

MH14/11 4.16 TARGET pend. Ex IL checking


MANHOLE ACHIEVEMENT APRIL 2018

TODAY REPORT :- 8-Jun-18 progress by WARAS progress by MH Subcon

Large Diameter Manhole Precast


Manhole Clearing Base Concreting Pipe Jointing Chamber Tappertop Coverslab Make-up Piece Cast Iron & Concrete Remarks Type of Pit
1st Wall Haunching Alumina 2nd Wall & Top Coal Tar Concreting Top
Cement Slab Epoxy Concreting WM Handover Memo
LINE 5
MH5/3 5-Jul 6-Jul Day 337 Timber Shoring
MH5/4 Done Done Done N/A Done Done N/A N/A Done Done Done Done Done Completed Timber Shoring
MH5/5 Done Done Done N/A Done Done N/A N/A Done Done Done Done Done Completed Timber Shoring handover 27/8/16 8/27/2016
MH5/6 Done Done Done N/A Done Done N/A N/A Done Done Done Done Done Completed Steel Caisson handover 27/8/16 8/27/2016
MH5/7 Done Done Done N/A Done Done N/A N/A Done Done Done Done Done Completed Timber Shoring handover 16/8/16 8/16/2016
MH5/8 Done Done Done N/A Done Done N/A N/A Done Done Done Done Done Completed Timber Shoring handover 24/8/16 8/24/2016
MH5/9 Done Done Done N/A Done Done N/A N/A Done Done Done Done Done Completed Timber Shoring handover 2/9/16 9/2/2016
MH5/10 Done Done Done N/A Done Done N/A N/A Done Done Done Done Done Completed Timber Shoring handover 20/9/16 9/20/2016
MH5/11 Done 23-Feb Done N/A Done 2-Mar N/A N/A 28-Feb 9-Mar 31-Mar 31-Mar 31-Mar Completed Timber Shoring handover 1/10/16 10/1/2016
MH5/12 Done 15-Feb Done N/A Done 20-Feb N/A N/A 4-Mar 9-Mar 31-Mar 31-Mar 31-Mar Completed Steel Caisson
MH5/15 Done 13-Mar 14-Mar N/A 17-Mar 20-Mar N/A N/A 22-Mar 23-Mar 29-Apr 29-Apr 29-Apr Completed Steel Caisson
MH5/20 29-Mar 29-Mar 31-Mar N/A 4-Apr 5-Apr N/A N/A 11-Apr 13-Apr 27-Jul 27-Jul 27-Jul Completed Steel Caisson handover 2/11/16 11/2/2016
MH5/21 20-Apr 22-Apr 28-Apr N/A 3-May 4-May N/A N/A Day 400 I-Beam obstruction Sheetpile
MH5/22 5-Apr 6-Apr 11-Apr N/A 14-Apr 19-Apr N/A N/A 29-Apr 3-May 27-Jul 27-Jul 27-Jul Completed Sheetpile handover 6/4/17 4/6/2017
MH5/23 30-Mar 31-Mar 5-Apr N/A 10-Apr 18-Apr N/A N/A 20-Apr 21-Apr 27-Jul 27-Jul 27-Jul Completed Concrete Caisson handover 6/4/17 4/6/2017
MH5/31 Steel Caisson
MH5/32 19-Jul 20-Jul Day 323 pipe jointing. Pipe ready Concrete Caisson
MH5/34 11-Jul 12-Jul 19-Jul Day 324 1st wall Concrete Caisson
MH5/35 Sheetpile handover 28/03/18 3/28/2018
MH5/36 Concrete Caisson handover 03/05/18 5/3/2018
MH5/38 Sheetpile handover 3/5/2018 5/3/2018
MH5/39 Done Done Done 14-Feb 14-Feb Done 4-Mar 18-Mar 29-Mar 30-Mar 27-Apr 27-Apr Done Completed Sheetpile handover 9/11/16 11/9/2016
MH5/40 Done Done Done 10-Feb 10-Feb Done 1-Mar 16-Mar 29-Mar 30-Mar 27-Apr 27-Apr Done Completed Sheetpile handover 28/11/16 11/28/2016
MH5/41 3-May 6-May 7-May 7-Jun 7-Jun 8-Jun Day 0 rebar base done Sheetpile handover 25/01/18 1/25/2018
MH5/42 12-Jan Day 147 Pipe rectification Sheetpile handover 25/01/18 1/25/2018
MH5/44 prepare discharge outlet Concrete Caisson
MH5/45 Sheetpile handover 6/4/17 4/6/2017
MH5/46 Done 28-Nov Done 5-Jan 19-Jan Done 13-Feb 14-Mar 24-Feb 17-Apr 18-Jul 18-Jul 18-Jul Completed Sheetpile
MH5/47 Done 30-Dec Done 10-Feb 21-Jan Done 21-Feb 18-Mar 17-Apr 21-Apr 7-Sep 7-Sep 7-Sep Completed Sheetpile
MH5/48 Done 30-Dec Done 14-Jan 19-Jan Done 13-Feb 13-Mar 24-Feb 17-Apr 18-Jul 18-Jul 18-Jul Completed Sheetpile handover 20/9/16 9/20/2016
MH5/49 Done 20-Jan Day 504 pipe jointing Sheetpile handover 20/9/2016 9/20/2016
MH5/50 Done 8-Mar 11-Mar 18-Mar 18-Mar 23-Mar 30-Mar 19-Apr 21-Apr 22-Apr 18-Jul 18-Jul 18-Jul Completed Sheetpile handover 6/10/16 10/6/2016
MH5/53 Done SSP level check Sheetpile handover 20/2/2017 2/20/2017
MH5/54 9-Apr 10-Apr 15-Apr 27-Apr 27-Apr 7-May 19-May 2-Jun 6-Sep 7-Sep Day 274 sheetpile Backfill completed Sheetpile handover 28/12/16 12/28/2016
MH5/55 Pipe Rec to Propose Sheetpile handover 28/12/16 12/28/2016
MH5/56 20-Apr Day 49 Sheetpile handover 24/4/2018 4/24/2018
MH5/57 Pipe rec pending Sheetpile
MH5/58 30-Mar 31-Mar 20-Apr 25-May 25-May 7-Oct Day 244 Sheetpile handover 25/11/16 11/25/2016
MH5/59 Sheetpile handover 6/5/17 & 3/5/2 4/26/2018
MH5/4-59 10-Aug 11-Aug Day 301 Concrete Caisson
LINE 6
MH6/17 17-Apr 18-Apr 19-Apr N/A 20-Apr 21-Apr N/A N/A 21-Apr 21-Apr Day 48 Pend Backfilling Concrete Caisson handover 28/03/18 3/28/2018
MH6/18 6-Apr 9-Apr 10-Apr N/A 12-Apr 13-Apr N/A N/A 13-Apr 13-Apr 20-Apr 20-Apr 20-Apr Completed Concrete Caisson handover 8/3/18 & 28/3 3/28/2018
MH6/21 17-Mar 24-Mar 26-Mar N/A 28-Mar 29-Mar N/A N/A 29-Mar 30-Mar 4-Apr 4-Apr 4-Apr Completed Sheetpile handover 8/3/18 3/8/2018
MH6/22 23-Sep 30-Sep 20-Oct N/A 25-Oct 26-Mar N/A N/A 28-Mar 28-Mar 30-Mar 30-Mar 30-Mar Pend Backfilling Steel Caisson
MH6/23 23-Sep Day 258 cut only N/A N/A N/A MOS pipe jointing Concrete Caisson *handover 17/8/17 8/17/2017
MH6/24 23-Sep 26-Sep 13-Oct N/A 16-Nov 27-Mar N/A N/A 7-Apr 7-Apr 9-Apr 9-Apr 9-Apr Pend Backfilling Concrete Caisson *handover 17/8/17 8/17/2017
MH6/26 Concrete Caisson handover 01/06/18 6/1/2018
MH6/33 N/A N/A N/A Concrete Caisson handover 01/06/18 6/1/2018
MH6/34 N/A N/A N/A Concrete Caisson handover 1/6/18 6/1/2018
MH6/35 N/A N/A N/A Concrete Caisson handover 25/01/18 1/25/2018
MH6/36 2-May 3-May 5-May N/A 7-May 8-May N/A N/A 8-May 8-May Day 31 Concrete Caisson handover 25/01/18 1/25/2018
MH6/38 16-Aug 14-May 15-May N/A 18-May 18-May N/A N/A 19-May 19-May Day 20 Concrete Caisson
MH6/39 Concrete Caisson handover 25/01/18 1/25/2018
MH6/41 Concrete Caisson
MH6/42 Concrete Caisson
MH6/43 Concrete Caisson handover 25/01/18 1/25/2018
MH6/44 Concrete Caisson handover 25/01/18 1/25/2018
MH6/44a 20-Feb 23-Feb NA NA Day 105 *Shifting PBA pipe/NPS pump Concrete Caisson *Temporary works for road opening
probleum
MH6/45 Sheetpile handover 25/01/18 1/25/2018
MH6/47 Concrete Caisson
MH6/48 Concrete Caisson handover 9/4/18 4/9/2018
MH6/49 Sheetpile handover 25/1/18 & 9/4 4/9/2018
MH6/50 Sheetpile handover 8/3/18 3/8/2018
MH6/51 Sheetpile handover 8/3/18 3/8/2018
MH6/52 Sheetpile handover 7/6/18
MH6/53-1 NA NA NA Concrete Caisson handover 24/4/18 4/24/2018
MH6/53-2 9-Mar 12-Mar 9-Apr N/A 11-Apr 12-Apr N/A N/A 12-Apr 12-Apr 23-Apr 23-Apr 23-Apr Completed Concrete Caisson handover 25/01/18 1/25/2018
MH6/53-3 NA NA NA Concrete Caisson handover 8/3/18 3/8/2018
MH6/53-4 13-Mar 15-Mar 15-Apr N/A 17-Apr 18-Apr N/A N/A 18-Apr 18-Apr 23-Apr 23-Apr 23-Apr Completed Concrete Caisson handover 8/3/18 3/8/2018
MH6/53-5 20-Dec 23-Apr 25-Apr N/A 26-Apr 27-Apr N/A N/A 28-Apr 28-Apr Day 41 Concrete Caisson
MH6/53-6 Concrete Caisson handover 1/6/18 6/1/2018
MH6/53-6-1 Concrete Caisson handover 01/06/2018 6/1/2018
MH6/53-6-2 Concrete Caisson handover 7/6/18
LINE 12
MH12/2 12-Nov 13-Nov N/A N/A 15-Nov 16-Nov N/A N/A Day 204 pipe backdrop installation Precast Caisson
MH12/3 24-Oct 26-Oct 31-Oct N/A 2-Nov 3-Nov N/A N/A 9-Nov 13-Nov 22-Nov 22-Nov 22-Nov Completed Precast Caisson
MH12/4 21-Nov 22-Nov 24-Nov N/A 24-Nov 25-Nov N/A N/A 30-Nov 11-Dec 23-Dec 23-Dec 23-Dec Completed Precast Caisson
MH12/5 24-Nov 24-Nov 27-Nov N/A 28-Nov 29-Nov N/A N/A 1-Dec 1-Dec 6-Dec 6-Dec 6-Dec Completed Precast Caisson *NCR
MH12/6 30-Nov 30-Nov 1-Dec N/A 2-Dec 4-Dec N/A N/A 6-Dec 22-Dec 23-Dec 23-Dec 23-Dec Completed Precast Caisson
MH12/7 6-Dec 7-Dec 9-Dec N/A 11-Dec 12-Dec N/A N/A 13-Dec 13-Dec 21-Dec 21-Dec 21-Dec Completed Concrete Caisson
MH12/8 24-Apr 25-Apr 26-Apr N/A 25-May 26-May N/A N/A 6-Jun 7-Jun Day 366 pipe backdrop installation Concrete Caisson
MH12/9 22-Aug 22-Aug 14-Dec N/A 15-Dec 16-Dec N/A N/A 21-Dec 21-Dec 8-Jan 8-Jan 8-Jan Completed Concrete Caisson *handover 17/8/17 8/17/2017
MH12/10 10-Aug 11-Aug Day 301 N/A N/A N/A will proceed works *SSP new flow- Concrete Caisson
in *handover 17/8/17 8/17/2017
MH12/11 31-Jul 1-Aug 20-Dec N/A 21-Dec 22-Dec N/A N/A 23-Dec 23-Dec 3-Jan 3-Jan 3-Jan Completed Concrete Caisson *handover 17/8/17 8/17/2017
MH12/12 21-Apr 21-Apr 24-Apr N/A 27-Apr 4-May N/A N/A 4-May 5-May 22-Aug 22-Aug 22-Aug Completed Concrete Caisson
MH12/13 12-Jun 15-Jun 19-Jun N/A 2-Aug 3-Aug N/A N/A 3-Aug 4-Aug 22-Aug 22-Aug 22-Aug Completed Concrete Caisson make good finishing level
MH12/14 26-Jul 27-Jul 30-Jul N/A 31-Jul 1-Aug N/A N/A 2-Aug 3-Aug 22-Aug 22-Aug 22-Aug Completed Concrete Caisson
MH12/15-4 Concrete Caisson handover 7/6/2018
MH12/15-5 23-May 24-May 25-May N/A 26-May 28-May N/A N/A 30-May 30-May 30-May 2-Jun 2-Jun Pend Backfilling Concrete Caisson handover 16/5/2018 5/16/2018
MH12/15-6 23-May 24-May N/A N/A 26-May 30-May N/A N/A 30-May 30-May 30-May 2-Jun 2-Jun Pend Backfilling Concrete Caisson
MH12/15-7 2-Feb 5-Feb 6-Feb N/A 7-Feb 8-Feb N/A N/A 8-Feb 10-Feb 2-Jun 2-Jun 2-Jun Completed Precast Caisson to proceed 2nd chambering n tappertop
MH12/15-8 27-Jan 30-Jan N/A N/A 1-Feb 2-Feb N/A N/A 2-Feb 5-Feb 7-Feb 7-Feb 7-Feb Completed Precast Caisson handover 25/1/2018 1/25/2018
MH12/16 26-Dec 27-Dec 10-Jan N/A 10-Feb Day 118 N/A N/A formwork for freedrop Concrete Caisson
MH12/17 21-Jan Day 138 N/A N/A N/A Hacking work Concrete Caisson
MH12/18 N/A N/A N/A Concrete Caisson
MH12/19 20-Aug 22-Aug Day 290 N/A N/A N/A Pipe Rec pending Concrete Caisson in progress
MH12/20 29-Aug 29-Aug 12-Jan N/A 15-Jan 17-Jan N/A N/A 17-Jan 30-Jan 1-Feb 1-Feb 1-Feb Completed Concrete Caisson *handover 17/8/17 8/17/2017
MH12/21 30-Aug 30-Aug 24-Oct N/A 24-Nov 2-Dec N/A N/A 8-Jan 9-Jan 17-Jan 17-Jan 17-Jan Completed Concrete Caisson *handover 17/8/17 8/17/2017
MH12/22 4-Oct 6-Oct 12-Oct N/A 3-Jan 4-Jan N/A N/A 4-Jan 8-Jan 17-Jan 17-Jan 17-Jan Completed Concrete Caisson Rectifield pipe lackage
MH12/23 22-Jan Day 137 N/A N/A N/A no LDM n backdrop needed Steel Caisson *handover 17/8/17 8/17/2017
MH12/24 20-Jun 29-Jun Done N/A 21-Jul 24-Jul N/A N/A 25-Jul 27-Jul 25-Sep 25-Sep 25-Sep Completed Concrete Caisson to re-hack for 300mm
MH12/26 10-Jun 14-Jun 16-Jun N/A 19-Jun 20-Jun N/A N/A 29-Jun 29-Jun 25-Sep 25-Sep 25-Sep Completed Concrete Caisson
MH12/27 22-May 23-May 7-Jun N/A 9-Jun 10-Jun N/A N/A 15-Jun 19-Jun 25-Sep 25-Sep 25-Sep Completed Concrete Caisson
MH12/28 9-Jun 9-Jun N/A 14-Jun 15-Jun 16-Jun N/A N/A 20-Jun 22-Jun 25-Sep 25-Sep 25-Sep Completed Concrete Caisson To hack & re-construct
MH12/29 Concrete Caisson
MH12/30 Concrete Caisson handover 8/3/18 3/8/2018
MH12/31 Concrete Caisson handover 8/3/18 3/8/2018
MH12/32 Concrete Caisson
MH12/33 Concrete Caisson
LINE 14
MH14/1 18-May 21-May 22-May N/A 22-May 23-May N/A N/A 24-May 24-May 2-Jun 2-Jun 2-Jun Completed
MH14/11-1 28-Feb 7-Mar 7-Jun N/A Day 1 N/A N/A Pipe jointing Precast Caisson
MH14/11-2 21-Feb 23-Feb 23-Feb N/A 27-Feb 1-Mar N/A N/A 1-Mar 7-Mar Day 93 Cover slab, makeup piece top Precast Caisson
MH14/11-3 22-Jul 22-Jul 12-Feb N/A 13-Feb 21-Feb N/A N/A 22-Feb 23-Feb 1-Mar 1-Mar 1-Mar Completed Precast Caisson *Clear debries
MH14/11-4 30-Jun 30-Jun 24-Jul N/A 26-Jul 21-Feb N/A N/A 13-Feb 27-Feb 1-Mar 1-Mar 1-Mar Completed Precast Caisson *start backfill on 13/03/18
MH14/14 Concrete Caisson
LIST OF MATERIALS

Alumina Cement: 172 5 5 3 3 4 5 3 3 3 3


OPC Cement 25 4 3 2 2 1 2
Paku 2 1/2" 10 2
Dawai ikat 8
6mm Normal plywood 60 3 3 3 3 3
12mm Normal plywood 48 5 2
Chambering 1200 d x 900 h 3
Chambering 1200 d x 1200 h 2
Chambering 1200 d x 1500 h 10
Chambering 1350 X 900 3 1 1
Chambering 1350 d X 1200 h 2 1 1
Chambering 1350 d X 1500 h 6
Chambering 1500 d x 600 h 0
Chambering 1500 d x 900 h 7 1
Chambering 1500 d x 1200 h 2
Chambering 1500 d x 1500 h 5
Chambering 1800 d X 600 h 5
Chambering 1800 d X 900 h 7 1 1 2 1
Chambering 1800 d X 1200 h 4 1 1 1
Chambering 1800 d X 1500 h 13 1 1 2
Tapper Top 1200 d x 600 h 1
Tapper top 1350 d X 900 h 5 1 1
Tapper top 1500 d X 900 h 4 1
Tapper top 1800 X 900 h 6 1 1 1 1 1 1
Chamber Cover 1020 x 600 x 14 5
Make up piece 600 d X 125 h 12 4 1
Make up piece 600 d X 150 h 7 1 1
Make up piece 600 d X 225 h 14 1 1
Make up piece 600 d X 300 h 7 1 1
Pipe 375mm D X 2.0m L (open cu 0
Pipe 450mm D X 2.0m L (open cu 33
Pipe 525mm D X 2.0m L(open cut 95 15
Pipe 600mm D X 2.92m L(open c 69
Pipe 750mm D X 2.92m L(open c 2
Pipe 900mm D X 2.92m L(open c 12
Pipe 1050mm D X 2.92m L(open
Pipe 1200mm D X 2.92m L(open
Pipe 1500mm D X 2.92m L(open
Pipe 375mm D X 2.0m L 0
Pipe 525mm D X 2.0m L 5
Pipe 600mm D X 2.92m L 0
Pipe 750mm D X 2.92m L 11
Pipe 900mm D X 2.92m L 2
Pipe 1050mm D X 2.92m L 4
Pipe 1200mm D X 2.92m L 4
Pipe 1500mm D X 2.92m L 7
Cast Iron Manhole Cover 8 2 1 1 1 1 1