Engineering Design Corrections

The document outlines several mistakes made on the Vedam project related to structure and basic design, piping and outfitting, and electrical systems. Structure issues included needed modifications to equipment foundations and deck winch foundations. Piping problems involved incorrect deck tank drain line installation and all system pipe routing. Electrical system mistakes were not specified.

Uploaded by

sathi11189
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
95 views1 page

Engineering Design Corrections

The document outlines several mistakes made on the Vedam project related to structure and basic design, piping and outfitting, and electrical systems. Structure issues included needed modifications to equipment foundations and deck winch foundations. Piping problems involved incorrect deck tank drain line installation and all system pipe routing. Electrical system mistakes were not specified.

Uploaded by

sathi11189
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Vedam Mistakes

Structure & Basic Design

1. Equipment Foundations modifications: AHU Control Panel Seating, DC fuse box, FW


cooling pump, Chlorination unit, VIU units, Heat exchanger modifications, macerator &
SW control panel seating, grease trap, UV Sterilizer, silencer and wet trap foundation,
100TV Antena Foundation, etc.,
2. Deck winches foundation boxes FE Analysis issue with class & modified in-place and
project delay.
3. Windlass foundation modified by ODC and asbuilt drawing got approved by class.
4. Fail to check the stability issue of increase in draft of 0.2m & leads to investigated and
solved by ODC & LR TID.
5. Tank Capacity Discrepancies
6. Tank Sounding Tables will effects content & Remote level gauge calibrations and Level
Gauge glass scale to be changed
7. Stability booklet modifications due to tank capacities

Piping and outfitting

1. Deck tanks drain lines are not fitted as per the class requirements
2. All system pipe routing
3. Tank Name Plates

Electrical