Hydro Graph
Hydro Graph
Introduction
When a storm occurs it contributes to the stream flow.
Various instruments are used to document storm
characteristics,
for example, rain gauges are used to record period and
depth of rainfall, current meter is used to find discharge
in streams, etc.
The data thus collected is analyzed for its beneficial
use. The stream flow characteristics are analyzed by
what is called hydrograph analysis.
Continued..
Hydrograph
Continued..
Hydrograph
Discharge Hydrograph
It is the graphical representation of discharge against time.
Generally a hydrograph means discharge hydrograph.
Stage Hydrograph
It is the graphical representation of stage against time.
Stage hydrograph is useful only for the design of flood-
protection works like embankment.
Velocity Hydrograph
It is the graphical representation of velocity against time.
A Typical Hydrograph
Effective Rainfall
Continued..
Basin Lag or Time Lag
Hydrograph
Lag
5.0
4.5
4.0
3.5
Discharge, Q
3.0
2.5
2.0
1.5
1.0
0.5
0.0
0 2 4 6 8 10
Time, t
Continued..
Parts of a Hydrograph
Continued..
Parts of a Hydrograph
Hydrograph
6.0 Crest
C
5.0
Discharge, Q
1.0 B E
0.0
0 2 4 6 8 10 12
Time, t
DRO Hydrograph
Continued..
Hydrograph Analysis
6.0 Crest
C
5.0 N
Discharge, Q
1.0 B E
0.0
0 2 4 6 8 10 12
Time, t
DRO Hydrograph
Hydrograph Analysis
Continued..
Hydrograph Analysis
Hydrograph
6.0
4.0
of hydrograph
3.0
2.0
1.0 A B
0.0
0 2 4 6 8 10 12
Time, t
DRO Hydrograph
Hydrograph
0.2
600 A
500
Extended
Discharge, Q
400 Recession
Curve
300
200
A B C
100
0
0 2 4 6 8 10 12
Time, t
DRO Hydrograph
Continued..
Hydrograph Analysis
Continued..
Hydrograph Analysis
Hydrograph
600
500
Extended
400 Recession
C
Curve Point of Inflexion
Discharge, Q
300
200
B
100 A E
D
0
0 2 4 6 8 10 12
Time, t
DRO Hydrograph
Continued..
Factors Affecting Hydrograph Shape
Intensity of Rainfall
The intensity of rainfall has a predominant effect
on the shape of the hydrograph.
If other conditions remain the same, a higher
intensity storm will produce a rapid rise in the
hydrograph and a higher peak than that in case of
a low intensity rainfall.
Such floods give little warning time and so are
dangerous.
Continued..
Storm Characteristics
Duration of Rainfall
The duration of rainfall is important if it is greater
than the time of concentration (defined as the time
of travel from the farthest point in the catchment
area to the gauging station).
In such a situation, if the rainfall of certain intensity
occurs uniformly, the whole of the catchment area
is contributing runoff at the gauging station and the
hydrograph attains its high peak.
Continued..
Storm Characteristics
Continued..
Storm Characteristics
Weather
The shape of the hydrograph greatly depends on the
seasonal distribution of rainfall. During summer losses due
to evaporation may produce a small peak hydrograph.
On the other hand, in winter, losses are small with the
result that even a small intensity storm may produce a
relatively rapid rise and high peak of the hydrograph.
Antecedent soil moisture conditions (generally being higher
in winter) are important as for high soil moisture; the storm
will produce more runoff.
Catchment Characteristics
Size of Catchment
The catchment area affects the stream flow in a variety of ways.
Even if the intensity and depth of precipitation is assumed to be
constant,
The hydrograph of a smaller catchment rises to its peak and then
recedes more rapidly than that for a larger catchment, because
for the latter, it takes longer for the runoff to reach the gauging
station.
The hydrograph of a larger catchment area, therefore, has
broader base than that of a smaller one. Moreover, the larger the
area, the greater will be the heterogeneity in soil and vegetation
cover, with a consequent effect on the stream flow of each part of
the catchment. The vegetation cover increases the time of
concentration.
Continued..
Catchment Characteristics
Continued..
Catchment Characteristics
Continued..
Catchment Characteristics
Continued..
Catchment Characteristics
Continued..
Catchment Characteristics
Continued..
Catchment Characteristics
Catchment Slope
The slope of the catchment affects stream flow by
reducing the rate of infiltration due to increased
speed of water-movement towards drainage
channels.
The steeper the slope the faster will be the flow
and rise in the hydrograph. The hydrograph in
such a situation will have higher peak and smaller
base.
Unit Hydrograph
Continued..
Unit Hydrograph
Empirical Formulae
Involving various physical characteristics of the basin i. e.
Q = C I A (Rational Formula) - - - - - - - - - - - - 4
Where,
I = Intensity of rainfall,
C = Constant, and
A = Area of cross-section.
Very detailed rainfall-runoff models have been developed
which estimate losses separately and hence calculate the
direct runoff
Continued..
Unit Hydrograph
Flood Routing
Flood Routing will be discussed in detail later.
Unit Hydrograph Method
Of the four methods of estimating maximum
probable rate of runoff, the unit hydrograph
method is being discussed in detail in this
discussion.
Continued..
Unit Hydrograph
Continued..
Unit Hydrograph
Continued..
Unit Hydrograph
Rainfall Duration
The volume under unit hydrograph is always the same for a
given catchment and is equal to one unit say one inch of
runoff (note that volume of one inch of runoff means that
one inch of rainfall excess over the whole catchment.
The actual volume will be the catchment area multiplied by
one). Peak value for a lesser duration unit hydrograph is
higher and is sharp, but the peak value for a higher
duration unit hydrograph is lower with larger base length.
Continued..
Unit Hydrograph
Continued..
Unit Hydrograph
Continued..
Derivation of Unit Hydrograph
A unit hydrograph derived from a single storm may have some
error, and it is desirable to average the unit hydrograph from
several storms of the same duration.
This should not be an arithmetic average of concurrent
coordinates; since, if peaks do not occur at the same time, the
average peak will be lower than many of the individual peaks.
The proper procedure is to compute the average of the peak
flows and times to peak. The average unit hydrograph is then
sketched to conform to those of the other graphs, passing
through the computed average peak, and having a volume of
one-inch.
Continued..
Derivation of Unit Hydrograph
Example 1
From the data given in Table 1 below, derive a 6-
hour unit hydrograph if this data is obtained from a
six-hours duration storm and the catchment area
is 3,200 square kilometers.
Continued..
Derivation of Unit Hydrograph
Date Time Discharge Base Flow
(day) (m³/s) (m³/s)
(1) (2) (3) (4)
Table 1: Data for Unit hydrograph
11-Jan 1st 21 21
12-Jan 2nd 21 21
13-Jan 3rd 21 21
14-Jan 4th 20 20
15-Jan 5th 20 20
16-Jan 6th 20 20
17-Jan 7th 20 20
18-Jan 8th 20 20
19-Jan 9th 521 11
20-Jan 10th 160 21
21-Jan 11th 82 29
22-Jan 12th 63 35
23-Jan 13th 59 47
24-Jan 14th 53 53
25-Jan 15th 47 47
26-Jan 16th 45 45
27-Jan 17th 38 38
Derivation of Unit Hydrograph
Solution
The calculations are shown in Table 2.
The Direct Runoff (DRO) is obtained by subtracting base
flow from discharge values.
The DRO is then multiplied by time interval to get total
volume. This total volume is divided by catchment area to
get depth of effective rainfall in centimeters spread uniformly
over whole catchment.
By definition of unit hydrograph, its ordinates are obtained by
dividing ordinates of DRO by effective rain.
Continued..
Derivation of Unit Hydrograph
Date Time Discharge Base Flow DRO Volume Ordinates of Unit Hydrograph
(day) (m³/s) (m³/s) (m³/s) (x106 m³) (m³/s)
(1) (2) (3) (4) (5)=(3)-(4) (6) (7)=(5)/Eff. Rain
11-Jan 1st 21 21 0 0.00 0.00
12-Jan 2nd 21 21 0 0.00 0.00
Table 2: Data for Unit hydrograph
500
400
300
200
100
0 5 10 15 20
Time (Day)
Continued..
Derivation of Hydrograph from a Unit
Hydrograph
The procedure will be as follows:
The unit hydrograph of a certain duration is given.
Derive the ordinates of direct runoff hydrograph by
multiplying the unit hydrograph ordinates by
effective rainfall.
Add base flow to the ordinates of direct runoff
hydrograph to get total runoff hydrograph. The
peak of this hydrograph gives the maximum flow
due to the storm.
Continued..
Derivation of Hydrograph from a Unit
Hydrograph
Example 2
Given the unit hydrograph of 4-hour duration
(Table 3), calculate the ordinates of total runoff
hydrograph of same duration from an excess
precipitation of 10 cm.
Assume constant Base Flow of 14 m3/sec.
Continued..
Derivation of Hydrograph from a Unit
Hydrograph
Date Time Ordinates of Unit Hydrograph
(Hours) (m³/s)
24 Midnight 3.00
24 Midnight 34.00
24 Midnight 17.00
24 Midnight 0.00
Table 3:Data for unit hydrograph and derivation of total runoff hydrograph.
Continued..
Derivation of Hydrograph from a Unit
Hydrograph
Solution
The excess rainfall has been reported as 10cm.
The ordinates of unit hydrograph are simply
multiplied by excess rainfall to get ordinates of
Direct Runoff (DRO).
Once the ordinates of DRO are obtained, base
flow is added to it to get Total flow ordinates.
These computations are given in Table 4.
Continued..
Derivation of Hydrograph from a Unit
Hydrograph
Date Time Time Ordinates of DRO Base Total Flow
Unit Flow
Hydrograph
(5)=(4) x Excess
(1) (2) (3) (4) (6) (7)=(5)+(6)
Rainfall Depth
600
Fig. 7: Total Runoff Hydrograph
550
500
450
400
Flow (m³/s)
350
300
250
200
150
100
50
0
0 20 40 60 80 100 120
Time (Hours)
Example 3
Given is a unit hydrograph of 2 hour duration (column 2 of
Table 5). Derive the 2 hours duration ‘S’ curve.
Time (Hours) Flow m³/s
0 0
2 95
4 164
6 121
8 91
10 54
12 18
14 0
Table 5: Ordinates of 2 -Hour Unit Hydrograph Continued..
S Curve
SOLUTION
First, we derive ‘S’ curve: The calculations are
shown in Table 6. In this table ordinates of unit
hydrograph of 2-hour duration are given in column
2. Column 1 is time in hours. Other columns have
ordinates in m³/s. Columns 3 to 14 show lagged
unit hydrographs. Column 15 is the addition which
is the ‘S’ curve.
The ‘S’ curve is shown in Figure 8
Continued..
S Curve
Table 6: Unit hydrograph data and derivation of S curve.
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15)
0 0 0
2 95 0 95
4 164 95 0 259
6 121 164 95 0 380
8 91 121 164 95 0 471
10 54 91 121 164 95 0 525
12 18 54 91 121 164 95 0 543
14 0 18 54 91 121 164 95 0 543
16 0 18 54 91 121 164 95 0 543
18 0 18 54 91 121 164 95 0 543
20 0 18 54 91 121 164 95 0 543
22 0 18 54 91 121 164 95 0 543
24 0 18 54 91 121 164 95 0 543
26 0 18 54 91 121 164 95 543
28 0 18 54 91 121 164
30 0 18 54 91 121
32 0 18 54 91
34 0 18 54
36 0 18
38 0
S Curve
S Curve
600
500
Flow (m³/s)
400
300
200
100
0
0 10 20 30 40
Time (Hours)
Continued..
Derivation of Any Duration Unit
Hydrograph
• The given 2 hr hydrograph and developed 6 hr hydrographs are shown in
Figure 9. It may be noted that increasing the duration of unit hydrograph
has decreased peak flow.
Time 2-hour Unit S-Curve Lagged S- Difference 6 Hour Unit
Hydrograph Curve Hydrograph Ordinates
Ordinates
(1) (2) (3) (4) (5)=(3)-(4) = (5) x 2 / 6
0 0 0 0 0
2 95 95 95 32
4 164 259 259 86
6 121 380 0 380 127
8 91 471 95 376 125
10 54 525 259 266 89
12 18 543 380 163 54
14 0 543 471 72 24
16 543 525 18 6
18 543 543 0 0
180
160
140
Flow (m³/s)
120
100
80
60
40
20
0
0 2 4 6 8 10 12
Time (Hours)
Continued..
Example 5
Given is hydrograph resulting from two storms
each of 6 hours duration (Table 8). The rainfall
intensity of first storm is 0.8 cm and that of second
storm is 0.6 cm each of 6 hr duration. Separate
the hydrograph of both storms and find 6 hr unit
hydrograph for each storm.
Continued..
Solution
Refer to Table 9. The following steps illustrate the
procedure
Total rainfall is 0.8 + 0.6 = 1.4 cm. The contribution of
second storm relative to the first storm is 0.6 / 0.8 =
0.75. The ordinates of first hydrograph are, therefore
obtained by subtracting effect of second hydrograph
from composite hydrograph. Since second storm occurs
6 hours later than the first one, the first ordinate of
composite hydrograph is due to contribution of first
storm. Therefore first ordinate of first hydrograph is 750
- 0 = 750.
Continued..
The second ordinate is obtained by subtracting
(0.6 / 0.8) x 750 = 562.50 from second ordinate
of composite hydrograph i.e. 1400 - 562.50 =
837.50. The third ordinate of first storm
hydrograph is obtained by subtracting 0.75 x
837.50 = 628.12 from third ordinate of
composite hydrograph i.e. 1671.88 and so on.
The calculations are shown in table 5.2
Continued..
The ordinates of second hydrograph are
obtained simply by subtracting ordinates of first
hydrograph from composite hydrograph.
For unit hydrograph ordinates of each
hydrograph are divided by their respective
rainfall intensities
Continued..
Date Time Composite Date Time Composite Date Time Composite
(Hours) Hydrograph (Hours) Hydrograph (Hours) Hydrograph
(cumecs) (cumecs) (cumecs)
22-04-65 0 - 25-04-65 60 19,100.00 27-04-65 120 3,300.00
6 750.00 66 15,000.00 126 2,900.00
12 1,400.00 72 11,400.00 132 2,600.00
18 2,300.00 78 9,300.00 138 2,100.00
23-04-65 24 3,000.00 84 7,800.00 28-04-65 144 1,700.00
30 7,000.00 90 6,300.00 150 1,300.00
36 13,000.00 26-04-65 96 5,700.00 156 900.00
42 23,000.00 102 4,800.00 162 600.00
24-04-65 48 29,700.00 108 4,000.00 29-04-65 168 -
54 25,000.00 114 3,700.00
Continued..
Table 9: Separation of Component Hydrographs
Date Time Composite First 6 Hour Second 6 Hour 6 Hour Unit 6 Hour Unit
Hydrograph Hydrograph Hydrograph Hydrograph (First Hydrograph
Storm) (Second Storm)
(Hours) (cumecs) (0.8 cm) (0.6 cm)
22-04-65 0 - - - -
6 750.00 750.00 - 937.50 -
12 1,400.00 837.50 562.50 1,046.88 937.50
18 2,300.00 1,671.88 628.13 2,089.84 1,046.88
23-04-65 24 3,000.00 1,746.09 1,253.91 2,182.62 2,089.84
30 7,000.00 5,690.43 1,309.57 7,113.04 2,182.62
36 13,000.00 8,732.18 4,267.82 10,915.22 7,113.04
42 23,000.00 16,450.87 6,549.13 20,563.58 10,915.22
24-04-65 48 29,700.00 17,361.85 12,338.15 21,702.31 20,563.58
54 25,000.00 11,978.61 13,021.39 14,973.27 21,702.31
60 19,100.00 10,116.04 8,983.96 12,645.05 14,973.27
66 15,000.00 7,412.97 7,587.03 9,266.21 12,645.05
Continued..
Date Time Composite First 6 Hour Second 6 Hour 6 Hour Unit 6 Hour Unit
Hydrograph Hydrograph Hydrograph Hydrograph (First Hydrograph
Storm) (Second
Storm)
(Hours) (cumecs) (0.8 cm) (0.6 cm)
25-04-65 72 11,400.00 5,840.27 5,559.73 7,300.34 9,266.21
78 9,300.00 4,919.80 4,380.20 6,149.74 7,300.34
84 7,800.00 4,110.15 3,689.85 5,137.69 6,149.74
90 6,300.00 3,217.38 3,082.62 4,021.73 5,137.69
26-04-65 96 5,700.00 3,286.96 2,413.04 4,108.70 4,021.73
102 4,800.00 2,334.78 2,465.22 2,918.47 4,108.70
108 4,000.00 2,248.92 1,751.08 2,811.14 2,918.47
114 3,700.00 2,013.31 1,686.69 2,516.64 2,811.14
27-04-65 120 3,300.00 1,790.02 1,509.98 2,237.52 2,516.64
126 2,900.00 1,557.49 1,342.51 1,946.86 2,237.52
132 2,600.00 1,431.88 1,168.12 1,789.85 1,946.86
138 2,100.00 1,026.09 1,073.91 1,282.61 1,789.85
Continued..
Date Time Composite First 6 Hour Second 6 Hour 6 Hour Unit 6 Hour Unit
Hydrograph Hydrograph Hydrograph Hydrograph (First Hydrograph
Storm) (Second Storm)
29-04-65 168 - - - - -
Continued..
SEPARATION OF COMPOSITE HYDROGRAPH
35,000
30,000
Discharge (cumec)
25,000
20,000
15,000
10,000
5,000
-
0 20 40 60 80 100 120 140 160 180
Time (Hours)
Time 1 2 3 4 5 6 7 8 9 10 11
Table 10
Continued..
Solution
Table 11 below gives calculations for determination of q2 & Q, in
which ordinates of q2 have been calculated by using a modified
but simple formula given in the table.
n TIME q1 Ordinates of q2=(R1/R2)xq1(n- Discharge Q of complex hydrograph
1).
0 1 0 0
1 2 200 0 200
2 3 400 240 640
3 4 1000 480 1480
Table 11
Continued..
Composite hydrograph along with component
hydrograph is shown in Figure 11.
COMPLEX HYDROGRAPH
6000
5000
4000
DISCHARGE
3000
2000
1000
0 2 4 6 8 10 12 14
TIME
Figure 6.11
Continued..
Example 7
Repeat example 6 for the case when ordinates
of Q are given (as shown in Table 12 below)
for its separation into its components q1 & q2
with R1/R2 =1.2
Continued..
Solution:
Table 12: Calculations for Separation of Complex hydrograph
n TIME Discharge Q of Ordinates of q1 = Qn - Ordinates of
complex (R1/R2) x q1(n-1). q2 = (R1/R2)xq1(n-1).
hydrograph
0 1 0 0
1 2 200 200 0
2 3 640 400 240
3 4 1480 1000 480
4 5 4000 2800 1200
5 6 4760 1400 3360
6 7 2580 900 1680
7 8 1780 700 1080
8 9 1320 480 840
9 10 776 200 576
10 11 240 0 240
11 12 0 0
Continued..
COMPONENTS OF A COMPLEX HYDROGRAPH
6000
5000
DISCHARGE
4000
3000
2000
1000
0
0 2 4 6 8 10 12 14
TIME
Time 1 2 3 4 5 6 7 8 9 10 11
Table 13
Solution
Table 14 below gives calculations for
determination of q2, q3 and Q, in which ordinates
of q2 and q3 have been calculated by using
modified but simple formulae given in the table.
n TIME q1 Ordinates of Ordinates of Discharge Q of
q2=(R1/R2)xq1(n-1). q3=(R1/R3)xq1(n-2). complex hydrograph
(1) (2) (3) (1) + (2) + (3)
0 1 0 0
1 2 200 0 200
2 3 400 240 0 640
3 4 1000 480 300 1780
4 5 2800 1200 600 4600
5 6 1400 3360 1500 6260
6 7 900 1680 4200 6780
7 8 700 1080 2100 3880
8 9 480 840 1350 2670
9 10 200 576 1050 1826
10 11 0 240 720 960
11 12 0 300 300
12 13 0 0
Table 14
COMPLEX HYDROGRAPH
8000
7000
6000
DISCHARGE
5000
4000
3000
2000
1000
0
0 2 4 6 8 10 12 14
TIME
Table 15: Calculations for Separation of Complex hydrograph (see Fig. 14)
COMPONENTS OF A COMPLEX
HYDROGRAPH
8000
DISCHARGE
6000
4000
2000
0
0 5 10 15
TIME
Figure 14
Synthetic Hydrograph
Continued..
Of these, Snyder’s Method is the most
commonly used method, which is briefly
described here.
Snyder’s method
Following are the steps involved in unit
hydrograph construction according to Snyder’s
method.
Continued..
Step (i)
To find ‘Time to Peak’, Snyder proposed,
tp = C1 Ct (L Lc)0.3 - - - - - - - - - - - - - - - - - - - - -(5)
Where,
tp = Basin Lag in Hours. Basin Lag is the time between centre of
mass of unit rain and peak flow (See Figure 15).
L = Distance from gauging station to catchment boundary.
Lc = Distance in kilometers between gauging station and
centroid of catchment. It is measured from gauging station
along the main stream to the point nearest to centroid of
catchment.
Ct = A coefficient determined from the gauged catchment in
same or similar region. Its value ranges from 1.35 to 1.65.
C1 is a constant whose value in MKS system of units is 0.75.
Continued..
Snyder's Standard Unit Hydrograph
tr
45
40 tp
35
30
Discharge, Q
25
20
15
10
0
0 10 20 30 40 50 60
Tim e, t
Continued..
Synthetic Unit Hydrograph by Snyder's Method
45
40
35 W75
30
Discharge, Q
25 W50
20
qp
15 0.75qp
10 0.5qp
5
0
0 10 20 30 40 50 60
Tim e, t
Continued..
If,
tPR = 5 tR then tR = tr
Else,
tPR = tp and qPR = qP
By back substitution, ‘Ct’ and ‘Cp’ can be determined from Equations (5)
and (6).
If,
tPR ≠ 5.5 tR , then the standard basin lag is
tP = tPR + tr-tR - - - - - - - - - - - - - - - - - - - - - - - - - (7)
4
Also, tp = 5.5 tr - - - - - - - - - - - - - - - - - - - - - - - - - - - - (8)
Equations (7) and (8) are solved simultaneously for ‘tr’ and ‘tP’. ‘Ct’ and
‘Cp’ are then found from Equations (5) and (6) with conditions qPR = qP
and tPR = tp. (Figure 17)
Continued..
Required Synthetic Unit Hydrograph
tR
45
40 tPR
Discharge per unit area
35
30
qPR
25
20
15
10
5
0
0 10 20 30 40 50 60
Tim e, t
tb
Continued..
Step (v)
Width of Hydrograph ‘W’ is given by equation 11.
The coefficient ‘Cw’ defines value of peak discharge
where width of hydrograph is required.
For example, width at discharge which is 75% and
50% of Peak discharge is to be calculated:
W = Cw qPR-1.08 - - - - - - - - - - - - - - - (11)
For qPR = 75%, Cw = 1.22
For qPR = 50%, Cw = 2.14
Continued..
Example 10
Develop 3-hour and 6-hour unit hydrographs for a
catchment area measuring
135.8 Sq. miles with following data:
Ct = 1.50, Cp = 0.60 L = 29.5 miles Lc = 15 miles
Continued..
Solution
Step-1
Basin Lag, tp = C1 x Ct x (L x Lc)0.30
= 1 x 1.50 x (29.5 x 15)0.30
= 9.33 hours
Standard duration of rainfall,
tr = tp /5.50
= 9.33/5.50
= 1.70 hours
Continued..
Step-2 3-hour duration unit hydrograph
tR = 3 hours > tr
Basin Lag, tPR = tP + [tR – tr]/4
= 9.33 + [3-1.70]/4
= 9.66 hours
Peak discharge, qPR= 640 x Cp x A /tPR
= 640 x 0.60 x 135.8/9.66
= 5398.36 cfs
Continued..
Time base, TR = 3 x (1 + tPR /24)
= 3 x (1 + 9.66/24)
= 4.21 days
= 101 hours
Continued..
Plot unit hydrograph using above calculated
values. The graph is shown in Fig 18 below.
It has been plotted using definitions given in
Figs. 16 and 17 above.
From Fig. 18, tabulate the values of
discharge against equal time interval of any
length say at 6 hours interval (17*6 = 102
close to 101). These values have been
shown in Table 16
Continued..
SYNTHETIC 3-HOUR UNIT HYDROGRAPH BY SNYDER'S METHOD
(EXAMPLE 6.10)
6000
DISCHARGE (cfs)
5000
4000
3000
2000
1000
0
0 20 40 60 80 100 120
TIME (HOURS)
Figure 18
Continued..
Time (Hours) Q (cfs)
0 0
6 2550.00
12 5200.00
Table 16 18 3100.00
24 1300.00
30 950.00
36 530.00
42 300.00
48 200.00
54 150.00
60 110.00
66 100.00
72 80.00
78 60.00
84 30.00
90 20.00
96 10.00
101 (say 102) 0
Total 14690
Total run-off = [14690 x 6 x 60 x 60]
[24 x 60 x 60]
= 3672.50 sfd
= 3672.50 / 26.90
= 136.52 inches-mile
Run-off = 136.52 / 135.8
= 1.00 inch
Continued..
Step 3: 6-hour duration unit hydrograph
tR = 6 hours > tr
Basin Lag, tPR = tP + [tR – tr]/4
= 9.33 + [6-1.70]/4
= 10.41 hours
Peak discharge, qPR = 640 x Cp x A /tPR
= 640 x 0.60 x 135.8/10.41
= 5009.34 cfs
Continued..
Time base, TR = 3 x (1 + tPR /24)
= 3 x (1 + 10.41/24)
= 4.30 days
= 103 hours
50% of qPR = 2504.67 cusecs
W50 = 770 / [qPR / A ]1.08
= 770 / [5009.34 / 135.8 ]1.08
= 15.64 hours
75% of qPR = 3757.00 cusecs
W75 = 440 / [qPR / A ]1.08
= 440 / [5009.34 / 135.8 ]1.08
= 8.94 hours
Continued..
Plot unit hydrograph using above calculated
values. The graph is shown in Fig 19 below.
It has been plotted using definitions given in
Figs. 16 and 17 above.
From Fig. 19, tabulate the values of
discharge against equal time interval of any
length say at 6 hours interval (17*6 = 102
close to 101). These values have been
shown in Table 17
Continued..
SYNTHETIC 6-HOUR UNIT HYDROGRAPH BY SNYDER'S METHOD
(EXAMPLE 6.1)
6000
DISCHARGE (cfs)
5000
4000
3000
2000
1000
0
0 20 40 60 80 100 120
TIME (HOURS)
Figure: 19
Continued..
Time (Hours) Q (cfs) Time (Hours) Q (cfs)
0 0 60 150.00
6 1880.00 66 110.00
12 4450.00 72 90.00
18 3800.00 78 80.00
24 1500.00 84 50.00
30 1050.00 90 30.00
36 600.00 96 20.00
48 250.00
Total 14610
54 200.00
Table 17
Continued..
Total run-off = [14610 x 6 x 60 x 60]
[24 x 60 x 60]
= 3652.50 sfd
= 3652.50 / 26.90
= 135.78 inches-mile
Run-off = 135.78 / 135.8
= 1.00 inch
Continued..
Questions
Continued..
What is the practical significance of a unit hydrograph? What
are the three propositions of the unit hydrograph theory?
Explain the step by step procedure for deriving unit hydrograph
from DRO hydrograph and vice versa?
What is S Curve? Explain its utility in hydrology.
How ordinates of unit hydrograph are related to rainfall
intensity?
Why we need separation of composite hydrographs?
What is synthetic hydrograph? Explain the method employed
for deriving synthetic hydrograph. Comment on the merits and
demerits of these methods.
Exercise
Problem 1
Table P1 shows the ordinates at 24 hour intervals for a
hydrograph. Separate the base flow from the direct runoff.
Compute the volume of DRO.
Problem 2
The hydrograph tabulated below in Table P2 resulted from
a 6-hour period of rainfall. Considering the base flow as 11
m³/s, find the 6-hour unit hydrograph for the basin having
148 sq. km drainage area.
Problem 3
Given below in Table P3 is the data for the unit hydrograph
resulting from a 4-hours duration rainfall, for a certain
basin. Derive the S-curve ordinates. Hence derive the
ordinates for unit hydrographs of 2-hours and 6-hours
durations
Continued..
Exercise
Problem 4
Table P4 shows the data for the hydrograph resulting from a 3-
hours duration rainfall for a catchment having area of 3,200 km².
Derive the unit hydrograph.
Time Day 1 Flow (m³/s) Day 2 Flow (m³/s)
3 AM 17 130
9 AM 170 99
12 Noon 269 88
Table P4:
6 PM 198 68
Hydrograph Data
9 PM 173 59
12 PM 150 54
Exercise
Problem 5
Three consecutive storms of 5 cm 7.5 cm and 4 cm of 6
hours durations each on a basin produced the stream flows
as given in Table P5. The basin area is 54 square
kilometers. Assuming a constant base flow of 7 m³/s and
average storm loss of 0.4 cm/hour, derive a 6 hour unit
hydrograph.
Problem 6
The hydrograph of Table P6 resulted from three successive
6-hour period rainfall, having runoff estimated as 1.5, 3.0
and 2.3 cm, respectively. The area of the basin is 148.5
km². Assuming a constant base flow of 10 m³/s, derive the
ordinates of a 6-hour unit hydrograph for the basin.
Time (Hours) Flow (m³/s) Time (Hours) Flow (m³/s)
0 10 21 99
3 31 24 65
6 89 27 36
Table P6: 9 90 30 19
Discharge Data
12 198 33 13
15 132 36 10
18 193
Exercise
Problem 7
The stream flows due to three successive storms of
3.7, 6 and 2.7 cm of 6-hours duration each on a basin
are given in Table P7. The area of the basin is 51 km².
Assuming a constant base flow of 8.5 m³/s and F index
of 0.25 cm/hour, derive a 6 hour unit hydrograph.
Time (Hours) Stream Flow (m³/s) Time (Hours) Stream Flow (m³/s)
0 8 21 42
3 12 24 31
Table P7: 6 15 27 21
Discharge Data 9 27 30 14
12 39 33 10
15 46 36 9
18 49 39 8
Exercise
Problem 8
Two catchments A and B are considered meteorology
similar. Their catchment characteristics are given below in
Table P8.
For catchment A, a 2-h unit hydrograph was developed and
was found to have a peak discharge of 50 m³/s. The time to
peak from the beginning of the rainfall excess in this unit
hydrograph was 9.0 h. Using Snyder’s method, develop a
unit hydrograph for catchment B.
Catchment A Catchment B
L = 39 km L = 45 km
Lca = 15 km Lca = 25 km
A = 250 km² A = 400 km²
Problem 9
A basin has 400 sq. km. of area, L=35 km and Lca
= 10 km. Assuming Ct = 1.5 and
Cp = 0.70, develop a 3-hour synthetic unit
hydrograph for this basin using Snyder’s method.
Exercise
Problem 10
Table P10 shows the ordinates of the 9-hour unit
hydrograph for the entire catchment of a river up to a dam
site
0 0 36 118
9 69 45 74
18 1000 54 46
27 210
Problem 11
Using Snyder’s method, derive the 6-hour unit
hydrograph by using the following data.
Ct = 2.65, Cp = 0.56, A = 3500 km²
L = 150 km, Lca = 75 km