The document outlines the submittal flowchart process. It begins with the general contractor submitting a submittal to the architect. The architect then reviews the submittal and determines if it meets specifications, returning it to the general contractor if needed for resubmittal. If approved, the architect routes it to the APS CMS system and engineer for review. It may also require review from other APS divisions. The project coordinator then reviews and approves or requests resubmittal. If approved, the final submittal is sent back to the general contractor and to the APS for records.

Uploaded by

Fredrick Boening
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
107 views1 page

Submittal Workflow

The document outlines the submittal flowchart process. It begins with the general contractor submitting a submittal to the architect. The architect then reviews the submittal and determines if it meets specifications, returning it to the general contractor if needed for resubmittal. If approved, the architect routes it to the APS CMS system and engineer for review. It may also require review from other APS divisions. The project coordinator then reviews and approves or requests resubmittal. If approved, the final submittal is sent back to the general contractor and to the APS for records.

Uploaded by

Fredrick Boening
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

SUBMITTAL FLOWCHART

Final Approved
G.C. Submits Submittal with
Submittal to Comments Sent
Architect to G.C. for
Material Order

Final Approved
Architect Submittal Sent
Reviews to APS for
Submittal Record

Architect Architect
Does Submittal Returns Packages
Meet no Submittal to Comments from
Specifications? G.C. to APS and
Resubmit Engineer

yes no yes

Architect
Routes Engineer Does Submittal
Submittal to Reviews Meet
APS CMS and Submittal Specifications?
Engineer for
Review

PC Routes
Submittal to Does Submittal
other APS Require Other
POC(s) for yes APS Division
Concurrent Review?
Review

no

Cleaning Materials - Environmental / M&O


Casework - M&O
Roofing & Flashing - M&O Does Submittal
Steel Doors and Frames - M&O / Security PC Reviews Meet
Doors Solid Core Wood - M&O / Security Submittal Specifications?
Overhead Coiling Doors - M&O / Security
Sectional Overhead Doors - M&O / Security yes
Aluminum-Framed Storefronts - M&O / Security
Unit Skylights - M&O / Security
Door Hardware - M&O / Security
Glazing - M&O / Security
Acoustical Tile Ceilings - M&O
Athletic Wood Flooring - Athetics & Activites / M&O
Paint - Environmental / M&O
Ceramic Tile - M&O
Resilient Flooring - M&O
Seamless Troweled Flooring - Environmental / M&O
Wall Coverings - M&O
Horizontal Louver Blinds - M&O / Security
Carpet - M&O
Toilet Compartments - M&O
Signs - M&O
Metal Lockers - M&O
Toilet and Bath Accessories - M&O
Elevators - M&O / Security
Plumbing - M&O (Plumbing)
HVAC - M&O (Mechanical) / Pat Other APS
Electrical - M&O (Electrical) POC's Review
Fire Alarm - M&O / Security Submittal
Lawn Sprinkler Components - M&O
Exterior Plant & Mulch (Rock) - Exterior Operations
Exterior Athletic Equipment - Athletics / M&O
SWPP - Environmental

You might also like