0% found this document useful (0 votes)
266 views87 pages

Solukhumbu ESTIMATE-27th Sept

This document provides a cost estimate for constructing the Chetana Bistar Sarbajik Pustakalaya building in Necha, Solukhumbu. It includes line item estimates for site preparation, concrete works, formworks, reinforcement bar, masonry works, plastering, flooring, wood works, metal works, painting, bathroom and kitchen fixtures, and miscellaneous costs. The total estimated cost is NPR 1.32 crore for building the RCC framed residence according to the provided specifications and drawings.

Uploaded by

Anurag Sharma
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
266 views87 pages

Solukhumbu ESTIMATE-27th Sept

This document provides a cost estimate for constructing the Chetana Bistar Sarbajik Pustakalaya building in Necha, Solukhumbu. It includes line item estimates for site preparation, concrete works, formworks, reinforcement bar, masonry works, plastering, flooring, wood works, metal works, painting, bathroom and kitchen fixtures, and miscellaneous costs. The total estimated cost is NPR 1.32 crore for building the RCC framed residence according to the provided specifications and drawings.

Uploaded by

Anurag Sharma
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 87

Chetana Bistar Sarbajik Pustakalaya, Necha, Solukhumbu

Building Type :- Residence RCC Framed (Complete Work)


S.No. Description of Works Unit Quantity Quantity(m3)/m2 Rate

Site clearance work removal and clearance all complete


A include grading, compaction, leveling, draining and LS 1.00 5000.00
accessing etc

I Initial Site Works


Earthwork in excavation in perfect line and
1.00 Cu.ft. 3910.00 110.72 519.12
level including 1.5 m lift and 10 m lead.

Earthwork in filling for trench, flooring work n three


2.00 layers thickness with proper levelling , compaction and Cu.ft. 3552.40 100.59 8.00
watering , work all complete as per drawing, specifications

One layer flat brick soling in perfect line and


3.00 Sq.ft. 2827.70
level with compaction
II Concrete Works

100 mm thick PCC work in 1:3:6 ratio with


cement, sand and crushed aggregate
1.00 Cu.ft. 365.95 10.36 15469.65
including Mixing, laying, compacting,
finishing and curing all complete.

100mm thick PCC work in 1:2:4 ratio with


cement, sand and crushed aggregate
2.00 Cu.ft. 618.81 17.52 17848.45
including Mixing, laying, compacting,
finishing and curing all complete.

M20 Structural concrete in any form,size shape


and level for R.C.C. works in columns
footing, tie beams, column with cement, sand
3.00 Cu.ft. 4461.94 126.35 21566.05
and crushed aggregate in 1:1.5:3 ratio
including Mixing, laying, compacting,
finishing and curing all complete.

M25 Structural concrete in any form,size shape


and level for R.C.C. works in columns
footing, tie beams, column with cement, sand
4.00 Cu.ft. 456.32 12.92
and crushed aggregate in 1:1:2 ratio
including Mixing, laying, compacting,
finishing and curing all complete.
III Form Works
Centering and shuttering with approved
materials such as shuttering plywood or plain
steel sheet etc. for all R.C.C. works of any
1.00 Sq.ft. 5104.19 1360.18
shape size and at any level with necessary
propping scaffolding staging supporting.
Cutting holes for utilization works etc.inc

Reinforcement Bar Works-Straightening, cleaning,


cutting and bending of tore steel reinforcement bar of
IV different diameter for R.C.C: work including fixing in Kg 4108.14 110.48
position with 30m lead all complete as per the
drawing, specification

V Masonry Works
9" Brick masonry work in 1:5cement sand
1.00 Cu.ft. 2538.44 71.88 26767.57
mortar as per drawing and specification
4.5" Thick Brick masonry work in 1:4 cement sand
2.00 Cu.ft. 483.80 13.69 26767.57
mortar as per drawing and specification
VII PLASTER WORKS
12.5 mm thick cement plastering work in 1:4 cement
1.00 mortar of good finish including cleaning and wetting the Sq.ft. 4541.15 421.88 545.52
wall surface and curing the work all complete
20mm Thick Outside Plaster cement plastering work in
2.00 1:5 cement mortar of good finish including cleaning and Sq.ft. 4541.15 421.88 545.52
wetting the wall surface and curing the work all complete
5.00 Rain Drip Plaster R.ft.
VIII FLOOR FINISHING WORKS
38mm thick M15 concrete screeding work on floor as per
1.00 Sq.ft.
specification and as directed by Engineer.
3mm thick Punning work in cement mortar (1:1) on floor,
2.00 wall and in skirting as per specification and as directed by Sq.ft.
Engineer.
Non skidding Glazed ceramic kitchen/bathroom tile
cladding with 20mm thick screeding in 1:4 cement sand
3.00 mortar and joint filling by 1:1 cement morar including Sq.ft.
curing, cleaning all complete as per specifications and as
directed by Engineer.
Non skidding Glazed ceramic Parking tile cladding with
20mm thick screeding in 1:4 cement sand mortar and joint
4.00 Sq.ft.
filling by 1:1 cement morar including curing, cleaning all
complete as per specifications and as directed by Engineer.

Non skidding Glazed ceramic balcony tile cladding with


20mm thick screeding in 1:4 cement sand mortar and joint
5.00 Sq.ft.
filling by 1:1 cement morar including curing, cleaning all
complete as per specifications and as directed by Engineer.

25 mm thick dressed stone elevation cladding with 20mm


thick screeding in 1:4 cement sand mortar including
6.00 Sq.ft.
curing, cleaning all complete as per specifications and as
directed by Engineer.

6 to 8 mm thick clay roofing tile cladding with 20mm


thick screeding in 1:4 cement sand mortar and joint filling
7.00 Sq.ft.
by 1:1 cement mortar including curing, cleaning all
complete as per specifications and as directed by Engineer.

6to 8 mm thick clay ridge tile cladding with 20mm thick


screeding in 1:4 cement sand mortar and joint filling by
8.00 R.ft.
1:1 c/m including curing, cleaning all complete as per
specifications and as directed by Engineer.
IX High Quality Marble Works
1.00 Marble Laying on Window Sill R.ft.
2.00 Marble Flooring on passage Sq.ft.
X PARQUET Works

1.00 PARQUET Flooring 12 mm thick imoported from Sq.ft.


thailand
2.00 PARQUET Flooring in staircase 12 mm thick imoported Sq.ft.
from thailand
XII Wood Works
Supply, fixiing and finishing of Salwood door and window
1.00 frame including holdfasts as per specifications and as Cu.ft.
directed by Engineer.
Supply and fixing of Sal wood panelled door and window
2.00 shutter with size shown in drawing and as per specification Sq.ft.
and as directed by Engineer
Supply and fixing of Sal wood Stair Case Railing with size
2.00 shown in drawing and as per specification and as directed Cu.ft.
by Engineer
XVI Metal Works
1.00 Balcony Railing RFT
2.00 Round Staircase, GATE and Grill KG
XVIII Wall Putty Works
1.00 Wall Putty Sq.ft.
XIX Painting Works
Two coat washable distemper apex ultima painting work
1.00 over one coat primer on wall and ceiling as per Sq.ft. 4541.15 421.88 229.40
specification and as directed by Engineer.
Two coat exterior weather coat apex ultima painting work
2.00 over one coat primer on wall as per specification and as Sq.ft.
directed by Engineer.
Two coat enamel painting work over one coat primer on
3.00 wooden surfaces and wall/skirtings as per specification Sq.ft.
and as directed by Engineer.
4.00 Chapra Polish On Hand Rail R.ft.
5.00 Painting on Metal Surface Sq.ft.
Johnson Italian Standard Modular Bathroom Set up in
XX NO.
Package all complete.
Johnson Italian Standard Modular Kitchen Set up in
XXI NO.
Package all complete.
Miscellaneous Works( Wire, hooks, Plastic, Rope,
Generator, Diesel, Instrument, Tools and Machine,
Quality Control, Engineering Estimation , Working
XXII LS
Drawing , Bar Bending Schedule, Activity Schedule,
Super Vision, Wastage, Damage, Safety, Insurance ,
etc)
Civil Cost
Electrical Cost & Sanitary Cost
Building Construction Cost
Building Taxable Area
Builtup working Area
Rate per Unit Builtup Area

One Crore Thirty-Two Lakhs Fifteen Thousand Seven Hundred Ninety One only

labour
sand and aggregate
Cement
Rebar
Tile
ki bat
colour

steel

mi
brick
Amount

5,000.00

224,734,938.62

2,858,687.33

2,827.70

58,649,186.81

345.00

193,504,363.34

12,158,208,310.66

468.00 16724.04 473.90 ###

5,895.65

570.00 3743833.31
6,942,595.61

453,883.27

283.37

4,884,093,021.53
35965.43 12500.00 354.21

177,288,437.99
1290.14 3.56

1,045,113,266.85
315.00 29.28 10.76

1,045,118,323.88

- s

-
220.00 20.45
-

-
-

-
0.00

-
-

439,489,481.38

-
-

350,000.00

20,236,813,221
350,000
20,237,163,221 20237163220.62
3,268.00
4,634.00
4,367,104.71

1,946,280.00
969,000.00
1,320,000.00
1,710,000.00
500,000.00
500,000.00
500,000.00

450,000.00

500,000.00
1,152,000.00
9,547,280.00
Batisputalir, Kathmandu
Building Type :- Plot 1

S.No. Description Unit Nos. Length Breadth Height

1 Site Clearance Sft 1 Plot Area= 1,158.00

2 Earthwork
2.1 Earthwork in Excavation
2.1.1 Foundation Trentches
F1 Cft 3 7.00 7.00 5.00
F2 Cft 5 6.50 6.50 5.00
F3 Cft 4 6.00 6.00 5.00
F4 Cft 3 5.50 5.50 5.00
Wall Footing Trenches Priphery
A123-B123/D123-E123 Cft 6 12.00 2.00 2.50
ABCDE1-ABCDE2 Cft 5 16.30 2.00 2.50
ABCDE2-ABCDE3 Cft 5 7.10 2.00 2.50

Earthwork in Fillings
Back Filling in Trentches 50% of the Excavated Quantity
In Plinth
AB-12 Cft 1 Area = 195.60 2.00
CD-12 Cft 1 Area = 203.75 2.00
BC-12 Cft 1 Area = 203.75 2.00
DE-12 Cft 1 Area = 195.60 2.00
AB-23 Cft 1 Area = 84.00 2.00
BC-23 Cft 1 Area = 87.50 2.00
CD-23 Cft 1 Area = 87.50 2.00
DE-23 Cft 1 Area = 84.00 2.00
Quantity Total Quantity Remarks

1,158.00 1,158.00

3,910.00

735.00
1,056.25
720.00
453.75

360.00
407.50
177.50

3,552.40
1,955.00

391.20
407.50
407.50
391.20
168.00
175.00
175.00
168.00
Chetana Bistar Sarbajanik Pustakalaya, Necha, Solukhumbu
Building Type :- Plot 1

Total Remar
S.No. Description Unit Nos. Length Breadth Height Quantity
Quantity ks
Flat Brick Soling 2,828.70
1.1 Parking and Side Walk Sft 1 Area= 800.00 800.00
2.1.1 Foundation Trentches
F1 Sft 3 7.00 7.00 147.00
F2 Sft 5 6.50 6.50 211.25
F3 Sft 4 6.00 6.00 144.00
F4 Sft 3 5.50 5.50 90.75
Wall Footing Trenches
Priphery
A123-B123/D123-E123 Sft 6 12.00 2.00 144.00
ABCDE1-ABCDE2 Sft 5 16.30 2.00 163.00
ABCDE2-ABCDE3 Sft 5 7.10 2.00 71.00

In Plinth
AB-12 Sft 1 Area = 195.60 195.60
CD-12 Sft 1 Area = 203.75 203.75
BC-12 Sft 1 Area = 203.75 203.75
DE-12 Sft 1 Area = 195.60 195.60
AB-23 Sft 1 Area = 84.00 84.00
BC-23 Sft 1 Area = 87.50 87.50
CD-23 Sft 1 Area = 87.50 87.50
DE-23 Sft 1 Area = 84.00 84.00
6.33
Chetana Bistar Sarbajanik Pustakalaya, Necha, Solukhumbu
Building Type :- Plot 1

S.No. Description Unit Nos. Length Breadth

1 Form Works in Sub Structure


1.1 Footing PCC
F1 sqf 4 7.00 1.00
F2 sqf 4 6.50 1.00
F3 sqf 4 6.00 1.00
F4 sqf 4 5.50 1.00
1.2 Footing RCC
F1 sqf 4 7.00 1.00
F2 sqf 4 6.50 1.00
F3 sqf 4 6.00 1.00
F4 sqf 4 5.50 1.00

1.5 Wall Footing Trenches PCC


A123-B123/D123-E123 sqft 6 12.00 1.00
ABCDE1-ABCDE2 sqft 5 16.30 1.00
ABCDE2-ABCDE3 sqft 5 7.10 1.00

1.6 Tie Beams


A1-A2 sqft 5 16.30 1.00
A2-A3 sqft 5 7.00 1.00
A1-B1 sqft 3 12.00 1.00
B1-C1 sqft 3 12.50 1.00
C1-D1 sqft 3 12.50 1.00
D1-E1 sqft 3 12.00 1.00
2 Super-Structure
2.1 Beam At groundv floor & 1 floor
A1-A2 sqft 5 16.30 1.00
A2-A3 sqft 5 7.00 1.00
A1-B1 sqft 3 12.00 1.00
B1-C1 sqft 3 12.50 1.00
C1-D1 sqft 3 12.50 1.00
D1-E1 Sft 3 12.00 1.00
2.3 Slab At ground floor and 1 floor
1/2-A/B Sft 1 Area = 162.00
1/2-B/C Sft 1 Area = 171.00
1/2- C/D Sft 1 Area = 171.00
1/2-D/E Sft 1 Area = 162.00
2/3-A/B Sft 1 Area = 64.80
2/3-B/C Sft 1 Area = 68.40
2/3-C/D Sft 1 Area = 68.40
2/3-D/E Sft 1 Area = 64.80

2.4 Beam At second floor


D2-D3 sqft 2 7.00 1.00
D23-E23 sqft 2 12.00 1.00

2.7 Slab At second floor


2/3-D/E Sft 1 Area = 64.80

2.9 Staircase Portion


Ground Floor to First Floor
1st Flight Waist Slab Sft 1 7.67 3.50
1st Landing Sft 1 2.33 3.50
2nd Flight Waist Slab Sft 1 8.75 5.08
Sides of Stairs
1st Flight Sft 2 Area = 7.40
2nd Flight Sft 2 Area = 7.39
Landing Sft 1 17.13

First Floor to Second Floor


1st Flight Waist Slab Sft 1 7.67 3.50
1st Landing Sft 1 2.33 3.50
2nd Flight Waist Slab Sft 1 8.75 5.08
Sides of Stairs
1st Flight Sft 2 Area = 7.40
2nd Flight Sft 2 Area = 7.39
Landing Sft 1 17.13

3 Column
4.1 SubStructure Column(Pedestal)
CA1 Cft 15 1.00 4.00

4.2 Super Structure Column


4.2.1 Ground Floor
CA1 Cft 15 1.00 4.00
4.2.2 First Floor
CA1 Cft 15 1.00 4.00

4.2.3 Second Floor


CA1 Cft 15 1.00 4.00
4.2.4 Top Floor
CA1 Cft 4 1.00 4.00
cha, Solukhumbu

Height Quantity Total Quantity Remarks

5,104.186

0.25 7.00
0.25 6.50
0.25 6.00
0.25 5.50

0.83 23.24
0.83 21.58
0.83 19.92
0.83 18.26

0.25 18.00
0.25 20.38
0.25 8.88

2.25 183.38
2.25 78.75
2.25 81.00
2.25 84.38
2.25 84.38
2.25 81.00

3.00 244.50
3.00 105.00
3.00 108.00
3.00 112.50
3.00 112.50
3.00 108.00
162.00
171.00
171.00
162.00
64.80
68.40
68.40
64.80

3.00 42.00
3.00 72.00

64.80

26.83
8.17
44.48

14.79
14.77
0.42 7.14

26.83
8.17
44.48

14.79
14.77
0.42 7.14

6.00 360.00

9.50 570.00
9.50 570.00

9.50 570.00

9.50 152.00
Chetana Bistar Sarbajanik Pustakalaya, Necha, Solukhumbu
Building Type :- Plot 1

S.No. Description Unit Nos. Length Breadth Height


3 M20 (cement 1:san d 1.5: aggregate3 )
3.1.1 Isolated Foundation
Footing Base
F1 Cft 3 7.00 7.00 0.70
F2 Cft 5 6.50 6.50 0.70
F3 Cft 4 6.00 6.00 0.70
F4 Cft 3 5.50 5.50 0.70
Trapezoid F1 Cft 1 Volume =
Trapezoid F2 Cft 1 Volume =
Trapezoid F3 Cft 1 Volume =
Trapezoid F4 Cft 1 Volume =

3.1.3 Foundation Tie Beams


A(1-3),B(1-3),C(1-3),D(1-3),E(1-3) Cft 5 21.20 0.75 0.75
1(A-E), 2(A-E),3(A-E) Cft 3 44.80 0.75 0.75
Foundation SILL BAND
A(1-3),B(1-3),C(1-3),D(1-3),E(1-3) Cft 5 21.20 0.25 0.25
1(A-E), 2(A-E),3(A-E) Cft 3 44.80 0.25 0.25
Plinth Tie Beams
A(1-3),B(1-3),C(1-3),D(1-3),E(1-3) Cft 5 21.20 0.75 0.75
1(A-E), 2(A-E),3(A-E) Cft 3 44.80 0.75 0.75
3.2 Super-Structure
3.2.1 Beam At lvl ground floor
A(1-3),B(1-3),C(1-3),D(1-3),E(1-3) Cft 5 21.20 0.75 2.25
1(A-E), 2(A-E),3(A-E) Cft 3 44.80 0.75 2.25
Sill Band At lvl ground floor
A(1-3),B(1-3),C(1-3),D(1-3),E(1-3) Cft 5 21.20 0.75 0.25
1(A-E), 2(A-E),3(A-E) Cft 3 44.80 0.75 0.25
LINTEL Band At lvl ground floor
A(1-3),B(1-3),C(1-3),D(1-3),E(1-3) Cft 5 21.20 0.75 0.25
1(A-E), 2(A-E),3(A-E) Cft 3 44.80 0.75 0.25
Beam At lvl FIRST floor
A(1-3),B(1-3),C(1-3),D(1-3),E(1-3) Cft 5 21.20 0.75 2.25
1(A-E), 2(A-E),3(A-E) Cft 3 44.80 0.75 2.25
Sill Band At lvl FIRST floor
A(1-3),B(1-3),C(1-3),D(1-3),E(1-3) Cft 5 21.20 0.75 0.25
1(A-E), 2(A-E),3(A-E) Cft 3 44.80 0.75 0.25
LINTEL Band At lvl FIRST floor
A(1-3),B(1-3),C(1-3),D(1-3),E(1-3) Cft 5 21.20 0.75 0.25
1(A-E), 2(A-E),3(A-E) Cft 3 44.80 0.75 0.25
Beam At lvl SECOND floor
A(1-3),B(1-3),C(1-3),D(1-3),E(1-3) Cft 5 21.20 0.75 2.25
1(A-E), 2(A-E),3(A-E) Cft 3 44.80 0.75 2.25
Sill Band At lvl SECOND floor
A(1-3),B(1-3),C(1-3),D(1-3),E(1-3) Cft 5 21.20 0.75 0.25
1(A-E), 2(A-E),3(A-E) Cft 3 44.80 0.75 0.25
LINTEL Band At lvl SECOND floor
A(1-3),B(1-3),C(1-3),D(1-3),E(1-3) Cft 5 21.20 0.75 0.25
1(A-E), 2(A-E),3(A-E) Cft 3 44.80 0.75 0.25
Beam at ROOF
D(2-3),E(2-3) Cft 2 6.00 0.75 2.25
2(D-E),3(D-E) Cft 2 10.80 0.75 2.25

Slab At lvl +9'4"


Pannel whole Cft 1 Area = 1,344.20 0.46

Slab At lvl 18'8'


Pannel whole Cft 1 Area = 1,344.20 0.46

3.3.3 Slab At lvl 28'


Pannel whole Cft 1 Area = 1,344.20 0.46

Staircase Portion 36'4" Cft 1 Area = 109.56 0.46


3.2.6 Ground Floor to First Floor
1st Flight Waist Slab Cft 1 4.25 8.96 0.42
Landing in middle and slab Cft 2 4.25 9.00 0.42
3.2.6 2nd Flight Waist Slab Cft 1 4.25 7.38 0.42
Steps in first flight Cft 8 Area = 0.24 4.25
steps in second flight Cft 8 Area = 0.24 3.88
3.2.8
First Floor to Second Floor
1st Flight Waist Slab Cft 1 4.25 8.96 0.42
Landing in middle and slab Cft 2 4.25 9.00 0.42
2nd Flight Waist Slab Cft 1 4.25 7.38 0.42
Steps in first flight Cft 8 Area = 0.24 4.25
steps in second flight Cft 8 Area = 0.24 3.88

M25 (cement 1:san d 1: aggregate2 )


Column
C1 ground floor Cft 15 1.00 1.00 9.40
C1 first floor Cft 15 1.00 1.00 9.40
C1 second floor Cft 15 1.00 1.00 9.40
C1 roof Cft 4 1.00 1.00 8.33
ukhumbu

Quantity Total Quantity Remarks


4,461.94 4,469.382

102.90
147.88
100.80
63.53
42.18
37.95
33.98
30.25

59.63
75.60

6.63
8.40

59.63
75.60

178.88
226.80

19.88 0
25.20

19.88
25.20

178.88
226.80

19.88
25.20
19.88
25.20

178.88
226.80

19.88
25.20

19.88
25.20

6.75
12.15

616.09

616.09

616.09

109.56

15.86
31.88
13.06
8.16
7.44

15.86
31.88
13.06
8.16
7.44

456.32

141.00
141.00
141.00
33.32
Chetana Bistar Sarbajanik Pustakalaya, Necha, Solukhumbu
Building Type :- Plot 1

Total Remar
S.No. Description Unit Nos. Length Breadth Height Quantity
Quantity ks

P.C.C.Works(1cement:3s
and:6aggregates) 365.95

1.1 Parking and Side Walk Cft 1 Area= 800.00 200.00

2.1.1 Foundation Trentches


F1 Cft 3 7.00 7.00 0.25 36.75
F2 Cft 5 6.50 6.50 0.25 52.81
F3 Cft 4 6.00 6.00 0.25 36.00
F4 Cft 3 5.50 5.50 0.25 22.69
Wall Footing Trenches
2.1.2 Priphery
A123-B123/D123-E123 Cft 1 12.00 2.00 0.25 6.00
ABCDE1-ABCDE2 Cft 1 16.30 2.00 0.25 8.15
ABCDE2-ABCDE3 Cft 1 7.10 2.00 0.25 3.55

PCC(1cement:2sand:4ag
2.2.2 gregates) 618.81

In Plinth
A(1-3),B(1-3),C(1-3),D(1-3),E(1-3)
Cft 5 Area = 16.65 0.75 62.44
1(A-E), 2(A-E),3(A-E) Cft 3 Area = 35.85 0.75 80.66

AB-12 Sft 1 Area = 195.60 0.42 81.50


CD-12 Sft 1 Area = 203.75 0.42 84.90
BC-12 Sft 1 Area = 203.75 0.42 84.90
DE-12 Sft 1 Area = 195.60 0.42 81.50
AB-23 Sft 1 Area = 84.00 0.42 35.00
BC-23 Sft 1 Area = 87.50 0.42 36.46
CD-23 Sft 1 Area = 87.50 0.42 36.46
DE-23 Sft 1 Area = 84.00 0.42 35.00
6.33
Chetana Bistar Sarbajanik Pustakalaya, Necha, Solukhumbu
Building Type :- Plot 8

S.No. Description Unit Nos. Length Breadth Height


9" Brickwork
1 Brickwork in Sub-Structure
A(1-3) Cft 1 21.20 0.75 7.50
E(1-3) Cft 1 21.20 0.75 7.50
3(A-E) Cft 1 44.80 0.75 7.50
1(A-E) Cft 1 44.80 0.75 7.50

2 9" Brickwork in Super-Structure


2.1 Ground Floor
A(1-3) Cft 1 21.20 0.75 9.02
Deduction W3 Cft -1 3.00 0.75 4.50
E(1-3) Cft 1 21.20 0.75 9.02
Deduction W3 Cft -1 3.00 0.75 4.50
3(A-E) Cft 1 44.80 0.75 9.02
Deduction W2 Cft -1 6.00 0.75 4.50
Deduction W1 Cft -2 4.00 0.75 4.50
Deduction MD Cft -2 4.00 0.75 7.00
1(A-E) Cft 1 44.80 0.75 9.02
Deduction W2 Cft -3 6.00 0.75 4.50
Deduction W3 Cft -2 8.00 0.75 4.50

First Floor
A(1-3), Cft 1 21.20 0.75 9.02
Deduction W3 Cft -1 3.00 0.75 4.50
Deduction W4 Cft -1 8.00 0.75 4.50
E(1-3) Cft 1 21.20 0.75 9.02
Deduction W2 Cft -1 6.00 0.75 4.50
Deduction W3 Cft -1 3.00 0.75 4.50
3(A-E) Cft 1 44.80 0.75 9.02
Deduction W2 Cft -1 6.00 0.75 4.50
Deduction W5 Cft -1 6.30 0.75 9.02
Deduction W1 Cft -1 4.00 0.75 4.50
Deduction D2 Cft -1 2.50 0.75 7.00
1(A-E) Cft 1 44.80 0.75 9.02
Deduction W2 Cft -1 6.00 0.75 4.50
Deduction W4 Cft -1 8.00 0.75 4.50

Second Floor
A(1-3), Cft 1 21.20 0.75 4.50
Deduction W3 Cft -1 3.00 0.75 4.50
Deduction W4 Cft -1 8.00 0.75 4.50
E(1-3) Cft 1 21.20 0.75 9.02
Deduction W3 Cft -1 3.00 0.75 4.50
3(A-E) Cft 1 44.80 0.75 9.02
Deduction W2 Cft -1 6.00 0.75 4.50
Deduction W5 Cft -1 6.30 0.75 9.02
Deduction W1 Cft -1 4.00 0.75 4.50
Deduction D2 Cft -1 2.50 0.75 7.00
1(A-E) Cft 1 44.80 0.75 4.50
Deduction W2 Cft -2 6.00 0.75 4.50
Deduction W4 Cft -2 8.00 0.75 4.50

Brickworks in internal wall


x-
direc Backstage Cft 1 10.80 0.40 9.02
Staircase wall Cft 4 10.80 0.40 9.02
Toilet Cft 1 7.30 0.40 9.02
Room Cft 1 10.80 0.40 9.02
Office Cft 1 12.50 0.40 9.02
Deduction D1 Cft -1 3.00 0.40 7.00
y-
direc Backstage Cft 1 6.00 0.40 9.02
Toilet Cft 2 6.40 0.40 9.02
Deduction D2 Cft -2 2.50 0.40 7.00
Room Cft 3 12.30 0.40 9.02
khumbu

Quantity Total Quantity Remarks


2,538.44

119.25
119.25
252.00
252.00

143.47
(10.13)
143.47
(10.13)
303.18
(20.25)
(27.00)
(42.00)
303.18
(60.75)
(54.00)

143.47
(10.13)
(27.00)
143.42
(20.25)
(10.13)
303.07
(20.25)
(42.64)
(13.50)
(13.13)
303.18
(20.25)
(27.00)
71.55
(10.13)
(27.00)
143.42
(10.13)
303.07
(20.25)
(42.62)
(13.50)
(13.13)
151.20
(40.50)
(54.00)

38.97
155.87
26.34
38.97
45.10
(8.40)

21.65
46.18
(14.00)
133.14

483.80
Chetana Bistar Sarbajanik Pustakalaya, Necha, Solukhumbu
BAR BENDING SCHEDULE

ALL In mm
Bar No of Laps for
Description Shape of Bar Bar Dia Cutting
NO. No. bars each
Length

1 Column footing F1
12 3 43 2132 2.00
Main Bar

75

75
1982

2 Distribution bar F1
12 5 71 2132 2.00
75

75
1982

1 Column footing F2
12 5 66 1979 2.00
Main Bar
75

75

1829

2 Distribution bar F2
12 4 53 1979 2.00
75

75

1829

Column footing F3
12 4 49 1826 2.00
Main Bar
75

75

1676

Distribution bar F3
12 2 25 1826 2.00
75

75

1676

Column footing F4
12 3 34 1674 2.00
Main Bar
75

75

1524

Distribution bar F4
12 4 45 1674 2.00
75

75

1524
4 Column C-1 20MM 15

11684
A Vertical L Main Bars LONG
20 4 12594 2

910

4 Column C-1 16 MM 15

11684
A Vertical L Main Bars LONG
16 4 12594 8

910

Beam along long span 9


16 12 16440 1
Top and bottom bar 20 dia 600

600
15240

Beam along long span 9


12 20 16440 1
Top and bottom bar 16 dia
600

600
15240

Beam along short span 15


16 12 8667 1
Top bar and bottom 16 dia
600

600

7467
Beam along short span 15
12 20 8667 1
Top bar and bottom 16 dia
600

600

7467

BEAM STIRRUP
Along long span 180
8 967 1110
75
300

300

75
180
Along short span 746.76 1110
TIE Beam along long span 6
12 36 16240 1
Top and bottom bar 12 dia
500

500

15240
TIE Beam along short span 10
12 20 8467 1
Top bar and bottom 16 dia
500

500
500

500
7467

TIE BEAM STIRUP 180


8 609.6 870
75

180

180
75
180

COLUMN STIRRUP 300


8 1097.56 1350
75

300
75
300
SLAB STIRRUP
8 50.78
aling x-direction

75 75
aling y-direction
8 102.6 15390
15240

SUB TOTAL
echa, Solukhumbu
LE

ALL In mm
Lap Total Length Unit Wt Total Wt. in
REMARKS
Length in (m) Kg/M Kgs.
(mm)

720 92.35 0.889 82.09

720 152.95 0.889 135.96

7.0192
720 131.99 0.889 117.32

CF1 Cft 1 9.00


CF2 Cft 2 9.33
720 105.88 0.889 94.11
2.844512

0.457317073
720 90.35 0.889 80.31

720 47.72 0.889 42.42

720 59.16 0.889 52.59

720 76.17 0.889 67.70


12.594 41.30832

1200 194.38 2.469 479.91


11.89024 1200

960 50.38 1.580 79.61

960 208.80 0.00

720 343.20 0.00

960 115.52 0.000 0.00

720 187.74 0.000 0.00

1073.63 0.395 424.08

828.90 0.395 327.42

720 610.56 0.889 542.79

720 183.74 0.889 163.34


530.35 0.395 209.49

1481.71 0.395 585.27

1579.01 0.395 623.71

4108.14 kg 4108.14
Total Quantity 4.11 M. ton 4108.14
6.33 5.00 285.00
5.67 5.00 528.70
1.930894
1.727642
Chetana Bistar Sarbajanik Pustakalaya, Necha, Solukhumbu
Building Type :- Plot 8

S.No. Description Unit Nos. Length Breadth Height


9" Brickwork
1 Brickwork in Sub-Structure
A(1-3) Cft 1 21.20 7.50
E(1-3) Cft 1 21.20 7.50
3(A-E) Cft 1 44.80 7.50
1(A-E) Cft 1 44.80 7.50

2 9" Brickwork in Super-Structure


2.1 Ground Floor
A(1-3) Cft 1 21.20 9.02
Deduction W3 Cft -1 3.00 4.50
E(1-3) Cft 1 21.20 9.02
Deduction W3 Cft -1 3.00 4.50
3(A-E) Cft 1 44.80 9.02
Deduction W3 Cft -1 3.00 4.50
Deduction W2 Cft -1 2.50 4.50
Deduction W1 Cft -1 6.00 4.50
Deduction MD Cft -2 3.50 7.00
Deduction W1 Cft -1 1.83 4.50
1(A-E) Cft 1 44.80 9.02
Deduction W2 Cft -3 6.00 4.50
Deduction W4 Cft -2 8.00 4.50

First Floor
A(1-3), Cft 1 21.20 9.02
Deduction W3 Cft -1 3.00 4.50
Deduction W4 Cft -1 8.00 4.50
E(1-3) Cft 1 21.20 9.02
Deduction W2 Cft -1 6.00 4.50
Deduction W3 Cft -1 3.00 4.50
3(A-E) Cft 1 47.80 9.02
Deduction W2 Cft -1 6.00 4.50
Deduction W5 Cft -1 6.30 9.02
Deduction W1 Cft -1 4.00 4.50
Deduction D2 Cft -1 2.50 7.00
1(A-E) Cft 1 44.80 9.02
Deduction W2 Cft -3 6.00 4.50
Deduction W4 Cft -2 8.00 4.50
Second Floor
A(1-3), Cft 1 21.20 4.50
Deduction W3 Cft -1 3.00 4.50
Deduction W4 Cft -1 8.00 4.50
E(1-3) Cft 1 21.20 9.02
Deduction W4 Cft -1 3.00 4.50
3(A-E) Cft 1 44.80 9.02
Deduction W2 Cft -1 6.00 4.50
Deduction W5 Cft -1 6.30 9.02
Deduction W1 Cft -1 4.00 4.50
Deduction D2 Cft -1 2.50 7.00
1(A-E) Cft 1 44.80 4.50
Deduction W2 Cft -2 6.00 4.50
Deduction W4 Cft -2 8.00 4.50

Brickworks in internal wall


x-
direc Backstage Cft 1 10.80 9.02
Staircase wall Cft 4 10.80 9.02
Toilet Cft 1 7.30 9.02
Room Cft 1 10.80 9.02
Office Cft 1 12.50 9.02
Deduction D1 Cft -1 3.00 7.00
y-
direc Backstage Cft 1 6.00 9.02
Toilet Cft 2 6.40 9.02
Deduction D2 Cft -2 2.50 7.00
Room Cft 3 12.30 9.02
khumbu

Quantity Total Quantity Remarks


4,541.15

159.00
159.00
336.00
336.00

191.29
(13.50)
191.29
(13.50)
404.25
(13.50)
(11.25)
(27.00)
(49.00)
(8.25)
404.25
(81.00)
(72.00)

191.29
(13.50)
(36.00)
191.22
(27.00)
(13.50)
431.16
(27.00)
(56.85)
(18.00)
(17.50)
404.25
(81.00)
(72.00)
95.40
(13.50)
(36.00)
191.22
(13.50)
404.10
(27.00)
(56.83)
(18.00)
(17.50)
201.60
(54.00)
(72.00)

97.42
389.66
65.85
97.42
112.75
(21.00)

54.12
115.46
(35.00)
332.84
Rate Analysis
Necha Salyan Gaunpalika

1) Site preparation for removing top soil with 15.20cm depth with disposal per m2
1.1 Labour QuantityUnit Rate Amount Remarks
Unskilled 0.16 md 630.00 100.80
Total RS 100.80 Per m2

2) Excavation in BMS including 30m lead & 1.5m lift per m3


2.2 Labour QuantityUnit Rate Amount Remarks
Unskilled 0.80 md 630.00 504.00
3% Tools & Plants 15.12
Total RS 519.12 Per m3

3)E/w excavation for drain and pipe line trenches in ordinary soil.
Labour Quantity Unit Rate Amount Remarks
Unskilled 1 md 630.00 630.00
3% Tools & Plants 18.90
648.90

4)Refilling of pipe line drain and trenches with soft soil and o. s.
Labour Quantity Unit Rate Amount Remarks
Unskilled 0.5 md 630.00 315.00
3% Tools & Plants 9.45
324.45
5) Excavation in OS including 30m lead & 1.5m lift per m3
2.14 Labour QuantityUnit Rate Amount Remarks
Unskilled 1.59 md 630.00 1001.70
3% Tools & Plants 30.05
Total RS 1031.75 Per m3

6) Excavation in OS including 30m lead & 1.5m lift per m3


2.1 Labour QuantityUnit Rate Amount Remarks
Unskilled 0.70 md 630.00 441.00
3% Tools & Plants 13.23
Total RS 454.23 Per m3

7) Dry Stone Soling work in Floor foundation including 30m lead & 1.5m lift per m3
6.5 Labour QuantityUnit Rate Amount Remarks
Unskilled 1.50 md 630.00 945.00
Materials
Block & B 1.10 m3 2520.00 2772.00
Total RS 3717.00 Per m3

8) Dry stone masonry work including 30m lead & 1.5m lift per m3
6.2.1 Labour QuantityUnit Rate Amount Remarks
Skilled 1.00 md 760.00 760.00
Unskilled 2.00 md 630.00 1260.00
Materials
Block & B 1.10 m3 2520.00 2772.00
Total RS 4792.00 Per m3

9) Stone masonry work in Mud mortar including 30m lead & 1.5m lift per m3
6.2.2 Labour QuantityUnit Rate Amount Remarks
Skilled 1.00 md 760.00 760.00
Unskilled 2.25 md 630.00 1417.50
Materials
Block & B 1.10 m3 2520.00 2772.00
Mud 0.42 m3 470.00 197.40
Total RS 5146.90 Per m3

10) Stone masonry work 1:3 in C/S mortar including 30m lead & 1.5m lift per m3
6.2 Labour QuantityUnit Rate Amount Remarks
Skilled 1.50 md 760.00 1140.00
Unskilled 5.00 md 630.00 3150.00
Materials
Block & B 1.10 m3 2520.00 2772.00
Cement 3.88 Bag 1328.00 5152.64
Sand 0.45 m3 7150.00 3217.50
Total RS 15432.14 Per m3

11) Stone masonry work 1:4 in C/S mortar including 30m lead & 1.5m lift per m3
6.2 Labour QuantityUnit Rate Amount Remarks
Skilled 1.50 md 760.00 1140.00
Unskilled 5.00 md 630.00 3150.00
Materials
Block & B 1.10 m3 2520.00 2772.00
Cement 3.18 Bag 1328.00 4223.04
Sand 0.45 m3 7150.00 3217.50
Total RS 14502.54 Per m3

12) Stone masonry work 1:6 in C/S mortar including 30m lead & 1.5m lift per m3
6.2 Labour QuantityUnit Rate Amount Remarks
Skilled 1.50 md 760.00 1140.00
Unskilled 5.00 md 630.00 3150.00
Materials
Block & B 1.10 m3 2520.00 2772.00
Cement 2.12 Bag 1328.00 2815.36
Sand 0.47 m3 7150.00 3360.50
Total RS 13237.86 Per m3

13) Plain Cement Concrete work (1:1.5:3) m3 beam,slab


7.2 gha Labour QuantityUnit Rate Amount Remarks
Skilled 0.80 md 760.00 608.00
Unskilled 7.00 md 630.00 4410.00
Materials
Cement 8.00 Bag 1328.00 10624.00
Sand 0.43 m3 7150.00 3038.75
Aggrigate 0.86 m3 3355.00 2885.30
Total RS 21566.05 Per m3

14 Plain Cement Concrete work (1:2:4) m3 beam slab


7.2 gha Labour QuantityUnit Rate Amount Remarks
Skilled 0.80 md 760.00 608.00
Unskilled 7.00 md 630.00 4410.00
Materials
Cement 6.40 Bag 1328.00 8499.20
Sand 0.45 m3 7150.00 3217.50
Aggrigate 0.85 m3 3355.00 2851.75
Total RS 19586.45 Per m3

15) Plain Cement Concrete work (1:2:4) m3


7.2 gha Labour QuantityUnit Rate Amount Remarks
Skilled 1.00 md 760.00 760.00
Unskilled 4.00 md 630.00 2520.00
Materials
Cement 6.40 Bag 1328.00 8499.20
Sand 0.45 m3 7150.00 3217.50
Aggrigate 0.85 m3 3355.00 2851.75
Total RS 17848.45 Per m3

16) Plain Cement Concrete work (1:3:6) m3


7.2 ga Labour QuantityUnit Rate Amount Remarks
Skilled 1.00 md 760.00 760.00
Unskilled 4.00 md 630.00 2520.00
Materials
Cement 4.40 Bag 1328.00 5843.20
Sand 0.47 m3 7150.00 3360.50
Aggrigate 0.89 m3 3355.00 2985.95
Total RS 15469.65 Per m3

17) 12.5 mm thick Cement sand plaster (1:2) per 100 m2


Labour QuantityUnit Rate Amount Remarks
Skilled 12.00 md 760.00 9120.00
Unskilled 16.00 md 630.00 10080.00
Materials
Cement 18.00 Bag 1328.00 23904.00
Sand 1.22 m3 7150.00 8723.00
Total RS 51827.00 Per 100 m2
Total RS 518.27 Per m2

18) 12.5 mm thick Cement sand plaster (1:3) per 100 m2


Labour QuantityUnit Rate Amount Remarks
Skilled 12.00 md 760.00 9120.00
Unskilled 16.00 md 630.00 10080.00
Materials
Cement 12.50 Bag 1328.00 16600.00
Sand 1.28 m3 7150.00 9152.00
Total RS 44952.00 Per 100 m2
Total RS 449.52 Per m2

19) 12.5 mm thick Cement sand plaster (1:4) per 100 m2


Labour QuantityUnit Rate Amount Remarks
Skilled 12.00 md 760.00 9120.00
Unskilled 16.00 md 630.00 10080.00
Materials
Cement 10.76 Bag 1328.00 14289.28
Sand 1.46 m3 7150.00 10439.00
Total RS 43928.28 Per 100 m2
Total RS 439.28 Per m2
20) 12.5 mm thick Cement sand plaster (1:6) per 100 m2
Labour QuantityUnit Rate Amount Remarks
Skilled 12.00 md 760.00 9120.00
Unskilled 16.00 md 630.00 10080.00
Materials
Cement 7.64 Bag 1328.00 10145.92
Sand 1.57 m3 7150.00 11225.50
Total RS 40571.42 Per 100 m2
Total RS 405.71 Per m2

21) 20 mm thick Cement sand plaster (1:3) per 100 m2


Labour QuantityUnit Rate Amount Remarks
Skilled 14.00 md 760.00 10640.00
Unskilled 19.00 md 630.00 11970.00
Materials
Cement 19.20 Bag 1328.00 25497.60
Sand 1.95 m3 7150.00 13942.50
Total RS 62050.10 Per 100 m2
Total RS 620.50 Per m2

22) 20 mm thick Cement sand plaster (1:4) per 100 m2


Labour QuantityUnit Rate Amount Remarks
Skilled 14.00 md 760.00 10640.00
Unskilled 19.00 md 630.00 11970.00
Materials
Cement 16.20 Bag 1328.00 21513.60
Sand 2.20 m3 7150.00 15730.00
Total RS 59853.60 Per 100 m2
Total RS 598.54 Per m2

23) 20 mm thick Cement sand plaster (1:6) per 100 m2


2.4 ga Labour QuantityUnit Rate Amount Remarks
Skilled 14.00 md 760.00 10640.00
Unskilled 19.00 md 630.00 11970.00
Materials
Cement 11.40 Bag 1328.00 15139.20
Sand 2.35 m3 7150.00 16802.50
Total RS 54551.70 Per 100 m2
Total RS 545.52 Per m2
24) 12 mm thick Mud plastering work per 100 m2
12.6 Labour QuantityUnit Rate Amount Remarks
Skilled 15.00 md 760.00 11400.00
Unskilled 20.00 md 630.00 12600.00
Materials
Soil 1.50 m3 470.00 705.00
cowdung 60.00 kg 4.00 240.00
Total RS 24945.00 Per 100 m2
Total RS 249.45 Per m2

25) 3mm thick cement punning per 10 m2


13.1.Kha Labour QuantityUnit Rate Amount Remarks
Skilled 1.00 md 760.00 760.00
Unskilled 1.00 md 630.00 630.00
Materials
Cement 1.06 Bag 1328.00 1407.68
Sand 0.00 m3 7150.00 0.00
Total RS 2797.68 Per 10 m2
Total RS 279.77 Per m2

26) Flush Pointing (1:3) per 100 m2


14ga Labour QuantityUnit Rate Amount Remarks
Skilled 10.00 md 760.00 7600.00
Unskilled 12.00 md 630.00 7560.00
Materials
Cement 3.10 Bag 1328.00 4116.80
Sand 0.32 m3 7150.00 2288.00
Total RS 21564.80 Per 10 m2
Total RS 215.65 Per m2

27) Two Coat white washing in new surface per 100 m2


13.1.Kha Labour QuantityUnit Rate Amount Remarks
Skilled 1.50 md 760.00 1140.00
Unskilled 1.10 md 630.00 693.00
Materials
White lim 22.00 Bag 160.00 3520.00
Gum 0.88 kg 250.00 220.00
Total RS 5573.00 Per 100 m2
Total RS 55.73 Per m2

28) Wooden form work for RCC work for beam slab per 10 m2
15.3 Labour QuantityUnit Rate Amount Remarks
Skilled 1.72 md 760.00 1307.20
Unskilled 2.57 md 630.00 1619.10
Materials
Wood 0.53 m3 21168.00 11219.04
Nail & Sc 2.50 L/S 50.00
Total RS 14195.34 Per 10 m2
Total RS 1419.53 Per m2

29) Wooden form work for RCC work for Column per 10 m2
15.3 Labour QuantityUnit Rate Amount Remarks
Skilled 1.44 md 760.00 1094.40
Unskilled 2.10 md 630.00 1323.00
Materials
Wood 0.53 m3 21168.00 11134.37
Nail & Sc 2.10 L/S 50.00
Total RS 13601.77 Per 10 m2
Total RS 1360.18 Per m2

30) Two coat readymade enamel painting with aster coat per 100 m2
13.5ga Labour QuantityUnit Rate Amount Remarks
Skilled 13.00 md 760.00 9880.00
Unskilled 12.00 md 630.00 7560.00
Materials
Primer 7.00 Lit 250.00 1750.00
Enamel 15.00 Lit 250.00 3750.00
Total RS 22940.00 Per 10 m2
Total RS 229.40 Per m2

31) Two coat Aluminium paint per 100 m2


13.6 Labour QuantityUnit Rate Amount Remarks
Skilled 10.75 md 760.00 8170.00
Unskilled 10.75 md 630.00 6772.50
Materials
Aluminiu 10.76 Lit 250.00 2690.00
Sand pap 4.00 No 25.00 100.00
Primer 8.10 Lit 250.00 2025.00
Total RS 19757.50 Per 10 m2
Total RS 197.58 Per m2

32) Reinforcement with cutting bending binding and placing in position for RCC work per MT
7.5 Labour QuantityUnit Rate Amount Remarks
Skilled 12.00 md 760.00 9120.00
Unskilled 12.00 md 630.00 7560.00
Materials
Rod 1050.00 kg 88.48 92904.00
Binding w 10.00 kg 90.00 900.00
Total RS 110484.00 Per MT
Total RS 110.48 Per kg

33) Local wood work for Door & Window Chaukhat per m3
10.1b Labour QuantityUnit Rate Amount Remarks
Skilled 34.00 md 760.00 25840.00
Unskilled 3.40 md 630.00 2142.00
Materials
Local wo 1.10 m3 21168.00 23284.80
Holdfast 92.00 No 25.00 2300.00
Screw,Nail 184.00 No 30.00 5520.00
Total RS 59086.80 Per m3

34)38 mm Thick Pannelled Shutter preparing frame (1.07*1.982=2.114m2)


10.2 Labour QuantityUnit Rate Amount Remarks
Skilled 10.00 md 760.00 7600.00
Unskilled 1.00 md 630.00 630.00
Materials
Local wo 0.08 m3 21168.00 1693.44
Kabja 6.00 No 50.00 300.00
Cheskini 2.00 No 50.00 100.00
Locking s 1.00 No 125.00 125.00
Handle 2.00 No 350.00 700.00
Screw,NailL/S No 150.00 150.00
Total RS 11298.44
Total RS 5354.71 per m2
35) Local wood work for Beam, Rafter, Purlin etc per m3
10.17.khaLabour QuantityUnit Rate Amount Remarks
Skilled 17.65 md 760.00 13414.00
Unskilled 1.76 md 630.00 1108.80
Materials
Local wo 1.05 m3 21168.00 22226.40
Screw,Nail
L/S No 150.00 150.00
Total RS 36899.20 per m3
36) Local wood work for Truss etc per m3
10.18 khaLabour QuantityUnit Rate Amount Remarks
Skilled 17.65 md 760.00 13414.00
Unskilled 26.00 md 630.00 16380.00
Materials
Local wo 1.05 m3 21168.00 22226.40
Screw,Nail
L/S No 150.00 150.00
Total RS 52170.40 per m3
37) 25 mm Local wood work for Eaves Board etc per 10 m2
10.18 khaLabour QuantityUnit Rate Amount Remarks
Skilled 1.43 md 760.00 1086.80
Unskilled 0.14 md 630.00 88.20
Materials
Local wo 0.28 m3 21168.00 5927.04
Screw,Nail
L/S No 150.00 150.00
Total RS 7252.04
Total RS 725.20 per m2

38) 38*75 mm Thick Glazed shutter preparing frame (1.07*1.982=2.114 m2)


3 mm Thick Glass
10.3 a Labour QuantityUnit Rate Amount Remarks
Skilled 9.00 md 760.00 6840.00
Unskilled 0.90 md 630.00 567.00
Materials
Local wo 0.05 m3 21168.00 1058.40
3.5 mm gl 1.09 No 680.00 741.20
Cheskini 4.00 No 50.00 200.00
Kabja 8.00 No 50.00 400.00
Handle 2.00 No 350.00 700.00
Screw,Nail
L/S No 15.00 100.00
Total RS 10606.60
Total RS 5017.31 per m2

39) 38*75 mm Thick Glazed shutter preparing frame (1.07*1.982=2.114 m2)


4 mm Thick Glass
10.3 a Labour QuantityUnit Rate Amount Remarks
Skilled 9.00 md 760.00 6840.00
Unskilled 0.90 md 630.00 567.00
Materials
Local wo 0.05 m3 21168.00 1058.40
4 mm glas 1.09 No 720.00 784.80
Cheskini 4.00 No 25.00 100.00
Kabja 8.00 No 50.00 400.00
Handle 2.00 No 350.00 700.00
Screw,Nail
L/S No 15.00 100.00
Total RS 10550.20
Total RS 4990.63 per m2

40) 38*75 mm Thick Glazed shutter preparing frame (1.07*1.982=2.114 m2)


6 mm Thick Glass
10.3 a Labour QuantityUnit Rate Amount Remarks
Skilled 9.00 md 760.00 6840.00
Unskilled 0.90 md 630.00 567.00
Materials
Local wo 0.05 m3 21168.00 1058.40
5 mm glas 1.09 No 860.00 937.40
Cheskini 4.00 No 25.00 100.00
Kabja 8.00 No 50.00 400.00
Handle 2.00 No 350.00 700.00
Screw,Nail
L/S No 15.00 100.00
Total RS 10702.80
Total RS 5062.82 per m2

41) 20mm Thick Local wooden celling work per 10m2


Labour QuantityUnit Rate Amount Remarks
Skilled 1.80 md 760.00 1368.00
Unskilled 1.50 md 630.00 945.00
Materials
Local wo 0.26 m3 21168.00 5503.68
Screw,Nail
L/S No 15.00 100.00
Total RS 7916.68 per 10m2
Total RS 791.67 per m2

42) 25mm Thick Local wooden flooring work per 10m2


Labour QuantityUnit Rate Amount Remarks
Skilled 6.50 md 760.00 4940.00
Unskilled 0.65 md 630.00 409.50
Materials
Local wo 0.42 m3 21168.00 8890.56
Screw,Nail
L/S No 15.00 100.00
Total RS 14340.06 per 10m2
Total RS 1434.01 per m2
43) Local wood work for Circular beam per m3
Labour QuantityUnit Rate Amount Remarks
Skilled md 760.00 0.00
Unskilled md 630.00 0.00
Materials
Local wo 1.00 m3 21168.00 21168.00
Screw,Nail
L/S No 100.00
Total RS 0.00 per m3
21268.00

44) Dismantaling Work


a Stone Masonry wall in mud mortar including 10 m lead Distance per m3
Labour QuantityUnit Rate Amount Remarks
Unskilled 1.06 md 630.00 667.80
Total RS 667.80 per m3

b Dismantling cement mortar transporting 10m distance & stacking per m2


Labour QuantityUnit Rate Amount Remarks
Skilled md 0.00
Unskilled 2.12 690.00 1462.80
Total RS 1462.80 per m3

c Dismantling RCC transporting 10m distance & stacking per m2


Labour QuantityUnit Rate Amount Remarks
Unskilled 11.00 md 690.00 7590.00
Total RS 7590.00 per m3

d Dismantling PCC transporting 10m distance & stacking per m2


Labour QuantityUnit Rate Amount Remarks
Unskilled 4.00 md 690.00 2760.00
Total RS 2760.00 per m3

e Dismantling Gabion work transporting 10m distance & stacking per m2


Labour QuantityUnit Rate Amount Remarks
Unskilled 1.00 md 690.00 690.00
Skilled 0.10 835.00 83.50
Total RS 690.00 per m3

f wooden dismantling transporting 10m distance & stacking per m2


Labour QuantityUnit Rate Amount Remarks
Skilled 0.05 md 760.00 38.00
Unskilled 0.08 md 630.00 50.40
Total RS 88.40 per m2
g Tile slate dismantling transporting 10m distance & stacking per m2
Labour QuantityUnit Rate Amount Remarks
Skilled 0.05 md 835.00 41.75
Unskilled 0.08 md 630.00 50.40
Total RS 92.15 per m2

45) 26 Gauge CGI sheet(59kg/wt per bundle) in Roof per 10 m2


Labour QuantityUnit Rate Amount Remarks
Skilled 1.10 md 760.00 836.00
Unskilled 1.25 md 630.00 787.50
Materials
CGI Sheet 12.00 m2 600.14 7201.68
Nut bolts 30.00 No 3.50 105.00
J hook 25.00 No 2.00 50.00
Washer 55.00 No 1.00 55.00
Total RS 9035.18 per 10m2
Total RS 903.52 per m2
46) 26Gauge Ridge cover in Roof per 10 m2
Labour QuantityUnit Rate Amount Remarks
Skilled 2.00 md 760.00 1520.00
Unskilled 3.00 md 630.00 1890.00
Materials
CGI Sheet 12.00 m2 573.29 6879.48
Nut bolts 30.00 No 3.50 105.00
J hook 25.00 No 2.00 50.00
Washer 55.00 No 2.00 110.00
Total RS 10554.48 per 10m2
Total RS 1055.45 per m2

47) 24Gauge CGI sheet in Roof per 10 m2


Labour QuantityUnit Rate Amount Remarks
Skilled 1.10 md 760.00 836.00
Unskilled 1.25 md 630.00 787.50
Materials
CGI Sheet 12.00 m2 802.52 9630.24
Nut bolts 30.00 No 3.50 105.00
J hook 25.00 No 2.00 50.00
Washer 55.00 No 2.00 110.00
Total RS 11518.74 per 10m2
Total RS 1151.87 per m2
Note:-28 gauge-50kg per bundle
26 gauge-65kg per bundle
24 gauge-82kg/bundle
48) OS Filling works spreading with 15/15 cm layer & compact properly
including carrying 10m dist without water sprinkling fokr per m3
2ka25 Labour QuantityUnit Rate Amount Remarks
Unskilled 0.25 md 630.00 157.50
Total RS 157.50 per m3
49) Making sedimentary stone with mecessary size of block with hammer
dressing upto 10m transporting & stacking per m3
3.8 Labour QuantityUnit Rate Amount Remarks
Unskilled 5.88 md 630.00 3704.40
Total RS 3704.40 per m3
50) Making necessary size of rubble stone with chisel breaking upto 10m
transportation & stacking per m3
3.8 Labour QuantityUnit Rate Amount Remarks
Unskilled 5.50 md 630.00 3465.00
Total RS 3465.00 per m3

51).5mm thick Slate Stone Flooring in 1:4 c/s


Labour QuantityUnit Rate Amount Remarks
Skilled 2.00 md 760.00 1520.00
Unskilled 4.50 md 630.00 2835.00
Materials
Slate Ston 11.00 m2 33.27 4355.00
Cement 0.06 Bag 1328.00 7190.00
Sand 0.165 m3 7150.00 7150.00
Total RS 23050.00
Total RS 2144.19 m2

52) Brick wall with chimny made in ground floor 1:3c/s ratio up to 30m lead.
Labour QuantityUnit Rate Amount Remarks
Skilled 1.50 md 835.00 1252.50
Unskilled 2.20 md 690.00 1518.00
Unskilled 0.20 690.00 138.00
Materials
Brick 560.00 Nos. 31.60 17696.00
Cement 0.13 mt 26561.00 3452.93
Sand 0.27 m3 7150.00 1930.50
Total RS 25987.93
add 3% for tools 779.64
Total RS 26767.57

53) Brick wall with chimny made in ground floor 1:4c/s ratio up to 30m lead.
Labour QuantityUnit Rate Amount Remarks
Skilled 1.50 md 760.00 1140.00
Unskilled 2.20 md 630.00 1386.00
Unskilled 0.20 630.00 126.00
Materials 0.00
Brick 560.00 Nos. 31.60 17696.00
Cement 0.10 m3 26561.00 2656.10
Sand 0.28 m3 7150.00 2002.00
Total RS 25006.10
add 3% for tools 750.18
Total RS 25756.28 per m3

54) Brick wall with chimny made above ground floor 1:4c/s ratio up to 30m lead.
Labour QuantityUnit Rate Amount Remarks
Skilled 1.50 md 760.00 1140.00
Unskilled 2.20 md 630.00 1386.00
Unskilled 0.70 630.00 441.00
Materials 0.00
Brick 560.00 Nos. 31.60 17696.00
Cement 0.10 m3 26561.00 2656.10
Sand 0.28 m3 7150.00 2002.00
Total RS 25321.10
add 3% for tools 759.63
Total RS 26080.73 per m3

55) Brick wall with chimny made above ground floor 1:6c/s ratio up to 30m lead.
Labour QuantityUnit Rate Amount Remarks
Skilled 1.50 md 760.00 1140.00
Unskilled 2.20 md 630.00 1386.00
Unskilled 0.70 630.00 441.00
Materials 0.00
Brick 560.00 Nos. 31.60 17696.00
Cement 0.07 m3 26561.00 1859.27
Sand 0.30 m3 7150.00 2145.00
Total RS 24667.27
add 3% for tools 740.02
Total RS 25407.29 per m3

56) Brick wall with chimny made in ground floor 1:6c/s ratio up to 30m lead.
Labour QuantityUnit Rate Amount Remarks
Skilled 1.50 md 760.00 1140.00
Unskilled 2.20 md 630.00 1386.00
Unskilled 0.20 630.00 126.00
Materials 0.00
Brick 560.00 Nos. 31.60 17696.00
Cement 0.07 m3 26561.00 1859.27
Sand 0.30 m3 7150.00 2145.00
Total RS 24352.27
add 3% for tools 730.57
Total RS 25082.84 per m3

Stone per cu meter


Khani 500 0
Trans. 700 Upto1km 0
transportation by tract1km
Breakking 4 630 2520
2520

Cement Rod
Factory Rate 2074 760 70
Vat 13% 0 98.8 9.1
Kattari to 2.52 50 126 2.52
Ghurmi to 1.84 50 92 1.84
Okhaldunga 2.385 50 119.25 2.385
Ramite to 2.64 50 132 2.64
1328.05 88.485
26.561
sand per m3 up to 4 km lead. 26561
Rs65 per ti 3575 4 14300 39
AggregateRs 3355 3355 22

wood per m3 up to 2 kosh transportation


in 1 m3=35.28m3 fit sowith
Chirani and 35.28 600 21168
mud mortar/m3 470
1328

7150
C work per MT
10kg/cm2
16mm
Item Qty. Unit Rate Amount
16mm
procurem
ent 1m 23.00 23
vat @13% 2.99
Total With vat: 25.99

Transportation by truck
Dharan to 220 km 0.055 12.10
Ghurmi to 42 km 0.065 2.73
Okhaldunga 45 km 0.055 2.48
Ramite to 22 0.12 2.64
Load unload 0.24
Transportation cost: 20.19
0.092 kg/m 1.86
Total Cost 27.85

20mm
Item Qty. Unit Rate Amount
16mm
procurem
ent 1m 36.00 36
vat @13% 4.68
Total With vat: 40.68

Transportation by truck
Dharan to 220 km 0.055 12.10
Ghurmi to 42 km 0.065 2.73
Okhaldunga 45 km 0.055 2.48
Ramite to 22 0.12 2.64
Load unload 0.24
Transportation cost: 20.19
0.134 kg/m 2.70
Total Cost 43.38

25mm dia0.202kg/m
Item Qty. Unit Rate Amount
16mm
procurem
ent 1m 56.00 56
vat @13% 7.28
Total With vat: 63.28

Transportation by truck
Dharan to 220 km 0.055 12.10
Ghurmi to 42 km 0.065 2.73
Okhaldunga 45 km 0.055 2.48
Ramite to 22 0.12 2.64
Load unload 0.24
Transportation cost: 20.19
0.202 kg/m 4.08
Total Cost 67.36
6kg/cm2

32mm dia0.334kg/m 32mm6kg/cm2 dia0.334kg/m


Item Qty. Unit Rate Amount Item Qty. Unit Rate
16mm 16mm
procurem procurem
ent 1m 93.00 93 ent 1m 56.50
vat @13% 12.09 vat @13%
Total With vat: 105.09 Total With vat:

Transportation by truck Transportation by truck


Dharan to 220 km 0.055 12.10 Dharan to 220 km 0.055
Ghurmi to 42 km 0.065 2.73 Ghurmi to 42 km 0.065
Okhaldunga 45 km 0.055 2.48 Okhaldunga 45 km 0.055
Ramite to 22 0.12 2.64 Ramite to 22 0.12
Load unload 0.24 Load unload
Transportation cost: 20.19 Transportation cost:
0.334 kg/m 6.74 0.226 kg/m
Total Cost 111.83 Total Cost

40mm dia0.514kg/m
Item Qty. Unit Rate Amount 40mm6kg/cm2 dia0.334kg/m
16mm
procurem Qty. Unit Rate
ent 1m 140.00 140 Item
16mm
procurem
vat @13% 18.2 ent 1m 93.00
Total With vat: 158.2 vat @13%
Total With vat:
Transportation by truck
Dharan to 220 km 0.055 12.10 Transportation by truck
Ghurmi to 42 km 0.065 2.73 Dharan to 220 km 0.055
Okhaldunga 45 km 0.055 2.48 Ghurmi to 42 km 0.065
Ramite to 22 0.12 2.64 Okhaldunga 45 km 0.055
Load unload 0.24 Ramite to 22 0.12
Transportation cost: 20.19 Load unload
0.514 kg/m 10.38 Transportation cost:
Total Cost 168.58 0.35 kg/m
Total Cost

50mm dia0.796kg/m
Item Qty. Unit Rate Amount 50mm6kg/cm2 dia0.334kg/m
16mm
procurem Qty. Unit Rate
ent 1m 221.00 221 Item
16mm
procurem
vat @13% 28.73 ent 1m 141.00
Total With vat: 249.73 vat @13%
Total With vat:
Transportation by truck
Dharan to 220 km 0.055 12.10 Transportation by truck
Ghurmi to 42 km 0.065 2.73 Dharan to 220 km 0.055
Okhaldunga 45 km 0.055 2.48 Ghurmi to 42 km 0.065
Ramite to 22 0.12 2.64 Okhaldunga 45 km 0.055
Load unload 0.24 Ramite to 22 0.12
Transportation cost: 20.19 Load unload
0.796 kg/m 16.07 Transportation cost:
Total Cost 265.80 0.542 kg/m
Total Cost

63mm 10kg/cm2 dia1.269kg/m


Item Qty. Unit Rate Amount 63mm6kg/cm2 dia0.334kg/m
16mm
procurem Qty. Unit Rate
ent 1m 351.00 351 Item
16mm
procurem
vat @13% 45.63 ent 1m 226.00
Total With vat: 396.63 vat @13%
Total With vat:
Transportation by truck
Dharan to 220 km 0.055 12.10 Transportation by truck
Ghurmi to 42 km 0.065 2.73 Dharan to 220 km 0.055
Okhaldunga 45 km 0.055 2.48 Ghurmi to 42 km 0.065
Ramite to 22 0.12 2.64 Okhaldunga 45 km 0.055
Load unload 0.24 Ramite to 22 0.12
Transportation cost: 20.19 Load unload
1.269 kg/m 25.61 Transportation cost:
Total Cost 422.24 0.85 kg/m
Total Cost

75mm 10kg/cm2 dia1.782kg/m


Item Qty. Unit Rate Amount 75mm6kg/cm2 dia0.334kg/m
16mm
procurem Qty. Unit Rate
ent 1m 501.00 501 Item
16mm
procurem
vat @13% 65.13 ent 1m 316.00
Total With vat: 566.13 vat @13%
Total With vat:
Transportation by truck
Dharan to 220 km 0.055 12.10 Transportation by truck
Ghurmi to 42 km 0.065 2.73 Dharan to 220 km 0.055
Okhaldunga 45 km 0.055 2.48 Ghurmi to 42 km 0.065
Ramite to 22 0.12 2.64 Okhaldunga 45 km 0.055
Load unload 0.24 Ramite to 22 0.12
Transportation cost: 20.19 Load unload
1.782 kg/m 35.97 Transportation cost:
Total Cost 602.10 1.191 kg/m
Total Cost

90mm 10kg/cm2 dia2.568kg/m


Item Qty. Unit Rate Amount 90mm6kg/cm2 dia0.334kg/m
16mm
procurem Qty. Unit Rate
ent 1m 715.00 715 Item
16mm
procurem
vat @13% 92.95 ent 1m 456.00
Total With vat: 807.95 vat @13%
Total With vat:
Transportation by truck
Dharan to 220 km 0.055 12.10 Transportation by truck
Ghurmi to 42 km 0.065 2.73 Dharan to 220 km 0.055
Okhaldunga 45 km 0.055 2.48 Ghurmi to 42 km 0.065
Ramite to 22 0.12 2.64 Okhaldunga 45 km 0.055
Load unload 0.24 Ramite to 22 0.12
Transportation cost: 20.19 Load unload
2.568 kg/m 51.84 Transportation cost:
Total Cost 859.79 1.715 kg/m
Total Cost

110mm 10kg/cm2 dia3.801kg/m


Item Qty. Unit Rate Amount 110mm6kg/cm2 dia0.334kg/m
16mm
procurem Qty. Unit Rate
ent 1m 1060.00 1060 Item
16mm
procurem
vat @13% 137.8 ent 1m 660.00
Total With vat: 1197.8 vat @13%
Total With vat:
Transportation by truck
Dharan to 220 km 0.055 12.10 Transportation by truck
Ghurmi to 42 km 0.065 2.73 Dharan to 220 km 0.055
Okhaldunga 45 km 0.055 2.48 Ghurmi to 42 km 0.065
Ramite to 22 0.12 2.64 Okhaldunga 45 km 0.055
Load unload 0.24 Ramite to 22 0.12
Transportation cost: 20.19 Load unload
3.801 kg/m 76.72 Transportation cost:
Total Cost 1274.52 2.545 kg/m
Total Cost

125mm 10kg/cm2 dia4.962kg/m


Item Qty. Unit Rate Amount 125mm6kg/cm2 dia0.334kg/m
16mm
procurem Qty. Unit Rate
ent 1m 1357.00 1357 Item
16mm
procurem
vat @13% 176.41 ent 1m 879.00
Total With vat: 1533.41 vat @13%
Total With vat:
Transportation by truck
Dharan to 220 km 0.055 12.10 Transportation by truck
Ghurmi to 42 km 0.065 2.73 Dharan to 220 km 0.055
Okhaldunga 45 km 0.055 2.48 Ghurmi to 42 km 0.065
Ramite to 22 0.12 2.64 Okhaldunga 45 km 0.055
Load unload 0.24 Ramite to 22 0.12
Transportation cost: 20.19 Load unload
4.962 kg/m 100.16 Transportation cost:
Total Cost 1633.57 3.293 kg/m
Total Cost

200mm 250mm
Item Qty. Unit Rate Amount Item

200- 250-
4kg/cm2 4kg/cm2
mm mm
procurem procurem
ent 1m 1260.46 1260.46 ent
vat @13% 163.8598 vat @13%
Total With vat: 1424.32 Total With vat:

Transportation by truck Transportation by truck


Dharan to 220 km 0.055 12.10 Dharan to
Ghurmi to 42 km 0.065 2.73 Ghurmi to
Okhaldunga 45 km 0.055 2.48 Okhaldunga
Ramite to 22 0.12 2.64 Ramite to
Load unload 0.24 Load unload
Transportation cost: 20.19 Transportation cost:
5.89 kg/m 118.89
Total Cost 1543.21 Total Cost
Amount

56.5
7.345
63.845

12.10
2.73
2.48
2.64
0.24
20.19
4.56
68.41

4kg/cm2

40mm6kg/cm2 dia0.334kg/m

Amount Qty. Unit Rate Amount


Item
16mm
procurem
93 ent 1m 62.75 62.75
12.09 vat @13% 8.1575
105.09 Total With vat: 70.9075

Transportation by truck
12.10 Dharan to 220 km 0.055 12.10
2.73 Ghurmi to 42 km 0.065 2.73
2.48 Okhaldunga 45 km 0.055 2.48
2.64 Ramite to 22 0.12 2.64
0.24 Load unload 0.24
20.19 Transportation cost: 20.19
7.06 0.251 kg/m 5.07
112.15 Total Cost 75.97

50mm6kg/cm2 dia0.334kg/m

Amount Qty. Unit Rate Amount


Item
16mm
procurem
141 ent 1m 94.50 94.5
18.33 vat @13% 12.285
159.33 Total With vat: 106.785

Transportation by truck
12.10 Dharan to 220 km 0.055 12.10
2.73 Ghurmi to 42 km 0.065 2.73
2.48 Okhaldunga 45 km 0.055 2.48
2.64 Ramite to 22 0.12 2.64
0.24 Load unload 0.24
20.19 Transportation cost: 20.19
10.94 0.378 kg/m 7.63
170.27 Total Cost 114.41
2.5kg/cm2

63mm6kg/cm2 dia0.334kg/m 63mm

Amount Qty. Unit Rate Amount Qty.


Item Item
16mm 16mm
procurem procurem
226 ent 1m 159.00 159 ent 1
29.38 vat @13% 20.67 vat @13%
255.38 Total With vat: 179.67 Total With vat:

Transportation by truck Transportation by truck


12.10 Dharan to 220 km 0.055 12.10 Dharan to 220
2.73 Ghurmi to 42 km 0.065 2.73 Ghurmi to 42
2.48 Okhaldunga 45 km 0.055 2.48 Okhaldunga 45
2.64 Ramite to 22 0.12 2.64 Ramite to 22
0.24 Load unload 0.24 Load unload
20.19 Transportation cost: 20.19 Transportation cost:
17.16 0.58 kg/m 11.71 0.403
272.54 Total Cost 191.38 Total Cost

75mm6kg/cm2 dia0.334kg/m 75mm

Amount Qty. Unit Rate Amount Qty.


Item Item
16mm 16mm
procurem procurem
316 ent 1m 220.00 220 ent 1
41.08 vat @13% 28.6 vat @13%
357.08 Total With vat: 248.6 Total With vat:

Transportation by truck Transportation by truck


12.10 Dharan to 220 km 0.055 12.10 Dharan to 220
2.73 Ghurmi to 42 km 0.065 2.73 Ghurmi to 42
2.48 Okhaldunga 45 km 0.055 2.48 Okhaldunga 45
2.64 Ramite to 22 0.12 2.64 Ramite to 22
0.24 Load unload 0.24 Load unload
20.19 Transportation cost: 20.19 Transportation cost:
24.04 0.846 kg/m 17.08 0.557
381.12 Total Cost 265.68 Total Cost

90mm6kg/cm2 dia0.334kg/m 90mm

Amount Qty. Unit Rate Amount Qty.


Item Item
16mm 16mm
procurem procurem
456 ent 1m 305.00 305 ent 1
59.28 vat @13% 39.65 vat @13%
515.28 Total With vat: 344.65 Total With vat:

Transportation by truck Transportation by truck


12.10 Dharan to 220 km 0.055 12.10 Dharan to 220
2.73 Ghurmi to 42 km 0.065 2.73 Ghurmi to 42
2.48 Okhaldunga 45 km 0.055 2.48 Okhaldunga 45
2.64 Ramite to 22 0.12 2.64 Ramite to 22
0.24 Load unload 0.24 Load unload
20.19 Transportation cost: 20.19 Transportation cost:
34.62 1.22 kg/m 24.63 0.799
549.90 Total Cost 369.28 Total Cost

110mm6kg/cm2 dia0.334kg/m 110mm

Amount Qty. Unit Rate Amount Qty.


Item Item
16mm 16mm
procurem procurem
660 ent 1m 430.00 430 ent 1
85.8 vat @13% 55.9 vat @13%
745.8 Total With vat: 485.9 Total With vat:

Transportation by truck Transportation by truck


12.10 Dharan to 220 km 0.055 12.10 Dharan to 220
2.73 Ghurmi to 42 km 0.065 2.73 Ghurmi to 42
2.48 Okhaldunga 45 km 0.055 2.48 Okhaldunga 45
2.64 Ramite to 22 0.12 2.64 Ramite to 22
0.24 Load unload 0.24 Load unload
20.19 Transportation cost: 20.19 Transportation cost:
51.37 1.703 kg/m 34.38 1.185
797.17 Total Cost 520.28 Total Cost

160mm 125mm

Amount Qty. Unit Rate Amount Qty.


Item Item
16mm 16mm
procurem procurem
879 ent 1m 975.00 975 ent 1
114.27 vat @13% 126.75 vat @13%
993.27 Total With vat: 1101.75 Total With vat:

Transportation by truck Transportation by truck


12.10 Dharan to 220 km 0.055 12.10 Dharan to 220
2.73 Ghurmi to 42 km 0.065 2.73 Ghurmi to 42
2.48 Okhaldunga 45 km 0.055 2.48 Okhaldunga 45
2.64 Ramite to 22 0.12 2.64 Ramite to 22
0.24 Load unload 0.24 Load unload
20.19 Transportation cost: 20.19 Transportation cost:
66.47 2.85 kg/m 57.53 1.53
1059.74 Total Cost 1159.28 Total Cost

Qty. Unit Rate Amount

1m 1260.46 1286.57
vat @13% 167.2541
Total With vat: 1453.824

Transportation by truck
220 km 0.055 12.10
42 km 0.065 2.73
45 km 0.055 2.48
22 0.12 2.64
Load unload 0.24
Transportation cost: 20.19
5.89 kg/m 118.89
Total Cost 1572.71
Unit Rate Amount

m 100.75 100.75
13.0975
113.8475

ation by truck
km 0.055 12.10
km 0.065 2.73
km 0.055 2.48
0.12 2.64
0.24
20.19
kg/m 8.13
121.98

Unit Rate Amount

m 139.25 139.25
18.1025
157.3525

ation by truck
km 0.055 12.10
km 0.065 2.73
km 0.055 2.48
0.12 2.64
0.24
20.19
kg/m 11.24
168.60

Unit Rate Amount

m 200.00 200
26
226

ation by truck
km 0.055 12.10
km 0.065 2.73
km 0.055 2.48
0.12 2.64
0.24
20.19
kg/m 16.13
242.13

Unit Rate Amount

m 298.00 298
38.74
336.74

ation by truck
km 0.055 12.10
km 0.065 2.73
km 0.055 2.48
0.12 2.64
0.24
20.19
kg/m 23.92
360.66

Unit Rate Amount

m 379.00 379
49.27
428.27

ation by truck
km 0.055 12.10
km 0.065 2.73
km 0.055 2.48
0.12 2.64
0.24
20.19
kg/m 30.88
459.15

You might also like