Solukhumbu ESTIMATE-27th Sept
Solukhumbu ESTIMATE-27th Sept
V Masonry Works
9" Brick masonry work in 1:5cement sand
1.00 Cu.ft. 2538.44 71.88 26767.57
mortar as per drawing and specification
4.5" Thick Brick masonry work in 1:4 cement sand
2.00 Cu.ft. 483.80 13.69 26767.57
mortar as per drawing and specification
VII PLASTER WORKS
12.5 mm thick cement plastering work in 1:4 cement
1.00 mortar of good finish including cleaning and wetting the Sq.ft. 4541.15 421.88 545.52
wall surface and curing the work all complete
20mm Thick Outside Plaster cement plastering work in
2.00 1:5 cement mortar of good finish including cleaning and Sq.ft. 4541.15 421.88 545.52
wetting the wall surface and curing the work all complete
5.00 Rain Drip Plaster R.ft.
VIII FLOOR FINISHING WORKS
38mm thick M15 concrete screeding work on floor as per
1.00 Sq.ft.
specification and as directed by Engineer.
3mm thick Punning work in cement mortar (1:1) on floor,
2.00 wall and in skirting as per specification and as directed by Sq.ft.
Engineer.
Non skidding Glazed ceramic kitchen/bathroom tile
cladding with 20mm thick screeding in 1:4 cement sand
3.00 mortar and joint filling by 1:1 cement morar including Sq.ft.
curing, cleaning all complete as per specifications and as
directed by Engineer.
Non skidding Glazed ceramic Parking tile cladding with
20mm thick screeding in 1:4 cement sand mortar and joint
4.00 Sq.ft.
filling by 1:1 cement morar including curing, cleaning all
complete as per specifications and as directed by Engineer.
One Crore Thirty-Two Lakhs Fifteen Thousand Seven Hundred Ninety One only
labour
sand and aggregate
Cement
Rebar
Tile
ki bat
colour
steel
mi
brick
Amount
5,000.00
224,734,938.62
2,858,687.33
2,827.70
58,649,186.81
345.00
193,504,363.34
12,158,208,310.66
5,895.65
570.00 3743833.31
6,942,595.61
453,883.27
283.37
4,884,093,021.53
35965.43 12500.00 354.21
177,288,437.99
1290.14 3.56
1,045,113,266.85
315.00 29.28 10.76
1,045,118,323.88
- s
-
220.00 20.45
-
-
-
-
0.00
-
-
439,489,481.38
-
-
350,000.00
20,236,813,221
350,000
20,237,163,221 20237163220.62
3,268.00
4,634.00
4,367,104.71
1,946,280.00
969,000.00
1,320,000.00
1,710,000.00
500,000.00
500,000.00
500,000.00
450,000.00
500,000.00
1,152,000.00
9,547,280.00
Batisputalir, Kathmandu
Building Type :- Plot 1
2 Earthwork
2.1 Earthwork in Excavation
2.1.1 Foundation Trentches
F1 Cft 3 7.00 7.00 5.00
F2 Cft 5 6.50 6.50 5.00
F3 Cft 4 6.00 6.00 5.00
F4 Cft 3 5.50 5.50 5.00
Wall Footing Trenches Priphery
A123-B123/D123-E123 Cft 6 12.00 2.00 2.50
ABCDE1-ABCDE2 Cft 5 16.30 2.00 2.50
ABCDE2-ABCDE3 Cft 5 7.10 2.00 2.50
Earthwork in Fillings
Back Filling in Trentches 50% of the Excavated Quantity
In Plinth
AB-12 Cft 1 Area = 195.60 2.00
CD-12 Cft 1 Area = 203.75 2.00
BC-12 Cft 1 Area = 203.75 2.00
DE-12 Cft 1 Area = 195.60 2.00
AB-23 Cft 1 Area = 84.00 2.00
BC-23 Cft 1 Area = 87.50 2.00
CD-23 Cft 1 Area = 87.50 2.00
DE-23 Cft 1 Area = 84.00 2.00
Quantity Total Quantity Remarks
1,158.00 1,158.00
3,910.00
735.00
1,056.25
720.00
453.75
360.00
407.50
177.50
3,552.40
1,955.00
391.20
407.50
407.50
391.20
168.00
175.00
175.00
168.00
Chetana Bistar Sarbajanik Pustakalaya, Necha, Solukhumbu
Building Type :- Plot 1
Total Remar
S.No. Description Unit Nos. Length Breadth Height Quantity
Quantity ks
Flat Brick Soling 2,828.70
1.1 Parking and Side Walk Sft 1 Area= 800.00 800.00
2.1.1 Foundation Trentches
F1 Sft 3 7.00 7.00 147.00
F2 Sft 5 6.50 6.50 211.25
F3 Sft 4 6.00 6.00 144.00
F4 Sft 3 5.50 5.50 90.75
Wall Footing Trenches
Priphery
A123-B123/D123-E123 Sft 6 12.00 2.00 144.00
ABCDE1-ABCDE2 Sft 5 16.30 2.00 163.00
ABCDE2-ABCDE3 Sft 5 7.10 2.00 71.00
In Plinth
AB-12 Sft 1 Area = 195.60 195.60
CD-12 Sft 1 Area = 203.75 203.75
BC-12 Sft 1 Area = 203.75 203.75
DE-12 Sft 1 Area = 195.60 195.60
AB-23 Sft 1 Area = 84.00 84.00
BC-23 Sft 1 Area = 87.50 87.50
CD-23 Sft 1 Area = 87.50 87.50
DE-23 Sft 1 Area = 84.00 84.00
6.33
Chetana Bistar Sarbajanik Pustakalaya, Necha, Solukhumbu
Building Type :- Plot 1
3 Column
4.1 SubStructure Column(Pedestal)
CA1 Cft 15 1.00 4.00
5,104.186
0.25 7.00
0.25 6.50
0.25 6.00
0.25 5.50
0.83 23.24
0.83 21.58
0.83 19.92
0.83 18.26
0.25 18.00
0.25 20.38
0.25 8.88
2.25 183.38
2.25 78.75
2.25 81.00
2.25 84.38
2.25 84.38
2.25 81.00
3.00 244.50
3.00 105.00
3.00 108.00
3.00 112.50
3.00 112.50
3.00 108.00
162.00
171.00
171.00
162.00
64.80
68.40
68.40
64.80
3.00 42.00
3.00 72.00
64.80
26.83
8.17
44.48
14.79
14.77
0.42 7.14
26.83
8.17
44.48
14.79
14.77
0.42 7.14
6.00 360.00
9.50 570.00
9.50 570.00
9.50 570.00
9.50 152.00
Chetana Bistar Sarbajanik Pustakalaya, Necha, Solukhumbu
Building Type :- Plot 1
102.90
147.88
100.80
63.53
42.18
37.95
33.98
30.25
59.63
75.60
6.63
8.40
59.63
75.60
178.88
226.80
19.88 0
25.20
19.88
25.20
178.88
226.80
19.88
25.20
19.88
25.20
178.88
226.80
19.88
25.20
19.88
25.20
6.75
12.15
616.09
616.09
616.09
109.56
15.86
31.88
13.06
8.16
7.44
15.86
31.88
13.06
8.16
7.44
456.32
141.00
141.00
141.00
33.32
Chetana Bistar Sarbajanik Pustakalaya, Necha, Solukhumbu
Building Type :- Plot 1
Total Remar
S.No. Description Unit Nos. Length Breadth Height Quantity
Quantity ks
P.C.C.Works(1cement:3s
and:6aggregates) 365.95
PCC(1cement:2sand:4ag
2.2.2 gregates) 618.81
In Plinth
A(1-3),B(1-3),C(1-3),D(1-3),E(1-3)
Cft 5 Area = 16.65 0.75 62.44
1(A-E), 2(A-E),3(A-E) Cft 3 Area = 35.85 0.75 80.66
First Floor
A(1-3), Cft 1 21.20 0.75 9.02
Deduction W3 Cft -1 3.00 0.75 4.50
Deduction W4 Cft -1 8.00 0.75 4.50
E(1-3) Cft 1 21.20 0.75 9.02
Deduction W2 Cft -1 6.00 0.75 4.50
Deduction W3 Cft -1 3.00 0.75 4.50
3(A-E) Cft 1 44.80 0.75 9.02
Deduction W2 Cft -1 6.00 0.75 4.50
Deduction W5 Cft -1 6.30 0.75 9.02
Deduction W1 Cft -1 4.00 0.75 4.50
Deduction D2 Cft -1 2.50 0.75 7.00
1(A-E) Cft 1 44.80 0.75 9.02
Deduction W2 Cft -1 6.00 0.75 4.50
Deduction W4 Cft -1 8.00 0.75 4.50
Second Floor
A(1-3), Cft 1 21.20 0.75 4.50
Deduction W3 Cft -1 3.00 0.75 4.50
Deduction W4 Cft -1 8.00 0.75 4.50
E(1-3) Cft 1 21.20 0.75 9.02
Deduction W3 Cft -1 3.00 0.75 4.50
3(A-E) Cft 1 44.80 0.75 9.02
Deduction W2 Cft -1 6.00 0.75 4.50
Deduction W5 Cft -1 6.30 0.75 9.02
Deduction W1 Cft -1 4.00 0.75 4.50
Deduction D2 Cft -1 2.50 0.75 7.00
1(A-E) Cft 1 44.80 0.75 4.50
Deduction W2 Cft -2 6.00 0.75 4.50
Deduction W4 Cft -2 8.00 0.75 4.50
119.25
119.25
252.00
252.00
143.47
(10.13)
143.47
(10.13)
303.18
(20.25)
(27.00)
(42.00)
303.18
(60.75)
(54.00)
143.47
(10.13)
(27.00)
143.42
(20.25)
(10.13)
303.07
(20.25)
(42.64)
(13.50)
(13.13)
303.18
(20.25)
(27.00)
71.55
(10.13)
(27.00)
143.42
(10.13)
303.07
(20.25)
(42.62)
(13.50)
(13.13)
151.20
(40.50)
(54.00)
38.97
155.87
26.34
38.97
45.10
(8.40)
21.65
46.18
(14.00)
133.14
483.80
Chetana Bistar Sarbajanik Pustakalaya, Necha, Solukhumbu
BAR BENDING SCHEDULE
ALL In mm
Bar No of Laps for
Description Shape of Bar Bar Dia Cutting
NO. No. bars each
Length
1 Column footing F1
12 3 43 2132 2.00
Main Bar
75
75
1982
2 Distribution bar F1
12 5 71 2132 2.00
75
75
1982
1 Column footing F2
12 5 66 1979 2.00
Main Bar
75
75
1829
2 Distribution bar F2
12 4 53 1979 2.00
75
75
1829
Column footing F3
12 4 49 1826 2.00
Main Bar
75
75
1676
Distribution bar F3
12 2 25 1826 2.00
75
75
1676
Column footing F4
12 3 34 1674 2.00
Main Bar
75
75
1524
Distribution bar F4
12 4 45 1674 2.00
75
75
1524
4 Column C-1 20MM 15
11684
A Vertical L Main Bars LONG
20 4 12594 2
910
4 Column C-1 16 MM 15
11684
A Vertical L Main Bars LONG
16 4 12594 8
910
600
15240
600
15240
600
7467
Beam along short span 15
12 20 8667 1
Top bar and bottom 16 dia
600
600
7467
BEAM STIRRUP
Along long span 180
8 967 1110
75
300
300
75
180
Along short span 746.76 1110
TIE Beam along long span 6
12 36 16240 1
Top and bottom bar 12 dia
500
500
15240
TIE Beam along short span 10
12 20 8467 1
Top bar and bottom 16 dia
500
500
500
500
7467
180
180
75
180
300
75
300
SLAB STIRRUP
8 50.78
aling x-direction
75 75
aling y-direction
8 102.6 15390
15240
SUB TOTAL
echa, Solukhumbu
LE
ALL In mm
Lap Total Length Unit Wt Total Wt. in
REMARKS
Length in (m) Kg/M Kgs.
(mm)
7.0192
720 131.99 0.889 117.32
0.457317073
720 90.35 0.889 80.31
4108.14 kg 4108.14
Total Quantity 4.11 M. ton 4108.14
6.33 5.00 285.00
5.67 5.00 528.70
1.930894
1.727642
Chetana Bistar Sarbajanik Pustakalaya, Necha, Solukhumbu
Building Type :- Plot 8
First Floor
A(1-3), Cft 1 21.20 9.02
Deduction W3 Cft -1 3.00 4.50
Deduction W4 Cft -1 8.00 4.50
E(1-3) Cft 1 21.20 9.02
Deduction W2 Cft -1 6.00 4.50
Deduction W3 Cft -1 3.00 4.50
3(A-E) Cft 1 47.80 9.02
Deduction W2 Cft -1 6.00 4.50
Deduction W5 Cft -1 6.30 9.02
Deduction W1 Cft -1 4.00 4.50
Deduction D2 Cft -1 2.50 7.00
1(A-E) Cft 1 44.80 9.02
Deduction W2 Cft -3 6.00 4.50
Deduction W4 Cft -2 8.00 4.50
Second Floor
A(1-3), Cft 1 21.20 4.50
Deduction W3 Cft -1 3.00 4.50
Deduction W4 Cft -1 8.00 4.50
E(1-3) Cft 1 21.20 9.02
Deduction W4 Cft -1 3.00 4.50
3(A-E) Cft 1 44.80 9.02
Deduction W2 Cft -1 6.00 4.50
Deduction W5 Cft -1 6.30 9.02
Deduction W1 Cft -1 4.00 4.50
Deduction D2 Cft -1 2.50 7.00
1(A-E) Cft 1 44.80 4.50
Deduction W2 Cft -2 6.00 4.50
Deduction W4 Cft -2 8.00 4.50
159.00
159.00
336.00
336.00
191.29
(13.50)
191.29
(13.50)
404.25
(13.50)
(11.25)
(27.00)
(49.00)
(8.25)
404.25
(81.00)
(72.00)
191.29
(13.50)
(36.00)
191.22
(27.00)
(13.50)
431.16
(27.00)
(56.85)
(18.00)
(17.50)
404.25
(81.00)
(72.00)
95.40
(13.50)
(36.00)
191.22
(13.50)
404.10
(27.00)
(56.83)
(18.00)
(17.50)
201.60
(54.00)
(72.00)
97.42
389.66
65.85
97.42
112.75
(21.00)
54.12
115.46
(35.00)
332.84
Rate Analysis
Necha Salyan Gaunpalika
1) Site preparation for removing top soil with 15.20cm depth with disposal per m2
1.1 Labour QuantityUnit Rate Amount Remarks
Unskilled 0.16 md 630.00 100.80
Total RS 100.80 Per m2
3)E/w excavation for drain and pipe line trenches in ordinary soil.
Labour Quantity Unit Rate Amount Remarks
Unskilled 1 md 630.00 630.00
3% Tools & Plants 18.90
648.90
4)Refilling of pipe line drain and trenches with soft soil and o. s.
Labour Quantity Unit Rate Amount Remarks
Unskilled 0.5 md 630.00 315.00
3% Tools & Plants 9.45
324.45
5) Excavation in OS including 30m lead & 1.5m lift per m3
2.14 Labour QuantityUnit Rate Amount Remarks
Unskilled 1.59 md 630.00 1001.70
3% Tools & Plants 30.05
Total RS 1031.75 Per m3
7) Dry Stone Soling work in Floor foundation including 30m lead & 1.5m lift per m3
6.5 Labour QuantityUnit Rate Amount Remarks
Unskilled 1.50 md 630.00 945.00
Materials
Block & B 1.10 m3 2520.00 2772.00
Total RS 3717.00 Per m3
8) Dry stone masonry work including 30m lead & 1.5m lift per m3
6.2.1 Labour QuantityUnit Rate Amount Remarks
Skilled 1.00 md 760.00 760.00
Unskilled 2.00 md 630.00 1260.00
Materials
Block & B 1.10 m3 2520.00 2772.00
Total RS 4792.00 Per m3
9) Stone masonry work in Mud mortar including 30m lead & 1.5m lift per m3
6.2.2 Labour QuantityUnit Rate Amount Remarks
Skilled 1.00 md 760.00 760.00
Unskilled 2.25 md 630.00 1417.50
Materials
Block & B 1.10 m3 2520.00 2772.00
Mud 0.42 m3 470.00 197.40
Total RS 5146.90 Per m3
10) Stone masonry work 1:3 in C/S mortar including 30m lead & 1.5m lift per m3
6.2 Labour QuantityUnit Rate Amount Remarks
Skilled 1.50 md 760.00 1140.00
Unskilled 5.00 md 630.00 3150.00
Materials
Block & B 1.10 m3 2520.00 2772.00
Cement 3.88 Bag 1328.00 5152.64
Sand 0.45 m3 7150.00 3217.50
Total RS 15432.14 Per m3
11) Stone masonry work 1:4 in C/S mortar including 30m lead & 1.5m lift per m3
6.2 Labour QuantityUnit Rate Amount Remarks
Skilled 1.50 md 760.00 1140.00
Unskilled 5.00 md 630.00 3150.00
Materials
Block & B 1.10 m3 2520.00 2772.00
Cement 3.18 Bag 1328.00 4223.04
Sand 0.45 m3 7150.00 3217.50
Total RS 14502.54 Per m3
12) Stone masonry work 1:6 in C/S mortar including 30m lead & 1.5m lift per m3
6.2 Labour QuantityUnit Rate Amount Remarks
Skilled 1.50 md 760.00 1140.00
Unskilled 5.00 md 630.00 3150.00
Materials
Block & B 1.10 m3 2520.00 2772.00
Cement 2.12 Bag 1328.00 2815.36
Sand 0.47 m3 7150.00 3360.50
Total RS 13237.86 Per m3
28) Wooden form work for RCC work for beam slab per 10 m2
15.3 Labour QuantityUnit Rate Amount Remarks
Skilled 1.72 md 760.00 1307.20
Unskilled 2.57 md 630.00 1619.10
Materials
Wood 0.53 m3 21168.00 11219.04
Nail & Sc 2.50 L/S 50.00
Total RS 14195.34 Per 10 m2
Total RS 1419.53 Per m2
29) Wooden form work for RCC work for Column per 10 m2
15.3 Labour QuantityUnit Rate Amount Remarks
Skilled 1.44 md 760.00 1094.40
Unskilled 2.10 md 630.00 1323.00
Materials
Wood 0.53 m3 21168.00 11134.37
Nail & Sc 2.10 L/S 50.00
Total RS 13601.77 Per 10 m2
Total RS 1360.18 Per m2
30) Two coat readymade enamel painting with aster coat per 100 m2
13.5ga Labour QuantityUnit Rate Amount Remarks
Skilled 13.00 md 760.00 9880.00
Unskilled 12.00 md 630.00 7560.00
Materials
Primer 7.00 Lit 250.00 1750.00
Enamel 15.00 Lit 250.00 3750.00
Total RS 22940.00 Per 10 m2
Total RS 229.40 Per m2
32) Reinforcement with cutting bending binding and placing in position for RCC work per MT
7.5 Labour QuantityUnit Rate Amount Remarks
Skilled 12.00 md 760.00 9120.00
Unskilled 12.00 md 630.00 7560.00
Materials
Rod 1050.00 kg 88.48 92904.00
Binding w 10.00 kg 90.00 900.00
Total RS 110484.00 Per MT
Total RS 110.48 Per kg
33) Local wood work for Door & Window Chaukhat per m3
10.1b Labour QuantityUnit Rate Amount Remarks
Skilled 34.00 md 760.00 25840.00
Unskilled 3.40 md 630.00 2142.00
Materials
Local wo 1.10 m3 21168.00 23284.80
Holdfast 92.00 No 25.00 2300.00
Screw,Nail 184.00 No 30.00 5520.00
Total RS 59086.80 Per m3
52) Brick wall with chimny made in ground floor 1:3c/s ratio up to 30m lead.
Labour QuantityUnit Rate Amount Remarks
Skilled 1.50 md 835.00 1252.50
Unskilled 2.20 md 690.00 1518.00
Unskilled 0.20 690.00 138.00
Materials
Brick 560.00 Nos. 31.60 17696.00
Cement 0.13 mt 26561.00 3452.93
Sand 0.27 m3 7150.00 1930.50
Total RS 25987.93
add 3% for tools 779.64
Total RS 26767.57
53) Brick wall with chimny made in ground floor 1:4c/s ratio up to 30m lead.
Labour QuantityUnit Rate Amount Remarks
Skilled 1.50 md 760.00 1140.00
Unskilled 2.20 md 630.00 1386.00
Unskilled 0.20 630.00 126.00
Materials 0.00
Brick 560.00 Nos. 31.60 17696.00
Cement 0.10 m3 26561.00 2656.10
Sand 0.28 m3 7150.00 2002.00
Total RS 25006.10
add 3% for tools 750.18
Total RS 25756.28 per m3
54) Brick wall with chimny made above ground floor 1:4c/s ratio up to 30m lead.
Labour QuantityUnit Rate Amount Remarks
Skilled 1.50 md 760.00 1140.00
Unskilled 2.20 md 630.00 1386.00
Unskilled 0.70 630.00 441.00
Materials 0.00
Brick 560.00 Nos. 31.60 17696.00
Cement 0.10 m3 26561.00 2656.10
Sand 0.28 m3 7150.00 2002.00
Total RS 25321.10
add 3% for tools 759.63
Total RS 26080.73 per m3
55) Brick wall with chimny made above ground floor 1:6c/s ratio up to 30m lead.
Labour QuantityUnit Rate Amount Remarks
Skilled 1.50 md 760.00 1140.00
Unskilled 2.20 md 630.00 1386.00
Unskilled 0.70 630.00 441.00
Materials 0.00
Brick 560.00 Nos. 31.60 17696.00
Cement 0.07 m3 26561.00 1859.27
Sand 0.30 m3 7150.00 2145.00
Total RS 24667.27
add 3% for tools 740.02
Total RS 25407.29 per m3
56) Brick wall with chimny made in ground floor 1:6c/s ratio up to 30m lead.
Labour QuantityUnit Rate Amount Remarks
Skilled 1.50 md 760.00 1140.00
Unskilled 2.20 md 630.00 1386.00
Unskilled 0.20 630.00 126.00
Materials 0.00
Brick 560.00 Nos. 31.60 17696.00
Cement 0.07 m3 26561.00 1859.27
Sand 0.30 m3 7150.00 2145.00
Total RS 24352.27
add 3% for tools 730.57
Total RS 25082.84 per m3
Cement Rod
Factory Rate 2074 760 70
Vat 13% 0 98.8 9.1
Kattari to 2.52 50 126 2.52
Ghurmi to 1.84 50 92 1.84
Okhaldunga 2.385 50 119.25 2.385
Ramite to 2.64 50 132 2.64
1328.05 88.485
26.561
sand per m3 up to 4 km lead. 26561
Rs65 per ti 3575 4 14300 39
AggregateRs 3355 3355 22
7150
C work per MT
10kg/cm2
16mm
Item Qty. Unit Rate Amount
16mm
procurem
ent 1m 23.00 23
vat @13% 2.99
Total With vat: 25.99
Transportation by truck
Dharan to 220 km 0.055 12.10
Ghurmi to 42 km 0.065 2.73
Okhaldunga 45 km 0.055 2.48
Ramite to 22 0.12 2.64
Load unload 0.24
Transportation cost: 20.19
0.092 kg/m 1.86
Total Cost 27.85
20mm
Item Qty. Unit Rate Amount
16mm
procurem
ent 1m 36.00 36
vat @13% 4.68
Total With vat: 40.68
Transportation by truck
Dharan to 220 km 0.055 12.10
Ghurmi to 42 km 0.065 2.73
Okhaldunga 45 km 0.055 2.48
Ramite to 22 0.12 2.64
Load unload 0.24
Transportation cost: 20.19
0.134 kg/m 2.70
Total Cost 43.38
25mm dia0.202kg/m
Item Qty. Unit Rate Amount
16mm
procurem
ent 1m 56.00 56
vat @13% 7.28
Total With vat: 63.28
Transportation by truck
Dharan to 220 km 0.055 12.10
Ghurmi to 42 km 0.065 2.73
Okhaldunga 45 km 0.055 2.48
Ramite to 22 0.12 2.64
Load unload 0.24
Transportation cost: 20.19
0.202 kg/m 4.08
Total Cost 67.36
6kg/cm2
40mm dia0.514kg/m
Item Qty. Unit Rate Amount 40mm6kg/cm2 dia0.334kg/m
16mm
procurem Qty. Unit Rate
ent 1m 140.00 140 Item
16mm
procurem
vat @13% 18.2 ent 1m 93.00
Total With vat: 158.2 vat @13%
Total With vat:
Transportation by truck
Dharan to 220 km 0.055 12.10 Transportation by truck
Ghurmi to 42 km 0.065 2.73 Dharan to 220 km 0.055
Okhaldunga 45 km 0.055 2.48 Ghurmi to 42 km 0.065
Ramite to 22 0.12 2.64 Okhaldunga 45 km 0.055
Load unload 0.24 Ramite to 22 0.12
Transportation cost: 20.19 Load unload
0.514 kg/m 10.38 Transportation cost:
Total Cost 168.58 0.35 kg/m
Total Cost
50mm dia0.796kg/m
Item Qty. Unit Rate Amount 50mm6kg/cm2 dia0.334kg/m
16mm
procurem Qty. Unit Rate
ent 1m 221.00 221 Item
16mm
procurem
vat @13% 28.73 ent 1m 141.00
Total With vat: 249.73 vat @13%
Total With vat:
Transportation by truck
Dharan to 220 km 0.055 12.10 Transportation by truck
Ghurmi to 42 km 0.065 2.73 Dharan to 220 km 0.055
Okhaldunga 45 km 0.055 2.48 Ghurmi to 42 km 0.065
Ramite to 22 0.12 2.64 Okhaldunga 45 km 0.055
Load unload 0.24 Ramite to 22 0.12
Transportation cost: 20.19 Load unload
0.796 kg/m 16.07 Transportation cost:
Total Cost 265.80 0.542 kg/m
Total Cost
200mm 250mm
Item Qty. Unit Rate Amount Item
200- 250-
4kg/cm2 4kg/cm2
mm mm
procurem procurem
ent 1m 1260.46 1260.46 ent
vat @13% 163.8598 vat @13%
Total With vat: 1424.32 Total With vat:
56.5
7.345
63.845
12.10
2.73
2.48
2.64
0.24
20.19
4.56
68.41
4kg/cm2
40mm6kg/cm2 dia0.334kg/m
Transportation by truck
12.10 Dharan to 220 km 0.055 12.10
2.73 Ghurmi to 42 km 0.065 2.73
2.48 Okhaldunga 45 km 0.055 2.48
2.64 Ramite to 22 0.12 2.64
0.24 Load unload 0.24
20.19 Transportation cost: 20.19
7.06 0.251 kg/m 5.07
112.15 Total Cost 75.97
50mm6kg/cm2 dia0.334kg/m
Transportation by truck
12.10 Dharan to 220 km 0.055 12.10
2.73 Ghurmi to 42 km 0.065 2.73
2.48 Okhaldunga 45 km 0.055 2.48
2.64 Ramite to 22 0.12 2.64
0.24 Load unload 0.24
20.19 Transportation cost: 20.19
10.94 0.378 kg/m 7.63
170.27 Total Cost 114.41
2.5kg/cm2
160mm 125mm
1m 1260.46 1286.57
vat @13% 167.2541
Total With vat: 1453.824
Transportation by truck
220 km 0.055 12.10
42 km 0.065 2.73
45 km 0.055 2.48
22 0.12 2.64
Load unload 0.24
Transportation cost: 20.19
5.89 kg/m 118.89
Total Cost 1572.71
Unit Rate Amount
m 100.75 100.75
13.0975
113.8475
ation by truck
km 0.055 12.10
km 0.065 2.73
km 0.055 2.48
0.12 2.64
0.24
20.19
kg/m 8.13
121.98
m 139.25 139.25
18.1025
157.3525
ation by truck
km 0.055 12.10
km 0.065 2.73
km 0.055 2.48
0.12 2.64
0.24
20.19
kg/m 11.24
168.60
m 200.00 200
26
226
ation by truck
km 0.055 12.10
km 0.065 2.73
km 0.055 2.48
0.12 2.64
0.24
20.19
kg/m 16.13
242.13
m 298.00 298
38.74
336.74
ation by truck
km 0.055 12.10
km 0.065 2.73
km 0.055 2.48
0.12 2.64
0.24
20.19
kg/m 23.92
360.66
m 379.00 379
49.27
428.27
ation by truck
km 0.055 12.10
km 0.065 2.73
km 0.055 2.48
0.12 2.64
0.24
20.19
kg/m 30.88
459.15