Time Schedule BG. TAMA 2502 (Additional) - 2

The document provides a schedule and progress report for dock repair works of a ship named BG TAMA 2502. It includes 18 items of work over an estimated time of 18 days. As of the report date, work was 51.90% completed with item 1 at 12.48% and item 2 at 0.19%.

Uploaded by

agus bahar27
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
130 views1 page

Time Schedule BG. TAMA 2502 (Additional) - 2

The document provides a schedule and progress report for dock repair works of a ship named BG TAMA 2502. It includes 18 items of work over an estimated time of 18 days. As of the report date, work was 51.90% completed with item 1 at 12.48% and item 2 at 0.19%.

Uploaded by

agus bahar27
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

TIMES SCHEDULE PROYEK DOCKING REPAIR

NAMA PROYEK : BG. TAMA 2502 STATUS DOCKING : DOCKING REPAIR


PT. DUTABAHARI MENARA LINE
DOCKYARD KODE PEKERJAAN : R - 8.142 /DR KLASIFIKASI : BKI / IS
Jl. Ir.H.P.M Noor, Kuin Cerucuk Banjarmasin - : 18 Hari : 76.20/75.15 x 21.94 x 4.87 Meter
ESTIMASI WAKTU REPAIR DOCK DIMENSI
70129
Telp. +62 511 4413364 Fax. +62 511 4413365 NO. PENAWARAN : PEMILIK KAPAL : PT. HABCO PRIMATAMA

1 2 3 4 5 6 7 8 9
Bobot Progress
NO DESCRIPTION OF WORKS Lama pekerjaan Alat /Gun Progress % Actual Progress %
%

10 11 12 13 14 15 16 17 18
HULL CONSTRUCTION 100.00% 51.90% 51.90%
Side shell Sb
Replating Sideshell Fr. 3/4 - 4/5 (Sb) 8 Hari 99.81% 12.48% 12.48% 12.48% 12.48% 12.48% 12.48% 12.48% 12.48%
Rewelding 1 Hari 0.19% 0.19%

Total 100.00% 12.48% 12.48% 12.48% 12.48% 12.48% 12.48% 12.48% 12.48% 0.19%
24.95% 37.43% 49.91% 62.38% 74.86% 87.34% 99.81% 100.00%

Demikian yang dapat kami sampaikan, atas perhatian dan kerjasamannya saya ucapkan terima kasih.

Direncanakan oleh, Diketahui Disetujui


Keterangan :
= Estimasi
= Re schedule
= Actual
Huruf warna hijau pekerjaan tambahan
Masudi Guszazif Titah P. Hadi Soetrisno = Tidak ada kerja
Pimpro Manager Produksi General Manager = Selesai