Manual Solution ch15
Manual Solution ch15
16 Resource Planning
DISCUSSION QUESTIONS
1. The purpose of this exercise is to get the students to think about the usefulness of
ERP for each of their major areas of interest. Because groups consist of different
functional area representatives, the discussion is intended to emphasize the cross-
functional needs that are satisfied with an information system such as ERP. Some
responses to this exercise include:
q Marketing—information about the availability of finished products that can be
promised for delivery; finished goods inventory performance (service levels,
stockouts).
q Finance—short-term financing needs for production plans, developed from the
order releases and projected inventory levels.
q Accounting—billing invoices for products shipped to customers; payments to
suppliers of raw materials and purchased components, developed from the
schedule of orders actually received.
q Operations—the schedule of order releases to support the master schedule;
estimates of capacity requirements at critical work centers.
3. A master flight schedule specifies the arrival and departure times for all the flights an
airline must produce to meet customer demands. Here, the lead time is the time
between departure and arrival, which is similar to the lead time in producing a
quantity of a product. The passenger size of the aircraft is analogous to a production
quantity, and the available-to-promise quantity in manufacturing bears similarity to
the seats available on a given flight. In general, the flight schedule can be used to
estimate the needs for resources such as pilots, flight attendants, airport slots, and
aircraft.
16-1
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall.
16-2 l PART 3 l Managing Supply Chains
4. The principles of MRP can be used for UPS by identifying bills of resources for
resources such as employees, trucks, planes, and equipment. Forecasts of delivery
requirements and the BORs can be used to estimate resource needs and project the
loads on critical sorting operations.
PROBLEMS
4. The bill of materials for item A with lead times is shown following.
a. Lead time is determined by the longest path
G-E-B-A = 12 weeks.
b. If purchased items D, F, G, and H are already in inventory, the lead time is
reduced to: A–B–E = 8 weeks.
c. Item G is the purchased item with the longest lead time in the longest path. This
purchased item could be kept in stock to reduce the overall lead time.
A
LT = 1
B(1) C(1)
LT = 2 LT = 2
G(1) H(1)
LT = 4 LT = 3
5. Refer to Figure 16.22 and Solved Problem 1.
FIGURE 15.19
A
LT = 1
B(3) C(1)
LT = 2 LT = 3
G(1)
LT = 3
( 5C �1D per C ) = 5D
6. MPS record in Figure 16.29 The following table is from the Master Production
Scheduling Solver in OM Explorer. The ATP row is not required for this problem.
Solver Master Production Scheduling
Lot Size 60
Lead Time 1
Quantity on Hand 35 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Forecast 20 18 28 28 23 30 33 38
MPS Quantity 60 60 60 60
MPS start 60 60 60 60
8. An end-item
Lot Size: 100 Week
Quantity on Hand: 80 1 2 3 4 5 6 7 8 9 10
Forecast 30 20 35 50 25 25 0 40 0 50
Customer orders (booked) 22 30 15 9 0 0 5 3 7 0
Projected on-hand inventory 50 20 85 35 10 85 80 40 33 83
MPS quantity 100 100 100
MPS start 100 100 100
9. Ball Bearings
Prospective MPS
a.
Solver Master Production Scheduling
Forecast 550 300 400 450 300 350 200 300 450 400
Customer Orders (Booked) 300 350 250 250 200 150 100 100 100 100
The first order for 500 (in week 4) should be accepted. Through week 4, on hand
(400) plus three MPS quantities of 500 each = 1900. Of those, (300 + 350 + 250 +
250) = 1150 have been sold, leaving 750 available (250 after this commitment).
b. The second order for 400 (in week 5) should be accepted. Through week 5, the
250 remaining after the first order plus one more MPS quantity of 500 = 750. Of
those, 200 have been sold in the 5th week and 150 in the 6th week. Therefore,
(250 + 500 – 200 – 150) = 400 are still available. There will be zero units
remaining for sale even after accepting this order.
The third order for 300 units (in week 1) should not be accepted. At that time, of the
400 on hand, plus 500 MPS quantity to arrive in the first week, a total of 300 plus 350
has been sold. Note that because no MPS is scheduled for the 2nd week, the 350
ordered for the 2nd week must come from those on hand or those arriving in the 1st
week. In total [(400 + 500) – (300 + 350)] = 250 remaining, which will not cover the
order for 300. Although a partial order of 250 could be fulfilled, these 250 units are
required to satisfy orders 1 and 2.
The fourth order for 300 units (in week 7) should be accepted. After accepting the
second order (part ii), zero units remain. In the 7th week 500 units arrive. Of those,
demands of 100 in each of weeks 7 and 8 have been promised, leaving (500 – 200) =
300. This order of 300 units would reduce the quantity available to promise to zero
units.
Week
Quantity on Hand: 150 1 2 3 4 5 6 7 8
Forecast 120 120 120 100 100 100 80 80
Customer orders (booked) 100 80 60 40 10 10 0 0
Projected on-hand inventory 30 110 190 90 190 90 10 130
MPS quantity 200 200 200 200
MPS start 200 200 200 200
Week
Quantity on Hand: 150 1 2 3 4 5 6 7 8
Forecast 120 120 120 150 150 150 100 100
Customer orders (booked) 100 80 60 40 10 10 0 0
Projected on-hand inventory 30 110 190 40 90 -60 -160 -60
MPS quantity 200 200 200 200
MPS start 200 200 200 200
Week
Quantity on Hand: 150 1 2 3 4 5 6 7 8
Forecast 120 120 120 100 100 100 80 80
Customer orders (booked) 100 280 60 40 10 10 0 0
Projected on-hand inventory 30 -50 30 -70 30 -70 -150 -30
MPS quantity 200 200 200 200
MPS start 200 200 200 200
Week
1 2 3 4 5 6 7 8
Forecast requirements 40 40 40 40 30 30 50 50
Customer orders (booked) 60 45 30 35 10 5 5 0
Projected on-hand inventory 25 55 15 50 20 65 15 40
MPS quantity 75 75 75 75 75
MPS start 75 75 75 75
Available-to-promise 25 30 65 75
(ATP) inventory
q Order 1 for 15 units in week 2 should be accepted because there are 25 units ATP
from week 1. After this order is accepted 10 units remain in ATP from Week 1.
q Order 2 for 30 units in week 5 should be accepted because there are 30 units ATP
from week 4. After this order is accepted 10 units still remain in ATP from week 1
and zero units from week 4.
q Order 3 for 25 units in week 3 should NOT be accepted because there are only
10 units remaining in ATP from week 1 and this is not adequate to fill the order
completely. After this order is rejected 10 units continue to remain in ATP from
week 1.
q Order 4 for 75 units in week 7 should be accepted because there will be 65 units
in ATP from week 6, which, along with the 10 units that continue to remain in
ATP from week 1, will be adequate to fill the order completely.
Week
1 2 3 4 5 6
Forecast requirements 15 40 10 20 50 30
Customer orders (booked) 20 25 10 20
Projected on-hand inventory 10 30 20 10 40
MPS quantity 60 60 60
MPS start 60 60 60
Available-to-promise 10 5 60 60
(ATP) inventory
b. The shipping date would be week 2 because we will have 10 units from week 1
and 5 units from week 2 available-to-promise inventory to fill this order.
Week
1 2 3 4 5 6 7 8 9 10 11 12
Forecast requirements 15 15 15 15 20 20 20 20 15 15 15 15
Customer orders 25 12 8 10 2 3 0 0 0 0 0 0
(booked)
Projected on-hand 25 10 35 20 0 20 0 20 5 30 15 0
inventory
MPS quantity 40 40 40 40 40
MPS start 40 40 40 40
Available-to-promise 13 20 37 40 40
(ATP) inventory
The tables following were generated with the Single-Item MRP solver from OM
Explorer.
b. L4L
c. POQ, P = 2
b. L4L
Item: Rotor assembly Lot Size: L4L
Lead Time: 2 weeks
Week 1 2 3 4 5 6 7 8
Gross requirements 65 15 45 40 80 80 80 80
Scheduled receipts 150
Projected on hand 20 105 90 45 5 0 0 0
Planned receipts 75 80 80 80
Planned order releases 75 80 80 80
c. POQ with P = 2
Item: Rotor assembly Lot Size: POQ, P = 2
Lead Time: 2 weeks
Week 1 2 3 4 5 6 7 8
Gross requirements 65 15 45 40 80 80 80 80
Scheduled receipts 150
Projected on hand 20 105 90 45 5 80 0 80 0
Planned receipts 155 160
Planned order releases 155 160
b. L4L
Item: Drive shaft Lot Size: L4L
Lead Time: 3 weeks
Week 1 2 3 4 5 6 7 8
Gross requirements 35 25 15 20 40 40 50 50
Scheduled receipts 80
Projected on hand 10 55 30 15 0 0 0 0 0
Planned receipts 5 40 40 50 50
Planned order releases 5 40 40 50 50
c. POQ with P = 4
Item: Drive shaft Lot Size: POQ, P = 4
Lead Time: 3 weeks
Week 1 2 3 4 5 6 7 8
Gross requirements 35 25 15 20 40 40 50 50
Scheduled receipts 80
Projected on hand 10 55 30 15 130 90 50 0 0
Planned receipts 135 50
Planned order releases 135 50
a. This solution was developed using the Material Requirements Planning module in
OM Solver.
a. This solution was developed using the Material Requirements Planning module in
OM Solver.
For item C, an inventory shortage will occur in week 2. This item has no
Projected On-Hand Inventory and the next Scheduled Receipt will not arrive until
week 3. Items D and E can cover all Gross Requirements from current On-Hand
Inventory, Scheduled Receipts and Planned Order Releases.
b. This solution was developed using the Material Requirements Planning module in
OM Solver.
The inventory shortage for item C may not be alleviated by placing a larger order
in week 1. The best solution may be to expedite the Scheduled Receipt currently
scheduled to arrive in week 3 to week 2.
Week 1 2 3 4 5 6 7 8
Gross requirements 160 130 250 160 200
Scheduled receipts
Projected on hand 250 90 90 0 0 0 0 0 0
Planned receipts 40 250 160 200
Planned order releases 40 250 160 200
Action notices signal the need to place orders for 80 Cs and 600 Es. Please note that
action notices were not asked for in the problem.
Action notices: Delay the scheduled receipt of 120 units of E and order 590 units of F.
Please note that action notices were not asked for in the problem.
23. MRP for Figure 16.42
a. This solution was developed using the Material Requirements Planning module in
OM Solver.
b. In week 1, an order for 155 units of item C should be released and an order for
610 units of item D should be released
c. This solution was developed using the Material Requirements Planning module in
OM Solver. This software shows the cascading changes required by adding a new
MPS of 200 units of product A in week 5.
As items D and E have multiple parents, the required changes are substantially
more complex. These changes are reflected in the records below. It should be
noted that planner intervention will be required for both of these items.
For item D, the Projected On-Hand Inventory becomes negative (-180) in week 2.
There is not enough inventory to accommodate the new Planed Order Release of
400 units in week 2 for part A. Further, without expediting, item D’s two-week
leadtime is too long for a new order to satisfy the resulting Gross Requirements.
For item E the situation is even more severe. The Gross Requirements in week
one increases from 610 to 1410 units. This new demand for 800 additional units
in week 1 produces an inventory shortage of 260 units.
b. In week 1, an order for 205 units of item C, an order for 700 units of item D, and an
order for 700 units of item E should be released.
B(3) C(1)
LT = 2 LT = 3
G(1)
LT = 3
Item
Data Category B C D E F G
Lot-size rule L4L L4L POQ (P = 2) L4L L4L FOQ = 100
Lead time 2 weeks 3 weeks 3 weeks 6 weeks 1 week 3 weeks
Safety stock 30 10 0 0 0 0
Scheduled receipts 150 50 None 400 40 None
(wk 2) (wk 2) (wk 6) (wk 3)
On-hand inventory 30 20 60 400 0 0
Item: A
Lot Size: 50 Week
Final Asm. Lead Time: 1 wk 1 2 3 4 5 6 7 8 9 10
Quantity On Hand: 5
MPS Start 50 50 50 50
Action notices are to issue orders for 180 Ds, 100 Es, and 100 Gs. Please note that
action notices were not asked for in the problem.
a. MPS
b. Order Acceptance
Accept order 1 for 40 units in period 3, which leaves 34 units in ATP for period 3.
Reject order 2 for 60 units in period 4, since we only have 8 available in period 1 and
34 available in period 3.
Accept order 3 for 70 units in period 6, which leaves 21 units in ATP for period 6.
Accept order 4 for 40 units in period 3, which leaves 2 units in ATP for period 1 and 0
units in ATP for period 3
Reject order 5 for 20 units in period 5, since we only have 2 units available in ATP for
period 1. (Could offer delivery in week 6, but assume here that declined.)
Reject order 6 for 115 units in period 9, since we only have2 units available in period
1 and 21 units available in period 6.
b. Order Acceptance
In week 1, an order for 25 units of item D and an order for 300 units of item E should be
released.
In week 1, an order for 300 units of item E and an order for 400 units of item F should be
released.
A. Synopsis
Flashy Flashers, Inc. is a company that produces a line of automotive electrical
components and serves about 95 auto parts suppliers and car dealers regionally.
Recently the company installed an MRP system. After one year’s use, Kathryn
Marley, the Vice President of Operations and Supply Chain Management, is looking
for ways to improve the resource planning process.
B. Purpose
This case provides the data to develop the MRP records for two products of Flashy
Flashers, Inc. In addition to reinforcing the skills of developing dependent demand
production plans, the case affords the opportunity to discuss possible implementation
problems when using MRP. The case also brings out the value of action notices,
capacity requirements planning, and the link between MRP and the MPS.
C. Analysis
A summary of the planned order release schedule is contained in Exhibit TN.1. The
MRP records for each of the component items are contained in Exhibit TN.2. Exhibit
TN.3 lists situations that the planner needs to act on this week in releasing new orders
or adjusting scheduled receipt due dates.
D. Recommendations
Recommendations to management include the following:
1. Manage the MPS process more effectively:
The feast-or-famine capacity situation on the shop floor might be created in
part at the MPS level by not checking that resources are available before the
MPS is authorized.
The ATP feature of MPS may not be used effectively, given the comment
about last-minute changes in the MPS that respond to requests by favorite
customers. Customers appreciate reliability in meeting promises, even more
than responding to expedited deliveries (unless on an exception basis). Giving
them a promise date and then delivering on it is valued. Wanting to
accommodate special requests is one thing, but being able to do so is another.
Freezing the short-term portion of the MPS should build in more stability in
the material requirements plan.
2. Create a more formal system for generating action notices, so that planners can
concentrate on the things that need their attention. It can be a simple list, such as
given in TN.3. These actions should not be automatically done by the MRP
system, because the planner needs to check if they are feasible, such as
components and capacity are available.
* The original version of this case was prepared by Dr. Soumen Ghosh, Georgia Institute of Technology, as
a basis for classroom discussion.
3. Consider a priority planning system that updates priorities, based on valid due
dates of scheduled receipts. This step will require updating scheduled receipt dues
dates as needs change.
4. Consider a capacity requirement planning system to project workloads into the
future, particularly for bottleneck operations. Consider ways to incorporate the
principles of TOC (see Chapter 7, “Constraint Management”) into the MRP
process, including lot sizing rules and how to respond to action notices.
5. While taking steps to level capacity requirements, the “overrides” by the shop
supervisor should be minimized and coordinated with the planners. His informal
system can undermine the effectiveness of the MRP system. MRP logic
“believes” that the due dates and quantities of scheduled receipts are going to
happen. At the same time, MRP flexibly takes into account the unexpected by
generating a new material requirements plan each week. The unanticipated
consequences of such overrides are demonstrated by the MRP records of items
SL123A and SL134P.
6. Train all employees who provide information to the MRP system in addition to
those who must update the system. Only selected employees received training in
the past. Everyone should be aware of the need for accurate and timely data. Also
train those who will be primary users of the MRP information.
E. Teaching Suggestions
Initially the instructor should get agreement on the planned order release form
(Exhibit TN.1). Be sure to rationalize any differences in the student forms because
they will spur the discussion of the mechanics of producing MRP reports. The results
lay the foundation for the conclusion that something definitely is wrong. Also
compare notes on Exhibit TM.3. Although the mechanics of identifying action notices
are not emphasized in the textbook, discussing them can enhance student insights on
MRP capabilites.
After the mechanics are understood, the instructor should raise the question,
“What can be done to improve this resource planning process?” The six points
described in Section D are a starting point. Students may also point to other
possibilities, including:
q Accepting orders on short notice, even if on-time delivery is unlikely
q Poor estimates for lead times
q Bad priority planning system
q Lack of capacity
q Bad input data
q Ineffective follow-up with suppliers
q Blaming everyone else
Week
Item Description
and Part Number 1 2 3 4 5 6
Side Lens
(SL111P) 350
Side Lens Rubber Gasket
(SL113P) 100 100 100
Side Frame Subassembly
(SL112A) 80 110
Side Frame
(SL121F) 110
Side Bulb Subassembly
(SL122A) 110
Flasher Bulb Subassembly
(SL123A) 200
Side Cable Grommet and Receptacle
(SL131F)
Flasher Cable Grommet and Receptacle
(SL133F)
Side Bulb
(SL132P)
Flasher Bulb
(SL134P) 100
Head Frame
Subassembly (HL211A) 120 90 75
Head Lens
(HL212P) 350
Head Lamp Module
(HL222P)
Head Frame
(HL223F) 165
Back Rubber Gasket
(C310P) 180 180
Screws
(C206P) 2500
Side Bulb Subassembly (SL112A) Postpone schedule receipt’s due date from
week 2 to week 3. Otherwise this job may be
occupying a bottleneck workstation at the
expense of an order that really does need to be
done in week 2.
1
Upon further investigation, Marley found that the quantity called for in a SL123A scheduled
receipt already finished was arbitrarily reduced in the shop, to help ease an overload. The
unfortunate consequence is that now there is no current on-hand inventory for item SL123A,
and a new rush order must be released with less than the 2-week offset for the lead time. Such
situations often can be accommodated, as long as they are the exception rather than the rule.
2
SL134P must be ordered as a rush job from the supplier, because of the unanticipated
problems created by the shop’s override on a prior order for SL123A. Item SL133F is also a
component of SL123A, but fortunately its current on-hand inventory is sufficient because of
the remnants created by its FOQ rule. Remnants in this case absorbed the negative effects of a
short shipment of SL123A.