SECTION - A (10 1 10 Marks) Answer All The Questions

This document appears to be an exam for a Software Project Management course, containing three sections with multiple choice and written answer questions. Section A contains 10 one-mark multiple choice questions testing basic concepts like system types, project management tools and techniques. Section B has 5 five-mark questions requiring longer written answers on topics like project scheduling and visualizing progress. Section C poses 5 eight-mark questions to be answered in detail, covering the software development life cycle, risk management, prototyping models and testing techniques.

Uploaded by

ackmuthukumar
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
66 views3 pages

SECTION - A (10 1 10 Marks) Answer All The Questions

This document appears to be an exam for a Software Project Management course, containing three sections with multiple choice and written answer questions. Section A contains 10 one-mark multiple choice questions testing basic concepts like system types, project management tools and techniques. Section B has 5 five-mark questions requiring longer written answers on topics like project scheduling and visualizing progress. Section C poses 5 eight-mark questions to be answered in detail, covering the software development life cycle, risk management, prototyping models and testing techniques.

Uploaded by

ackmuthukumar
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 3

CMS COLLEGE OF SCIENCE AND COMMERCE ( AUTONOMOUS)

CHINNAVETAMPATTI, COIMBATORE -06


BCA Degree Examination – Semester VI
07BCA18 - SOFTWARE PROJECT MANAGEMENT

Time: 3 Hours Max Marks: 75

SECTION – A (10*1=10 Marks)


Answer all the questions
1. __________ are those that interact with the environment.
a) open system b) closed system
c) sociotechnical system d) none
2. CCTA stands for _____________.
3. A _______ is any item or person required for the execution of the project.
a) cost b) resource c) activity d) none
4. One of the simplest and oldest technique for tracking project progress is the ________.
a) time-line chart b) slip chart
c) Gantt chart d) ball chart
5. Expand PRINCE.
6. Prototyping model is a ___________ software development model.
a) complete b) partial or use and through model
c) both a and b d) none
7. Test policy is a high level development description of the test levels to be performed.
(True/False)
8. ________ is formally a parallel developemnt of functions and subsequent integration.
a) Rational Unified Process b) Rapid Application Development
c) Capability Maturity Model d) none
9. The __________ matric is based on the number of decisions in aprogram.
a) cyclomatic complexity b) line of coding
c) both a and b d) none
10. _____________ is a good all-round specification based block box technique.
a) Equivalence Partitioning b) Boundary Value anaysis
c) Decision Tables d) None

SECTION – B (5*5=25 Marks)


Answer all the questions
11. a) Discuss about the information and control in an organization.
OR
11. b) What is project schdule? Explain.

12. a) What are the categories of resources? Explain.


OR
12. b) Discuss the various visualizing project progress.

13. a) What is prototyping? Discuss.


OR
13. b) Discuss about the PRINCE planning technique with neat diagram.

14. a) Discuss the objective of defining software testing.


OR
14. b) What is integration testing? Explain.

15. a) Write notes on static analysis by tools.


OR
15. b) Discuss the various categories of test design techniques.
SECTION – C (5*8=40 Marks)
Answer all the questions

16. a) Explain a typical project life cycle model with neat diagram.
OR
16. b) Explain the step wise project planning activities.

17. a) Explain about the various risk identification factors.


OR
17. b) Discuss in detail about the different motivation models proposed for people to
work.

18. a) Explain the prototyping models in detail.


OR
18. b) Explain the overview of PRINCE project management technique.

19. a) Explain the fundamental test process.


OR
19. b) Explain about V-model software development life cycle activity with neat diagram.

20. a) Discuss in detail about the different phases of a formal review process.
OR
20. b) Explain in detail about white box testing techniques.