Ee 158 Finals Sy 15 16

The document provides details for a final examination for an engineering course. It includes 3 problems related to power plant engineering: 1) calculating average power generated and generator rating for a hydroelectric project, 2) determining reservoir level change after supplying a load for 3 hours, and 3) designing an off-grid solar power system based on given load and component specifications. The exam is scheduled for March 4, 2016 from 9:00-11:00 AM in rooms 312/313.

Uploaded by

Leeam Martin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
505 views1 page

Ee 158 Finals Sy 15 16

The document provides details for a final examination for an engineering course. It includes 3 problems related to power plant engineering: 1) calculating average power generated and generator rating for a hydroelectric project, 2) determining reservoir level change after supplying a load for 3 hours, and 3) designing an off-grid solar power system based on given load and component specifications. The exam is scheduled for March 4, 2016 from 9:00-11:00 AM in rooms 312/313.

Uploaded by

Leeam Martin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd

FINAL EXAMINATION

Subject: EE 158-POWER PLANT ENGINEERING Prepared by:


Exam Date: March 4, 2016
Time: 9:00 – 11:00 A.M. Engr. Marc-Eric E. Villanueva
Room: 312/313

I. PROBLEM SOLVING:

1. Calculate the average power in MW that can be generated in a hydroelectric project


from the following data:

Catchment area: 5 hectares yield factor: 85%


Annual Rainfall: 1.75m Load factor: 40%
Overall efficiency: 85%

- If the mean head used is equivalent to the minimum rating of a francis type turbine,
calculate the rating of the generator that should be installed for this type?

2. A hydro electric generating station is supplied from a reservoir of capacity 6,000,000


m3 at a head of 170m. Assume a hydraulic efficiency of 80% and electrical efficiency
of 90%. The fall in the reservoir level after a load of 15MW has been supplied for
3hrs, if the area of the reservoir is 2.5km2 is closest to:
a.) 5.39cm c.) 5.98cm
b.) 4.32cm d.) none of the above

3. Design for an appropriate off-grid solar power using the following data:
Loads: ACU1 = 2547 BTU/Hr Lighting system using LED bulbs:
ACU2 = 3820 BTU/Hr (3pcs) – 5w, (2pcs)- 7w, (3pcs) – 3w
Refrigerator: 120w Electric fan1: 50w
Motor pump: ¾ HP Electric fan2: 45w
TV1= 100w exhaust fan: 60w
TV2= 130w rice cooker: 300w
Conditions: ACU 1 & 2 are used 8hrs a day, ref. @ 24hrs, motor pump @ approx. 2hrs
a day, TV 1= 8hrs a day, Tv2= 10hrs a day, lighting sys. Is used simultaneously at
12hrs a day, electric fan 1= 8hrs a day, electric fan 2 = 12hrs a day, exhaust fan @ 3
hrs a day, and rice cooker@ 3 hrs a day. If you will be using a 250w polycrystalline
24V system, and 60Amps MPPT solar charge controller, compute for the appropriate
design for the PV, SCC, Inverter, and the batteries if the available in the market is a
100 amp-hr solar master battery,12V system @ 50% DOD, and 70% PV eff’cy using 5
at sun-peak hrs, and 150% inverter eff’cy.
-Design a 24V system for this off-grid power, design also the protection ratings for
this system.

GOOD LUCK!!!

Checked by: Approved by:

Engr. Marc-Eric E. Villanueva Engr. Hector K. Pintor


Program Head Academic Dean

FINAL EXAMINATION
Subject: EE 158-POWER PLANT ENGINEERING             
               Prepared by:
Exam Date: March 4, 2016