Leak Test Valve Report

This leak test valve report summarizes the testing of a 4" ball valve. The valve body and seats passed both a low pressure test and high pressure test, with the specified leakage and test durations. The valve was inspected and accepted, meeting the engineering and supplier documentation and code specifications. The valve installation was also confirmed to be erected according to the drawings by subcontractor quality control, the EPC contractor, and the owner.

Uploaded by

adnansh1
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views2 pages

Leak Test Valve Report

This leak test valve report summarizes the testing of a 4" ball valve. The valve body and seats passed both a low pressure test and high pressure test, with the specified leakage and test durations. The valve was inspected and accepted, meeting the engineering and supplier documentation and code specifications. The valve installation was also confirmed to be erected according to the drawings by subcontractor quality control, the EPC contractor, and the owner.

Uploaded by

adnansh1
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 2

LEAK TEST VALVE REPORT

DOC NO : REV . NO :

REPORT NO. : TEST PACKAGE NO.:

TAG/ITEM ENGINEERING DOCUMENT N. SUPPLIER DOCUMENT N. CODE/SPECIFICATION

IDENTIFICATION OF MONITORING AND MEASURING DEVICES PAGE: OF

DATE: MANUFACTURER:

TYPE VALVE
Gate Globe Ball x Check Butterfly

Size:4" Class (Rating):150

Trim material: Tag No. / symbol:

Body material: ID NO.:


Body Heat # Bonnet Heat #
FOR CAST STEEL VALVES ONLY

PRESSURE TEST
VALVE BODY HYDRO TEST

Test Duration :………………..………(min) Test Pressure ……………. Pass Fail

RETEST

Test Duration :………………..………(min) Test Pressure ……………. Pass Fail

UPSTREAM VALVE SEAT DOWNSTREAM VALVE SEAT

LOW PRESSURE TEST ……...………………..PSIG ………….……..LEAKAGE ………………..…… # DROPS , BUBBLES / MINUT

Pass Fail

HIGH PRESSURE TEST ……...………………..PSIG ………….……..LEAKAGE ………………..…… # DROPS , BUBBLES / MINUT

Pass Fail TEST DURATION …………………………..Minutes

Test Result: Accepted Rejected If rejected , see MER/NCR # ……………

NOTE: INSPECTION NOTIFICATION REFERENCE

REPORT NO.:

ISSUE DATE:

ABOVE MENTIONED LINE HAS BEEN ERECTED AS PER DWG.

SUBCONTRACTOR (QC) EPC CONTRACTOR OWNER

NAME : NAME : NAME :

SIGN : SIGN : SIGN :

DATE : DATE : DATE :