300 TPD Refinery Erection

The document provides a 6-month manpower estimation for an erection project. It estimates that 52 people at various roles like engineers, supervisors, fitters, riggers, welders and electricians will be needed at a total cost of Rs. 3,96,000 including a 10% contingency amount. The roles, numbers of people required and their estimated salaries are broken down.

Uploaded by

Yadav Shweta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
94 views2 pages

300 TPD Refinery Erection

The document provides a 6-month manpower estimation for an erection project. It estimates that 52 people at various roles like engineers, supervisors, fitters, riggers, welders and electricians will be needed at a total cost of Rs. 3,96,000 including a 10% contingency amount. The roles, numbers of people required and their estimated salaries are broken down.

Uploaded by

Yadav Shweta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Period 6 months

Erection Manpower Mech 42


Eelct 6
Inst 4
Team leader 1 3000 3000 18000
Engineer 1 2000 2000 12000
superviser 2 1500 3000 18000
Fitter 8 1200 9600 57600
Rigger/khalasi 14 1000 14000 84000
semi skilled 12 800 9600 57600
Welder 8 1000 8000 48000
Electrician 2 1200 2400 14400
Semi skilled 4 1000 4000 24000
Instruments 2 1200 2400 14400
Semi skilled 2 1000 2000 12000
52000 360000
52

360000
Contigency @10 36000
To quote 396000
6000
36000
2448000