JSA Installation of Gearbox

1) This JSA outlines the steps and safety measures for installing a gearbox at the ABPR 1&2 site. 2) Potential hazards include non-compliance with safety procedures, poor task planning, lifting overloads or mechanical failures that could cause injury. 3) Mitigation measures include following permit procedures, inspections, competent crews, lifting analysis, and maintaining safe distances and load limits.

Uploaded by

prasong
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (3 votes)
3K views2 pages

JSA Installation of Gearbox

1) This JSA outlines the steps and safety measures for installing a gearbox at the ABPR 1&2 site. 2) Potential hazards include non-compliance with safety procedures, poor task planning, lifting overloads or mechanical failures that could cause injury. 3) Mitigation measures include following permit procedures, inspections, competent crews, lifting analysis, and maintaining safe distances and load limits.

Uploaded by

prasong
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Job Safety Analysis

JSA No: Mec-001


Activity: Installation of Gearbox
(Rev-001)
Project No:
Project Title: ABPR 1&2

Site/Facility: Work Area: Permit No:


P&S Emergency Contact Number: HRSG 21
Date:
0817628414
Personal Protective Equipments: Hard Hat, Safety Shoes, Hand Gloves, Safety Harness, Coverall
RESIDUAL
JOB STEPS POTENTIAL HAZARDS RISK RATING MITIGATION MEASURES RISK RATING
• Permit To Work procedure Amata Begrimm to be
complied
• Ensure all equipments are inspected and certified
as per Amata Begrimm
• All personnel shall undergo Project HSE Induction
• Non-compliance of and EOD Training prior to mobilize 2B
3D
safety procedure • Any findings of EOD, stop the activity, inform (Low)
(Medium)
Company and keep personnel away from the area.
• All Lifting tools and Tackles shall have inspected
prior to mobilize to site.
• All lifting Equipment shall complete the HSE
Inspection and Colour Code.
• Ensure the equipment is certified & visually
inspected and fit for the intended purpose.
Pre - work • Confirm the operators are with both licenses of
construction and driving.
• Ensure all lifting gears and shackles are inspected
with necessary authorized 3rd party inspection
certificates and color coded.
• Poor Task Planning
• Ensure the operator and the rigging crews are
competent, experienced and trained (Awareness
• Non Competent Crew 3D 2B
Training) by III rd Party.
(Medium) • Check the ground condition is safe for operation
(Low)
• Area of activity
and underground services identified and
adequately protected.
• Ensure area of lifting is barricaded and caution
signage placed.
• Clear media of communication shall be
maintained.
• Conduct TBT and discuss about the safe way of
lifting.
• Ensure the ground is stable and properly
compacted.
• Ensure out riggers must have an outrigger pad of
adequate size and thickness.

• Provide steel matting as appropriate if required


• Positioning of the
4D for critical/ heavy lifts. 2B
crane/hiam on unstable
(High) • Maintain safe distance while placing the crane (Low)
ground / Marshy land
Lifting of Gearbox from the excavation/Trench.
• Safe distance shall be maintained from the
overhead power lines.
• Site Safety Analysis for lifting shall be prepared
and approved prior to commence the Lifting

• Over Load • Conduct regular visual inspection of all lifting


4D 2B
gears and mechanism of crane prior to start any
(High) lifting operation by a competent person. (Low)
Page 1 of 2
• Mechanical failure • Do not exceed the Safe Working Load of the crane
as per manufacturer standards under any
circumstances.
• Do not override any inbuilt safety devices or take
short cuts during the lifting operations.
• All Lifting tools and tackles shall be visually
inspected and ensured the condition.
• Sharp edges of the load shall be provided with
packing to protect the Lifting tools and tackles
from damage.
• Equipment maintenance shall be done
periodically and records maintained.
• Ensure proper wind up and housekeeping at work
site.
• The accessories and tools shall be clean and store
• Scattered lifting tools and properly.
Job Completion 3C • Vehicle/Equipment shall be parked/ secured in a
1A
other accessories.
House keeping (Medium) (Low)
• House keeping safe place.
• Ensure stored materials will not block the
adjacent Access / Egress.
• Barricade the area placed with Caution Signage

Additional Hazards
(Other than
indicated above)

Permit No: Work Area:

JSA Done Name: Controlling Team:


by Permit
Applicant P&S. No. Signature:

JSA Reviewed Name: Controlling Team:


by Permit
Issuer AMATA BEGRIMM. No. Signature:

Page 2 of 2