Urbantree PPT by KNN - 25-05-2019

This document provides a status update on construction projects as of May 25, 2019 for a development called Fantastic in Vanagaram. It outlines the progress of various construction tasks across multiple blocks (A through H), the clubhouse, and common areas. Work underway includes false ceilings, wall plastering, electrical, plumbing, waterproofing, flooring, painting, and more. The overall development appears to be in an active construction phase with various interior and exterior tasks in different stages of completion across the site.

Uploaded by

svrao4u
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
51 views32 pages

Urbantree PPT by KNN - 25-05-2019

This document provides a status update on construction projects as of May 25, 2019 for a development called Fantastic in Vanagaram. It outlines the progress of various construction tasks across multiple blocks (A through H), the clubhouse, and common areas. Work underway includes false ceilings, wall plastering, electrical, plumbing, waterproofing, flooring, painting, and more. The overall development appears to be in an active construction phase with various interior and exterior tasks in different stages of completion across the site.

Uploaded by

svrao4u
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 32

URBAN TREE INFRASTRUCTURES

PRIVATE LIMITED
PROJECT NAME: FANTASTIC
LOCATION : VANAGARAM
STATUS AS ON : 25-05-2019
A Block – A111 – False ceiling work Completed
A Block – 4th Floor Internal door shutter work under progress
B Block – 4th floor wall plastering work under progress
B Block – Terrace Floor Electrical pipe laying work
completed
B Block – Terrace Floor water proofing work completed &
LMR plastering work completed
B Block – 4th Floor wall plastering work under progress
B – 2nd Floor Internal plumbing work completed, Toilet
water proofing work under progress
Club House – Interior works under progress
Club House – 1st Floor Toilet wall dado & Flooring work
completed
Club House – 1st floor False ceiling work completed
Club House – 1st Floor False ceiling work completed
Club House – 2nd Floor False ceiling work & Brick Wall
dado under Completed
Club House – 3rd Floor Wooden work & False ceiling work
under progress
Club House – 3rd Floor plumbing work completed
C Block – 1st & 2nd floor Primer work completed
Block D – Balcony Water proofing work under progress
Block D – 2nd floor Wall dado work & Granite edge polishing
Under progress
Block D –1st Floor & 2nd Floor Putty work completed
Block D – Common Area – Plumbing Shaft work under
progress
Block D – Terrace floor – Screed work Under progress
Block E – East side paver laying work completed
E Block – FRP tank fixing work completed
E & F Block – 1st coat emulsion & Paint for joineries work
completed
F Block – Stilt Floor – In between E & F Driveway Paver
Block laying work completed
G Block – All floor – 1st coat primer for joineries work
completed
Block G & H – Stilt floor – Manhole cover top plastering
work Completed
H Block – All floor - 1st coat painting work completed
G & H Block – Manhole cover fixing under progress
Common Work – Store shifting work completed
Common Work – Transformer yard Erection work under progress
Thank you
for
viewing Regards
Fantastic
Execution Team