SCHEDULE PEKERJAAN
PEMBANGUNAN FIX CRUSHER PADA
PT MIFA BERSAUDARA
ID Task Name Duration Start Finish Year 2
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15
S O N D J F M A M J J A S O N
1 PENGADAAN PEKERJAAN PEMBANGUNAN 354 days Mon 05/11/18 Thu 24/10/19 05/11 24/10
PENAMBAHAN FIX CRUSHER
2 PREPARATION 29 days Mon 05/11/18 Mon 03/12/18 05/11 03/12
6 ENGINEERING 345 days Fri 09/11/18 Sat 19/10/19 09/11 19/10
22 PROCUREMENT 295 days Thu 29/11/18 Thu 19/09/19 29/11 19/09
121 CONSTRUCTION 340 days Wed 07/11/18 Sat 12/10/19 07/11 12/10
265 PRE-COMMISIONING & COMMISIONING 26 days Wed 25/09/19 Sun 20/10/19 25/09 20/10
277 FINISHING WORK 15 days Tue 08/10/19 Tue 22/10/19 08/10 22/10
279 DEMOBILISASI 7 days Fri 18/10/19 Thu 24/10/19
Project: Schedule Crusher PT Mifa Task Progress Summary External Tasks Deadline
Date: Sat 29/09/18 Split Milestone Project Summary External Milestone