Schedule for Crusher Project PT Mifa

This schedule outlines the key tasks for a 354 day project to expand a fixed crusher at PT Mifa Bersaudara from November 2018 to October 2019. The project involves preparation, engineering, procurement, construction, pre-commissioning and commissioning. Construction will take place from November 2018 to October 2019, with finishing work and demobilization occurring in October 2019.

Uploaded by

Jèfrì Pìném
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
143 views1 page

Schedule for Crusher Project PT Mifa

This schedule outlines the key tasks for a 354 day project to expand a fixed crusher at PT Mifa Bersaudara from November 2018 to October 2019. The project involves preparation, engineering, procurement, construction, pre-commissioning and commissioning. Construction will take place from November 2018 to October 2019, with finishing work and demobilization occurring in October 2019.

Uploaded by

Jèfrì Pìném
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

SCHEDULE PEKERJAAN

PEMBANGUNAN FIX CRUSHER PADA


PT MIFA BERSAUDARA
ID Task Name Duration Start Finish Year 2
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15
S O N D J F M A M J J A S O N
1 PENGADAAN PEKERJAAN PEMBANGUNAN 354 days Mon 05/11/18 Thu 24/10/19 05/11 24/10
PENAMBAHAN FIX CRUSHER
2 PREPARATION 29 days Mon 05/11/18 Mon 03/12/18 05/11 03/12
6 ENGINEERING 345 days Fri 09/11/18 Sat 19/10/19 09/11 19/10
22 PROCUREMENT 295 days Thu 29/11/18 Thu 19/09/19 29/11 19/09
121 CONSTRUCTION 340 days Wed 07/11/18 Sat 12/10/19 07/11 12/10
265 PRE-COMMISIONING & COMMISIONING 26 days Wed 25/09/19 Sun 20/10/19 25/09 20/10

277 FINISHING WORK 15 days Tue 08/10/19 Tue 22/10/19 08/10 22/10
279 DEMOBILISASI 7 days Fri 18/10/19 Thu 24/10/19

Project: Schedule Crusher PT Mifa Task Progress Summary External Tasks Deadline
Date: Sat 29/09/18 Split Milestone Project Summary External Milestone