Vs M Presentation
Vs M Presentation
Bill Paolucci
IPFW
March 17, 2009
Discussion Points
1. Introduction & Getting Started
2. The Current State Map
3. Lean Value Stream
4. The Future State Map
5. Achieving the Future State
6. Conclusion
Market
Present Profit Cost Price
Market
Future Profit Cost Price
Lean
Organization
0
Lean Manufacturing
Value Stream
Waste
• No Reason!!
• The lean approach is to place these four
processes immediately adjacent to one
another (cellular)
• Have the operators pass parts from one
process to another.
• Keep operator’s work content just below the
takt time.
Cycling Faster than Takt Time
(Operator Balance Chart)
62s Takt = 60 sec
46s
Assy
40s
39s
Assembly
Assembly
Assembly
Weld
Stamping 1s
Weld
Weld
Value-Added Time
Manufacturing Cycle Efficiency = Total Lead Time
Stretch Objective: A Lean process is one in which the value-added time in the process is more
than 25% of the total lead time of that process. Improvements in Cycle Efficiency will result in:
• Reduction in quality costs
• Shorter lead times increasing process flexibility
• Less inventory, reducing storage cost and increasing inventory turns
• Elimination of wastes due to scrap and repair resulting in improved
manufacturing overhead cost
Where: Cycle Efficiency should be collected at the end of the process.
When: Cycle Efficiency should be collected and used, at minimum, semi-annually. When a
project or kaizen has been implemented to set a new baseline, or when projects are being
evaluated for cost reduction potential.
Manufacturing Cycle Efficiency Calculation
Manufacturing Cycle Efficiency = Value-Added Time
Total Lead Time
Value added time = 3 hours
Total lead time = 96 hours ( 12, 8 hour days)
Poka-Yoke SMED
One-Piece
TPM Kanban
Flow
Standardized Empowered
Work Teams 5S Safety
Seeing The Whole
(mapping the extended value stream)
Process Level
Creating Continuous Flow
Single Plant
Learning to See
Multiple Plants