Answer Key
Answer Key
10. The Building environment rating system under SPP 203 is needed
to evaluate the performance of a building to encourage market
migration towards sustainable design. The rating system must meet
the criteria below in order have the certification. SPP 203 –
203.12
a. Flexible, such that projects need not meet identical
requirements to qualify.
b. All of the above
c. Credit based, allowing projects to earn points for environment-
friendly use of the building/ structure and actions taken during
planning, design, construction and occupancy.
d. Consensus-based and market driven in order to accelerate the
development and implementation of green building practices.
20. Specialist personnel who may be consulted by the Jurors during the
conduct of the ADC to permit them to obtain all necessary relevant
information. SPP 208 – 2.4
A. jury
B. architect
C. Technical Advisors
D. Professional Advisor
21. The body formed by the Owner and approved by the Professional
Advisor, to assist the Professional Advisor and the Jury in the
administrative conduct of the ADC SPP 208 – 2.5
A. Competition Secretariat
B. Competitor Secretariat
C. Competition Secretary
D. Jury
23. Which of the ff. services is not performed by the Architect under
the design-build service by administration? SPP 207 – 2 SCOPE OF
DESIGN BUILD BY ADMIN
A. Prepares schedule of work, construction program, construction
estimate, bill of mat’ls, etc
B. Keeps records and books of accounts
C. points construction superintendent, purchasing agent,
timekeeper, property clerks, etc.
D. Advances funding for payment of expenditures connected with work
26. Which of the following services are expected from the architect
serving as building/ground administrator? SPP 205 – 1.1.3
A. Building maintenance
B. Post-construction evaluation
C. Equipment maintenance
D. Billing of tenants for rentals/utilities
27. Under the Civil Code, under what condition can the Architect or
Engineer be held liable for damages within fifteen years after project
completion?
A. Due to violation of terms of contract
B. Structure collapse due to faulty construction
C. Structure collapse due to defects in plans/specification
D. Structure collapse due to defective materials
28. What is the role of the project Manager during the Pre-Construction
phase of the project? SPP-206– 9.2
A. Recommends early purchase of equipment/materials requiring a
long lead for procurement and delivery for expediency
B. Observes work in progress to assure compliance with
drawings/specification
C. Manages general coordination and scheduling of work
D. Revise and refines estimates as construction proceeds
30. Within how many days from the date a change is ordered shall any
claim for adjustment involving questions of facts be asserted?
A. 5 days C. 15 days
B. 10 days D. 30 days
AREA 02:ESTIMATES
31. If a partition wall has a width of 8.0 m, and the wall height is
3.0m at both of its ends and 6.0m at the middle, how many 6” CHB is
needed ?
a. 300 pcs c. 600 pcs
b. 450 pcs d. 750 pcs
NOTE : THERE ARE 12.50 PCS. OF CHB PER SQ. M. OF
WALL
RECTANGLE WALL = 8.00 M. X 3.00 M. = 24.00 SQ.
M.
TRIANGLE WALL = ( 8.00 M. X 3.00 M. ) / 2
= 24.00 SQ. M. / 2 = 12.00 SQ. M.
TOTAL WALL AREA = RECTANGLE WALL + TRIANGLE WALL
= 24 SQ. M. + 12 SQ. M. = 36 SQ. M.
NO. OF CHB = TOTAL WALL AREA X 12.5 PCS. PER SQ.
M. FIGURE 3
= 36.00 SQ. M. X 12.5 PCS. PER SQ. M. = 450 PCS.
39. The degree by which a color differs from a gray of the same
lightness or brightness, corresponding to saturation of the perceive
color.
a. Hue b. Saturation c. Chroma d. Lightness
44. The LINEAR CITY design was first developed by ___________ in Spain
during the 19th century
a. Hippodamus b. Arturo Soria y Mata
c. Leonardo Da Vinci d. Antonio Sant’elia
45. Who proposed the SECTOR MODEL in urban land use and demography
modified the concentric zone model of city development?
a. Homer Hoyt b. Frank Lloyd Wright
c. Ernest W. Bugress d. Sir Ebenezer Howard
56. How many months to release retention after the date of final
payment?
a. 2 months b. 6 months c. 3 months d. 12 months
AREA 2: STRUCTURE
AREA 2 TIP
(search nyo ang ibang choices, kahit di yun ang answer para more
knowledge lang)
64. Longitudinal beams which rest on top chord, and preferably at the
joints of the truss
a. purlins b. jack rafter c. rafters d. girders
65. It is the general term applied for all forces which act upon a
structure and anything else which causes stresses or deformation
within a structure or part thereof.
a. loads b. none of the listed c. strain d. weights
66. These members are inclined joists used to support sloping roofs
a. plates b. purlins c. rafters d. planks
73. A common paint film defect where progressive powdering from the
surface inward occurs. It is called:
a) blistering c) chalking
b) peeling d) alligatoring
74. In column, the ratio of its effective length to its least radius of
gyration is called:
a) Moment of Inertia c) Slenderness ratio
b) Development length d) Ratio and proportion
77. The point in the moment diagram at which the curvature reverses as
it changes from concave to convex is called:
a) Point of deflection
b) Moment of Inertia
c) Point of Inflection
d) Magnitude
80. The tendency for one part of the beam to move vertically with
respect to an adjacent part is called:
a) Shear c) Force
b) Moment d) Strength
Take note: Shear lang ang nag-iisang choice jan na nag-iindicate ng
deformation, so automatic shear ang answer. Kung namali ka pa ☹,
reviewhin mo ang types of structural deformation, and yang mga nasa
choices
90. A high-speed rotary shaping hand power tool use to make smooth
cutting and curving on solid wood is called:
a) Surface planer c) portable hand router
b) Dado plane d) Lathe machine
92. Wood defects are heart shake, cup shake, star shake and:
a) Knots c) Deterioration
b) Discoloration d) Rotten
93. The other kind of handsaw other than rip-cut saw is:
a) Diagonal cut saw c) Circular saw
b) Cross-cut d) Coping saw