UPDATED PROGRESS SCHEDULE
ID Nom de la tâche % Complete Duration Actual Start Actual Baseline Start Baseline Start Finish Finish Task Calendar Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Finish Finish Variance Apr May Jun Jul Aug Sep Oct Nov Dec
1 SUMMARY 15% 138.38 days 24/05/19 NA 24/05/19 10/11/19 24/05/19 10/11/19 0.13 days None
2 Contract Award 100% 0.88 days 24/05/19 24/05/19 24/05/19 24/05/19 24/05/19 24/05/19 0 days None
3 PHASE1: PRELIMINARY 90% 26.13 days 01/06/19 NA 30/05/19 24/06/19 01/06/19 01/07/19 6.13 days None
4 Preparation Work 90% 26.13 days 01/06/19 NA 30/05/19 24/06/19 01/06/19 01/07/19 6.13 days None
5 Moblization and personal and 100% 25.88 days 01/06/19 30/06/19 30/05/19 15/06/19 01/06/19 30/06/19 13.75 days None
equipement
6 Site installation 100% 14.88 days 13/06/19 30/06/19 13/06/19 20/06/19 13/06/19 30/06/19 8.75 days None
7 Geotechnical study 100% 5.13 days 01/06/19 08/06/19 01/06/19 08/06/19 01/06/19 08/06/19 0 days None
8 Execution study 70% 22.88 days 09/06/19 NA 09/06/19 24/06/19 09/06/19 01/07/19 11.94 days Recovery Calendar
9 PHASE2: WORKS 3% 83.5 days 10/07/19 NA 20/06/19 07/11/19 10/07/19 24/10/19 -11.63 days None
10 CIVIL WORK 9% 69.63 days 10/07/19 NA 20/06/19 24/10/19 10/07/19 08/10/19 -14.13 days None
11 Foundation 30% 27 days 10/07/19 NA 20/06/19 30/07/19 10/07/19 13/08/19 9.63 days None
12 Excavation 100% 2 days 10/07/19 11/07/19 20/06/19 22/06/19 10/07/19 11/07/19 17 days None
13 Blinding bed 50mm thick 100% 3 days 13/07/19 15/07/19 20/06/19 23/06/19 13/07/19 15/07/19 19.13 days None
14 Reinforced Concrete for foundation30% 6.13 days 18/07/19 NA 23/06/19 30/06/19 18/07/19 23/07/19 37.88 days Recovery Calendar
15 Concrete for vertical column 30% 4.38 days 18/07/19 NA 01/07/19 06/07/19 18/07/19 29/07/19 38.56 days Recovery Calendar
16 Reinforced concrete for 30% 8.75 days 18/07/19 NA 06/07/19 16/07/19 18/07/19 06/08/19 36.5 days Recovery Calendar
Orthogonal and curved ground
17 Backfill 0% 3.5 days NA NA 16/07/19 20/07/19 06/08/19 08/08/19 32.75 days Recovery Calendar
18 Ground Slabs 0% 8.75 days NA NA 20/07/19 30/07/19 08/08/19 13/08/19 24.88 days Recovery Calendar
19 Elevation 0% 20.81 days NA NA 30/07/19 24/09/19 14/08/19 12/09/19 -9.69 days None
20 Masonry 0% 18.38 days NA NA 30/07/19 20/08/19 14/08/19 24/08/19 7.44 days Recovery Calendar
21 Vertical column 0% 13.13 days NA NA 10/08/19 25/08/19 19/08/19 26/08/19 3 days Recovery Calendar
22 Roof slab 0% 13.13 days NA NA 25/08/19 09/09/19 26/08/19 04/09/19 -7.63 days Recovery Calendar
23 Coated on masonry 0% 13.13 days NA NA 09/09/19 24/09/19 04/09/19 12/09/19 -19.94 days Recovery Calendar
24 Waterproofing 0% 4.19 days NA NA 24/09/19 05/10/19 12/09/19 17/09/19 -14.25 days None
25 Liquid Applied Water Proof Roof 0% 8.75 days NA NA 24/09/19 05/10/19 12/09/19 17/09/19 -29.5 days Recovery Calendar
Coating
26 Floor coating 0% 21.81 days NA NA 24/09/19 24/10/19 12/09/19 08/10/19 -14.13 days None
27 Floor and wall coating in quarry/ 0% 7 days NA NA 24/09/19 02/10/19 12/09/19 16/09/19 -26.44 days Recovery Calendar
ceramic tiling/ mosaic
28 Painting Clear Finishing 0% 8.75 days NA NA 15/10/19 24/10/19 03/10/19 08/10/19 -27.13 days Recovery Calendar
29 BUILDING FABRIC SUNDRIES 0% 6.63 days NA NA 02/10/19 17/10/19 16/09/19 24/09/19 -20 days None
30 Fire Stopping Systems 0% 13.13 days NA NA 02/10/19 17/10/19 16/09/19 24/09/19 -38.75 days Recovery Calendar
31 Unframed Isolated Trims/ 0% 13.13 days NA NA 02/10/19 17/10/19 16/09/19 24/09/19 -38.75 days Recovery Calendar
Skirtings/ Sundry Items
32 Door/Window Ironmongery 0% 8.75 days NA NA 02/10/19 13/10/19 16/09/19 21/09/19 -36 days Recovery Calendar
33 SPECIAL LOT 0% 41.31 days NA NA 16/07/19 14/10/19 07/08/19 03/10/19 -9.69 days None
Baseline Milestone Récapitulative Durée uniquement Jalons externes
Baseline Summary Récapitulatif du projet Report récapitulatif manuel Échéance
Projet : Nouakchott learning centre Mauritania Critical Split Tâche inactive Récapitulatif manuel Avancement
Date : 24/07/19 Tâche Jalon inactif Début uniquement Progression manuelle
Fractionnement Récapitulatif inactif Fin uniquement Critical
Jalon Tâche manuelle Tâches externes Baseline
Page 1
UPDATED PROGRESS SCHEDULE
ID Nom de la tâche % Complete Duration Actual Start Actual Baseline Start Baseline Start Finish Finish Task Calendar Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Finish Finish Variance Apr May Jun Jul Aug Sep Oct Nov Dec
34 LININGS/SHEATHING/DRY WALL 0% 10 days NA NA 05/10/19 14/10/19 17/09/19 29/09/19 -13 days None
PARTITIONING
35 Gypsum Board 0% 8.75 days NA NA 05/10/19 14/10/19 24/09/19 29/09/19 -25.31 days Recovery Calendar
Linings/Partitions/Ceilings
36 Panels Cubicles/Ducts And Wall 0% 8.75 days NA NA 05/10/19 14/10/19 17/09/19 22/09/19 -36.69 days Recovery Calendar
Linings/Screens
37 Demountable Suspended Ceiling 0% 8.75 days NA NA 05/10/19 14/10/19 17/09/19 22/09/19 -36.69 days Recovery Calendar
38 Windows/Doors/Stairs 0% 41.31 days NA NA 16/07/19 14/10/19 07/08/19 03/10/19 -9.69 days None
39 Aluminium Windows, doors, 0% 13.13 days NA NA 24/09/19 09/10/19 24/09/19 02/10/19 -12.13 days Recovery Calendar
wooden and general glazing
40 MEP 0% 41.31 days NA NA 16/07/19 14/10/19 07/08/19 03/10/19 -9.69 days None
41 Underfloor trunking system 0% 8.75 days NA NA 22/07/19 31/07/19 07/08/19 25/08/19 13.88 days None
Installation
42 Trunking 0% 3.5 days NA NA 16/07/19 20/07/19 25/08/19 29/08/19 27.63 days None
43 Service outlet boxes 0% 4.38 days NA NA 20/07/19 24/07/19 29/08/19 04/09/19 27.63 days None
44 Junctions 0% 3.5 days NA NA 25/07/19 29/07/19 04/09/19 09/09/19 27.63 days None
45 Vertical access 0% 1.75 days NA NA 29/07/19 31/07/19 09/09/19 10/09/19 27.63 days None
46 Electrical supply/power 0% 17.5 days NA NA 24/09/19 14/10/19 12/09/19 03/10/19 -9.69 days None
lighting system
47 Ventilation/Air conditioning system
0% 13.13 days NA NA 24/09/19 09/10/19 12/09/19 28/09/19 -9.69 days None
48 Fluid works, piping 0% 8.75 days NA NA 20/07/19 30/07/19 10/08/19 27/08/19 17.38 days None
49 Fluid works, sanitation and 0% 13.13 days NA NA 09/09/19 24/09/19 05/09/19 21/09/19 -3.38 days None
drainage systems
50 FURNITURE / EQUIPMENT 0% 37.63 days NA NA 31/07/19 07/11/19 10/09/19 24/10/19 -11.63 days None
51 Vending area joinery and Breakfast 0% 13.13 days NA NA 23/10/19 07/11/19 06/10/19 21/10/19 -14.13 days None
bar-Spec 111 & 112,
52 Chairs-Spec 177A 0% 13.13 days NA NA 23/10/19 07/11/19 06/10/19 21/10/19 -14.13 days None
53 Tables-Spec 126 0% 13.13 days NA NA 23/10/19 07/11/19 06/10/19 21/10/19 -14.13 days None
54 Storage units in admin office-Spec 136
0% 13.13 days NA NA 23/10/19 07/11/19 06/10/19 21/10/19 -14.13 days None
55 White board to meeting room spec 194 0% 13.13 days NA NA 23/10/19 07/11/19 06/10/19 21/10/19 -14.13 days None
56 General Internal Signage System 0% 13.13 days NA NA 23/10/19 07/11/19 06/10/19 21/10/19 -14.13 days None
57 Permanent Access And Safety 0% 2.63 days NA NA 23/10/19 26/10/19 06/10/19 09/10/19 -14.13 days None
Equipments
58 ICT Equipements Supply 0% 33.25 days NA NA 31/07/19 08/09/19 10/09/19 20/10/19 35.63 days None
59 ICT Equipements Installation 0% 14.88 days NA NA 08/08/19 26/08/19 07/10/19 24/10/19 50.38 days None
60 PHASE3: COMMISION AND COMPLETIONS 0% 14 days NA NA 24/10/19 11/11/19 24/10/19 10/11/19 -1.13 days None
61 Cleaning and finishing work 0% 13.13 days NA NA 24/10/19 09/11/19 24/10/19 09/11/19 -0.25 days None
62 Provisional acceptance 0% 3.5 days NA NA 06/11/19 10/11/19 06/11/19 10/11/19 -0.13 days None
Baseline Milestone Récapitulative Durée uniquement Jalons externes
Baseline Summary Récapitulatif du projet Report récapitulatif manuel Échéance
Projet : Nouakchott learning centre Mauritania Critical Split Tâche inactive Récapitulatif manuel Avancement
Date : 24/07/19 Tâche Jalon inactif Début uniquement Progression manuelle
Fractionnement Récapitulatif inactif Fin uniquement Critical
Jalon Tâche manuelle Tâches externes Baseline
Page 2