Estimating & Budgeting Worksheet

This document is an estimating and budgeting worksheet template. It includes sections for general requirements, site prep, on-site water and sewer, utilities, and excavation and earthwork. Each section lists estimated costs, actual costs, variances, completion percentages, amounts paid, and amounts due.

Uploaded by

kedar kavathekar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
206 views6 pages

Estimating & Budgeting Worksheet

This document is an estimating and budgeting worksheet template. It includes sections for general requirements, site prep, on-site water and sewer, utilities, and excavation and earthwork. Each section lists estimated costs, actual costs, variances, completion percentages, amounts paid, and amounts due.

Uploaded by

kedar kavathekar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 6

ESTIMATING & BUDGETING WORKSHEET V2.2.

VENDOR ESTIMATED COST


DESCRIPTION ACTUAL VARIANCE % CURRENT AMOUNT NOTES
SUBCONTRACTOR/CONTRACTOR LABOR MATERIALS TOTAL COST Complete PAID DUE

GENERAL REQUIREMENTS 0 0
Plans and Specifications 0 0
Plan Review 0 0
Permits: Zoning, Building, Environmental,
Other 0 0
Survey 0 0
Impact Fee 0 0
Administrative Costs 0 0
Financing Costs 0 0
Legal Fees 0 0
Engineering Fees 0 0
Other 0 0
Subtotal 0 0 0 0 0 0 0
SITE PREP 0 0
Demolition (Remodel) 0 0
Jacking & Shoring (Remodel) 0 0
Dust control, Surface Protection
(Remodel) 0 0
Job-Site Access 0 0
Job-Site Security 0 0
Dumpster & Removal 0 0
Clear Lot 0 0
Storage On Site 0 0
Portable Toilet 0 0
Temporary Power 0 0
Temporary Heat 0 0
Scaffolding Rental 0 0
Tool/Equipment Rental 0 0
Other 0 0
Subtotal 0 0 0 0 0 0 0
ON-SITE WATER/SEWER 0 0
Soil & Perc Tests 0 0
Septic System Design 0 0
Septic Permits, Inspections, Fees 0 0
Septic System Onstallation, Tie In To House
0 0
Dewatering (High Water Table) 0 0
Well, Pump, Trenching, Plumbing To
House, Pressure Tank 0 0
Well Permits & Fees 0 0
Other 0 0
Subtotal 0 0 0 0 0 0 0
ESTIMATING & BUDGETING WORKSHEET V2.2.1

VENDOR ESTIMATED COST


DESCRIPTION ACTUAL VARIANCE % CURRENT AMOUNT NOTES
SUBCONTRACTOR/CONTRACTOR LABOR MATERIALS TOTAL COST Complete PAID DUE

UTILITIES 0 0
Town Water: Tap Fees & Hookup 0 0
Town Sewer: Tap Fees & Hookup 0 0
Electrial: Permit, Connection Fee,
Installation 0 0
Gas: Permit, Connection Fee, Hookup 0 0
LPN: Tank Installation, Hookup 0 0
Oil Tank Installation 0 0
Telecom Hookup 0 0
Other 0 0
Subtotal 0 0 0 0 0 0 0
EXCAVATION & EARTHWORK 0 0
Cut & Fill 0 0
Blasting 0 0
Removal Of Stone/Dirt 0 0
Rough Grading 0 0
Trenching For Utility Hookups 0 0
Foundation Excavation 0 0
Foundation Footing Drains 0 0
Curtain Drains 0 0
Culverts 0 0
Swales 0 0
Retaining Walls 0 0
Ponds 0 0
Other Site Drainage 0 0
Backfill 0 0
Compaction 0 0
Top Soil 0 0
Finish Grading 0 0
Seeding/Sod 0 0
Other 0 0
Subtotal 0 0 0 0 0 0 0
FOUNDATION 0 0
Footings/Pads 0 0
Foundation walls/stem walls/grade beams 0 0
Piers 0 0
Slabs - Foundation, Basement, Garage 0 0
Steel Reinforcing 0 0
Anchor Bolts, Hold Downs 0 0
Bulkheads 0 0
Sub-Slab Vapor Barrier 0 0
Sump Pump 0 0
Sub-Slab Vapor Barrier 0 0
Crawlspace Vapor Barrier 0 0
Crawlspace Vents 0 0
Foundation Windows 0 0
Damproofing, Waterrproofing 0 0
Foundation Drain Board 0 0
Waterproofing/Damproofing 0 0
Slab insualtion: Edge/Below 0 0
Exterior Foundation Insulation 0 0
Exterior Insulation Coating/Protection 0 0
Other 0 0
Subtotal 0 0 0 0 0 0 0
ESTIMATING & BUDGETING WORKSHEET V2.2.1

VENDOR ESTIMATED COST


DESCRIPTION ACTUAL VARIANCE % CURRENT AMOUNT NOTES
SUBCONTRACTOR/CONTRACTOR LABOR MATERIALS TOTAL COST Complete PAID DUE

OTHER MASONRY/PAVING 0 0
Patios 0 0
Exterior Stairs 0 0
Masonry Chimneys 0 0
Fireplaces/Hearths 0 0
Driveway 0 0
Walkways 0 0
Other 0 0
Subtotal 0 0 0 0 0 0 0
ROUGH FRAMING 0 0
Sill & Seal 0 0
Steel/Wood Carrying Beam, Lolly columns 0 0
Floor Framing 0 0
Exterior & Interior Walls, Rough Stairs 0 0
Sheathing, Subflooring 0 0
Roof Framing/Trusses 0 0
Subfascia 0 0
Steel Framing Connectors 0 0
Nails, Screws, Fasteners 0 0
Prep for Plaster, Drywall 0 0
Rough Framing - Labor Only 0 0
Other 0 0
Subtotal 0 0 0 0 0 0 0
ROOFING 0 0
Underlayment 0 0
Membrane 0 0
Flashing: Chimney, Vent Pipes, Sidewalls,
Other Penetrations 0 0
Drip Edge 0 0
Roofing Installation 0 0
Gutters & Downspouts 0 0
Skylights 0 0
Ridge and roof vents 0 0
Other 0 0
Subtotal 0 0 0 0 0 0 0
EXTERIOR 0 0
Exterior Foam Sheathing 0 0
Weather Barrier (Tyvek, etc.) 0 0
Membrane & Flashing 0 0
Vinyl or Composite Siding 0 0
Wood Siding 0 0
Brick Vneer 0 0
Stone Veneer 0 0
Stucco 0 0
Fascia, Soffit, Frieze, Corner Boards, Water
Table 0 0
Soffit/Gable vents 0 0
Window/Door Trim 0 0
Other Exterior Trim 0 0
Exterior Stairs, Landing 0 0
Exterior Paint, Stain, Caulk 0 0
Exterior, labor-only 0 0
Other 0 0
Subtotal 0 0 0 0 0 0 0
ESTIMATING & BUDGETING WORKSHEET V2.2.1

VENDOR ESTIMATED COST


DESCRIPTION ACTUAL VARIANCE % CURRENT AMOUNT NOTES
SUBCONTRACTOR/CONTRACTOR LABOR MATERIALS TOTAL COST Complete PAID DUE

WINDOWS/EXTERIOR DOORS 0 0
Membrane & Flashing 0 0
Exterior doors, prehung 0 0
Exterior door slabs 0 0
Exterior door frames, sills 0 0
Sidelights, transoms 0 0
Locksets, knobs, door hardware 0 0
Patio doors: sliding or hinged 0 0
Windows 0 0
Garage Doors & Opener 0 0
Other 0 0
Subtotal 0 0 0 0 0 0 0
PLUMBING 0 0
Drain/Waste/Vent 0 0
Water Supply Piping 0 0
Gas Piping 0 0
Water Treatment 0 0
Water Heater 0 0
Fixtures: Toilets,Tubs, Sinks, Showers 0 0
Faucets, Mixing Valves, Shower Heads 0 0
Disposal 0 0
Other 0 0
Subtotal 0 0 0 0 0 0 0
ELECTRICAL 0 0
Service Panel, Sub-Panels 0 0
Rough Wiring 0 0
Phone, Cable, Internet Wiring 0 0
Lighting Fixtures 0 0
Low-Voltage Fixtures/transformers 0 0
Exterior Lighting 0 0
Devices: outlets, switches, dimmers 0 0
Lighting control system 0 0
Doorbell System 0 0
Smoke, CO2 Alarms 0 0
Intercom system 0 0
Security system 0 0
Home Theater/Entertainment 0 0
Other 0 0
Subtotal 0 0 0 0 0 0 0
HVAC 0 0
Furnace/Heat Pump 0 0
Central AC 0 0
Air Handler 0 0
Ductwork, Grilles, Registers 0 0
Air Filter 0 0
Boiler, Piping 0 0
Radiators 0 0
Whole-House Ventilation (HRV, ERV,
Exhaust Only, Other) 0 0
HVAC Controls 0 0
Solar hot water 0 0
Other 0 0
Subtotal 0 0 0 0 0 0 0
ESTIMATING & BUDGETING WORKSHEET V2.2.1

VENDOR ESTIMATED COST


DESCRIPTION ACTUAL VARIANCE % CURRENT AMOUNT NOTES
SUBCONTRACTOR/CONTRACTOR LABOR MATERIALS TOTAL COST Complete PAID DUE

INSULATION & AIR SEALING 0 0


Roof/Attic Insulation 0 0
Roof/Eave Baffles 0 0
Wall Cavity Insulation 0 0
Foam Board Insulation 0 0
Spray Foam Insulation 0 0
Basement Insulation Iinterior) 0 0
Crawlspace Insulation 0 0
Air Sealing 0 0

Energy Diagnostics (Blower Door, Infrared)


0 0
Other 0 0
Subtotal 0 0 0 0 0 0 0
DRYWALL/PLASTER 0 0
Walls 0 0
Ceilings, Soffits 0 0
Decorative Plaster 0 0
Drywall Labor Only 0 0
Other 0 0
Subtotal 0 0 0 0 0 0 0
INTERIOR FINISH 0 0
Interior Doors, prehung 0 0
Interor Door slabs 0 0
Interior Door frames, thresholds 0 0
Door knobs,
Interior Trim:hardware
Baseboard, Casings, Crown, 0 0
Chair Rail, Other 0 0
Wainscotting, Paneling 0 0
Built-In Shelving, Cabinets 0 0
Closet Shelving, Hardware 0 0
Stairs, Railings, Newels 0 0
Interior Painting, Staining 0 0
Wood Flooring 0 0
Carpeting 0 0
Resilient/Vinyl
Ceramic Flooring
Tile/Stone (& Underlayment, 0 0
Surface Prep) 0 0
Other Flooring 0 0
Acoustical, Metal, Decorative Ceilings 0 0
Interior Carpentry Labor Only 0 0
Other 0 0
Subtotal 0 0 0 0 0 0 0
ESTIMATING & BUDGETING WORKSHEET V2.2.1

VENDOR ESTIMATED COST


DESCRIPTION ACTUAL VARIANCE % CURRENT AMOUNT NOTES
SUBCONTRACTOR/CONTRACTOR LABOR MATERIALS TOTAL COST Complete PAID DUE

Kitchen & Bath 0 0


Kitchen Cabinets 0 0
Bath Cabinets 0 0
Cabinet Pulls, Hardware 0 0
Countertops, Backsplash 0 0
Ceramic Tile, Stone 0 0
Raised Tub Platform 0 0
Tub Enclosure 0 0
Shower enclosure/doors 0 0
Medicine Cabinets 0 0
Mirrors 0 0
Towel hangers, toilet paper holders,
accessories 0 0
K&B Labor Only 0 0
Other 0 0
Subtotal 0 0 0 0 0 0 0
Porches & Decks 0 0
Open Porch 0 0
Screened Porch 0 0
Wood or Composite Deck 0 0
Fencing 0 0
Other Outdoor Structures 0 0
Other 0 0
Subtotal 0 0 0 0 0 0 0
Appliances 0 0
Refrigerator 0 0
Range, Cooktop 0 0
Microwave 0 0
Range Hood 0 0
Dishwasher 0 0
Washer/Dryer 0 0
Other 0 0
Subtotal 0 0 0 0 0 0 0
[New Category] 0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
Subtotal 0 0 0 0 0 0 0
TOTAL CONSTRUCTION COSTS 0 0 0 0 0 0 0
Note: Add 20% to 25% for contractor’s overhead and profit, plus 8% for sales and marketing if purchased from a developer.