BULK OIL STORAGE AND TRANSPORTATION
COMPANY,
ACCRA PLAINS ADIMINISTRATIVE WORKS
ACCRA-Ghana
INTERIM PROGRESS REPORT
AS AT MARCH 22,2019
Employer: BOST, Accra-Ghana
Contractor: China State Hualong Construction (GH) Ltd.
INTERIM PROGRESS REPORT AS AT MARCH 22nd,2019
Client: Bulk Oil storage and transportation company, Accra Plains Administrative Works-Ghana
Commencement date: 22nd January 2019
Completion date: 22nd July 2019
Overall Actual Progress: 60
Overall Planned Progress: 50
Overall Forecast Progress: 85
1. WORK PROGRESS
S/N ACTIVITY PLANNED ACTUAL FORECAST REMARKS
PROGRESS PROGRESS PROGRESS
(AT MARCH 22) (AT APRIL 22)
1.0 WATER TANK STANDS WORKS(4 No.) 100 100
1.1 Substructure works 100 100 - completed
1.2 Superstructure works 100 100 - completed
2.0 SECURITY POST WORKS (2 No.) 70 70 100
2.1 Substructure works 100 100 - completed
2.2 Superstructure works 60 70 100 -
i)blockworks 100 100 -
ii)Columns works 100 -
iii)Lintel works 100 -
3.0 FENCEWALL WORKS 85 85 100
3.1 Demolition of existing fencewall 100 100 completed
3.2 Substructure works 100 100 completed
3.3 Superstructure
i)Blockworks 60 65 100 -
ii)Casting columns 60 65 100 -
4.0 CHAIN-LINK FENCE WORKS 30 30 80 -
i)Fabrication of chain-link posts 100 100 completed
5.0 PAVING WORKS 70 85 100 -
i) Kerbs works 90 90 100 -
ii)Laying of pavement blocks 65 65 100 -
iii)Compaction of pavement blocks 70 70 100 -
6.0 LANDSCAPING WORKS 70 80 100 -
i)Black soil filling works 100 100 completed
ii)Planting of grass 70 -
7.0 ELECTRICAL WORKS 20 20 45
i) Trenching to receive electrical cables 100 100 100 completed
ii) Laying of cables to draw points 50
iii)Security lightings 40
2. SITE LABOUR FORCE
Chinese Staff Ghanaian Staff
Project Manager 1 1.Foreman 1
Site Manager 2 2.Masons 5
3.Carpenters 4
4.Steel benders 4
5. Labourers 11
Total 3
Total 25
3. MATERIALS ON SITE
S/N Item Unit Q`ty
1 Cement bags 200
2 Fine Aggregate m3 24
3 Coarse Aggregate m3 22
4 Pavement blocks pcs 4200
5 Quarry dust m3 16
6 kerbs pcs 560
4. Progress photos
Pavement works Water stand works Fencewall works
Fig 1 Fig 2 Fig 3
Security Post works
Fig 4