Bulk Oil Storage and Transportation Company, Accra Plains Adiministrative Works ACCRA-Ghana

This interim progress report provides updates on construction projects for Bulk Oil Storage and Transportation Company in Accra, Ghana as of March 22, 2019. Overall actual progress is reported at 60% complete, ahead of the planned 50% but slightly behind the forecast of 85%. Specific updates are provided on the status and progress of various construction activities including water tank stands, security posts, fencing, paving, and landscaping. The report also includes details on site labor force and materials on hand. Progress photos document some of the ongoing work.

Uploaded by

Nana Barima
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
98 views4 pages

Bulk Oil Storage and Transportation Company, Accra Plains Adiministrative Works ACCRA-Ghana

This interim progress report provides updates on construction projects for Bulk Oil Storage and Transportation Company in Accra, Ghana as of March 22, 2019. Overall actual progress is reported at 60% complete, ahead of the planned 50% but slightly behind the forecast of 85%. Specific updates are provided on the status and progress of various construction activities including water tank stands, security posts, fencing, paving, and landscaping. The report also includes details on site labor force and materials on hand. Progress photos document some of the ongoing work.

Uploaded by

Nana Barima
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

BULK OIL STORAGE AND TRANSPORTATION

COMPANY,

ACCRA PLAINS ADIMINISTRATIVE WORKS


ACCRA-Ghana

INTERIM PROGRESS REPORT

AS AT MARCH 22,2019

Employer: BOST, Accra-Ghana

Contractor: China State Hualong Construction (GH) Ltd.


INTERIM PROGRESS REPORT AS AT MARCH 22nd,2019
Client: Bulk Oil storage and transportation company, Accra Plains Administrative Works-Ghana
Commencement date: 22nd January 2019
Completion date: 22nd July 2019
Overall Actual Progress: 60
Overall Planned Progress: 50
Overall Forecast Progress: 85

1. WORK PROGRESS

S/N ACTIVITY PLANNED ACTUAL FORECAST REMARKS


PROGRESS PROGRESS PROGRESS
(AT MARCH 22) (AT APRIL 22)
1.0 WATER TANK STANDS WORKS(4 No.) 100 100

1.1 Substructure works 100 100 - completed

1.2 Superstructure works 100 100 - completed

2.0 SECURITY POST WORKS (2 No.) 70 70 100

2.1 Substructure works 100 100 - completed

2.2 Superstructure works 60 70 100 -


i)blockworks 100 100 -

ii)Columns works 100 -

iii)Lintel works 100 -

3.0 FENCEWALL WORKS 85 85 100

3.1 Demolition of existing fencewall 100 100 completed

3.2 Substructure works 100 100 completed

3.3 Superstructure
i)Blockworks 60 65 100 -

ii)Casting columns 60 65 100 -


4.0 CHAIN-LINK FENCE WORKS 30 30 80 -
i)Fabrication of chain-link posts 100 100 completed

5.0 PAVING WORKS 70 85 100 -


i) Kerbs works 90 90 100 -

ii)Laying of pavement blocks 65 65 100 -

iii)Compaction of pavement blocks 70 70 100 -

6.0 LANDSCAPING WORKS 70 80 100 -


i)Black soil filling works 100 100 completed

ii)Planting of grass 70 -

7.0 ELECTRICAL WORKS 20 20 45


i) Trenching to receive electrical cables 100 100 100 completed

ii) Laying of cables to draw points 50

iii)Security lightings 40

2. SITE LABOUR FORCE

Chinese Staff Ghanaian Staff


Project Manager 1 1.Foreman 1
Site Manager 2 2.Masons 5
3.Carpenters 4
4.Steel benders 4
5. Labourers 11
Total 3
Total 25

3. MATERIALS ON SITE

S/N Item Unit Q`ty


1 Cement bags 200
2 Fine Aggregate m3 24
3 Coarse Aggregate m3 22
4 Pavement blocks pcs 4200
5 Quarry dust m3 16
6 kerbs pcs 560

4. Progress photos

Pavement works Water stand works Fencewall works


Fig 1 Fig 2 Fig 3

Security Post works


Fig 4