Preliminary Method Statement
Preliminary Method Statement
CONSTRUCTION (EPC)
FOR
Rev: 0
24.10.2017
Originator:
OGASCO
PROJECT: EPC for Replacement of 42” LP Flare Header at BAB BCDS PAGE: 1 of 30
DOCUMENT No: Rev: 0 ADCO Invitation No. DATE: 24.10.2017
16534.01
REVISION RECORD
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 2 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
INDEX
1. INTRODUCTION 5
2. BRIEF PROJECT DESCRIPTION 6
3. OGASCO PROJECT CYCLE FOR EPC WORKS 7
4. PROJECT MANAGEMENT 8
4.1Project Team 8
4.2Project Office 9
4.3Planning, Monitoring and Reporting 10
5. EXECUTION 10
5.1Kick – off Meeting 10
5.2Site Visit/Survey Phase 11
5.3Topographical/Geotechnical/Underground Detection Survey 11
5.4Detailed Design 12
5.5Procurement 16
5.6Construction & Erection 18
6 CONSTRUCTION MANAGEMENT 19
7 MANPPOWER MANAGEMENT 22
7.1General 22
7.2Construction Resources 22
8 MAJOR EQUIPMENT MANAGEMENT 23
9 SITE FACILITIES 24
9.1General 24
9.2Required Spaces 24
9.3Site Offices 25
9.4Contractor Temporary Warehouse 25
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 3 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
9.5Contractor Laydown Area 25
9.6Other Facilities And Service 25
9.7Construction Utilities 27
9.8Environmental Consideration 27
10 CONSTRUCTION METHODS AND PROCEDURE 28
11 PRECOMMISSIONING AND COMPLETION 29
12 PROJECT EXECUTION – ORGANIZATION CHART 30
13 ATTACHMENTS 30
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 4 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
1. INTRODUCTION
Oil & Gas Construction LLC (OGASCO) “Tenderer” has been invited by ADCO (hereinafter
COMPANY) to submit a proposal for carrying out the Replacement of 42” LP Flare Header at
BAB CDS Project which encompasses detailed engineering procurement, construction, pre-
commissioning and provision of assistance and supervision during start-up and
commissioning for the completed facilities.
It is not intended that this method statement shall be incorporated into or forms part of the
Contract. This document will be enhanced and further developed during the project execution
stages.
The document intends to clearly identify the key areas of the Project and to describe
Tenderer methodology employed to ensure that the overall requirements and objectives as
set for in the contracts are met. The methodology to be adopted for this project will be based
on a common system long in practice to ensure its successful completion in order to meet
the requirements to Safety, Quality, Cost and Schedule.
In executing the project, Tenderer will adopt the following principles set below which are
critical features for the execution of the CONTRACT to ensure proper control and co-
ordination:
Execution of the work in meeting the requirements of the Project Scope of Work and the
Contract Documentations.
Adherence to an establish Project Quality Plan incorporating the requirements of latest
ISO standards.
Development of procedures to establish effective communications.
Strategic planning and control of the Project utilizing proven project control and reporting
systems.
Maximizing work efficiency through the appropriate use of IT facilities.
Assignment of qualified, proactive and experienced personnel familiar with Project
requirements.
Internal reviews.
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 5 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
2. BRIEF PROJECT DESCRIPTION
The BAB Central Degassing Station (BCDS) consists of 42” LP Flare which has been in
operation for more than 22 years. Hence an Ultra-sonic testing was carried out to check the
integrity of the 42” LP Flare Header.
The UT scanning showed alarming situation for the integrity of the line with approximately
6mm diameter holes in two locations. The UT report revealed that the metal loss is than 60-
90% at more than twenty weak points.
The project objective is to replace these corroded sections of the 42” LP Flare Header upto
the Flare skid including all associated affected items such as process and utility piping,
foundations, electrical and instrumentation at BCDS.
Tenderers understanding of the Scope of Work are outlined as below:
Provision of new 42” flare piping within BCDS upto fence located near the main process
area.
Provision of new pipe supports and foundations within the BCDS with new isolation
valves on the train sub headers to facilitate any future requirement to replace sub-
headers to existing trains.
New piping systems and tie-ins with the existing network.
Replacement of existing piping based on integrity check. The integrity check shall be
carried out by Tenderer.
Modification of closed drain piping system and tie-in with the existing network.
Modification of the existing test separator piping system and tie-in with the existing
network.
Modification of gas piping, plant air, potable water, instrument air and nitrogen piping
system and tie-in with existing network.
OPTIONAL SCOPE
Replacement of the entire 42” LP flare header downstream of BCDS fence upto the LP
flare stack (FL-1903) instead of replacing the corroded segments of the headers based
on the outcome of the integrity check and COMPANY approval .
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 6 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
3. OGASCO PROJECT CYCLE FOR EPC WORKS
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 7 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
4. PROJECT MANAGEMENT
4.1 Project Team
Tenderer plans to execute this Project utilizing our resources and expertise as per given
below
Entity Responsibility Summary of Scope
OGASCO, Mussafah – Abu Dhabi Main Office Overall Management
All related works except for
engineering
ADCO Approved Engineering Engineering Support Detailed Engineering Works
Consultant
OGASCO has the relevant experience and expertise in handling the brown field work of used
material in hydrocarbon contaminated area within live plant. For best delivery of quality
deliverables, we propose to utilize/hire few specialists in this project to take advantage of
their expertise and specialty in handling brown field projects.
Tenderer plans to execute the Project with dedicated leads in each discipline area, and has
adequate technical personnel that can be utilized on an as needed basis for specific
technical studies and analysis. The COMPANY representatives will be located in the same
offices together with Tenderer’s Project Management team.
The key OGASCO team members include: Project Manager, QA-QC Manager, HSE
Manager, and Procurement Manager & Sub-Contracts Engineer.
The Project Manager will be the principle point of contact through the duration of the project
and through the team will be responsible for
Ensure full compliance with all obligations required for the project.
Monitor/Control the resource allocation and timely mobilization.
Prepare planning package including schedule and project execution plan.
Closely monitor project progress.
Issue project control procedures including document control.
Prepare and issue regular progress reports.
Prepare and lead project meetings at all levels.
Issuance of all deliverables.
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 8 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
Setup invoicing procedures
Provide full liaison and support to the client and the other Contractors.
Resource Management in line with the planned progress.
Approval of Documentation Issued.
Project Engineer will be responsible for liaising with the Engineering Manager, Sub-
Contractors and Lead Discipline Engineers in the following capacity:
Assist in the overall delivery of the Scope of Work.
Assist in the overall HSE performance for the Scope of Work.
Reporting and accountability to Project Manager for performance.
Assist in coordination of team building activities.
Participation in technical reviews meetings.
Project Summary – Close Out Report.
Lead Discipline Engineers will have responsibility over specific discipline area work-scope.
The Lead Engineer also is to coordinate with COMPANY representatives.
4.2 Project Office
All the services will be executed from Tenderers main office situated in AbuDhabi, UAE.
A dedicated project area will be allocated for COMPANY representatives and Tenderer’s
Project Management Team to execute the services.
The PMT office located in Mussafah shall be responsible for
Overall Project management
Material & Equipment Management
Engineering Management
Subcontractor Management
QA/QC function
Construction & Erection
The PMT office located at site shall be responsible for
Tight Co-operation with COMPANY during project execution
Co-operation with sub-Contractors
Management of Technical assistance during erection
Performing pre-commissioning and commissioning assistance
Site Logistics and storage of materials
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 9 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
4.3 Planning, Monitoring and Reporting
The Project Team will manage the overall Project planning, progress monitoring and
reporting. Progress will be measured by agreed milestones and weighted to get the overall
progress. The Project Manager will be responsible for monitoring and controlling the
expenditure and progress. Project Control will be organized around the Schedule Level 3 and
Master Document Register. The physical progress will be calculated and reported against
planned.
Schedule will be updated by the Planning Engineer according to the actual date of
completion of the event in the Master Deliverable Register.
For project planning, we propose to use the PRIMAVERA Project Planner software.
A Deliverable Register will be issued within two (2) weeks of the commencement of this
project and will be updated for submission to COMPANY every month thereon.
The Project Manager assisted by his team will prepare Weekly Progress Reports. Weekly
reports will provide a brief status of the project statistics, an update of the one-week look
ahead schedule, an update of the current week activities, and description of areas of
concerns. Main attachments include S-curve and histogram charts.
5. EXECUTION
5.1 Kick – off Meeting
Following the award of the contract, OGASCO shall initiate a robust Project Management
approach to the project. The project activities will commence with a kick off meeting to be
held in COMPANY office in Abu Dhabi which shall be attended by the Tenderer and the
Tenderers engineering consultant. The purpose of the meeting will be to define;
An overview of the project.
Restatement of the scope of work and services
Establishment of communication protocols
Review any information relating to other ongoing projects that may have a bearing on
the scope of work.
Review project schedule
Arrangement of site visit dates
Obtain all relevant documents drawings and data of existing facilities from COMPANY.
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 10 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
5.2 Site Visit/Survey Phase
Following the KO meeting, Tenderer shall forward relevant requests to the COMPANY to
enable security passes to be obtained for the site visit and data collection exercise for the
proposed modification area and proposed tie-in locations.
The Project Manager will lead the site visit supported by the relevant discipline engineers.
The aim of the site visit will include the following
Familiarisation with the existing field operations and site details
Review of existing operator documentation.
Collect and review As-built drawings and document relevant to this scope of work.
To further verify all data presented to OGASCO during the ITB and KOM, clarify any
inconsistencies and obtain any additional information that may be required to complete
the work.
Identify/check the location of tie-in points, crossings and other critical areas, determine
the civil, piping, electrical and instrumentation work interfaces as relevant to this work.
Additional information necessary to evaluate possible problem areas will be obtained in this
exercise in order to identify primary alternatives for more detailed evaluation.
On return from site visit, OGASCO shall prepare and submit to COMPANY a site survey
report for review and approval. This will then create a working document for the survey and
subsequent progress of the project.
5.3 Topographical/Geotechnical/Underground Detection Survey
The survey works shall be carried out by a specialist third party. Following the survey
following documents provided by sub-contractors shall be provided to Tenderers Engineering
Consultant;
Survey Report;
Preliminary Profile (in approved editable AutoCAD format);
Preliminary Route (in approved editable AutoCAD format);
A preliminary method statement regarding to the topographical survey has been attached
along with which forms a part of this document.
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 11 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
5.4 Detailed Design
Upon verification of all critical basic FEED design deliverables, Engineering Consultant will
commence with the detailed design activities. The detailed design will address the activities
listed below.
Design Basis
Process
Piping
Instrumentation/Controls
Electricals
Civil/Structural
HSE
Following shall be the proposed deliverables that shall be submitted to COMPANY during the
engineering stages
LIST OF DELIVERABLES
GENERAL
PROJECT EXECUTION AND QUALITY PLAN
DESIGN BASIS MEMORANDUM
DESIGN REVIEW REPORT
SITE VISIT REPORT
FEED ENDORSEMENT REPORT
PROCESS
HAZOP CLOSEOUT REPORT
OPERATING & CONTROL PHILOSOPHY
PRE-COMMISSIONING & COMMISSIONING PHILOSOPHY
TIE-IN PHILOSOPHY
ISOLATION PHILOSOPHY
PROCESS SAFEGUARDING PHILOSOPHY
DRAIN /VENT PHILOSOPHY
START-UP /SHUT DOWN PHILOSOPHY
PROCESS HYDRAULICS CALCULATIONS
PROCESS FLOW DIAGRAMS
PROCESS AND INSTRUMENTATION DIAGRAMS (DEMOLITION)
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 12 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
PROCESS AND INSTRUMENTATION DIAGRAMS (CONSTRUCTION)
SPECIFICATION FOR SAFETY EQUIPMENT/SIGNS)
DATASHEET FOR SAFETY EQUIPMENT/SIGNS
MR FOR SAFETY EQUIPMENT/SIGNS
TBE FOR SAFETY EQUIPMENT/SIGNS
SAFETY EQUIPMENT REGISTER
SAFETY EQUIPMENT DRAWING
FLARENET MODEL FOR FLARE SYSTEM HYDRAULICS
PIPING
PIPE WALL THICKNESS CALCULATIONS
PIPING STRESS ANALYSIS REPORTS
PIPING MATERIAL SPECIFICATION
SPECIFICATIONS FOR VALVES
DATASHEETS FOR VALVES
MR FOR VALVES
TBE FOR VALVES
SPECIFICATION FOR PIPING SPECIALITY ITEMS
DATASHEETS FOR PIPING SPECIALITY ITEMS
MR FOR PIPING SPECIALITY ITEMS
TBE FOR PIPING SPECIALITY ITEMS
LINE SCHEDULE
TIE-IN SCHEDULE
PIPE SUPPORT SCHEDULE
EQUIPMENT SCHEDULE
MATERIAL TAKE-OFFS
PLOT PLAN
PIPING GENERAL ARRANGEMENT DRAWINGS (CONSTRUCTION)
PIPING GENERAL ARRANGEMENT DRAWINGS (DEMOLITION)
PIPING LAYOUTS (CONSTRUCTION)
PIPING LAYOUTS (DEMOLITION)
PIPING KEY PLANS
STANDARD PIPE SUPPORT DRAWINGS
PIPING ISOMETRICS DRAWINGS
SCOPE OF WORK FOR TOPOGRAPHIC SURVEY
SCOPE OF WORK FOR GEOTECHNICAL INVESTIGATION
INSTRUMENTATION
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 13 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
SPECIFICATION & SOW
ADDENDUM TO SPECIFICATION OF INSTRUMENT DESIGN CRITERIA
ADDENDUM TO SPECIFICATION OF INSTRUMENT INSTALLATION DESIGN
ADDENDUM TO SPECIFICATION OF INSTRUMENT CABLES
ADDENDUM TO SPECIFICATION OF CONTROL VALVES
SPECIFICATION FOR FIELD INSTRUMENTS
SPECIFICATION FOR INSTALLATION MATERIAL
SPECIFICATION FOR F&G DEVICES
SPECIFICATION FOR FLOW METERS
DATASHEET FOR FLOW METERS
MR FOR FLOW METERS
TBE FOR FLOW METERS
DATASHEETS FOR PRESSURE GAUGES AND TRANSMITTERS
MR FOR PRESSURE GAUGES AND TRANSMITTERS
TBE FOR PRESSURE GAUGES AND TRANSMITTERS
DATASHEETS FOR LEVEL TRANSMITTERS
MR FOR LEVEL TRANSMITTERS
TBE FOR LEVEL TRANSMITTERS
DATASHEET FOR CONTROL VALVES
MR FOR CONTROL VALVES
TBE FOR CONTROL VALVES
DATASHEET FOR PRESSURE SWITCHES
MR FOR PRESSURE SWITCHES
TBE FOR PRESSURE SWITCHES
DATASHEET FOR FLOW TRANSMITTERS
MR FOR FLOW TRANSMITTERS
TBE FOR FLOW TRANSMITTERS
INSTRUMENT SCHEDULE
INSTRUMENT CABLE SCHEDULE
INSTRUMENTATION BULK MTO
INTERCONNECTION WIRING DIAGRAMS F&G, DCS
INSTRUMENT TERMINATION DETAILS
INSTRUMENT LOOP DIAGRAMS
INSTRUMENT LOCATION AND CABLE ROUTING LAYOUT
INSTRUMENT TYPICAL INSTALLATION DETAIL
INSTRUMENT TYPICAL HOOK-UP DETAIL
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 14 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
INSTRUMENT ENGINEERING SHEETS
ELECTRICAL
ELECTRICAL LOAD FLOW STUDY
ELECTRICAL SHORT CIRCUIT STUDY
CABLE SIZING CALCULATIONS
ELECTRICAL CABLE SPECIFICATIONS
DATASHEET FOR ELECTRICAL CABLES
MR FOR ELECTRICAL CABLES
TBE FOR ELECTRICAL CABLES
ELECTRICAL LOAD LISTS
ELECTRICAL CABLE SCHEDULES
ELECTRICAL TIE-IN SCHEDULES
ELECTRICAL MATERIAL TAKE-OFFS
INTERCONNECTION DIAGRAMS
ELECTRICAL CABLE ROUTING LAYOUTS
EARTHING LAYOUTS
ELECTRICAL INSTALLATION DETAILS DRAWINGS
DEMOLITION SINGLE LINE DIAGRAMS
DEMOLITION ELECTRICAL LAYOUTS
CIVIL/STRUCTURAL
SOW FOR TOPO/GEO/UG SURVEYS
TBE FOR TOPO/GEO/UG SURVEYS
DESIGN CALCULATIONS FOR PIPE SUPPORT, PIPE RACKS
DESIGN CALCULATIONS FOR STORM WATER, OILY WATER
GENERAL NOTES ABBREVIATIONS AND SYMBOLS
TYPICAL ROAD AND PAVEMENT DETAILS
TYPICAL FENCE AND GATE DETAILS
TYPICAL CONCRETE PROTECTION DETAILS
TYPICAL STEEL LADDER DETAILS
TYPICAL TRAFFIC AND ROAD MARKING DETAILS
TYPICAL CRASH BARRIER DETAILS
CIVIL GENERAL ARRANGEMENT PLANS AND SECTIONS
STRUCTURAL GA PLANS AND SECTIONS
ROADS AND PAVING LAYOUTS
OILY WATER LAYOUT
FOUNDATION LAYOUTS
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 15 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
FOUNDATION DETAILS
PIPE SUPPORT DETAILS
DEMOLITION LAYOUTS
TRESTLE STRUCTURAL STEEL DETAILS - GENERAL ARRANGEMENT
TRESTLE CALCULATION REPORTS
SPECIFICATION FOR RC WORKS
SPECIFICATION FOR STEEL, SITE PREPARATION AND EARTH WORKS
HSE
HSE PLAN
HSE PHILOSOPHY
SIL CLOSEOUT REPORT
HAZID CLOSEOUT REPORT
PHSER CLOSEOUT REPORT
HSE TRACKING REGISTER (INPUTS TO EPC REGISTER)
SIMOPS CLOSE OUT REPORT
CONSTRUCTABILITY REVIEW REPORT
PFP LAYOUTS
5.5 Procurement
Procurement activities will be coordinated and carried out by purchasing/procurement teams
under the management of purchasing/procurement managers (PPM) in the PMT office at
Mussafah. PPM and their teams will be responsible for elaborating the vendor list and for
establishing procedures and forms (purchase order, terms and conditions) for the project
procurement activities.
Technical requisitions will be prepared by engineering contractor under coordination of each
discipline engineer in the PMT office. After review, a technical documentation is performed in
accordance with standard procedures and approval by the responsible project engineer.
These requisitions will be issued to the purchasing/procurement team including the names of
the bidder from vendor list agreed in the Contract document.
In order to comply with the project requirements and schedules, procurement activities will
follow below mentioned regulations:
Selection of technically qualified vendors from vendor list
Delivery time is consistent with overall schedule of contractual documentation
Requirements of contract and specifications are fulfilled
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 16 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
Purchasing/Procurement Manager (PPM) as a member of PMT is responsible for
procurement management. Proposed procurement organization in detail will be presented
after contract award.
Purchase of equipment and materials will be executed by qualified purchasers under
direction of the PPM. Purchasers will share their responsibilities for the following categories
of equipment and materials:
Mechanical equipment
Piping
Fabricated products
Electrical equipment and instruments
Fire fighting
Responsibility of expeditors, who are members of PPM team, commences from time they
receive the information of placement the purchase order till the time they hand over all
necessary particulars concerning the purchase order to invoicing team.
Quality assurance inspector is responsible for the following activities:
Performing the inspection and testing
Review and endorsement of test records submitted by vendor
Review of manufacturer data record
Issuance of inspection release note
Reporting non-conformities
Procurement plan comprises the following procedures:
Inquiries will be issued to vendor included in vendor short list.
Evaluation of Quotations
Technical evaluation in engineering team (un-priced quotations)
Commercial evaluation by PPM and finally by PM
Upon receiving approval of vendor selection from project manager the purchaser
shall place the respective purchase order.
Expediting plan shall follow delivery schedule which has been submitted to
COMPANY.
Storage of the procured materials
The warehouse for storage of Materials for the Project shall be located on the
planned area of the Site. However, those Goods/ materials shall also be
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 17 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
stored at the Site if that storage is convenient for erection/ installation, saving
time for Goods/materials utility as well as reducing cost of transportation
without any negative impact to the construction execution.
All the Materials will be stored and mobilized in required quality, quantity, and
model. The proper care and storage in accordance with the requirements and
specifications of each Materials shall not only keep the Materials in good
quality but also make the management procedure easily, safely and
conveniently.
5.6 Construction & Erection
All field construction and erection will be performed by OGASCO or subcontracted to well
qualified subcontractors and will be performed under its total responsibility and management.
The field organization consists of Construction Management, Field Planning and Control,
QA/QC, HSE/Security, Commissioning, Administration/ Accounting, Material Control, Field
Engineering.
Civil works shall be sub-contracted to COMPANY approved contractor. Civil contractor shall
become involved with EPC Project execution immediately after contract award with the
assignment of the Construction Manager to Contractor's Project Management Team.
Construction staff will be mobilized to Site to set up the Site Temporary Facilities like
construction power, construction water, storage yard, construction yard etc. The Construction
Manager takes direct control.
During his PMT office assignment, the Construction Manager prepares, with construction
specialists, detailed plans for the field activities including subcontractor selection, schedules,
site facilities, mobilization plans, construction equipment requirements and heavy lifts etc. In
general, every aspect of construction and Site activity is planned in great detail, based on
engineering and procurement information from nominated Engineering Contractor.
The Construction Manager (CM) reports to the Project Manager. The CM has full authority
supported by respective specialists and responsibility on all field activities.
For efficient control of construction, the work would be divided into several areas, each
managed by Coordinator responsible for Mechanical, Piping, Civil/Building and Electrical/
Instrumentation.
Activities are organized and implemented on an area basis but, as completion approaches, it
is shifted into system basis to allow an early start of pre-commissioning activities.
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 18 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
We set up the construction plan for the Project focused on the Project’s critical issues
especially related to construction activities such as areas for lay-down, temporary facilities,
warehousing, etc. and availability of skilled craft labor.
This plan is a preliminary construction plan worked out on the basis of past experiences and
the latest information. We will prepare and submit more practical construction execution plan
in detail, providing that the Project’s information such as scope of work and supply,
discipline, magnitude and volume, the condition of temporary facility space for the
construction work be provided to the Contractor.
6. CONSTRUCTION MANAGEMENT
We plan, manage and control all the construction activities for the project with full knowledge
of applicable laws and regulations, conditions of labor, local conditions, the site conditions
and environmental aspects and will comply with requirements thereof.
After contract award, the Construction Management Team (CMT) is organized in the head
office. The CMT begins by studying and reviewing key elements of project schedule
including progress, manpower, construction equipment, materials and other construction
procedures including constructability study.
The CMT then develops and defines the construction plan to provide maximum value and
minimized costs for the overall project and project execution paying careful consideration to
the sequence of construction in order to meet safety requirements and achieve defined
mechanical completion and startup dates.
Later we organize the CMT at the site to manage and coordinate all construction efforts
associated with the work and ensure the required safety, quality, and performance. This
effort includes, but is not limited to, site HSE, monitoring all subcontractor schedules,
materials management, progress assessment, project report, quality assurance and quality
control, field engineering, turn-over of facilities, obtainment of permits and approvals.
The CMT will
provide management, inspection and coordination among subcontractors.
coordinate the provision of materials, if applicable, and services furnished by sub-
contractor
provide interface coordination among all of its subcontractor’s work force in addition
to other contractor’s interface activities and the Owner and/or other entities.
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 19 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
Contractor’s scope of work and services for construction management at the site will include
the followings:
Achieve the highest level of safety to avoid accidents/incidents with stimulation of
health and well-being of the people on the job and no negative impact on the
environment through strict adherence to the Owner’s HSE procedures Safety
requirements
Effectively manage contractor’s own and subcontractor’s construction staff
Prepare risk management plans and accordingly identify risks early and mitigate
construction risks
Meet the quality requirements as set forth in the project specification through effective
quality assurance and quality control plan
Ensure that construction is carried out to meet the design requirements as set out in
the project specification and conforms to the approved engineering drawings and
documents.
Manage, coordinate and monitor the subcontractor’s activities and work.
Award, manage, control and administer subcontractors.
Meet the intermediate milestones target dates to achieve the scheduled completion
date
Meet construction completion within the approved budgets and costs
Interface management and coordination with all parties within and outside the project
Perform field engineering as required including interface and coordination with the
engineering team of home office
Organize, manage and coordinate with the vendor representatives during installation
and pre-commissioning
Adhere to national, local and the Owner’s rules and regulations.
Manage and control field procurement, logistics and materials.
Organize, manage and provide training at the site for the Owner’s staff as stated in
the project specification
Maintenance of good public relations
Contractor’s method of executing the construction and pre-commissioning will be applied to
subcontractors under the direction of the CMT. The whole construction work shall be
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 20 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
subdivided some subcontract packages in consideration of homogeneous construction
disciplines, magnitude of the works and construction program requirements.
Contractor may adjust and modify this organization in the process of construction execution
of the project in order to accommodate any requirement that may be developed in
consideration of homogeneous construction disciplines and magnitude of the works.
We will perform overall construction management services and construction work activities
through subletting to subcontractors. All the mechanical works shall be carried out by
contractor (both at shop and site) whereas all other activities such as civil, E&I and cathodic
protection shall be sub contracted.
Contractor will control all phases of the construction work fully utilizing all functions and
departments within the site organization. Field control activities will be performed in
accordance with schedule, progress, manpower, cost, materials and quality control
procedures.
Accurate schedule forecasting will be achieved by monitoring of actual progress which will be
compared against scheduled progress from which forecasts will be developed through
effective utilization of computer system. Based on the analysis of forecast trends, corrective
actions will be immediately recommended where required.
In order to realize the above control concept in field construction, the following Construction
Management Service will be provided in accordance with the relevant plans and procedures
which shall include, but not limited to, the following:
Field Scheduling
Progress Measurement
Field Material Control
Field Quality Assurance
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 21 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
Safety
Security
Site Work Rules
Construction Reporting
Manpower Control
Environmental Control
Field Changes
The Subcontractor may modify and update above procedures in the process of execution to
accommodate any requirement that may be developed.
Dimensional or design errors which may occur in drawings or specifications.
Incorrect or insufficient material take-off
Late delivery of equipment or materials
Faulty shop inspections
Faulty action in the field
7. MANPPOWER MANAGEMENT
7.1 General
A well prepared and logical mobilization plan for construction resources is essential in
ensuring a coordinated and successful start-up to construction work and to further ensure the
early preparation and completion of all construction procedures and similar documentation.
The mobilization plan will deal with all activities necessary to ensure the timely arrival on site
of personnel, construction equipment as required to commence and subsequently maintain
the agreed construction schedule.
7.2 Construction Resources
The Construction management team (CMT) begins work in the home office Engineering
Center during early detailed design and planning phases to provide construction input with
regard to procedure preparation, design solutions, planning, etc. and to carry out
constructability reviews on an on-going basis. Special attention will be taken to interface
coordination from the early stage.
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 22 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
The Contractor will establish an integrated Construction Management Team at the
construction site to supervise the construction activities at the site.
The Contractor is featured with numerous and sufficient manpower resources within its
organization to mobilize for the project. However in case if required Contractor propose to
utilize/hire few specialists in this project to take advantage of their expertise and specialty in
handling such brown field projects.
Meanwhile, contractor will mobilize the capable and experienced construction management
personnel for the project by the roll-over of resources.
All construction equipment will be available at the site in accordance with the construction
equipment mobilization schedule.
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 23 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
9. SITE FACILITIES
9.1 General
The detailed execution plan for construction and operation of temporary facilities will be
developed on the basis of designated area provided by the COMPANY. Site Facilities plan
such as site offices, lay-down will be finalized on the basis of work volume and labor
quantities will be developed later on.
The Contractor will design, procure, install and properly maintain all its provided temporary
facilities necessary for full and complete performance of work within the area assigned by the
COMPANY. Temporary facilities work will be started prior to the commencement of civil work
during site preparation stage.
The Contractor will establish site temporary facilities plan including site offices, toilet/washing
facilities, first aid facilities, warehouse, work shop, maintenance shop for construction
equipment, lay-down area, etc. in allocated area by the Owner for contractor/subcontractor’s
management and supervision staffs.
The Contractor will also construct site temporary facilities including utility systems for water
and power in compliance with the Owner’s requirements. The detail plan of all temporary
facilities and site offices will be finalized at the early in construction stage after confirmation
to the COMPANY and the finalisation of the subcontractor packages.
9.2 Required Spaces
Enough spaces for temporary facilities area such as site offices and lay-down area for
Contractor and subcontractor are required to perform construction work up to the completion
of the Project. Designated spaces for lay-down area will be expected to allocate in close
complex.
Lay-down area for bulk material such as pipe spools, prefabricated plate for tank and steel
structure material and buildings such as warehouse, workshop, civil work shop,
prefabrication shop and E&I shop should be provided for construction activities.
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 24 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
The specific configuration of lay-down areas with respect to each other will be determined
later on. However, for the reference, minimum spaces shall be allocated as per Contractor’s
in-house data as shown below.
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 25 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
reporting of minor first aid cases. Medical Facilities (MF) in the site offices will be installed
for minor injuries, equipped with a first aid facilities will be positioned around Contractor’s
area.
Other first aid will be installed at Contractor’s Medical Treatment Facility (CMF) in the Camp
area. Contractor’s Medical Treatment Facility with adequate ambulance transportation and
highly trained staff will be located in camp area. Contractor’s Medical Treatment Facility will
be operated and staffed 24 hours per day, under the direct responsibility of Contractor.
The Contractor will provide facilities to communicate with the COMPANY by various means.
Contractor’s communication and IT infrastructure will include software, hardware and cabling
for e-mail, LAN, telephony, fax services and two-way radio communication services.
The Contractor will provide, install, configure, administer and maintain all contractor
communication system infrastructures. The Contractor will install the temporary security
fence and gates for contractor’s temporary facilities areas for site offices area, lay-down area
and camp area respectively to secure contractor’s office area and/or materials and
equipment.
The Contractor will provide adequate lighting facilities at working area, storage area, camp
area and other required area. Perimeter lighting will be installed with the outer fence for the
security. The detailed information will be submitted in early construction stage based on
actual site conditions.
A temporary emergency power station will provide electricity for the temporary facilities in
case of emergency. The supply will be by means of diesel-generators and will comprise of
generators sized to have spare capacity.
The Contractor will provide adequate fire protection measures throughout the construction
period at a level commensurate with the prevailing risk. Fire protection measures will meet
the requirements of the authorities and the COMPANY.
The Contractor will erect, operate and maintain fire extinguisher sets and other fire fighting
equipment at the camp. Smoke detectors will be provided, too. Contractor’s and
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 26 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
subcontractors’ personnel will be trained for the operation of all fire protection system and
equipment
The sanitary sewage from the temporary facilities area and construction areas will be
collected in sewage holding tank at camp area and transferred to a local sewage treatment
facilities until a central sanitary sewage treatment plant.
The Contractor will dispose waste water from pipe and equipment flushing, residues of
chemical cleaning, hydro test water and other liquid wastes from construction activities
including all other contaminated materials in an environmentally safe manner though site
drainage system to tie-in point allocated by the Owner.
Garbage and other refuse are collected in closed garbage containers which are emptied
daily, and the contents hauled to approved/designated disposal area. Scrap materials will be
gathered at the location in the temporary facility area.
Mobile air compressors will be provided by contractor and subcontractor, when required.
Site offices will be equipped with wall mounted type room air conditioner and exhaust fan.
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 27 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
The environmental and management issues that have been specifically considered within
this Environmental Management Plan include:
Water Quality;
Air Quality, including dust, emissions and odors;
Noise and Vibration;
Waste Management;
Worksite Housekeeping;
Emergency Response Plans.
This plan is designed to assist project management in developing appropriate environmental
controls and integrate the controls into site activities. It provides an outline of the specific
responsibilities and documentation to be maintained to facilitate internal and external
auditing of environmental controls.
The Contractor expects all parties involved in projects to comply with all applicable HSE
legislation as a minimum standard. The adoption of best practice will be positively
encouraged, and all parties will be required to demonstrate their application of best practice
and innovation in order to reduce adverse environmental impacts.
It is Contractor’s intention to complete the construction work to the highest possible standard
using the best possible techniques at each stage of construction.
Contractor will issue after the contract award the construction procedures to be implemented
at the site to regulate and govern relations among COMPANY, Contractor and
Subcontractors.
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 28 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
This is a preliminary list of the procedures to be adopted at site:
Site co-ordination procedure
Site correspondence procedure
Site meeting procedure
Contractor schedules, sequence of work and reporting procedure
Construction planning and reporting procedure
Construction progress measurement and monitoring procedures
Site HSE plan
Materials handling and storage procedure at site
Field quality control procedure
Sub-contract administration procedure
Documents/drawings management procedure, including field design change
Procedure for the treatment of non-conforming material at site
Mechanical completion procedure
Environmental protection measures procedure
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 29 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017
12. PROJECT EXECUTION – ORGANIZATION CHART
PROJECT OWNER/COMPANY/CLIENT
PROJECT MANGER
PROCESS ENGINEERS PROC. SERVICES SITE MANAGEMENT
CIVIL ENGINEERS PURCHASE ORDER QA/QC
PIPING ENGINEERS VENDOR QUAL. LOCAL PROC.
MECH. ENGINEERS EXPEDITING COMMISSIONING
ELEC. ENGINEERS LOGISTICS COMPLETION
INST. ENGINEERS SUB-CONTRACTS STARTUP
13. ATTACHMENTS
METHOD STATEMENT FOR CIVIL WORKS (TYPICAL)
METHOD STATEMENT FOR UNDERGROUND SCANNING SERVICES (TYPICAL)
PRELIMINARY PROJECT SCHEDULE
DOCUMENT TITLE:
ADCO Invitation No. 16534.01
PRELIMINARY PROJECT EXECUTION PLAN for
Replacement of 42”LP Flare Header at BAB CDS
PAGE 30 of 30
DOCUMENT No: Rev: 0 Date:24.10.2017