Two Storey Residential: Project: Location: Duration: 5 Months Subject

This document provides a PERT chart for a two storey residential project over a duration of 5 months. It outlines the key tasks such as site preparation, excavation, concreting, masonry, wall finishes, electrical works, and plumbing over their estimated durations. The critical path activities include concreting taking 28 days, masonry and plastering taking 35 days, and project completion in 70 days.

Uploaded by

Dave Inn
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
670 views1 page

Two Storey Residential: Project: Location: Duration: 5 Months Subject

This document provides a PERT chart for a two storey residential project over a duration of 5 months. It outlines the key tasks such as site preparation, excavation, concreting, masonry, wall finishes, electrical works, and plumbing over their estimated durations. The critical path activities include concreting taking 28 days, masonry and plastering taking 35 days, and project completion in 70 days.

Uploaded by

Dave Inn
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Project: Two Storey Residential

Location:
Duration: 5 Months
Subject: PERT CPM
Plumbing & Sanitary

65 d

Metal Doors &


Decking Windows

3d 21 d

Roof Framing Floor Finishes


Formworks
26 d 28 d 31 d
Gen Req. & Site Prep. & Gravel Bed & soil Masonry & Wall Finishes
Mobilization Layout Excavation Poisoning Concreting Plastering Demobilization
6d 3d 7d 9d 28 d 35 d 70 d
Rebar Works Ceiling
Finishes
26 d 21 d

Exterior
Finishes
28 d
Electrical

65 d