Applies to
SAP Plant Maintenance Module for Master Data upload.
Summary
Manufacturing Industries run on complex business processes and so require huge amount of Master Data like Machines and spare parts from tiny
Bearings to giant Rollers. This article describes Creation/ Upload of Master Data in system using LSMW at one-go.
Author: Ankur Saraf
Company: NTT Data Americas
Created on: 5 October 2012
Author Bio
Ankur Saraf is currently working in NTT Data Americas as SAP PM Consultant. He has knowledge in Maintenance Planning, Maintenance
Order and Notifications Management, Serial Number Management and PMIS Reporting.
Table of Contents
Applies to
Summary
Author Bio
LSMW: An Introduction
Considerations: Before you proceed
Project preparation: Creating Project, Subproject and Object
Recording Creation:
LSM Workbench: Process Steps
Step 1: Maintain Object Attributes
Step 2: Maintain Source Structures
Step 3: Maintain Source Fields
Step 4: Maintain Structure Relations
Step 5: Maintain Field Mapping and Conversion Rules
Step 6: Maintain Fixed Values, Translations, User-Defined Routines
Step 7: Specify Files
Step 8: Assign Files
Step 9: Read Data
Step 10: Display Read Data
Step 11: Convert Data
Step 12: Display Converted Data
Step 13: Create Batch Input Session
Step 14: Run Batch Input Session
Related Content
LSMW: An Introduction
LSMW- Legacy System Migration Workbench is an SAP tool used for master data upload/ Create into the system. You can use this tool while
uploading data from legacy system into R/3 environment or to create and upload master data of huge amount. This tool follows a step-by-step
procedure of 14 steps to create the master data into the system.
Recording Creation:
In the Menu Bar, Goto- ‘Recordings’.
Create a new recording and give the description. System will automatically populate the ‘owner’ field.
In the ‘General’ tab provide your required details. Here Object type’, ‘Manufacturer’ and ‘Model number’ details are entered.
Enter ‘Location’ related data in the tab in respective fields.
Enter ‘Account assignment’ and ‘Responsibilities’ relevant data as per your business requirements.
Now Install Equipment in appropriate Function Location.
When ‘Saving’ the master data, system internally will be creating Recording so as to provide reusabiliy and reference for mass data
upload.
Here, we are using ‘Batch Input Recording’ method to upload master data.
Select ‘Display <-> Change’ button and get it in change mode.
Enter the Recording which was created through beginning steps, i.e.‘REC_EQUIP’ and click on ‘Save’.
When the first step is completed, the system takes you to previous screen and populates the field against it.
Step 2: Maintain Source Structures
Source structures can be used to design the hierarchy of the files to be uploaded. However, here highest hierarchy level is sufficient. Structures
are prerequisites for Maintaining Source Fields.
Select the next step radio button and Execute. System then takes you to ‘Display’ mode of Source Structure.
From Table view, select ‘TABNAME’, ‘Type’ and ‘Length’ and maintain the excel sheet.
By default system takes to the ‘Display’ mode of Source Fields.
Go to Change mode, place the cursor on structure and click ‘Table Maintenance’ button.
Now, maintain the excel sheet values in Source Fields for Source Structure.
System takes internal table reference and populates the Field description with reference to Field name.
Save and go back.
All fields of all target structures, which were selected in the previous step, will be displayed.
Bring the screen into Change mode and then In menu bar, go to ExtrasàAuto Field Mapping
Now accept proposal for all the fields which need to upload.
At the end of proposal acceptance for all the entries system displays the below message:
After auto field mapping complete, save and back.
Click on ‘Execute’ and the data read status and number of records would be displayed on the screen.
Step 10: Display Read Data
Here, we can display the records which were read in previous step.
Check, whether data has been correctly fit into fields. We can also give the line selection based on need.
Step 11: Convert Data
Here, the legacy data is converted into SAP standards. We can check the data converted later on.
Click on ‘Execute’ button and system displays the status for the data conversion.
Note: Check the number of records from Step 9. Both should be same.
Step 12: Display Converted Data
Executing this step displays the data converted in the previous step.
Note: Here the visual check can be performed to check the values lifted by the file against the fields of SAP to be correct and as per
requirements.
Step 13: Create Batch Input Session
In this step, we create batch input session.
Make sure to check box for ‘Keep batch input folder’.
Step 14: Run Batch Input Session
Here, we run the batch input session, which is created in the previous step.
Now, the Master data for the Equipment will get uploaded in the SAP System.