Distillery Wastwater Treatment-CDM Project-2012
Distillery Wastwater Treatment-CDM Project-2012
(CDM - Version 03
CONTENTS
D. Environmental impacts
E. Stakeholders’ comments
Annexes
Annex 1: Contact information on participants in the proposed small scale project activity
Version : 01.8
Date : 20/12/2012
ctivity:
Purpose of the Project Activity:
M/s. Green Elephant India Private Limited is a renewable energy company focusing on biomethanation
projects to produce biogas. The company was incorporated and registered in India under the Indian
Companies Act 1956 on 9th May 2008 and is a wholly owned subsidiary company of Green Elephant
GmbH, Germany. The project activity is setting up a biomethanation plant to produce biogas from
organic waste (spent wash) which is one of the most potent substrate to generate biogas. The thermal
energy generation unit which consumes biogas from the biogas purification unit is located at the distillery
unit of M/s. Kisan Veer Satara Sahakari Sakhar Kharkana
Kharkana Limited (KVSSSKL) in Satara district of
Maharashtra, India. KVSSSKL operates a sugar plant adjacent to the distillery unit.
Prior to the project activity, the old system consists of 5 boilers. Out ut of which steam from four boilers
were utilized by the sugar industry for meeting the heat and power demand and the fifth boiler is
exclusively used by the distillery unit. The new system consisting of 22 MW cogeneration and Biogas
fired distillery boiler will replace the old system. The 22MW cogeneration on system will cater the needs
(both heat and power) of the sugar industry. The biogas fired boiler (distillery boiler) will provide thermal
energy required by distillery unit.
unit. In absence of the project activity, 22 MW cogeneration system would
have catered the needs (both heat and power) of the sugar mill and the new coal fired boiler would meet
the steam requirement for the distillery unit. The new 22 MW cogeneration System is not a part of the
project boundary. The project boundary is clearly given in the
th section B.3.
CPCB states that, all distilleries unit will achieve zero discharge
discharge in surface water bodies and 100 %
utilization of spent wash. In Maharashtra, the project site contains the co operative sugar industry and the
distillery unit as similar to the project activity; they used to bio compost the press mud from sugar
industry with the spent wash from the distillery unit. These distillery units achieve 100% utilisation of
spent wash with the press mud for bio composting. This is the common practise for spent wash treatment
in Maharashtra for achieving the Zero Discharge in surface
sur water bodies1.
1
http://business-standard.net.in/india/news/maharashtra
standard.net.in/india/news/maharashtra-distilleries-question-effluent-order/418963/
order/418963/
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
The purpose of the project activity is to install anaerobic wastewater treatment system which consists of
an anaerobic digester with biogas capturing unit. This anaerobic digester will disintegrate most organic
matter in the waste water, thus reducing the amount of COD and BOD. This biogas will be purified with
biogas purification unit to remove H2S by using bioskrubber technology. The purified biogas will be used
to generate steam thus replacing the equivalent amount of coal in the boiler. This biogas pl
plant will be set
up next to the existing downstream discharge lagoon which is about 1.5 km from the distillery unit and
the thermal energy generation unit.
Contribution to sustainable
ustainable development:
Ministry of Environment and Forests, Govt. of India2 has stipulated the social well being, economic well
being, environmental well being and technological well being as the four indicators for sustainable
development
opment in the interim approval guidelines host country approval eligibility criteria for Clean
Development Mechanism (CDM) projects.
All the above are the contribution of the project activity for the sustainable development.
2
http://envfor.nic.in/divisions/ccd/cdm_iac.html
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
Name of Party involved Private and/or public entity(ies) Kindly indicate if the
(*) Project participants (*) party involved wishes to
((host) indicates a host (as applicable) be considered as project
Party) participant (yes/no)
India (Host) Private entity: No
M/s. Green Elephant India Private Limited.
India (Host) Private entity: No
M/s. Kisan Veer Satara Sahakari Sakhar
Kharkana Limited
(*) In accordance with the CDM modalities and procedures, at the time of making the CDMCDM-PDD public
at the stage of validation, a Party involved may or may not have provided its approval. At the time of
requesting registration, the approval by the Party(ies) involved is required.
Country: India
State: Maharashtra
Village : Bhuinj
Taluk : Wai
District : Satara
Green Elephant Biogas project is located at Bhuinj village in the Satara District of Maharashtra. The
project site is 154 km from Mumbai which is the capital of Maharashtra.
Maharashtra The nearest rail head is
Koregaon railway station which is 10 km from the site. The nearest airport is in Pune which is 130 km
from the project site.
The geographical location3 of the project site is between Longitude East 73.9894
8940 and Latitude North
0
17.8595 .
3
http://www.mapsofindia.com/maps/india/india
http://www.mapsofindia.com/maps/india/india-political-map.htm
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
Maharashtra State
Satara District
Project Activity
Project Technology:
The project activity involves anaerobic treatment of spent wash in a closed digester system (Continuous
Stirrer Type Reactor (CSTR)) with the facility for the capture of methane enriched biogas. Spent wash is
highly organic and obnoxious in characteristics and is produced during alcohol production from the sugar
molasses.. Figure below shows schematic of a CSTR system.
Anaerobic digestion of distillery effluent is done using CSTR technology. This is also aids in the efficient
collection of resultant biogas. The gas is the purified of harmful sulphur fumes using the bioskrubber
technology from an experienced manufacturer. The following figure depicts the processes involved in the
project activity.
4
http://cdm.unfccc.int/UserManagement/FileStorage/NGP9SCJXDTWBMRQ15E4LHAY2K06Z7U
http://cdm.unfccc.int/UserManagement/FileStorage/NGP9SCJXDTWBMRQ15E4LHAY2K06Z7U
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
The digested effluent will flow into a degassing vessel where the entrapped gases are released. The
degassed effluent flows to a lamella clarifier for the separation of active biomass from outgoing treated
effluent. The effluent leaves the lamella clarifier
clarifier for disposal or for a secondary treatment in the digester.
The surplus of the active biomass will be removed from the bottom of digester regularly to the sludge
bed. The excess biomass can either be disposed or be used as farm manure.
The two digesters have a capacity to treat 600 m³ of spent wash per day and generate through an
anaerobic digestion approximately 25,000
2 ,000 m³ biogas per day. The renewable gas contains around 60%
methane (CH4) with the remainder being mainly CO2 with contaminants of H2S.
After the biogas is generated in the digester it flows into the desulphurization unit (purification unit)
which consists mainly of a washing tower followed by a bioreactor and a sulphur settler. The liquid in the
washing tower has an alkaline nature and absorbs
ab the H2S. Then the H2S-loaded
loaded washing liquid is
recycled in a bioreactor releasing the sulphur in a settler. The recycled washing liquid can be used again
and returns to the process in the washing tower.
The produced biogas accumulates in the digester digester roof, from where it flows to the gasholder. The
gasholder acts as intermediate gas storage as well as a Pressure Control Vessel (PCV). The raw gas will
be pumped with the help of biogas blower to the gas purification plant. The biogas produced from the
project
roject activity is used in the distillery boiler to produce the thermal energy. In absence of the biogas or
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
more fuel required to produce thermal energy, coal is the secondary fuel in the distillery boiler. Surplus
biogas,
gas, if any, can be burnt in a gas flaflare
re unit whenever gas is not being utilised
utilised. Flame arresters are
provided in gas lines to protect the digester from backfire from the flare.
This purified biogas will be monitored by the flow meter which is placed at at the inflow of the distillery
boiler. Power consumption for this project activity is consumed directly from the renewable cogeneration
project. In case of any exigency, PP has planned to run the backup diesel generator to produce power for
their in house consumption. Active biomass or sludge from the digester is removed at regular intervals
and used for land applications with the help of bio composting with press mud. The detailed process flow
diagram is given in the section B.3
S. No Parameters Units
1 Make Super steam Boiler
2 Type Multi fuel Boiler
3 Steam Production Temperature 4250C
4 Pressure 45 Kg/Cm2
5 Quantity of Steam 10 TPH
6 Feed Water Temperature 900C
7 Efficiency of Distillery Boiler 85 %
The technology supplier of the biogas plant is M/s. Ecoboard Industries Limited has vast experience in
supply of CSTR biogas plant for generation of biogas, a non conventional source of energy from distillery
5
Technical Specification from the Technology Supplier
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
A.4.3 Estimated amount of emission reductions over the chosen crediting period
period:
Estimation of annual
Years emission reductions in
tonnes of CO2e
2013 6, 779
2014 6, 779
2015 6, 779
2016 6, 779
2017 6, 779
2018 6, 779
2019 6, 779
2020 6, 779
2021 6, 779
2022 6, 779
Total estimated reductions 67, 790
(tonnes of CO2e)
Total number of crediting years 107
Annual average of the 6, 779
estimated reductions over the
crediting period (tCO
( 2e )
6
From the Technology Supplier
7
PP has chosen 10 year fixed crediting period
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
A.4.5. Confirmation that the small-scale project activity is not a debundled component of a
large scale project activity:
According to paragraph 2 of Appendix C8 of the Simplified Modalities and Procedures for Small-Scale
Small
CDM project Activities, the following results into debundling
debundling of large CDM project:
“A proposed small-scale
scale project activity shall be deemed to be a debundled component of a large project
activity if there is a registered small-scale
small scale CDM project activity or an application to register another
small-scale CDM project activity:
For the proposed project activity, the project participants does not implement any more biogas projects in
the state of Maharashtra; hence they could not have gone for additional registration for any similar project
within the previous 2 years whose project boundary is within 1 km of the project boundary of the
proposed activity. Thus it is confirmed that the small scale project activity is not a debundled component
of a larger project activity.
B.1. Title and reference of the approved baseline and monitoring methodology applied to the
small-scale project activity:
Tools Used : Tool10 to calculate the project or leakage CO2 emissions from fossil fuel
Combustion. Version 02/EB – 41 Annex 11
Tool11 to calculate baseline, Project and/or leakage emissions from
electricity consumption. EB 39, Annex 7
Tool12 to determine project emissions from flaring gases containing
methane. EB 28, Annex 13
8
http://cdm.unfccc.int/EB/Meetings/007/eb7ra07.pdf
9
http://cdm.unfccc.int/methodologies/DB/6EL4AG49US2S1DNH55Y4S7GDQFA2JF
odologies/DB/6EL4AG49US2S1DNH55Y4S7GDQFA2JF
10
http://cdm.unfccc.int/methodologies/PAmethodologies/tools/am
http://cdm.unfccc.int/methodologies/PAmethodologies/tools/am-tool-03-v2.pdf/history_view
v2.pdf/history_view
11
http://cdm.unfccc.int/EB/039/eb39_repan07.pdf
12
http://cdm.unfccc.int/EB/028/eb28_repan13.pdf
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
The project activity will treat the waste water produce from the sugar industry and the biogas is generated
from the treated waste water. The produced biogas will be used in the distillery boiler to replace the fossil
fuel like coal to generate thermal energy. The generated thermal energy is used in the in in-house
consumption. The project activity is in line with methodology AMS. I.C, version 19; the specific features
of project and applicability of methodology AMS.I.C are discussed below:
13
http://cdm.unfccc.int/methodologies/PAmethodologies/tools/am
http://cdm.unfccc.int/methodologies/PAmethodologies/tools/am-tool-07-v2.2.0.pdf
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
The total installed/rated thermal energy The total installed capacity of this project activity
generation
eneration capacity of the project equipment is is 8.01 MW14 thermal which is less than 45 MW
equal to or less than 45 MW thermal (see thermal
paragraph 6 for the applicable limits for
cogeneration project activities).
For co fired systems, the total installed thermal The total installed capacity of this project activity
energy generation capacity of the project which consume both biogas and coal to generate
equipment when using both fossil and renewable steam is 8.01 MW thermal which is less than 45
fuel shall not exceed 45 MW thermal (see MW thermal
paragraph 6 for the applicable limits for
cogeneration project activities).
The following capacity limits apply for biomass The proposed project activity is not a cogeneration
cogeneration units: system. The project activity produces biogas from
(a) If the project activity includes emission the wastewater treatment system to displace coal
reductions from both the thermal and electrical used as the fuel source in the distillery boiler to
energy components, the total installed energy generate thermal energy.
generation capacity (thermal and electrical) of
the project equipment shall nott exceed 45 MW
thermal. For the purpose of calculating this
capacity limit the conversion factor of 1:3 shall
be used for converting electrical energy to
thermal energy (i.e., for renewable project
activities, the maximal limit of 15MW(e) is
equivalent to 45 MW thermal output of the
equipment or the plant).
(b) If the emission reductions of the cogeneration
project activity are solely on account of thermal
energy production (i.e. no emission reductions
accrue from electricity component), the total
installed thermal energy production capacity of
the project equipment of the cogeneration unit
shall not exceed 45 MW thermal.
(c) If the emission reductions of the cogeneration
project activity are solely on account of electrical
energy production (i.e. no emission
emissio reductions
accrue from thermal energy component), the total
installed electrical energy generation capacity of
the project equipment of the cogeneration unit
shall not exceed 15 MW.
The capacity limits specified in the above The project replaces the old distillery boiler. The
14
The total installed capacity of the project activity is 8.01 MW. The Detailed calculation is 10 T/h * 1000 kg
/ t *(3266 kJ/kg - 381.5 kJ/kg) / 3600 kJ / MWh.
Whereas:
The thermal capacity
apacity of the Distillery Boiler is 10 TPH, Specific enthalpy of steam is 3266.0 kJ/kg and the specific
enthalpy of feed water is 381.5 kJ/kg
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
paragraphs apply to both new facilities and project activity satisfies capacity limits as
retrofit projects. In the case of project activities mentioned in the paragraph 4 to 6
that involve the addition of renewable energy
units at an existing renewable energy facility, the
total capacity of the units added by the project
should comply with capacity limits in paragraph
4 to 6 and should be physically distinct from the
existing units
Project activities that seek to retrofit or modify The biogas based thermal energy generation
an existing facility for renewable energy system is under commissioning
commissioning. There is no
generation are included in this category existing facility in the project premises.
New Facilities and project activities involving The project replaces the old distillery boiler. It does
capacity additions compared to the baseline not involve a capacity addition. Hence this criteria
scenario are only eligible if they comply with the is not applicable.
relevant requirements in the “General Guidelines
to SSC CDM Methodologies”
If solid biomass fuel is used, it shall be There is no solid biomass fuel is used in this
demonstrated that it has been produced using proposed project activity.
solely renewable biomass and all project or
leakage emissions associated with its production
shall be taken into account in the emission
reduction calculations
Where the project participant is not the producer There is no solid biomass fuel is used in this
of the processed solid biomass fuel, f the project proposed project activity.
participant and the producer are bound by a
contract that shall enable the project participant
to monitor the source of the renewable biomass
to account for any emissions associated with
solid biomass fuel production. Such a contract
shall also ensure that there is no double counting
of emission reductions
If electricity and/or steam/heat produced by the The biogas from the Green Elephant which is
project activity is delivered to third party supplied to the KVSSSKL SSSKL thermal energy
i.e.,another facility
ity or facilities within the project generation system which is located at the close to
boundary, a contract between the supplier and the distillery unit. The steam produced from the
consumer(s) of the energy will have to be entered biogas based thermal energy system is used for
into that there is no double counting of emission KVSSSKL in-house requirement
requirement. Steam energy
reductions produced from the distillery boiler is not exported
to any other facility.
If the project activity recovers and utilizes biogas The project activity recovers andd utilizes biogas for
for power/heat production and applies this thermal energy generation. The methodology AMS
methodology on a standalone basis i.e. without 1.C was applied without using Type III component
using a Type III component of a SSC of a SSC methodology.
methodology, any incremental emissions
occurring due to the implementation of the Project emissions was included in the analysis from
project activity (e.g. physical leakage of the (1) the on-site
site consumption of fossil fuels, i.e. coal
anaerobic digester, emissions due to inefficiency consumption
tion at the distillery boiler and diesel
of the flaring) shall be taken into account either consumption at the back-upup diesel generator at the
as project or leakage emissions. biogas plant and (2) the consumption of electricity
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
The proposed project activity produces biogas from the wastewater treatment system to displace coal used
as the fuel source in the distillery boiler to generate thermal energy.
energy. The biogas generated from the
biomethanation plant will be used in the thermal energy generation system to di displace the coal
consumption and the capacity of the project activity is well below the qualifying limit of 45 MWthermal.
Hence the choice of the project type and category is justified.
a) All plants generating power and /or heat located at the project site, whether fired with biomass,
fossil fuels or a combination of both;
b) All power plants connected
nnected physically to the electricity system (grid) that the project plant is
connect to
c) Industrial, Commercial or residential facility, or facilities, consuming energy generated by the
steam and the processes or equipment affected by the project activity;
d) The processing plant of biomass residues, for project activities using solid biomass fuel (e.g.,
briquette), unless all associated emissions are accounted for as leakage emissions
e) The transportation itineraries, if the biomass is transported over distances greater than 200
kilometres, unless all associated emissions are accounted for as leakage emissions
f) The site of the anaerobic digester in the case of project activity that recovers and utilizes biogas
for power/heat production and applies this methodology
methodology on a stand alone i.e., without using a
Type III component of a ssc methodology”.
methodology
In line with the methodology, thhe project activity produces biogas from the wastewater treatment system
which displaces coal used as the fuel source in the distillery
distillery boiler to generate thermal energy. It covers
all the facilities affected by the project activity including the sites where processing, transportation and
application or disposal of waste products as well as biogas takes place.
The methodological choices for baseline emissions, project emissions and leakage emissions from the
systems affected by the project activity are discussed below:
According to the paragraph 45 and 46 of this methodology, there is no energy generating equipment is
transferred from another activity to this project activity. Hence there is no leakage from the project
activity.
Table 2: Baseline Emission of the Project Activity
15
This is also in line with the methodology AMS III H which states that if the sludge is controlled combusted,
disposed in a landfill with biogas recovery, or used for soil application in aerobic conditions in the project activity,
the project emission through
rough sludge shall be neglected.
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
In absence of the project, fossil fuels (coal) are combusted for the production of steam in a steam
generator. Alternatives have been established as baseline scenario in the absence of the project.
As per paragraph 16 of the methodology AMS I.C., “For “For renewable energy technologies that displace
technologies using fossil fuels, the simplified baseline is the fuel consumption of the technologies would
have been used in the absence of the project activity times an emission factor for the fossil fuel displaces”
displaces
The project involves the combustion of biogas from industrial spent wash in the distillery boiler and
therefore the project applies a renewable energy technology.
Alternative 1: Steam Generation using biogas & Coal in the distillery boiler without CDM Revenue.
Alternative 2: Steam Generation using fossil fuel in the distillery boiler.
Alternative 3: Steam Generation
neration using own bagasse in the distillery boiler.
Alternative 4: Steam Generation using bagasse from other regional producers.
Alternative 5: Steam Generation from the 22 MW cogeneration unit with bagasse fuel.
Alternative 6: Steam Generation from the 22 MW cogerneration unit with fossil fuel.
Alternative 7: Steam Generation from the existing old boiler
Alternative 1:
Steam generation using biogas & coal in the distillery boiler without CDM revenue. In section B.5 it is
demonstrated that is not an economically attractive alternative.
Alternative 3:
Steam generation using own bagasse in the distillery boiler is not a feasible option. The bagasse produced
from the sugar industry is com
completely
pletely consumed by the 22 MW cogeneration unit. The same can be
verified from the Heat Mass balance diagram of the project activity. Hence the steam produced from
owns bagasse in the distillery boiler is not a plausible alternative.
Alternative 4:
Steam generation using bagasse from other regional producers is not a feasible option. Cogeneration can
enable India to meet the goals for green energy from renewable and sustainable biomass. Cogeneration
availability gap for power. Sugar industry16 has been
can be small but certain step to bridge the availability
16
http://www.mnre.gov.in/prog-biomasspower.htm
biomasspower.htm
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
traditionally practising cogeneration by using bagasse as a fuel. The sugar industry available in the
regions is having the cogeneration unit. These cogeneration units consume all the bagasse produced from
their
ir sugar industry as a fuel. Consuming bagasse from the other regional producers is not a viable
options and the cost of bagasse from other regional producer is very high. Hence consuming bagasse from
other regional producer is not a possible alternative
Alternative 5:
Steam generation from the 22 MW cogeneration unit for distillery unit is not a possible option. Steam
characteristics from the cogeneration unit are different from the distillery requirement17. Hence steam
consumption from the 22 MW cogeneration
cogenera unit is not a plausible alternative.
The decision of fossil fuel that would have been used in the absence of project activity will be based on
the cost of various fuels options, i.e. fuel cost per unit of energy supplied.
The unit cost of various fuels options available for steam generation per unit of energy generation are as
follows:
As it is evident from the above, coal has the lowest unit cost amongst all the fuel options available (It is
substantially low). Besides this, prior to the project activity project proponent has been using coal as fuel
to meet its steam requirement.. Therefore coal has been chosen as the possible fuel alternatives for the
project activity.
Alternative 2:
Steam generation using fossil fuel in the distillery boiler is the feasible option. During the biogas plant
shut down period, the distillery boiboiler
ler will run through fossil fuel only. Hence the steam generation using
fossil fuel in the distillery boiler is also a plausible alternative.
17
The supporting document is submitted to the DOE for validation.
18
As per IPCC default Value
19
http://www.bharatpetroleum.com/sbu/ind_comm/gen_petroprices.asp?from=ind
20
As per IPCC default Value
21
http://www.iocl.com/products/HighSpeedDiesel.aspx
/products/HighSpeedDiesel.aspx
22
As per Supplier Quotation
23
As per Supplier Quotation
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
Alternative 6:
Steam generation from the 22 MW cogeneration unit for distillery unit is not a possible option. Steam
characteristics from the cogeneration unit are different from the distillery requirement24. Hence steam
consumption from the 22 MW cogeneration unit is not a plausible alternative.
Alternative 7:
Steam generation with the existing old boiler is not a feasible option. As the existing boiler reached the
end of life time and the existing boiler is decommissioned already. Hence this is not a possible alternative.
In line with the paragraph 16 of the methodology, this project activity generates biogas from the treated
waste water which is a renewable energy technologies and the generated biogas will be used as a fuel in
the distillery boiler to produce thermal energy for the in-house
in se consumption which directly displaces the
fossil fuel consumption (coal) in the distillery boiler.
Since the project activity is using coal in the baseline for steam generation, therefore the baseline
emission is calculated as per paragraph 22 of the methodology
methodology AMS.I.C Version 19. As per paragraph 22
of the methodology, “For
For Steam/heat produced using fossil fuels the baseline emissions are calculated as
follows”
Where
BE thermal, co2, y = The baseline emissions from steam displaced by the project activity during the year y
EGthermal,y = The net quantity of steam supplied by the project activity
activity during the year y
EFff, co2 = The CO2 emission factor of the fossil fuel that would have been used in the baseline
plant; tCO2/TJ obtained from reliable local or national data if available, otherwise IPCC
default emission factors are used.
η BL, thermal = The efficiency of the plant using the fossil fuel that would have been used in the
absence of the project activity
24
The supporting document is submitted to the DOE for validation.
25
Sub – bituminous Coal
26
http://www.natcomindia.org/brochure5.pdf
27
As per Tool to calculate the project emission from the fossil fuel combustion, the upper limit (95% Confidence
Interval) of the fossil fuel is considered as emission factor for calculating the project emission.
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
B.5. Description of how the anthropogenic emissions of GHG by sources are reduced below
those that would have occurred in the absence of the registered small-scale CDM project activity:
The project is a steam generating project using biogas and coal in the distillery
distillery boiler. Alternative 2
(Steam
Steam Generation using fossil fuel in the distillery boiler)
boiler) has been established as baseline scenario.
The additionality for the Project Activity has been demonstrated as per ““Guidelines on the
demonstration of additionality
ty of small-scale
small project activities, Version 09” and “Non-binding best
practice examples to demonstrate additionality for SSC project activities” (EB35, Annex 34).
As per EB35 report, Annex 34, Project participants shall provide an explanation to show that the project
activity would not have occurred anyway due to at least one of the following barriers:
The Additionality for the proposed project activity is established with an in depth investment analysis in
line with the Guidelines on the Assessment of Investment Analysis Version 05. .
Investment Barriers:
The purpose of the investment analysis is to determine whether the proposed project activity is
economically or financially attractive or not without the revenue from sale of certified emission
reductions (CERs).
The Net Present Value (NPV), which is calculated by a series of cash flows,, both incoming and outgoing,
can be described as the difference amount between the sums of discounted: cash inflows and cash
outflows. It is relevant to calculate and compared to the baseline scenario based on the applied discount
rate. The rate used to discount
iscount future cash flows to the present value is a key variable of this process
thereforee the Weighted Average Cost of C Capital (WACC) was calculated. In order to analyse the financial
attractiveness of the project activity, the prime financial indicator that
that has been used is the NPV. The
NPV is considered as appropriate financial indicator for demonstrating the financial additionality of the
project activity. The project related cash-flows
cash of both Green Elephant India Private Limited and
Kissan Veer SSK aree considered in the financial analysis.
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
Cost of Equity:
As per the “Guidelines on the assessment of investment analysis, EB 62, Annex 5, Guidance 15” 15”, which
states “if the benchmark is based on parameters that are standard in the market, the cost of equity should
be determined either by (a) selecting the values provided in Appendix A (of the guidelines)
guidelines); or by (b)
calculating the cost of equity using best financial practices.
practices. The PP of the present project activity has
chosen the default value of cost of equity. The value published for the host country i.e. India which falls
under the Group I category is 11.75%. It can be converted to 13.75 % pre-taxtax rate of return by applying
the minimum alternative tax rate of 16.995%. Further since the investment analysis is carried out in
nominal terms, the real term value of cost of equity given can be converted to nominal value by adding
the inflation rate.
In accordance with paragraph 7 of the Appendix to the “Guidelines on the Assessment of Investment
Analysis” the inflation target of 5% of the Reserve Bank of India can then
t be added28. The pre-tax rate
with 5% inflation is then 18.75%.
The cost of debt is considered as the average value of RBI Lending Rate in India which was available at
the time of Decision Making. The interest rate was: 11.63 %. The debt to equity ratio was considered as
50 % in line with § 18 of the “Guidelines
“ on the Assessment of Investment Analysis
nalysis, Version 5. The
WACC considered is 15.19 %29
Table 6: Input values for the estimation of NPV of the project activity
Table 7: Input values for the estimation of NPV of the baseline scenario
28
http://www.rbi.org.in/scripts/bs_viewcontent.aspx?Id=2602
29
Calculated based on the formulae: (50 % of Cost of Equity) +(50 % of Cost of Debt)
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
Based on the above assumptions, the NPV for this project activity is -429.09 million INR which is below
than the baseline scenario -406.3
406.35 million INR.. Therefore the project is not financially attractive. These
financial calculations include all the relevant revenues and the cost associated with the project.
Sensitivity Analysis:
The purpose of the sensitivity analysis is to examine whether the conclusion regarding the financial
viability of the project activity is sound and tenable with those reasonable variation in the assumptions.
Sensitivity Analysis
Guidance Reasoning
Guidance 20: Only variables, including the In line with the guidance, the following variables are
initial investment cost, that constitute more subjected to the variation
riation in the sensitivity analysis
than 20% of either total project costs or total carried out –
project revenues should be subjected to
reasonable variation (all parameters varied • Biogas production
need not necessarily be subjected to t both • Project Cost
negative and positive variations of the same • Operation & Maintenance Cost
magnitude), and the results of this variation • Fuel costs (Coal price)
should be presented in the PDD and be
reproducible in the associated spreadsheets.
Guidance 21: As a general point of departure In line with the guidance, a range of +10% to -10%
variations in the sensitivity analysis should at was considered for all the above variables in the
least cover a range of +10%0% and -10%, unless sensitivity analysis.
this is not deemed appropriate in the context of
the specific project circumstances.
In the above background, the PP of the project activity submits that the project is unlikely to achieve the
benchmark even under favorable conditions and hence justifies the need of CDM funds to help in
improving the project competitiveness and financial sustainability
sustainability.
Conclusion:
Registering the project activity
ivity as a CDM project expected after approval and registration, would provide
additional revenue to the project activity by reducing the cost of energy generation. Thus the CDM
benefits would alleviate different kind of barriers associated with the implementat
ation and operation of
this project activity.
The starting date of this project activity is 29th October 2009 from the agreement of supplier and the
project participant sent the intimation letter to the Host Party DNA and the UNFCCC Secretariat in
writing about the commencement of the project activity on 06th March 2009.
09. This shows that the project
participant informed the DNA and the UNFCCC secretariat about the project activity before the starting
date
ate and also made the contract agreement with the CDM Consultant to develop this project under the
CDM process. This shows that the project proponent has the awareness about the CDM process and its
benefits.
Table 9:: Chronologies of events of the project activity:
30
http://cdm.unfccc.int/UserManagement/FileStorage/PU2ARNBM3KFXS9HZ6OELGTICJ81VYD
31
Intimation Letter sent to UNFCCC and DNA about the Commencement of this Project activity
32
Ministry of Environment
ent and Forest
33
Start date of the project activity
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
The project activity consumes the biogas from the biogas purification system to replace fossil fuel in the
thermal energy generation. Formula used to calculate the net emission reduction for the project activity is
as follows
Where,
ERy - Emission Reduction in tCO2/year
BEy - Baseline emission in tCO2/year
PEy - Project emissions in tCO2/year
LEy - Emissions due to leakage in tCO2/year
As discussed in section 3.4, the baseline for the project activity is Steam is produced through coal based
boiler unit, therefore baseline emission is calculated as per Para 18 of the small
small scale methodology AMS
I. C version 19.
Where
BE thermal, co2, y = The baseline emissions from steam displaced by the project activity during the year y
EGthermal,y = The net quantity of steam supplied by the project activity during the year y
EFCoal, co2 = The CO2 emission factor of the fossil fuel that would have been used in the baseline
plant; tCO2/TJ obtained from reliable local or national data if available, otherwise IPCC
default emission factors are used.
η BL, thermal = The efficiency of the plant using the fossil fuel that would have been used in the
absence of the project activity
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
As per the Tool to calculate baseline, Project and/or leakage emissions from electricity consumption, the
project emission is calculated as follow:
34
http://cdm.unfccc.int/methodologies/PAmethodologies/tools/am
http://cdm.unfccc.int/methodologies/PAmethodologies/tools/am-tool-07-v2.2.0.pdf
35
http://cdm.unfccc.int/methodologies/PAmethodologies/tools/am
http://cdm.unfccc.int/methodologies/PAmethodologies/tools/am-tool-07-v2.2.0.pdf
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
Authority (CEA)36, Government of India has divided the Indian Power Sector into two regional grids (see
table below).
Table 10: National Grid in India
The project activity is located in the state of Maharashtra which comes under NEWNE grid in India and
the electricity consumed by this project displaces the electricity from NEWNE grid. The project activity
consumes power from the 22 MW cogeneration systems, which export the surplus power to the NEWNE
grid. Due to the displacement of electricity the project activity would have an impact on the NEWNE
grid. Thus all the power generation facilities connected to this grid form the boundary for the purpose of
baseline estimation. Since the project consumes electricity from the cogeneration unit, which export the
surplus power to the NEWNE grid, emissions generated
generated due to the electricity genera
generated by the NEWNE
grid as per CM calculations will serve as the baseline for this project.
Option I corresponds to the procedure contained in earlier versions of this tool. Option II allows the
inclusion of off-grid
grid power generation in the grid emission factor. Option
Option II aims to reflect that in some
countries off-grid
grid power generation is significant and can partially be displaced by CDM project
activities, e.g. if off-grid
grid power plants are operated due to an unreliable and unstable electricity grid.
Option II requires
ires collecting data on off-grid
off grid power generation as per Annex 2 and can only be used if
the conditions outlined therein are met. Option II may be chosen only for the operating margin emission
The Project
roject Participant chooses the grid connected power plants
plants (Option I) to calculate the operating
margin and build margin Emission Factor.
36
http://www.cea.nic.in/reports/planning/cdm_co2/Database_publishing_ver5.zip
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
Any of the four methods can be used. However, the simple OM method (option a) can be used if low low-
cost/must-run
run resources constitute less than 50% of total grid generation in: 1) average of the five most
recent years, or 2) based on long--term averages for hydroelectricity production.
The above table clearly shows that the percentage of total grid generation by low-cost/must
low cost/must-run plants (on
the basis of average of five most recent years) for the NEWNE grid is only 19.64 % which is much lesser
than 50% of the total generation. Thus, Simple
Simple OM method can be used for calculating the emission
factor.
For the simple OM, the emissions factor can be calculated using either of the two following data vintages:
The project proponent has chosen an ex ante option for the calculation of the OM with a three year
generation weighted average, based on the most recent data available at the time of submission of the
CDM-PDD
PDD to the DOE for validation.
Step 4 Calculate the Operating Margin emission factor according to the selected method.
The simple OM emission factor is calculated as the generation weighted average CO2 emissions per unit
electricity generation (tCO2/MWh) of all generating power plants serving the system not including low
low-
cost /must run power plant/ units. The simple OM may be calculated:
Option A: Based on the net electricity generation and a CO2 emission factor
tor of each power unit.
Option B: Based on the total net electricity generation of all power plants serving the system and the fuel
types and total fuel consumption of the project electricity system
37
http://www.cea.nic.in/reports/planning/cdm_co2/Database_publishing_ver5
http://www.cea.nic.in/reports/planning/cdm_co2/Database_publishing_ver5.zip
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
b) Only nuclear and renewable power generation are considered as low- low-cost/must-run power
sources and the quantity of electricity supplied to the grid by these sources is known; and
c) Off-grid
grid power plants are not included in the calculation
calculation (i.e., if option I has chosen in step
2).
Option A: Calculation based on average efficiency and electricity generation of each plant under this
option, the simple OM emission factor is calculated
calculated based on the net electricity generation of each power
unit and an emission factor for each power plant as follows:
∑, , ∗
,,
= ∑
,
....................................................................................................................(
....................................................................................................................(5)
Where:
EFgrid, OM simple,y = Simple Operating margin CO2 emission factor in year y (tCo2 /MWh)
EGm,y = Net quantity of electricity generated
generated and delivered to the grid by power unit m in
year y (MWh)
EFEL,m,y = CO2 emission factor of power unit m in year y(tCO2/MWh)
m = All power plants/units serving the grid in year y except low cost must run power
/units
y = The relevant year as per the data vintage chosen in step 3
Determination of EFEL,m,y:
The emission factor of each power unit m has been determined by Option A1, equation 2 of the tool as
follows:
∑, ,,∗, ∗ ,,
,, = ∑
,
.............................................................................................................................
.............................................................................................................................(6)
Where:
EFEL,m,y = CO2 emission factor of power unit m in year y(tCO2/MWh)
FCi, m,y = Amount of fossil fuel type i consumed by power plant/unit m in year y (mass or
volume unit)
NCVi,y = Net calorific value (energy content) of fossil fuel type i in year y (GJ / mass or
volume unit)
EFCO2,i,y = CO2 emission factor of fossil fuel type i in year y (tCO2/GJ)
EGm,y = Net electricity generated and delivered to the grid by power plant/ unit m in year
y (MWh)
m = All power plants/units serving the grid in year except low cost must run power
plants/units
i = All fossil fuel types combusted in power plant/unit m in year y
y = Either the three most recent years for which data is available at the time of
submission of the CDM-PDD
CDM to the DOE for validation.
38
http://www.cea.nic.in/reports/planning/cdm_co2/Database_publishing_ver5.zip
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
Option 1
Calculate the Build Margin emission factor EFBM, y ex-ante based on the most recent information
available on plants already built for sample group m at the time of PDD submission. The sample group m
consists of either the five power plants that have been built most recently or the power plant capacity
additions in the electricity system that comprise 20% of the system generation (in MWh) and that have
been built most recently. Project participants should
should use from these two options that sample group that
comprises the larger annual generation.
Option 2
For the first crediting period, the Build Margin emission factor EFBM, y must be updated annually ex-post
ex
for the year in which actual project generation
generation and associated emissions reductions occur. For subsequent
crediting periods, EFBM, y should be calculated ex
ex-ante,
ante, as described in option 1 above. The sample group
m consists of either the five power plants that have been built most recently or the powe
power plant capacity
additions in the electricity system that comprise 20% of the system generation (in MWh) and that have
been built most recently. Project participants should use from these two options that sample group that
comprises the larger annual generation.
gener
∑ , ∗ ,,
,, = ∑ ,
.............................................................................................(
.............................................................................................(7)
Where:
EFgrid,BM,y = Build margin CO2 emission factor in year y (tCO2/MWh).
EGm,y = Net quantity of electricity generated and delivered to the grid by power unit m in
year y (MWh).
(MWh)
EFEL,m,y = CO2 emission factor of power unit m in year y (tCO2/MWh)
m = Power units included in the build margin.
margin
y = Most recent historical year for which power generation data is available.
Where:
EFgrid,BM,y = Build margin CO2 emission factor in year y (tCO2/MWh)
EFgrid,OM,y = Operating margin CO2 emission factor in year y (tCO2/MWh)
wOM40 = Weighting of operating margin emissions factor (%)
wBM = Weighting of build margin emissions factor (%)
Where:
PE fc, Coal,y = Are the CO2 emissions from coal combustion in process j during the year y (tCO2/yr);
FC fc, Coal, y = Is the quantity of coal combusted in process j during the year y (mass or volume
unit/yr);
COEFCoal,y = Is the CO2 emission coefficient of Coal in year y (tCO2/mass or volume unit)
The CO2 emission coefficient COEFCoal,y is calculated based on net calorific value and CO2 emission
factor of the fuel type i, as follows:
Where:
COEFCoal,y = Is the CO2 emission coefficient of Coal in year y (tCO2/mass or volume unit)
40
For all project activities except wind & solar: wOM = 0.50 and wBM = 0.50 is used as a default values
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
NCVCoal,y = Is the weighted average net calorific value of the Coal in year y (GJ/mass or volume
unit)
EFCO2,coal = Is the weighted average CO2 emission factor of Coal i in year y (tCO2/GJ)
CO2 emissions from fossil fuel combustion in process j are calculated based on the quantity of fuels
combusted and the CO2 emission coefficient of those fuels, as follows:
Where:
PEdiesel,y = Are the CO2 emissions from diesel combustion in process j during the year y (tCO2/yr);
FCdiesel,y = Is the quantity of fuel type diesel combusted in process during the year y (mass or
volume unit/yr);
COEFdiesel = Is the CO2 emission coefficient of diesel in year y (tCO2/mass or volume unit)
The CO2 emission coefficient COEF diesel can be calculated using Option B:
Option B: The CO2 emission coefficient COEFdiesel is calculated based on net calorific value and CO2
emission factor of the fuel type i, as follows:
Where:
COEFdiesel = CO2 emission coefficient of diesel in year y (tCO2/mass or volume unit)
NCVdiesel = weighted average net calorific value of the diesel (GJ/mass or volume unit)
The PP has selected the option B as COEF (CO2 emission coefficient of fuel) testing facility for
“Weighted
Weighted average mass fraction of carbon in fuel type i in year y”
y under option A is not available to PP.
Hence, the project emissions for the proposed project activity can be calculated as follows:
Where,
FCdiesel, y = quantity of diesel used during the year
NCVdiesel = weighted average net calorific
calorifi value of diesel
EFco2,diesel = weighted average CO2 emission factor of diesel
These emissions are accounted for in the project activity in the event that the biogas is flared. In normal
operation, it is not expected that the flare will be used. The flare is only for emergency purposes.
Methane emissions due to flaring in year y are ar calculated as per the “Tool41 to determine project
emissions from flaring gases containing methane” (tCO2e). PP has installed open flaring system. For the
determination of the flare efficiency, the default value of 50% will be used for the calculation oof project
emissions from flaring gases.
Steps 1 to 7 of the “Tool to determine project emissions from flaring gases containing methane”
(hereafter the flaring tool) are used to determine the project emissions from flaring of the residual gas
stream.
According to the step 1 of the flaring tool, to calculate mass flow rate of residual gas that is calculated as
per the following equation;
Where,
Parameter Details
FMRG,h Mass flow rate of the residual gas in hour h (kg/h)
ρRG,n,h Density of the residual gas at normal conditions in hour h (kg/m3)
FVRG,h Volumetric flow rate of the residual gas in dry basis at normal conditions in the hour h
(m3/h)
Pn
ρRG,n,h = ………............................................................
…............................................................ .............................................…(
.............................................…(15)
Ru
* Tn
MMRG , h
Where,
Parameter Details
ρRG,n,h Density of residual gas at normal conditions in hour h (kg/m3)
Pn Atmospheric pressure at normal conditions (pa)
Ru Universal ideal gas constant (Pa.m3/kmol.k)
MMRG,h Molecular mass of the residual gas in hour h (kg/kmol)
Tn Temperature at normal conditions (K)
MMRG , h = ∑ ( fv
i
i, h * MMi) ……
……................................................................................................…
…................................................................................................… ((16)
Where,
Parameter Details
MMRG , h Molecular Mass of the residual gas in hour h (kg/kmol)
fvi,h Volumetric fraction of component i in the residual gas in the hour h
41
http://cdm.unfccc.int/EB/028/eb28_repan13.pdf
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
According to step 2 of the flaring tool, determination of the mass fraction of carbon, hydrogen, oxygen
and nitrogen in the residual gas are as follows:
Where,
Parameter Details
fm j , h Mass fraction of element j in the residual gas in hour h
fvi , h Volumetric fraction of component i in the residual gas in the hour h
AMj Atomic mass of element j(kg/kmol)
NAj , i Number of atoms of element j in component i
MMRG , h Molecular Mass of the residual gas in hour h (kg/kmol)
j The elements carbon, hydrogen, oxygen and nitrogen
i The components CH4, CO, CO2, O2, H2, N2
As a simplified approach42, project participants may only measure the volumetric fraction of methane and
consider the difference to 100% as being nitrogen (N2). In line with the above statement from the flaring
tool, PP has considered the difference between the volumetric fraction of methane and the difference to
100% as Nitrogen (N2).
Step 3 & 4 of the flaring tool are not applicable for this project activity, since the flare efficiency is not
continuously monitored and it is open flare system.
As per the Step 5 of the flaring tool, methane mass flow rate in the residual gas on a dry basis is
calculated as per following equation
Where,
Parameter Details
TMRG,h Mass flow rate of methane in the residual gas in the hour h (kg/h)
FVRG,h Volumetric flow rate of the residual gas in dry basis at normal conditions in hour h
(m3/h)
fvCH4, RG,h Volumetric fraction of methane in the residual gas on dry basis in hour h
ρCH4,n Density of methane at normal condition (0.716 kg/m3)
As per Step 6 of the flaring tool for determination of the hourly flare efficiency, the following default
flare efficiency will considered for open flares depending upon the hours of operation of the flare.
42
From the Tool to determine project emission from flaring gases containing methane, Page No 05 of step 1
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
As per step 7 of the flaring tool, annual project emissions from flaring are calculated as the sum of
emissions from each hour h, based on the methane flow rate in the residual gas
as (TMRG,h) and the flare
efficiency during each hour h (ŋflare, h), as follows:
8760
PEflare,y = ∑ TM
h =1
RG,h * (1-ŋflare,hh) * GWPCH4/ 1000 …………………………………………...…….…(
…………………………………………...…….…(20)
Where,
Parameter Details
PEflare,y Project emissions from flaring of the residual gas stream in year y (tCO2e)
TMRG,h Mass flow rate of methane in the residual gas in the hour h (kg/h)
ŋflare, h Flare efficiency in hour h
GWPCH4 Global Warming Potential of methane valid for the commitment period (tCO2e/tCH4)
Leakage Emission:
According to the paragraph 45 and 46 of this methodology, there is no energy generating equipment is
transferred from another activity to this project activity. Hence there is no leakage from the project
activity.
LEy = 0 tCO2/year
Major risk and uncertainties that can influence the emission reduction estimates:
Emission reduction generated by the project activity depends on the quantum
quantum of energy supplied by the
renewable fuel, biogas. Any unpredictable variation in the biogas generation will result in a reduction in
the emission reduction. Biogas generation in anaerobic digester is temperature dependent. Climatic
condition of the proposed
posed project location varies over year. Hence any unpredictable change in the
climatic condition may be one of the risks that can influence the emission reduction.
43
http://www.natcomindia.org/brochure5.pdf
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
measurement methods
and procedures actually
applied :
Any comment: The above value is fixed ex- ante and it is same for the entire crediting period.
Data / Parameter: Τn
Data unit: °K
Description: Temperature at normal conditions
Source of data used: Tool to determine project emissions from flaring gases containing methane
Value applied: 273.15
Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
Any comment: The above value is fixed ex- ante and it is same for the entire crediting period.
Data / Parameter: Pn
Data unit: Pa
Description: Atmospheric Pressure at normal conditions
Source of data used: Tool to determine project emissions from flaring gases containing methane
Value applied: 101, 325
Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
Any comment: The above value is fixed ex- ante and it is same for the entire crediting period.
Description: Weighted average CO2 emission factor of the diesel consumed in the project
activity in year y.
Source of data used: IPCC default values
values at the upper limit of the uncertainty at a 95% confidence
interval as provided in table 1.4 of Chapter1
Chapter1 of Vol. 2 (Energy) of the 2006
IPCC Guidelines on National GHG Inventories.
Inventories
Value applied: 74.8
Justification of the IPCC values have been used for diesel because no country specific data is
choice of data or available. In case of any revision in the IPCC guidelines, the revised value shall
description of be taken into account.
measurement methods
and procedures actually
applied :
Any comment: The Monitored Data to be kept for a minimum of two years after the end of the
crediting period.
44
Tool to calculate baseline, project and /or leakage emissions from electricity consumption
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
B.6.3 Ex-ante
ante calculation of emission reductions:
Formula used to calculate the emission reduction for the project activity is
ERy = BEy – PEy – LEy …………………………………………
……………………………………………………(23)
The daily energy production (EG thermal, d, y)) is calculated on a daily basis from the flow (Q steam, d, y), the
pressure (p steam, d, y)) and the temperature (T steam, d, y)) of the steam as well as the pressure45 (p FW, d, y) and
temperature (TFW, d, y)
Where:
QSteam, d,y = 10 TPH
PSteam, d, y = 44.13 bar
TSteam, d, y = 4250 C
TFW, d, y = 900 C
PFW = 58.84 bar
EnthalpySteam, d, y = 3266.0 kJ/kg
Enthalpy FW, d, y = 381.5 kJ/kg
45
The software for calculating the enthalpy of steam & feed water is
http://www.peacesoftware.de/einigewerte/calc_dampf.php5
46
The enthalpy of Steam flow and feed water is calculated from the Temperature, pressure of the steam flow, feed
water using the steam table.
47
Detailed Calculation for the emission reduction is given in the separate sheet
48
Default Efficiency as per the methodology AMS.I.C.
49
http://www.natcomindia.org/brochure5.pdf
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
As per paragraph 35 of the methodology, the project emissions are calculated as follows:
FCcoal,y = 5,417tonnes/y
Project
roject emission from consumption of electricity is calculated as follows:
PEEC,y = 1,567
Project emission from consumption of diesel in the project activity is calculated as follows:
The project emissions due to the combustion of diesel are considered as zero for estimating ex ex-ante
emission reductions. The quantity of diesel consumed for operating the DG set during emergency
situations is expected to be negligible. However the quantity of diesel combusted in the project activity
will be monitored during each year of crediting period and project emissions wi will be deducted from
baseline emissions. Provisions have been provided in Section B.6.1 for calculating project emissions.
Since the quantity of diesel that will be consumed is unpredictable before actual operation of the project,
and also to simplify the ex-ante
ante calculations of emission reductions, excluding project emissions is
considered reasonable.
PEDiesel, y = 0 tCO2 e
50
Default Value from the Tool to calculate baseline, project and/or leakage emissions from electricity consumptions
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
biogas will be deducted from baseline emissions. Provisions have been provided in Section B.6.
B.6.1 for
calculating project emissions.
PE flaring y = 0 tCO2e
= 9,560 +1,567+0+0
= 11, 127 tCO2e
51
The detailed calculation is given in the detailed spread sheet.
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
52
http://www.synergyearthglobal.com/advantages_of_biogas.html
al.com/advantages_of_biogas.html
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
Source of data to be Continuous on site measurement would be carried out using steam flow meter
used: cum totalizer with accuracy ± 0.25%. Data will be recorded in plant log book on
daily basis. For emission reduction calculation data will be sourced from plant
log book.
Value of data 64, 80053
Description of Measurement Method: As per Industrial Standard
measurement methods Measuring Equipment: Steam flow meter cum totalizer
tot
and procedures to be Monitoring Frequency: Data will be monitored and measured continuously
applied: Recording Frequency: Daily
Accuracy: 0.25%
Calibration Frequency: Once in a year by NABL accredited laboratory
Data will be stored in paper and /or in electronic form
QA/QC procedures to Steam flow meter will be calibrated/ tested annually independently by a third
be applied: party.
Any comment: The parameter is measured to calculate EG thermal, y and the Monitored Data to be
kept for a minimum of two years after the end of the crediting period.
53
Calculated based on the capacity of 10 tonnes of steam per hour and the expected operation time of 6, 480 hours
per year
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
Any comment: The parameter is measured to calculate EG thermal, y and the Monitored Data to be
kept for a minimum of two years after the end of the crediting period.
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
54
National Accreditation Board for testing and calibration laboratories
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
55
Orsat Apparatus
56
http://cdm.unfccc.int/EB/028/eb28_repan13.pdf
57
http://www.peacesoftware.de/einigewerte/calc_dampf.php5
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
The project participant proposed the following structure for data monitoring, collection, data archiving
and calibration of equipments for this project activity. The team comprises of the following members.
• Director
• Plant Manager
• Shift Engineer
• Technicians
Data source:
As per section B.7.1
Frequency of Monitoring:
As per the section B.7.1
Archiving of data:
Data collected as a part of monitoring plan will be archived and kept for at least 2 years after the crediting
period or from last issuance.
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
The Plant manager from Green Elephant will provide training to KVSSSKL staff about the CDM and the
required monitoring parameter said in the section B.7.1 for calculating
calculating the emission reduction. And also
Plant manager of Green Elephant will provide special training to the KVSSSKL technicians for
measuring, monitoring and storage of the monitoring parameter. Plant Manager of Green Elephant will
provide training to the director
ector of KVSSSKL about the necessary of calibration of all parameters.
Emergency Preparedness:
It is expected that all the instruments shall be functioning continuously for recording data. The project
activity does not result in any unidentified activity that can result in substantial emissions from the project
activity. The biogas plant of Green Elephant is a closed system. Once biogas is generated the gas is
processed and piped to the burners of the KVSSSKL. The integrated system assures that during the course
of normal operation no gas is emitted to the atmosphere. The constant maintenance of the plant keeps the
plant in this position. In case of interrupted operation of the plant excess gas will be directed to the
emergency burners. Both the digeste
digesters
rs and the purification unit are connected to this system. The
operation of the emergency flare start automatically and no unintended gas emission occurs.
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
In the unexpected case of overpressure gas in the digester breaks through a water seal and is being
emitted to the atmosphere. This scenario is only applicable if the flaring system does not work and the gas
storing system is entirely occupied. After the overpressure is reduced the water seals prevents further gas
outflow. In case of force major or unintended third party damage the gas leakage are traceable by the flow
meter, pressure sensors or visible inspection. There is no plausible scenario in the project activity which
can lead to emergency situation leading to unaccounted GHG emissions during the crediting period. No
need for emergency preparedness in data monitoring is visualized.
Emission reduction calculations and monitoring report will be done annually based on the data collected.
This will be done by the CDM team. The monitoring report and the emission reduction calculation will be
maintained by the head for verification. All equipment will be calibrated and maintained in accord
accordance to
the manufacturer’s recommendations to ensure accuracy of measurements. Records of calibration and
maintenance will be retained as part of the CDM Monitoring system.
B.8 Date of completion of the application of the baseline and monitoring methodol
methodology and the
name of the responsible person(s)/entity(ies)
58
M/s. Green Elephant India Private limited is also a Project Participant listed in Annex 1
59
From the date of Agreement with Biogas Plant Supplier
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
15 Years, 00 Months60
Project Participant has chosen fixed crediting period in this project activity
NA
NA
31/12/2012 or from the date of complete submission of the project activity to EB for registration
whichever is later
C.2.2.2. Length:
10 Years, 00 months
An environmental impact assessment is not required by law for these types of project activities61. As per
the prevailing regulation of the Host Party i.e. India represented by Ministry of Envi
Environment and Forests
(MoEF), Govt. of India and also the line ministry for environmental issues in India EIA need not to be
carried out for projects which falls under the list whose investment is less than Rs. 1000 million62,63. As
per MoEF (Government of India) ia) notification the project activity does not fall under the purview of the
60
From the Technology Supplier
61 http://envfor.nic.in/legis/eia/so1533.pdf
s/eia/so1533.pdf (page 10, Schedule)
62 http://envfor.nic.in/legis/eia/so-60(e).html
60(e).html (schedule 1)
63 http://www.envfor.nic.in/legis/eia/eia130602.html
/eia/eia130602.html (sub point [iii])
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
Environmental impact Assessment thus the project activity is exempted from the environmental
clearances64.
As explained above, the government of India does not require a formal analysis
analysis of environmental impacts
for projects of the size and scale of the proposed project activity. The proposed project involves the
installation of a digester and a boiler to the existing distillery plant and thus does not involve major
construction on the site. The project captures and utilises the biogas generated by the decomposition of
organic matter and therefore aims to reduce the overall emission of green house gases into the
atmosphere. The project does not cause any major air or water pollution in the surrounding environment.
Effluents from the digester will be used in composting therefore creating a scenario of zero discharge.
The final sludge from the digester will be used in land application as a fertilizer and therefore does not
impact the environment.
The proposed project activity will not undertake any other activity, which will adversely affect the
ecological balance in area.
The project will have local environmental benefits associated with elimination of odour due to handling
of waste water
ater in a closed container rather than open lagoons and also a reduction in the emission of
green house gases.
D.2. If environmental impacts are considered significant by the project participants or the host
Party,, please provide conclusions and all references to support documentation of an environmental
impact assessment undertaken in accordance with the procedures as required by the host Party:
E.1. Brief description how comments by local stakeholders have been invited and compiled:
The project promoter explained briefly about the agenda of the meetings and introduced the global
warming and the climate change. He also explained the role of Kyoto protocol and clean development
mechanism in mitigating the impacts of climate change. After the brief introduction of climate ch
change,
Kyoto Protocol and CDM, project participant explained
plained the purpose of the stakeholder consultation
meeting as to seek the concern, opinion and suggestion of the stakeholders.
64 http://envfor.nic.in/divisions/iass/notif/eia.htm (schedule 1 )
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
The local village people asked some queries about the project activity and the CDM pr process. The project
participant explained clearly about the CDM process and their queries. The local village people also
agreed that due to this project activity the employment opportunities have increased. The local population
welcomes the project due to various benefits, such as development of infrastructure in the area, increase
of income due to the employment and improvement in their standards of living. There were no negative
comments received from the local stakeholders. The local stake holder consultation
ation is not required by law
for this kind of project activities and the same was done for the purpose of CDM registration. No negative
comments were received on the project activity, which is evident from the licenses/approvals/ clearances
accorded to the project activity by the stakeholders.
E.3. Report on how due account was taken of any comments received:
There were no negative comments received from the local people near to the project activity. Hence no
report is applicable.
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
(CDM - Version 03
Annex 1
Annex 2
Annex 3
BASELINE INFORMATION
Annex 4
MONITORING INFORMATION