Kailash Nath Vs DDA Original Judgement
Kailash Nath Vs DDA Original Judgement
Versus
JUDGMENT
R.F. Nariman, J.
1. Leave granted.
made the highest bid for Plot No.2-A, Bhikaji Cama Place, District
Centre, New Delhi for 3.12 Crores (Rupees Three Crores Twelve
Lakhs). As per the terms and conditions of the auction, the appellant,
Page 1
Seventy Eight Lakhs), being 25% of the bid amount, with the DDA,
this being earnest money under the terms of the conditions of auction.
Page 2
purchaser without any interest unless the earnest money
is forfeited under para 2 (iv) above.”
DDA extended time for payment upto 28.10.1982 with varying rates
Page 3
5. The second High Powered Committee recommended that the
the balance amount. Despite the fact that on 14.5.1984 the DDA
written by the appellant to DDA from 1984 to 1987 but no answer was
basis of which the fate of this appeal largely depends, the DDA stated
as follows:
“WITHOUT PREJUDICE’
DELHI DEVELOPMENT AUTHORITY
VIKAS SADAN
I.N.A.
New Delhi-23……198… .
No.F.32(2)/82/Impl.-I/4
To,
Page 4
18, Bara Khamba Road,
New Delhi-110001.
Sir,
Dated 1.12.87
Yours faithfully,
Sd/
DIRECTOR (C.L)”
7. The appellant replied to the said letter on the same day itself in
Page 5
Tel.: 3312648, 3314269
1006, KANCHENJUNGA,
18, BARAKHAMBA ROAD,
NEW DELHI-II0001
Dear Sir,
Thanking you,
Yours faithfully
For KAILASH NATH & ASSOCIATES,
Sd/
6
Page 6
Partner
Advance copy sent through Special Messenger.”
1.3.1990 that the land auctioned to the appellant was not Nazul land
Industries Private Limited and M/s Skipper Tower Private Limited had
been allowed to pay the balance 75% premium and were in fact
allotted other plots. Pleading Article 14, the appellant stated that they
held that as the auction was held as per terms and conditions of the
Page 7
liberty to take whatever steps are permitted to the appellant under law
“REGD.A.D.
No.F.32(2)/82/CL/3816
To,
Sir,
Yours faithfully,
8
Page 8
Sd/
(JAGDISH CHANDER)
DEPUTY DIRECTOR (CL)”
Lakhs). Shortly after the suit was filed, on 23.2.1994, the DDA re-
Page 9
sent back the file of the plaintiff only on account of the
fact that the land in question was not Nazul land. The net
effect of this is that there was no permission required
from the UOI and the decision taken by defendant no.1 to
extend the time period for making the payment, thus,
stood as it is.
Page 10
UOI for its approval assuming the case to be one of
Nazul land. Plaintiff sent repeated reminders vide letters
dated 9-12-1985 (Ex.P-11), 20-10-1986 (Ex.P-12), 10-
12-1986(Ex.P-13), 10-02-1987 (Ex.P-14), 11-04-
1987(Ex.P-16), 10-08-1987(Ex.P-17) and 10-10-1987
(Ex.P-18) calling upon defendant no.1 to give an offer of
deposit of balance 25% of the premium so as to bring the
total payment equivalent to 50% of the total premium
and for release of the possession of the land to the
plaintiff for purpose of construction. Defendant no.1
vide its letter received on 1.12.1987 by the plaintiff
(Ex.P-19) sought the consent of the plaintiff to abide by
the recommendations of the high-powered committee and
the consent was duly given on the even date (Ex.P-20).
Thereafter no offer was made to the plaintiff and without
any notice of compliance for payment, the letter of
cancellation dated 6.10.1993 (Ex.P-26) was issued. It
appears that defendant no.1 itself was not aware of the
land being non-Nazul land as the first communication
was addressed to the plaintiff only on 1.3.1990.
11
Page 11
12. DDA appealed against the Single Judge’s judgment to a
Division Bench of the Delhi High Court. The Division Bench set
aside the judgment of the Single Judge holding that the forfeiture of
of the appellant, urged that time may have been of the essence under
the original terms and conditions of the auction. However, time had
promptly replied and said it would be willing to pay the entire 75%
the part of the appellant. Further, since the DDA sold the plot for
11.78 Crores (Rupees Eleven Crores Seventy Eight Lakhs), there was
law.
behalf of the DDA, rebutted these contentions and added that the case
12
Page 12
Anr. v. Tata Aircraft Ltd., 1970 (3) SCR 127. He argued further
that since the letter of 1.12.1987 had been issued under a mistake of
fact, it would be void under Section 20 of the Contract Act and the
completely in order as the appellant was in breach. The fact that the
DDA ultimately sold the plot for a much larger sum, according to
the very outset to notice that earnest money can be forfeited under
sub-clause (iv) set out hereinabove, only in the case of default, breach,
the bid, was not insisted upon by the DDA. On the contrary, after
look into the grievances of the appellant, the DDA extended time at
13
Page 13
least twice. It is, therefore, very difficult to say that there was a breach
months which the DDA could have insisted upon had specifically
16. The other noticeable feature of this case on facts is that DDA
This was on the footing that the Nazul Rules of 1981 would be
marked “without prejudice” and the DDA made it clear that the letter
Government may not relax the provision of the Nazul Rules, in which
case nothing further could be done by the DDA. If, however, the
interest.
14
Page 14
17. Mr. Sharan argued that since the Central Government ultimately
found that this was not a Nazul land, the letter was obviously based on
Act. We are afraid we are not able to accept this plea. Long after the
involved in the present case is not Nazul land, the DDA by its letter of
therefore, was that what was important was payment of the balance
75% which was insisted upon by the letter dated 1.12.1987 and which
Further, Mr. Sharan’s argument that since the letter was “without
prejudice” and since no commitment had been made, they were not
bound by the terms of the letter also fails to impress us. The letter
the DDA because the Central Government may well not relax the
Nazul Rules. On the other hand, if the Central Government had, later
on, relaxed the Nazul Rules, DDA could not be heard to say that
despite this having been done, DDA would yet cancel the allotment of
the plot. That this could not have been done is clear because of the
15
Page 15
aforesaid construction of the letter dated 1.12.1987 and also because
arbitrarily.
Division Bench.
20. In our judgment, Webb’s case would directly apply to the facts
Page 16
no longer of the essence of the contract. But, on the
other hand, it must be borne in mind that a purchaser is
not bound to wait an indefinite time; and if he finds,
while the negotiations are going on, that a long time will
elapse before the contract can be completed, he may in a
reasonable manner give notice to the vendor, and fix a
period at which the business is to be terminated.”
21. Based on the facts of this case, the Single Judge was correct in
the plot within a certain stated time. In the absence of such notice,
22. Tilley v. Thomas, (1867 3 Ch.A 61) would not apply for the
reason that the expression “without prejudice” was only used as stated
above because the Central Government may not relax the Nazul
Rules.
Justice Stone and the other by Chagla,J. as he then was. Stone C.J.
held:-
17
Page 17
“In my judgment, reading the correspondence as a
whole, it at no stage passed from the melting pot of
negotiations to crystallize as an agreement to extend the
time for the performance of the contract. The attitude of
the purchaser throughout the correspondence was:
“Satisfy us that you are doing your best to obtain the
goods from your suppliers and we will then consider
fixing a new date for delivery of the goods to us”. On the
other hand the attitude of the vendors throughout the
correspondence was to avoid the purchaser's demand
and to simply say: “You know that we cannot effect
delivery from our suppliers and until we do so we cannot
deliver the goods to you”. There was never in my
judgment any consensus ad-idem, no agreement, express
or implied, to extend the time either to any particular
date or to the happening of some future event. Mere
forbearance in my opinion to institute proceedings or to
give notice of rescission cannot be an extension of the
time for the performance of a contract within the
meaning of s. 63 of the Contract Act.” (at 226 & 227)
Chagla, J. in a separate judgment held:-
18
Page 18
Therefore it is only as a result of the operation of s. 63 of
the Indian Contract Act that the time for the performance
of the contract can be extended and that time can only be
extended by an agreement arrived at between the
promisor and the promisee.” (at 229)
fixed for his own benefit. Thus, in Keshavlal Lallubhai Patel and
Ors. v. Lalbhai Trikumlal Mills Ltd 1959 SCR 213, this Court
held:-
25. However, such is not the position here. In the present case, the
situation, DDA can certainly unilaterally extend the time for payment
under Section 63 of the Contract Act as the time for payment is not for
19
Page 19
DDA’s own benefit but for the benefit of the appellant. The present
20
Page 20
or, in some cases, even by evidence of conduct including
forbearance on the part of the other party. [See in this
connection the observations of this Court in Keshavlal
Lallubhai Patel v. Lalbhai Trikumlal Mills Ltd., 1959
SCR 213 : AIR 1958 SC 512, para 8. See also in this
connection Saraswathamma v. H. Sharad Shrikhande,
AIR 2005 Kant 292 and K. Venkoji Rao v. M. Abdul
Khuddur Kureshi, AIR 1991 Kant 119, following the
judgment in Keshavlal Lallubhai Patel (supra).] Thus, in
this case there was a variation in the date of
performance by express representation by the defendants,
agreed to by the act of forbearance on the part of the
plaintiffs. What was originally covered by the first part of
Article 54, now fell within the purview of the second part
of the article. Pazhaniappa Chettiyar v. South Indian
Planting and Industrial Co. Ltd. [AIR 1953 Trav Co 161]
was a similar instance where the contract when initially
made had a date fixed for the performance of the
contract but the Court was of the view that “in the events
that happened in this case, the agreement in question
though started with fixation of a period for the
completion of the transaction became one without such
period on account of the peculiar facts and
circumstances already explained and the contract,
therefore, became one in which no time was fixed for its
performance” and held that what was originally covered
by the first part of Article 113 of the Limitation Act, 1908
would fall under the second part of the said article
because of the supervening circumstances of the
case.”(at Page 777)
paragraph 37 stated:-
21
Page 21
contractual obligation, they would be bound by the
contract and the only reasonableness would be of the
kind envisaged by the Supreme Court in the decision
reported as AIR 1963 SC 1144 T.P. Daver v. Lodge
Victoria No.363 SC Belgaum & Ors. On the subject of a
member of a club being expelled, and the relationship
being a contract as per the rules and regulations of the
club, adherence whereto was agreed to by he who
became a member of the club and the management of the
club, the Supreme Court observed that in such private
affairs, it would be good faith in taking an action which
is rooted in the minds of modern men and women i.e. in a
modern democratic society and no more. The decision
guides that where a private affair i.e. a contract is so
perverted by a party that it offends the concept of a fair-
play in a modern society, alone then can the action be
questioned as not in good faith and suffice would it be to
state that anything done not in good faith would be
unreasonably done.”
28. It will be noticed at once that T.P. Daver v. Lodge Victoria No.
at all. It deals with clubs and the fact that rules or bye-laws which
Corpn. of India Ltd., (2004) 3 SCC 553 at paras 22 and 23, the
Page 22
298 : 2001 SCC (L&S) 227] against whom the writ
petition was filed was not a State or an instrumentality of
a State as contemplated under Article 12 of the
Constitution, hence, in the normal course, no writ could
have been issued against the said industry. But it was the
contention of the writ petitioner in that case that the said
industry was obligated under the statute concerned to
perform certain public functions; failure to do so would
give rise to a complaint under Article 226 against a
private body. While considering such argument, this
Court held that when an authority has to perform a
public function or a public duty, if there is a failure a
writ petition under Article 226 of the Constitution is
maintainable. In the instant case, as to the fact that the
respondent is an instrumentality of a State, there is no
dispute but the question is: was the first respondent
discharging a public duty or a public function while
repudiating the claim of the appellants arising out of a
contract? Answer to this question, in our opinion, is
found in the judgment of this Court in the case of Kumari
Shrilekha Vidyarthi v. State of U.P. [(1991) 1 SCC 212 :
1991 SCC (L&S) 742] wherein this Court held: (SCC pp.
236-37, paras 22 & 24)
“The impact of every State action is also on
public interest. … It is really the nature of its
personality as State which is significant and
must characterize all its actions, in whatever
field, and not the nature of function,
contractual or otherwise, which is decisive of
the nature of scrutiny permitted for examining
the validity of its act. The requirement of
Article 14 being the duty to act fairly, justly
and reasonably, there is nothing which
militates against the concept of requiring the
State always to so act, even in contractual
matters.”
23. It is clear from the above observations of this Court,
once the State or an instrumentality of the State is a
party of the contract, it has an obligation in law to act
23
Page 23
fairly, justly and reasonably which is the requirement of
Article 14 of the Constitution of India. Therefore, if by
the impugned repudiation of the claim of the appellants
the first respondent as an instrumentality of the State has
acted in contravention of the abovesaid requirement of
Article 14, then we have no hesitation in holding that a
writ court can issue suitable directions to set right the
arbitrary actions of the first respondent.”
29. Based on the facts of this case, it would be arbitrary for the
held above. And second, DDA not having been put to any loss, even if
contract in this case and the finding of the Division Bench on this
“38. The learned Single Judge has held that the property
was ultimately auctioned in the year 1994 at a price
which fetched DDA a handsome return of Rupees 11.78
crores and there being no damages suffered by DDA, it
could not forfeit the earnest money.
24
Page 24
39. The said view runs in the teeth of the decision of the
Supreme Court reported as AIR 1970 SC 1986 Shree
Hanuman Cotton Mills & Anr. V. Tata Aircraft Ltd. which
holds that as against an amount tendered by way of
security, amount tendered as earnest money could be
forfeited as per terms of the contract.
read:
Page 25
compensation not exceeding the amount so named or, as
the case may be, the penalty stipulated for.
26
Page 26
34. In Fateh Chand v. Balkishan Das, 1964 SCR (1) 515, this
Court held:
Page 27
according to settled principles. The section undoubtedly
says that the aggrieved party is entitled to receive
compensation from the party who has broken the
contract, whether or not actual damage or loss is proved
to have been caused by the breach. Thereby it merely
dispenses with proof of "actual loss or damages"; it does
not justify the award of compensation when in
consequence of the breach no legal injury at all has
resulted, because compensation for breach of contract
can be awarded to make good loss or damage which
naturally arose in the usual course of things, or which
the parties knew when they made the contract, to be
likely to result from the breach.”(At page 526, 527)
28
Page 28
35. Similarly, in Maula Bux v. Union of India (UOI), 1970 (1)
SCR 928, it was held:
29
Page 29
contract. But the expression "whether or not actual
damage or loss is proved to have been caused thereby" is
intended to cover different classes of contracts which
come before the Courts. In case of breach of some
contracts it may be impossible for the Court to assess
compensation arising from breach, while in other cases
compensation can be calculated in accordance with
established rules. Where the Court is unable to assess the
compensation, the sum named by the parties if it be
regarded as a genuine pre-estimate may be taken into
consideration as the measure of reasonable
compensation, but not if the sum named is in the nature
of a penalty. Where loss in terms of money can be
determined, the party claiming compensation must prove
the loss suffered by him.
30
Page 30
(2) It represents a guarantee that the contract will be
fulfilled or, in other words, 'earnest' is given to bind the
contract.
31
Page 31
such contentions covered by the second point, noted
above. It is therefore unnecessary for us to go into the
question as to whether the amount deposited by the
appellants, in this case, by way of earnest and forfeited
as such, can be considered to be reasonable or not. We
express no opinion on the question as to whether the
element of unreasonableness can ever be considered
regarding the forfeiture of an amount deposited by way
of earnest and if so what are the necessary factors to be
taken into account in considering the reasonableness or
otherwise of the amount deposited by way of earnest. If
the appellants were contesting the claim on any such
grounds, they should have laid the foundation for the
same by raising appropriate pleas and also led proper
evidence regarding the same, so that the respondents
would have had an opportunity of meeting such a
claim.”(At page 142)
37. And finally in ONGC Ltd. v. Saw Pipes Ltd., (2003) 5 SCC
Page 32
is named in the contract as the amount to be paid in case
of such breach, the party complaining of breach is
entitled, whether or not actual loss is proved to have
been caused, thereby to receive from the party who has
broken the contract reasonable compensation not
exceeding the amount so named. Section 74 emphasizes
that in case of breach of contract, the party complaining
of the breach is entitled to receive reasonable
compensation whether or not actual loss is proved to
have been caused by such breach. Therefore, the
emphasis is on reasonable compensation. If the
compensation named in the contract is by way of penalty,
consideration would be different and the party is only
entitled to reasonable compensation for the loss suffered.
But if the compensation named in the contract for such
breach is genuine pre-estimate of loss which the parties
knew when they made the contract to be likely to result
from the breach of it, there is no question of proving such
loss or such party is not required to lead evidence to
prove actual loss suffered by him.
67……..In our view, in such a contract, it would be
difficult to prove exact loss or damage which the parties
suffer because of the breach thereof. In such a situation,
if the parties have pre-estimated such loss after clear
understanding, it would be totally unjustified to arrive at
the conclusion that the party who has committed breach
of the contract is not liable to pay compensation. It
would be against the specific provisions of Sections 73
and 74 of the Indian Contract Act. There was nothing on
record that compensation contemplated by the parties
was in any way unreasonable. It has been specifically
mentioned that it was an agreed genuine pre-estimate of
damages duly agreed by the parties. It was also
mentioned that the liquidated damages are not by way of
penalty. It was also provided in the contract that such
damages are to be recovered by the purchaser from the
bills for payment of the cost of material submitted by the
contractor. No evidence is led by the claimant to
establish that the stipulated condition was by way of
33
Page 33
penalty or the compensation contemplated was, in any
way, unreasonable. There was no reason for the Tribunal
not to rely upon the clear and unambiguous terms of
agreement stipulating pre-estimate damages because of
delay in supply of goods. Further, while extending the
time for delivery of the goods, the respondent was
informed that it would be required to pay stipulated
damages.
34
Page 34
38. It will be seen that when it comes to forfeiture of earnest
heavily relied by the Division Bench again was a case where the
the respondents also pleaded that the appellants had to pay them a sum
of Rs.42,499/- for loss and damage sustained by them. (See: 1970 (3)
SCR 127 at Page 132). This being the fact situation, only two
questions were argued before the Supreme Court: (1) that the amount
paid by the plaintiff is not earnest money and (2) that forfeiture of
reasonable. (at page 133). Both questions were answered against the
held:-
35
Page 35
contention that the amount of deposit is so unreasonable
and therefore forfeiture of the entire amount is not
justified. The decision in Maula Bux's [1970]1SCR928
had no occasion to consider the question of
reasonableness or otherwise of the earnest deposit being
forfeited. Because, from the said judgment it is clear that
this Court did not agree with the view of the High Court
that the deposits made, and which were under
consideration, were paid as earnest money. It is under
those circumstances that this Court proceeded to
consider the applicability of Section 74 of the Contract
Act. (At page 143)”
40. From the above, it is clear that this Court held that Maula
Bux’s case was not, on facts, a case that related to earnest money.
money under a contract if reasonable does not fall within Section 74,
penalty is not on a matter that directly arose for decision in that case.
36
Page 36
forgotten that as has been stated above, forfeiture of earnest money on
the earnest money is paid. In the present case, under the terms and
money has to be paid) may well have been rejected. In such cases,
42. In the present case, forfeiture of earnest money took place long
forfeited without any loss being shown. In fact it has been shown that
far from suffering any loss, DDA has received a much higher amount
37
Page 37
43. On a conspectus of the above authorities, the law on
be as follows:-
compensation.
38
Page 38
3. Since Section 74 awards reasonable compensation for
Section.
defendant in a suit.
future.
39
Page 39
44. The Division Bench has gone wrong in principle. As has been
that the fact that the DDA made a profit from re-auction is irrelevant,
as that would fly in the face of the most basic principle on the award
46. Mr. Sharan submitted that in case we were against him, the
7% per annum and not 9% per annum interest as was done in other
cases. We are afraid we are not able to agree as others were offered
the refund of earnest money way back in 1989 with 7% per annum
interest which they accepted. The DDA having chosen to fight the
40
Page 40
present appellant tooth and nail even on refund of earnest money,
47. In the result, the appeal is allowed. The judgment and order of
the Single Judge is restored. Parties will bear their own costs.
…..…………………J.
(Ranjan Gogoi)
…..…………………J.
(R.F. Nariman)
New Delhi;
January 09, 2015.
41
Page 41