Pondosi Sumuran 1

This document summarizes the design of a pile foundation system. It includes dimensions for the piles, pile cap, and columns. Load values from structural analysis software are listed. The analysis involves checking the foundation for adequate vertical capacity, total and eccentric loads, shear strength, and moment strength. Reinforcement sizes and spacing are designed to satisfy the strength requirements.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
188 views3 pages

Pondosi Sumuran 1

This document summarizes the design of a pile foundation system. It includes dimensions for the piles, pile cap, and columns. Load values from structural analysis software are listed. The analysis involves checking the foundation for adequate vertical capacity, total and eccentric loads, shear strength, and moment strength. Reinforcement sizes and spacing are designed to satisfy the strength requirements.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

PONDASI SUMURAN

1 Dimensi
M.T
Dimensi
Kolom
H1 Kp = 40 cm
Kl = 40 cm
Sumuran

T
D = 70 cm
Luas = 3848 cm2
Keliling = 219,9 cm'

H2
Dimensi pile cab
L B = 100 cm h.1 = 150 cm
L = 100 cm h.2 = 500 cm
f2
kb
C

x = 0 cm t= 30 cm
B

ka

a = 45 cm e= 35 cm
D
C

c = 50 cm
f2

f1 D f1 f1 = 10 cm
Data Tanah (hasil soundir ) f2 = 10 cm
Keterangan
qc = 250 kg/cm2
fs = 0 kg/cm2
Data bahan
fc' = 18 Mpa
fy = 300 Mpa
 beton = 0,0024 kg/cm3
 tanah = 0,0015 kg/cm3

2 Load (dari Out Put reakasi joint base analisis struktur dengan ETABS V.09)
Pu =            31.000,0 kg FZ MX MY
Mx = - kg.cm ##### 0 0
My = - kg.cm

3 Analisi Pondasi sumuran


a. analisis terhadap beban vertikal
Qijin = (Luas.qc+keliling*fs*H2)/SF-Berat Pondasi SF : faktor keamanan =3-6
= 319.318,81 kg
n = Pu/Qult
= 0,10 bh ≈ 1 bh
b. Analisis terhadap beban total dan momen
Pu = 31.000 kg
Beban tanah atas Poer = 2250 kg
Beban pile cap = 720 kg
Beban lantai = 225 kg
V = 34.195 kg
eksentrisitas

P=

= 34.195 kg < Q ijin aman


c. Penulangan pondasi sumuran
Ast = 1%*Luas Tiang
= 3848,45 mm2
Jumlah tulangan
As = 201,0619298 = Diamter tulang 16 mm
n = 19
Pu = 457.523 Kg > P Aman

Sengkang
Asspiral = 50,26548246 mm2 tulangan dia 8 mm
Jarak sengkang maksimal 48*D.Sengkang
S= 384 mm
Dipasang sekang dia 8-300 mm

4 Analisa Poer
a. Check terhadap geser
Ukuran Poer
B = 100 cm
L = 100 cm
t = 30 cm
d' = 7 cm
d (t-d') = 23 cm
Beban Poer = 3,42 kg/cm2
bo =2* (ka+d)+2*(kb+d) = 252 cm
Vu = 20.623 kg
Vc = 2.459.035 N
= 245.903 kg
= 147.542 > Vu, aman
Geser 1 arah x
bo = 7
Vu = 2.394 Kg
Vc = 1/6*√fc'*bo*d
4.950 kg > Vu, aman
Geser arah Y
bo = 7
Vu = 2.394 kg
Vc = 1/6*√fc'*bo*d
= 4.950 kg > Vu aman
b Check terhadap Momen

z = 30
Mu = 153.878 kg.cm
= 15.387.750 N.mm
Mu+My = 15.387.750 N.mm
 min = 0,0047
Asmin = 1073,3 mm2
As pakai = 12 Ø 6
= 339,3 mm2
a = 0,024586377
Mr = 18.727.918 N.mm
187.279,18 kg.cm
Dipasang Ø = 12-15
Tulangan susut = 0,002.b.d
= 140
As pakai = 5 Ø 10
= 392,7 mm2
Jarak Tulangan susut 20 cm

You might also like