DPR - Feb

This daily progress report summarizes work done on an external chilled water piping project on February 10th. Key activities included welding and fitting of 18-inch pipes in Zone 3, excavation in Zone 3, and backfilling in Zone 5. Progress is provided on laying and installing pipes of various diameters. Planned activities for the following day include further excavation, welding, fitting, and preparation of piping and structures. The report also provides manpower and equipment details for the main contractor and two subcontractors working on the project.

Uploaded by

Ajas Aju
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
131 views108 pages

DPR - Feb

This daily progress report summarizes work done on an external chilled water piping project on February 10th. Key activities included welding and fitting of 18-inch pipes in Zone 3, excavation in Zone 3, and backfilling in Zone 5. Progress is provided on laying and installing pipes of various diameters. Planned activities for the following day include further excavation, welding, fitting, and preparation of piping and structures. The report also provides manpower and equipment details for the main contractor and two subcontractors working on the project.

Uploaded by

Ajas Aju
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 108

PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI

PROJECT NO: AD- 16 - 4061 E


DAILY PROGRESS REPORT
Date: 10-Feb-16 Weather: Sunny Temperature: 22ºC

A. Manpower report as on 9-Feb-16 Total Manpower:


B. Equipment report as on 9-Feb-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 9-Feb-16

1 Fit up for 18" pipe and welding done for Zone 3.


2 Excavation for Zone 3 under progress.
3 Back filling for Zone 5 upto ETS B under progress.
4 ETS - 3/1 Valve chamber Second wall concrete costing completed.
5 ETS - 1 Roof slab costing ocmpleted.
6 ETS-3 Parapet wall concrete completed.
7 Leveling the main lin eabove PVC Sleeve near the plant area done.
8
Activity - 20 & 18 INCH Previous in Total in
Current in mtr/no
PIPE mtr/no mtr/no
1 Excavation (Zone -1 and 2) 20 1903 1923
2 Bedding 20 1120 1140
3 Fit up 4 153 157
4 Doubling 2 151 153
5 Pipe Laying Fit up 3 80 81
6 Pipe Laying Welding 3 70 73
7 UPVC Sleeve Laying 100 600 800
8 Backfilling 100 600 700
Previous in Total
Activity - 12 inch Current inmtr/no mtr/no inmtr/no

1 Bedding 100 300 400


2 Fit up 2 70 72
3 Doubling 2 62 64
4 Pipe Laying 300 280 580
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Previous in Total in
Activity - 10 inch Current in mtr/no mtr/no mtr/no

1 Bedding 400 370 770


2 Fit up 2 67 69
3 Welding 2 37 39
4 Pipe Laying 20 620 640
5 First Layer Back Filling 100 200 300

Contractor Sign & Stamp Client Sign & Stamp


D. Today Planned Activities 10-Feb-16
1 Deshuttering for the ETS-1 & ETS 3 Works under prgress.
2 Zone - 4 pipe line welding under progress.
3 ETS - A pipe route fabrication and welding under progress.
4 Excavation Zone - 3 Under progress
5 Welding and Fit up under progress for 18"
6 Preparation of the ETS - 2 Piping inside our work shop.
7 Preparation of the steel bending works for parapet and columns for ETS 2.
8 Back filling is under progress for ETS - B line.
9 Inside militry school Pipe laying and welding under progress.

Previous in Total
Activity - 14 inch Current inmtr/no mtr/no inmtr/no

1 Bedding 80 40 120
2 Fit up 2 49 51
3 Welding 2 46 48
4 Pipe Laying 50 100 150
5 First Layer Back Filling 50 150 200

Other Activity:
1 Inspection for the Electrical sleeves in ETS 1 Slab done
2 Sample laying of upvc barrier to Tabreed Engineer.
3
4
5
6
7
8
9
10
11
12
Working Time: 7 am to 6:00pm

118
57

Remarks

On Progress
On Progress Total
On Progress Excavation
On Progress Completed in
Mtr
On Progress 1923
On Progress
On Progress
On Progress
Client Sign & Stamp
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 10-Feb-16

Manpower Details Equipment Details


Sl No. Designation Qty Sl No. Equipments Qty
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1

10 Safety Officer 1 31 Portable Oven 5


11 Welder 6 32 1
12 Fitter 1 33 25 ton Crane 1
13 Sheet Fabricator 1 34 Water Tanker 1
14 Helper 6
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1
2 Site Engineer 1 10 Wheel Excavator 1
3 Safety Officer 1 11 Roller Compactor 1

4 Site Foreman 1 12 SHOVEL 1


5 Fitter 0 13 25 ton Crane 0
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 6 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50
Contractor Sign & Stamp Client Sign & Stamp
SubContractor - Richmond - J&J
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 10 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 38 Total 7
Total Manpower Total Equipments 7

HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers
2 Safety barriers, safety cones and signage boards installed near to the road area
3 Pipes at ETS A near fance barricaded with warning Taypes
4 Provided signages board near road area
5 Provided mesh along with the crush barriers and safety cones beside the road
6 pipes are covered with tarpolin
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh
8 Excavation at ETS-2 are barricaded with orange Mesh
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted
10 Barricades provided near road area (Near Plant Area)
MAHAWI

Working Time: 7 am to 6:00pm

Other Details
Sl No. Others Qty

Direct Manpower
20 Rigger 3

21 Pipe Fabricator 5
22 Multi Skill Helper 5
23 Electrican 1
24 Crane Operator 1
25 Tanker Driver 1

Total 16
LLC
Other Details
Sl No. Others Qty

15 Shovel Operator
16 Crane Operator
17 Draughts man 1

18 BUS DRIVER 0
19 Site Surveyor 1
Total 2

Client Sign & Stamp


Other Details
Sl No. Others Qty

Total 0

Done
Done
Done
Done
Done
Done
Done
Done
Done
Done
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 9-Feb-16 Weather: Sunny Temperature: 22ºC

A. Manpower report as on 8-Feb-16 Total Manpower:


B. Equipment report as on 8-Feb-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 8-Feb-16

1 Zone - 4 pipe line proceed the fence crossing reach upto the valve chamber
2 Zone - 3 piping is under progress
3 Dewatering under progress
4 ETS - 1 valve chamber Second Concrete works completed.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completed , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH Previous in Total in
Current in mtr/no
PIPE mtr/no mtr/no
1 Excavation (Zone -1 and 2) 20 1903 1923
2 Bedding 20 1120 1140
3 Fit up 4 153 157
4 Doubling 2 151 153
5 Pipe Laying Fit up 3 80 81
6 Pipe Laying Welding 3 70 73
7 UPVC Sleeve Laying 100 600 800
8 Backfilling 100 600 700
Previous in Total
Activity - 12 inch Current inmtr/no mtr/no inmtr/no

1 Bedding 100 300 400


2 Fit up 2 70 72
3 Doubling 2 62 64
4 Pipe Laying 300 280 580
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Previous in Total in
Activity - 10 inch Current in mtr/no mtr/no mtr/no

1 Bedding 400 370 770


2 Fit up 2 67 69
3 Welding 2 37 39
4 Pipe Laying 20 620 640
5 First Layer Back Filling 100 200 300

Contractor Sign & Stamp Client Sign & Stamp


D. Today Planned Activities 9-Feb-16
1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Previous in Total
Activity - 14 inch Current inmtr/no mtr/no inmtr/no

1 Bedding 80 40 120
2 Fit up 2 49 51
3 Welding 2 46 48
4 Pipe Laying 50 100 150
5 First Layer Back Filling 50 150 200

Other Activity:
1 Electrical Sleeves Installation at ETS-3 Completed
2 Electrical Sleeves Installation at ETS-B Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed
Working Time: 7 am to 6:00pm

118
57

Remarks

On Progress
On Progress Total
On Progress Excavation
On Progress Completed in
Mtr
On Progress 1923
On Progress
On Progress
On Progress
Client Sign & Stamp
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 9-Feb-16

Manpower Details Equipment Details


Sl No. Designation Qty Sl No. Equipments Qty
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1

10 Safety Officer 1 31 Portable Oven 5


11 Welder 6 32 1
12 Fitter 1 33 25 ton Crane 1
13 Sheet Fabricator 1 34 Water Tanker 1
14 Helper 6
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1
2 Site Engineer 1 10 Wheel Excavator 1
3 Safety Officer 1 11 Roller Compactor 1

4 Site Foreman 1 12 SHOVEL 1


5 Fitter 0 13 25 ton Crane 0
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 6 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50
Contractor Sign & Stamp Client Sign & Stamp
SubContractor - Richmond - J&J
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 10 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 38 Total 7
Total Manpower Total Equipments 7

HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers
2 Safety barriers, safety cones and signage boards installed near to the road area
3 Pipes at ETS A near fance barricaded with warning Taypes
4 Provided signages board near road area
5 Provided mesh along with the crush barriers and safety cones beside the road
6 pipes are covered with tarpolin
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh
8 Excavation at ETS-2 are barricaded with orange Mesh
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted
10 Barricades provided near road area (Near Plant Area)
MAHAWI

Working Time: 7 am to 6:00pm

Other Details
Sl No. Others Qty

Direct Manpower
20 Rigger 3

21 Pipe Fabricator 5
22 Multi Skill Helper 5
23 Electrican 1
24 Crane Operator 1
25 Tanker Driver 1

Total 16
LLC
Other Details
Sl No. Others Qty

15 Shovel Operator
16 Crane Operator
17 Draughts man 1

18 BUS DRIVER 0
19 Site Surveyor 1
Total 2

Client Sign & Stamp


Other Details
Sl No. Others Qty

Total 0

Done
Done
Done
Done
Done
Done
Done
Done
Done
Done
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 8-Feb-16 Weather: Sunny Temperature: 22ºC

A. Manpower report as on 7-Feb-16 Total Manpower:


B. Equipment report as on 7-Feb-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 7-Feb-16

1 Zone - 4 pipe line proceed the fence crossing Approval got from CMW
2 Zone - 3 piping is under progress
3 Dewatering under progress
4 ETS - 1 valve chamber Second Shutter works completed.
5 ETS - B Route pipe line back filling second 2nd layer and mest under progress
6 Zone -4 Excavation is going on Near fence area
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completed , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH Previous in Total in
Current in mtr/no
PIPE mtr/no mtr/no
1 Excavation (Zone -1 and 2) 20 1903 1923
2 Bedding 20 1120 1140
3 Fit up 4 153 157
4 Doubling 2 151 153
5 Pipe Laying Fit up 3 80 81
6 Pipe Laying Welding 3 70 73
7 UPVC Sleeve Laying 100 600 800
8 Backfilling 100 600 700
Previous in Total
Activity - 12 inch Current inmtr/no mtr/no inmtr/no

1 Bedding 100 300 400


2 Fit up 2 70 72
3 Doubling 2 62 64
4 Pipe Laying 300 280 580
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Previous in Total in
Activity - 10 inch Current in mtr/no mtr/no mtr/no

1 Bedding 400 370 770


2 Fit up 2 67 69
3 Welding 2 37 39
4 Pipe Laying 20 620 640
5 First Layer Back Filling 100 200 300

Contractor Sign & Stamp Client Sign & Stamp


D. Today Planned Activities 8-Feb-16
1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Previous in Total
Activity - 14 inch Current inmtr/no mtr/no inmtr/no

1 Bedding 80 40 120
2 Fit up 2 49 51
3 Welding 2 46 48
4 Pipe Laying 50 100 150
5 First Layer Back Filling 50 150 200

Other Activity:
1 Electrical Sleeves Installation at ETS-3 Completed
2 Electrical Sleeves Installation at ETS-B Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed
Working Time: 7 am to 6:00pm

118
57

Remarks

On Progress
On Progress Total
On Progress Excavation
On Progress Completed in
Mtr
On Progress 1923
On Progress
On Progress
On Progress
Client Sign & Stamp
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 8-Feb-16

Manpower Details Equipment Details


Sl No. Designation Qty Sl No. Equipments Qty
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1

10 Safety Officer 1 31 Portable Oven 5


11 Welder 6 32 1
12 Fitter 1 33 25 ton Crane 1
13 Sheet Fabricator 1 34 Water Tanker 1
14 Helper 6
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1
2 Site Engineer 1 10 Wheel Excavator 1
3 Safety Officer 1 11 Roller Compactor 1

4 Site Foreman 1 12 SHOVEL 1


5 Fitter 0 13 25 ton Crane 0
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 6 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50
Contractor Sign & Stamp Client Sign & Stamp
SubContractor - Richmond - J&J
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 10 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 38 Total 7
Total Manpower Total Equipments 7

HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers
2 Safety barriers, safety cones and signage boards installed near to the road area
3 Pipes at ETS A near fance barricaded with warning Taypes
4 Provided signages board near road area
5 Provided mesh along with the crush barriers and safety cones beside the road
6 pipes are covered with tarpolin
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh
8 Excavation at ETS-2 are barricaded with orange Mesh
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted
10 Barricades provided near road area (Near Plant Area)
MAHAWI

Working Time: 7 am to 6:00pm

Other Details
Sl No. Others Qty

Direct Manpower
20 Rigger 3

21 Pipe Fabricator 5
22 Multi Skill Helper 5
23 Electrican 1
24 Crane Operator 1
25 Tanker Driver 1

Total 16
LLC
Other Details
Sl No. Others Qty

15 Shovel Operator
16 Crane Operator
17 Draughts man 1

18 BUS DRIVER 0
19 Site Surveyor 1
Total 2

Client Sign & Stamp


Other Details
Sl No. Others Qty

Total 0

Done
Done
Done
Done
Done
Done
Done
Done
Done
Done
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Feb-16 Weather: Sunny Temperature: 22ºC

A. Manpower report as on 6-Feb-16 Total Manpower:


B. Equipment report as on 6-Feb-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 6-Feb-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -3 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completed , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH Previous in Total in
Current in mtr/no
PIPE mtr/no mtr/no
1 Excavation (Zone -1 and 2) 20 1883 1903
2 Bedding 20 1100 1120
3 Fit up 4 153 157
4 Doubling 2 151 153
5 Pipe Laying Fit up 3 80 81
6 Pipe Laying Welding 3 70 73
7 UPVC Sleeve Laying 100 600 800
8 Backfilling 100 600 700
Previous in Total
Activity - 12 inch Current inmtr/no mtr/no inmtr/no

1 Bedding 100 300 400


2 Fit up 2 70 72
3 Doubling 2 62 64
4 Pipe Laying 300 280 580
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Previous in Total in
Activity - 10 inch Current in mtr/no mtr/no mtr/no

1 Bedding 400 370 770


2 Fit up 2 67 69
3 Welding 2 37 39
4 Pipe Laying 20 620 640
5 First Layer Back Filling 100 200 300

Contractor Sign & Stamp Client Sign & Stamp


D. Today Planned Activities 7-Feb-16
1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Previous in Total
Activity - 14 inch Current inmtr/no mtr/no inmtr/no

1 Bedding 80 40 120
2 Fit up 2 49 51
3 Welding 2 46 48
4 Pipe Laying 50 100 150
5 First Layer Back Filling 50 150 200

Other Activity:
1 Electrical Sleeves Installation at ETS-3 Completed
2 Electrical Sleeves Installation at ETS-B Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed
Working Time: 7 am to 6:00pm

118
57

Remarks

On Progress
On Progress Total
On Progress Excavation
On Progress Completed in
Mtr
On Progress 1903
On Progress
On Progress
On Progress
Client Sign & Stamp
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Feb-16

Manpower Details Equipment Details


Sl No. Designation Qty Sl No. Equipments Qty
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1

10 Safety Officer 1 31 Portable Oven 5


11 Welder 6 32 1
12 Fitter 1 33 25 ton Crane 1
13 Sheet Fabricator 1 34 Water Tanker 1
14 Helper 6
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1
2 Site Engineer 1 10 Wheel Excavator 1
3 Safety Officer 1 11 Roller Compactor 1

4 Site Foreman 1 12 SHOVEL 1


5 Fitter 0 13 25 ton Crane 0
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 6 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50
Contractor Sign & Stamp Client Sign & Stamp
SubContractor - Richmond - J&J
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 10 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 38 Total 7
Total Manpower Total Equipments 7

HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers
2 Safety barriers, safety cones and signage boards installed near to the road area
3 Pipes at ETS A near fance barricaded with warning Taypes
4 Provided signages board near road area
5 Provided mesh along with the crush barriers and safety cones beside the road
6 pipes are covered with tarpolin
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh
8 Excavation at ETS-2 are barricaded with orange Mesh
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted
10 Barricades provided near road area (Near Plant Area)
MAHAWI

Working Time: 7 am to 6:00pm

Other Details
Sl No. Others Qty

Direct Manpower
20 Rigger 3

21 Pipe Fabricator 5
22 Multi Skill Helper 5
23 Electrican 1
24 Crane Operator 1
25 Tanker Driver 1

Total 16
LLC
Other Details
Sl No. Others Qty

15 Shovel Operator
16 Crane Operator
17 Draughts man 1

18 BUS DRIVER 0
19 Site Surveyor 1
Total 2

Client Sign & Stamp


Other Details
Sl No. Others Qty

Total 0

Done
Done
Done
Done
Done
Done
Done
Done
Done
Done
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 6-Feb-16 Weather: Sunny Temperature: 22ºC

A. Manpower report as on 5-Feb-16 Total Manpower:


B. Equipment report as on 5-Feb-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 5-Feb-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -3 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completed , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH Previous in Total in
Current in mtr/no
PIPE mtr/no mtr/no
1 Excavation (Zone -1 and 2) 20 1883 1903
2 Bedding 20 1100 1120
3 Fit up 4 153 157
4 Doubling 2 151 153
5 Pipe Laying Fit up 3 80 81
6 Pipe Laying Welding 3 70 73
7 UPVC Sleeve Laying 100 600 800
8 Backfilling 100 600 700
Previous in Total
Activity - 12 inch Current inmtr/no mtr/no inmtr/no

1 Bedding 100 300 400


2 Fit up 2 70 72
3 Doubling 2 62 64
4 Pipe Laying 300 280 580
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Previous in Total in
Activity - 10 inch Current in mtr/no mtr/no mtr/no

1 Bedding 400 370 770


2 Fit up 2 67 69
3 Welding 2 37 39
4 Pipe Laying 20 620 640
5 First Layer Back Filling 100 200 300

Contractor Sign & Stamp Client Sign & Stamp


D. Today Planned Activities 6-Feb-16
1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Previous in Total
Activity - 14 inch Current inmtr/no mtr/no inmtr/no

1 Bedding 80 40 120
2 Fit up 2 49 51
3 Welding 2 46 48
4 Pipe Laying 50 100 150
5 First Layer Back Filling 50 150 200

Other Activity:
1 Electrical Sleeves Installation at ETS-3 Completed
2 Electrical Sleeves Installation at ETS-B Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed
Working Time: 7 am to 6:00pm

118
57

Remarks

On Progress
On Progress Total
On Progress Excavation
On Progress Completed in
Mtr
On Progress 1903
On Progress
On Progress
On Progress
Client Sign & Stamp
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 6-Feb-16

Manpower Details Equipment Details


Sl No. Designation Qty Sl No. Equipments Qty
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1

10 Safety Officer 1 31 Portable Oven 5


11 Welder 6 32 1
12 Fitter 1 33 25 ton Crane 1
13 Sheet Fabricator 1 34 Water Tanker 1
14 Helper 6
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1
2 Site Engineer 1 10 Wheel Excavator 1
3 Safety Officer 1 11 Roller Compactor 1

4 Site Foreman 1 12 SHOVEL 1


5 Fitter 0 13 25 ton Crane 0
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 6 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50
Contractor Sign & Stamp Client Sign & Stamp
SubContractor - Richmond - J&J
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 10 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 38 Total 7
Total Manpower Total Equipments 7

HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers
2 Safety barriers, safety cones and signage boards installed near to the road area
3 Pipes at ETS A near fance barricaded with warning Taypes
4 Provided signages board near road area
5 Provided mesh along with the crush barriers and safety cones beside the road
6 pipes are covered with tarpolin
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh
8 Excavation at ETS-2 are barricaded with orange Mesh
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted
10 Barricades provided near road area (Near Plant Area)
MAHAWI

Working Time: 7 am to 6:00pm

Other Details
Sl No. Others Qty

Direct Manpower
20 Rigger 3

21 Pipe Fabricator 5
22 Multi Skill Helper 5
23 Electrican 1
24 Crane Operator 1
25 Tanker Driver 1

Total 16
LLC
Other Details
Sl No. Others Qty

15 Shovel Operator
16 Crane Operator
17 Draughts man 1

18 BUS DRIVER 0
19 Site Surveyor 1
Total 2

Client Sign & Stamp


Other Details
Sl No. Others Qty

Total 0

Done
Done
Done
Done
Done
Done
Done
Done
Done
Done
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 4-Feb-16 Weather: Sunny Temperature: 30ºC

A. Manpower report as on 3-Feb-16 Total Manpower:


B. Equipment report as on 3-Feb-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 3-Feb-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -3 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completed , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH Previous in Total in
Current in mtr/no
PIPE mtr/no mtr/no
1 Excavation (Zone -1 and 2) 20 1863 1883
2 Bedding 20 1100 1120
3 Fit up 4 149 153
4 Doubling 2 151 153
5 Pipe Laying Fit up 3 78 81
6 Pipe Laying Welding 2 67 69
7 UPVC Sleeve Laying 100 600 800
8 Backfilling 100 600 700
Previous in Total
Activity - 12 inch Current inmtr/no mtr/no inmtr/no

1 Bedding 100 300 400


2 Fit up 2 70 72
3 Doubling 2 62 64
4 Pipe Laying 300 280 580
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Previous in Total in
Activity - 10 inch Current in mtr/no mtr/no mtr/no

1 Bedding 400 370 770


2 Fit up 2 67 69
3 Welding 2 35 37
4 Pipe Laying 20 620 640
5 First Layer Back Filling 100 200 300

Contractor Sign & Stamp Client Sign & Stamp


D. Today Planned Activities 4-Feb-16
1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Previous in Total
Activity - 14 inch Current inmtr/no mtr/no inmtr/no

1 Bedding 80 40 120
2 Fit up 2 47 49
3 Welding 2 44 46
4 Pipe Laying 50 100 150
5 First Layer Back Filling 50 150 200

Other Activity:
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed
Working Time: 7 am to 6:00pm

118
57

Remarks

On Progress
On Progress Total
On Progress Excavation
On Progress Completed in
Mtr
On Progress 1883
On Progress
On Progress
On Progress
Client Sign & Stamp
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 4-Feb-16

Manpower Details Equipment Details


Sl No. Designation Qty Sl No. Equipments Qty
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1

10 Safety Officer 1 31 Portable Oven 5


11 Welder 6 32 1
12 Fitter 1 33 25 ton Crane 1
13 Sheet Fabricator 1 34 Water Tanker 1
14 Helper 6
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1
2 Site Engineer 1 10 Wheel Excavator 1
3 Safety Officer 1 11 Roller Compactor 1

4 Site Foreman 1 12 SHOVEL 1


5 Fitter 0 13 25 ton Crane 0
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 6 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50
Contractor Sign & Stamp Client Sign & Stamp
SubContractor - Richmond - J&J
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 10 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 38 Total 7
Total Manpower Total Equipments 7

HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers
2 Safety barriers, safety cones and signage boards installed near to the road area
3 Pipes at ETS A near fance barricaded with warning Taypes
4 Provided signages board near road area
5 Provided mesh along with the crush barriers and safety cones beside the road
6 pipes are covered with tarpolin
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh
8 Excavation at ETS-2 are barricaded with orange Mesh
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted
10 Barricades provided near road area (Near Plant Area)
MAHAWI

Working Time: 7 am to 6:00pm

Other Details
Sl No. Others Qty

Direct Manpower
20 Rigger 3

21 Pipe Fabricator 5
22 Multi Skill Helper 5
23 Electrican 1
24 Crane Operator 1
25 Tanker Driver 1

Total 16
LLC
Other Details
Sl No. Others Qty

15 Shovel Operator
16 Crane Operator
17 Draughts man 1

18 BUS DRIVER 0
19 Site Surveyor 1
Total 2

Client Sign & Stamp


Other Details
Sl No. Others Qty

Total 0

Done
Done
Done
Done
Done
Done
Done
Done
Done
Done
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 3-Feb-16 Weather: Sunny Temperature: 30ºC

A. Manpower report as on 2-Feb-16 Total Manpower:


B. Equipment report as on 2-Feb-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 2-Feb-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -3 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completed , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH Previous in mtr/no Total in
Current in mtr/no
PIPE mtr/no
1 Excavation (Zone -1 and 2) 20 1863 1883
2 Bedding 20 1100 1120
3 Fit up 4 149 153
4 Doubling 2 151 153
5 Pipe Laying Fit up 3 78 81
6 Pipe Laying Welding 2 67 69
7 UPVC Sleeve Laying 100 600 800
8 Backfilling 100 600 700
Total
Activity - 12 inch Current inmtr/no Previous in mtr/no inmtr/no

1 Bedding 100 300 400


2 Fit up 2 70 72
3 Doubling 2 62 64
4 Pipe Laying 300 280 580
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Previous in Total in
Activity - 10 inch Current in mtr/no mtr/no mtr/no

1 Bedding 400 370 770


2 Fit up 2 67 69
3 Welding 2 35 37
4 Pipe Laying 20 620 640
5 First Layer Back Filling 100 200 300

Contractor Sign & Stamp Client Sign & Stamp


D. Today Planned Activities 3-Feb-16
1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Previous in Total
Activity - 14 inch Current inmtr/no mtr/no inmtr/no

1 Bedding 80 40 120
2 Fit up 2 47 49
3 Welding 2 44 46
4 Pipe Laying 50 100 150
5 First Layer Back Filling 50 150 200

Other Activity:
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed
Working Time: 7 am to 6:00pm

118
57

Remarks

On Progress
On Progress Total
On Progress Excavation
On Progress Completed in
Mtr
On Progress 1883
On Progress
On Progress
On Progress
Client Sign & Stamp
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 3-Feb-16

Manpower Details Equipment Details


Sl No. Designation Qty Sl No. Equipments Qty
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1

10 Safety Officer 1 31 Portable Oven 5


11 Welder 6 32 1
12 Fitter 1 33 25 ton Crane 1
13 Sheet Fabricator 1 34 Water Tanker 1
14 Helper 6
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1
2 Site Engineer 1 10 Wheel Excavator 1
3 Safety Officer 1 11 Roller Compactor 1

4 Site Foreman 1 12 SHOVEL 1


5 Fitter 0 13 25 ton Crane 0
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 6 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50
Contractor Sign & Stamp Client Sign & Stamp
SubContractor - Richmond - J&J
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 10 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 38 Total 7
Total Manpower Total Equipments 7

HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers
2 Safety barriers, safety cones and signage boards installed near to the road area
3 Pipes at ETS A near fance barricaded with warning Taypes
4 Provided signages board near road area
5 Provided mesh along with the crush barriers and safety cones beside the road
6 pipes are covered with tarpolin
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh
8 Excavation at ETS-2 are barricaded with orange Mesh
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted
10 Barricades provided near road area (Near Plant Area)
MAHAWI

Working Time: 7 am to 6:00pm

Other Details
Sl No. Others Qty

Direct Manpower
20 Rigger 3

21 Pipe Fabricator 5
22 Multi Skill Helper 5
23 Electrican 1
24 Crane Operator 1
25 Tanker Driver 1

Total 16
LLC
Other Details
Sl No. Others Qty

15 Shovel Operator
16 Crane Operator
17 Draughts man 1

18 BUS DRIVER 0
19 Site Surveyor 1
Total 2

Client Sign & Stamp


Other Details
Sl No. Others Qty

Total 0

Done
Done
Done
Done
Done
Done
Done
Done
Done
Done
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 2-Feb-16 Weather: Sunny Temperature: 30ºC

A. Manpower report as on 1-Feb-16 Total Manpower:


B. Equipment report as on 1-Feb-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 1-Feb-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -3 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completed , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH Previous in mtr/no Total in
Current in mtr/no
PIPE mtr/no
1 Excavation (Zone -1 and 2) 20 1863 1883
2 Bedding 20 1100 1120
3 Fit up 4 149 153
4 Doubling 2 151 153
5 Pipe Laying Fit up 3 78 81
6 Pipe Laying Welding 2 67 69
7 UPVC Sleeve Laying 100 600 800
8 Backfilling 100 600 700
Total
Activity - 12 inch Current inmtr/no Previous in mtr/no inmtr/no

1 Bedding 100 300 400


2 Fit up 2 70 72
3 Doubling 2 62 64
4 Pipe Laying 300 280 580
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Previous in Total in
Activity - 10 inch Current in mtr/no mtr/no mtr/no

1 Bedding 400 370 770


2 Fit up 2 67 69
3 Welding 2 35 37
4 Pipe Laying 20 620 640
5 First Layer Back Filling 100 200 300

Contractor Sign & Stamp Client Sign & Stamp


D. Today Planned Activities 2-Feb-16
1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Previous in Total
Activity - 14 inch Current inmtr/no mtr/no inmtr/no

1 Bedding 80 40 120
2 Fit up 2 47 49
3 Welding 2 44 46
4 Pipe Laying 50 100 150
5 First Layer Back Filling 50 150 200

Other Activity:
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed
Working Time: 7 am to 6:00pm

118
57

Remarks

On Progress
On Progress Total
On Progress Excavation
On Progress Completed in
Mtr
On Progress 1883
On Progress
On Progress
On Progress
Client Sign & Stamp
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 2-Feb-16

Manpower Details Equipment Details


Sl No. Designation Qty Sl No. Equipments Qty
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1

10 Safety Officer 1 31 Portable Oven 5


11 Welder 6 32 1
12 Fitter 1 33 25 ton Crane 1
13 Sheet Fabricator 1 34 Water Tanker 1
14 Helper 6
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1
2 Site Engineer 1 10 Wheel Excavator 1
3 Safety Officer 1 11 Roller Compactor 1

4 Site Foreman 1 12 SHOVEL 1


5 Fitter 0 13 25 ton Crane 0
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 6 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50
Contractor Sign & Stamp Client Sign & Stamp
SubContractor - Richmond - J&J
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 10 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 38 Total 7
Total Manpower Total Equipments 7

HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers
2 Safety barriers, safety cones and signage boards installed near to the road area
3 Pipes at ETS A near fance barricaded with warning Taypes
4 Provided signages board near road area
5 Provided mesh along with the crush barriers and safety cones beside the road
6 pipes are covered with tarpolin
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh
8 Excavation at ETS-2 are barricaded with orange Mesh
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted
10 Barricades provided near road area (Near Plant Area)
MAHAWI

Working Time: 7 am to 6:00pm

Other Details
Sl No. Others Qty

Direct Manpower
20 Rigger 3

21 Pipe Fabricator 5
22 Multi Skill Helper 5
23 Electrican 1
24 Crane Operator 1
25 Tanker Driver 1

Total 16
LLC
Other Details
Sl No. Others Qty

15 Shovel Operator
16 Crane Operator
17 Draughts man 1

18 BUS DRIVER 0
19 Site Surveyor 1
Total 2

Client Sign & Stamp


Other Details
Sl No. Others Qty

Total 0

Done
Done
Done
Done
Done
Done
Done
Done
Done
Done
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 1-Feb-16 Weather: Sunny Temperature: 30ºC

A. Manpower report as on 31-Jan-16 Total Manpower:


B. Equipment report as on 31-Jan-16 Total Equipment:
C. Progress Report - Executive Summary
Sl No. Activities Done On 31-Jan-16

1 Zone - 4 pipe line doubling fit up.


2 Main Line 20 inch pipe fit up and welding.
3 Zone -3 Excavation.
4 ETS - B valve chamber Second wall steel work.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completed , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH Previous in mtr/no Total in
Current in mtr/no
PIPE mtr/no
1 Excavation (Zone -1 and 2) 20 1843 1863
2 Bedding 20 1100 1120
3 Fit up 4 149 153
4 Doubling 2 151 153
5 Pipe Laying Fit up 3 78 81
6 Pipe Laying Welding 2 67 69
7 UPVC Sleeve Laying 100 600 800
8 Backfilling 100 600 700
Total
Activity - 12 inch Current inmtr/no Previous in mtr/no inmtr/no

1 Bedding 100 300 400


2 Fit up 2 70 72
3 Doubling 2 62 64
4 Pipe Laying 300 280 580
5 First Layer Back Filling
6 Pipe Laying Fit up
7 Pipe Laying Welding

Previous in mtr/no Total in


Activity - 10 inch Current in mtr/no mtr/no

1 Bedding 400 370 770


2 Fit up 2 67 69
3 Welding 2 35 37
4 Pipe Laying 20 620 640
5 First Layer Back Filling 100 200 300

Contractor Sign & Stamp Client Sign & Stamp


D. Today Planned Activities 1-Feb-16
1 ETS-B TIE BEAM Steel fixing , Deshuttering for Tie Beam ETS 3 , Shifting Shuttering to ETS B.
2 Zone - 4 pipe line doubling fit up is going on.
3 ETS - B Pipe line Doubling and welding is goin on.
4 Zone - 2 - 20 inch Pipe Doubling and Welding is going on.
5 Main Line 20 inch pipe fit up and welding is going on.- Z-2 & 1
6 20 inch main line Doubling and Welding in Zone - 2 & 1
7 Zone - 2 and 4 Excavation is going on.
8 ETS - B and A Route pipe line fit up and welding is going on.
9 Inside militry school excavation is going on - Zone -2 and Zone - 4

Previous in Total
Activity - 14 inch Current inmtr/no mtr/no inmtr/no

1 Bedding 80 40 120
2 Fit up 2 47 49
3 Welding 2 44 46
4 Pipe Laying 50 100 150
5 First Layer Back Filling 50 150 200

Other Activity:
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed
Working Time: 7 am to 6:00pm

118
57

Remarks

On Progress
On Progress Total
On Progress Excavation
On Progress Completed in
Mtr
On Progress 1863
On Progress
On Progress
On Progress
Client Sign & Stamp
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 1-Feb-16

Manpower Details Equipment Details


Sl No. Designation Qty Sl No. Equipments Qty
Indirect Manpower 20 Welding machine 4
1 Project Manager 1 21 Grinding machine 8
2 Piping Engineer 1 22 JCB 1
3 Electrical Engineer 1 23 Gas Cutters 2
4 Civil engineer 1 24 Wheel Excavator 1
5 QHSE Engineer 1 25 3 ton pick up 1
6 Planning Engineer 1 26 1 ton pick up 2
7 Draftsman 1 27 32 seat bus 1
8 Surveyor 1 28 Generators 4
Direct Manpower 29 Pipe Cutters 1
9 Mechanical Supervisor 1 30 Electric oven - 50 Kg 1

10 Safety Officer 1 31 Portable Oven 5


11 Welder 6 32 1
12 Fitter 1 33 25 ton Crane 1
13 Sheet Fabricator 1 34 Water Tanker 1
14 Helper 6
15 Mason 1
16 Excavator & Shovel Operator 2
17 JCB Operator 1

18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1
2 Site Engineer 1 10 Wheel Excavator 1
3 Safety Officer 1 11 Roller Compactor 1

4 Site Foreman 1 12 SHOVEL 1


5 Fitter 0 13 25 ton Crane 0
6 Tak Welder 2 14 Diesel Welding machine 2
7 General Workers 6 15 Electric Welding machine 3
8 BUS DRIVER 2 16 Electric oven - 50 Kg 1
9 Welders 6G 6 17 Portable Oven 5
10 Fabricator 3 18 50 ton Crane 1
11 QC Inspector 1
12 Operators 4
13 Electrican 1
14 Rigger 1
Total 30 Total 16
Total Manpower 80 Total Equipments 50
Contractor Sign & Stamp Client Sign & Stamp
SubContractor - Richmond - J&J
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Richmond - J&J
1 Project Engineer 1 9 Mini Bus 1
2 Document Controller 1 10 Wheel Excavator 1
3 Office Asst 0 11 Roller Compactor 1
4 Site Foreman 2 12 SHOWEL 0
5 Mason 6 13 3 ton pick up 1
6 Helper 10 14 Steel Cutting Machine 1
7 Carpenter 8 15 Steel Bending machine 1
8 BUS DRIVER 1 16 JCB 0
9 Steel Worker 8 17 2 ton roller compactor 1

10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0

Total 38 Total 7
Total Manpower Total Equipments 7

HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers
2 Safety barriers, safety cones and signage boards installed near to the road area
3 Pipes at ETS A near fance barricaded with warning Taypes
4 Provided signages board near road area
5 Provided mesh along with the crush barriers and safety cones beside the road
6 pipes are covered with tarpolin
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh
8 Excavation at ETS-2 are barricaded with orange Mesh
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted
10 Barricades provided near road area (Near Plant Area)
MAHAWI

Working Time: 7 am to 6:00pm

Other Details
Sl No. Others Qty

Direct Manpower
20 Rigger 3

21 Pipe Fabricator 5
22 Multi Skill Helper 5
23 Electrican 1
24 Crane Operator 1
25 Tanker Driver 1

Total 16
LLC
Other Details
Sl No. Others Qty

15 Shovel Operator
16 Crane Operator
17 Draughts man 1

18 BUS DRIVER 0
19 Site Surveyor 1
Total 2

Client Sign & Stamp


Other Details
Sl No. Others Qty

Total 0

Done
Done
Done
Done
Done
Done
Done
Done
Done
Done