DPR - Feb
DPR - Feb
Previous in Total in
Activity - 10 inch Current in mtr/no mtr/no mtr/no
Previous in Total
Activity - 14 inch Current inmtr/no mtr/no inmtr/no
1 Bedding 80 40 120
2 Fit up 2 49 51
3 Welding 2 46 48
4 Pipe Laying 50 100 150
5 First Layer Back Filling 50 150 200
Other Activity:
1 Inspection for the Electrical sleeves in ETS 1 Slab done
2 Sample laying of upvc barrier to Tabreed Engineer.
3
4
5
6
7
8
9
10
11
12
Working Time: 7 am to 6:00pm
118
57
Remarks
On Progress
On Progress Total
On Progress Excavation
On Progress Completed in
Mtr
On Progress 1923
On Progress
On Progress
On Progress
Client Sign & Stamp
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 10-Feb-16
18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1
2 Site Engineer 1 10 Wheel Excavator 1
3 Safety Officer 1 11 Roller Compactor 1
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 38 Total 7
Total Manpower Total Equipments 7
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers
2 Safety barriers, safety cones and signage boards installed near to the road area
3 Pipes at ETS A near fance barricaded with warning Taypes
4 Provided signages board near road area
5 Provided mesh along with the crush barriers and safety cones beside the road
6 pipes are covered with tarpolin
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh
8 Excavation at ETS-2 are barricaded with orange Mesh
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted
10 Barricades provided near road area (Near Plant Area)
MAHAWI
Other Details
Sl No. Others Qty
Direct Manpower
20 Rigger 3
21 Pipe Fabricator 5
22 Multi Skill Helper 5
23 Electrican 1
24 Crane Operator 1
25 Tanker Driver 1
Total 16
LLC
Other Details
Sl No. Others Qty
15 Shovel Operator
16 Crane Operator
17 Draughts man 1
18 BUS DRIVER 0
19 Site Surveyor 1
Total 2
Total 0
Done
Done
Done
Done
Done
Done
Done
Done
Done
Done
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 9-Feb-16 Weather: Sunny Temperature: 22ºC
1 Zone - 4 pipe line proceed the fence crossing reach upto the valve chamber
2 Zone - 3 piping is under progress
3 Dewatering under progress
4 ETS - 1 valve chamber Second Concrete works completed.
5 ETS - B and A Route pipe line fit up and welding.
6 Zone -4 Excavation is going on.
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completed , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH Previous in Total in
Current in mtr/no
PIPE mtr/no mtr/no
1 Excavation (Zone -1 and 2) 20 1903 1923
2 Bedding 20 1120 1140
3 Fit up 4 153 157
4 Doubling 2 151 153
5 Pipe Laying Fit up 3 80 81
6 Pipe Laying Welding 3 70 73
7 UPVC Sleeve Laying 100 600 800
8 Backfilling 100 600 700
Previous in Total
Activity - 12 inch Current inmtr/no mtr/no inmtr/no
Previous in Total in
Activity - 10 inch Current in mtr/no mtr/no mtr/no
Previous in Total
Activity - 14 inch Current inmtr/no mtr/no inmtr/no
1 Bedding 80 40 120
2 Fit up 2 49 51
3 Welding 2 46 48
4 Pipe Laying 50 100 150
5 First Layer Back Filling 50 150 200
Other Activity:
1 Electrical Sleeves Installation at ETS-3 Completed
2 Electrical Sleeves Installation at ETS-B Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed
Working Time: 7 am to 6:00pm
118
57
Remarks
On Progress
On Progress Total
On Progress Excavation
On Progress Completed in
Mtr
On Progress 1923
On Progress
On Progress
On Progress
Client Sign & Stamp
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 9-Feb-16
18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1
2 Site Engineer 1 10 Wheel Excavator 1
3 Safety Officer 1 11 Roller Compactor 1
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 38 Total 7
Total Manpower Total Equipments 7
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers
2 Safety barriers, safety cones and signage boards installed near to the road area
3 Pipes at ETS A near fance barricaded with warning Taypes
4 Provided signages board near road area
5 Provided mesh along with the crush barriers and safety cones beside the road
6 pipes are covered with tarpolin
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh
8 Excavation at ETS-2 are barricaded with orange Mesh
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted
10 Barricades provided near road area (Near Plant Area)
MAHAWI
Other Details
Sl No. Others Qty
Direct Manpower
20 Rigger 3
21 Pipe Fabricator 5
22 Multi Skill Helper 5
23 Electrican 1
24 Crane Operator 1
25 Tanker Driver 1
Total 16
LLC
Other Details
Sl No. Others Qty
15 Shovel Operator
16 Crane Operator
17 Draughts man 1
18 BUS DRIVER 0
19 Site Surveyor 1
Total 2
Total 0
Done
Done
Done
Done
Done
Done
Done
Done
Done
Done
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 8-Feb-16 Weather: Sunny Temperature: 22ºC
1 Zone - 4 pipe line proceed the fence crossing Approval got from CMW
2 Zone - 3 piping is under progress
3 Dewatering under progress
4 ETS - 1 valve chamber Second Shutter works completed.
5 ETS - B Route pipe line back filling second 2nd layer and mest under progress
6 Zone -4 Excavation is going on Near fence area
7 Inside military school excavation is going on Zone -2 and Zone - 4
8 Casting for ETS 3 Tie beam completed , Back filling in ETS 1 & 3
Activity - 20 & 18 INCH Previous in Total in
Current in mtr/no
PIPE mtr/no mtr/no
1 Excavation (Zone -1 and 2) 20 1903 1923
2 Bedding 20 1120 1140
3 Fit up 4 153 157
4 Doubling 2 151 153
5 Pipe Laying Fit up 3 80 81
6 Pipe Laying Welding 3 70 73
7 UPVC Sleeve Laying 100 600 800
8 Backfilling 100 600 700
Previous in Total
Activity - 12 inch Current inmtr/no mtr/no inmtr/no
Previous in Total in
Activity - 10 inch Current in mtr/no mtr/no mtr/no
Previous in Total
Activity - 14 inch Current inmtr/no mtr/no inmtr/no
1 Bedding 80 40 120
2 Fit up 2 49 51
3 Welding 2 46 48
4 Pipe Laying 50 100 150
5 First Layer Back Filling 50 150 200
Other Activity:
1 Electrical Sleeves Installation at ETS-3 Completed
2 Electrical Sleeves Installation at ETS-B Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed
Working Time: 7 am to 6:00pm
118
57
Remarks
On Progress
On Progress Total
On Progress Excavation
On Progress Completed in
Mtr
On Progress 1923
On Progress
On Progress
On Progress
Client Sign & Stamp
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 8-Feb-16
18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1
2 Site Engineer 1 10 Wheel Excavator 1
3 Safety Officer 1 11 Roller Compactor 1
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 38 Total 7
Total Manpower Total Equipments 7
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers
2 Safety barriers, safety cones and signage boards installed near to the road area
3 Pipes at ETS A near fance barricaded with warning Taypes
4 Provided signages board near road area
5 Provided mesh along with the crush barriers and safety cones beside the road
6 pipes are covered with tarpolin
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh
8 Excavation at ETS-2 are barricaded with orange Mesh
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted
10 Barricades provided near road area (Near Plant Area)
MAHAWI
Other Details
Sl No. Others Qty
Direct Manpower
20 Rigger 3
21 Pipe Fabricator 5
22 Multi Skill Helper 5
23 Electrican 1
24 Crane Operator 1
25 Tanker Driver 1
Total 16
LLC
Other Details
Sl No. Others Qty
15 Shovel Operator
16 Crane Operator
17 Draughts man 1
18 BUS DRIVER 0
19 Site Surveyor 1
Total 2
Total 0
Done
Done
Done
Done
Done
Done
Done
Done
Done
Done
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Feb-16 Weather: Sunny Temperature: 22ºC
Previous in Total in
Activity - 10 inch Current in mtr/no mtr/no mtr/no
Previous in Total
Activity - 14 inch Current inmtr/no mtr/no inmtr/no
1 Bedding 80 40 120
2 Fit up 2 49 51
3 Welding 2 46 48
4 Pipe Laying 50 100 150
5 First Layer Back Filling 50 150 200
Other Activity:
1 Electrical Sleeves Installation at ETS-3 Completed
2 Electrical Sleeves Installation at ETS-B Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed
Working Time: 7 am to 6:00pm
118
57
Remarks
On Progress
On Progress Total
On Progress Excavation
On Progress Completed in
Mtr
On Progress 1903
On Progress
On Progress
On Progress
Client Sign & Stamp
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 7-Feb-16
18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1
2 Site Engineer 1 10 Wheel Excavator 1
3 Safety Officer 1 11 Roller Compactor 1
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 38 Total 7
Total Manpower Total Equipments 7
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers
2 Safety barriers, safety cones and signage boards installed near to the road area
3 Pipes at ETS A near fance barricaded with warning Taypes
4 Provided signages board near road area
5 Provided mesh along with the crush barriers and safety cones beside the road
6 pipes are covered with tarpolin
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh
8 Excavation at ETS-2 are barricaded with orange Mesh
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted
10 Barricades provided near road area (Near Plant Area)
MAHAWI
Other Details
Sl No. Others Qty
Direct Manpower
20 Rigger 3
21 Pipe Fabricator 5
22 Multi Skill Helper 5
23 Electrican 1
24 Crane Operator 1
25 Tanker Driver 1
Total 16
LLC
Other Details
Sl No. Others Qty
15 Shovel Operator
16 Crane Operator
17 Draughts man 1
18 BUS DRIVER 0
19 Site Surveyor 1
Total 2
Total 0
Done
Done
Done
Done
Done
Done
Done
Done
Done
Done
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 6-Feb-16 Weather: Sunny Temperature: 22ºC
Previous in Total in
Activity - 10 inch Current in mtr/no mtr/no mtr/no
Previous in Total
Activity - 14 inch Current inmtr/no mtr/no inmtr/no
1 Bedding 80 40 120
2 Fit up 2 49 51
3 Welding 2 46 48
4 Pipe Laying 50 100 150
5 First Layer Back Filling 50 150 200
Other Activity:
1 Electrical Sleeves Installation at ETS-3 Completed
2 Electrical Sleeves Installation at ETS-B Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed
Working Time: 7 am to 6:00pm
118
57
Remarks
On Progress
On Progress Total
On Progress Excavation
On Progress Completed in
Mtr
On Progress 1903
On Progress
On Progress
On Progress
Client Sign & Stamp
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 6-Feb-16
18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1
2 Site Engineer 1 10 Wheel Excavator 1
3 Safety Officer 1 11 Roller Compactor 1
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 38 Total 7
Total Manpower Total Equipments 7
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers
2 Safety barriers, safety cones and signage boards installed near to the road area
3 Pipes at ETS A near fance barricaded with warning Taypes
4 Provided signages board near road area
5 Provided mesh along with the crush barriers and safety cones beside the road
6 pipes are covered with tarpolin
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh
8 Excavation at ETS-2 are barricaded with orange Mesh
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted
10 Barricades provided near road area (Near Plant Area)
MAHAWI
Other Details
Sl No. Others Qty
Direct Manpower
20 Rigger 3
21 Pipe Fabricator 5
22 Multi Skill Helper 5
23 Electrican 1
24 Crane Operator 1
25 Tanker Driver 1
Total 16
LLC
Other Details
Sl No. Others Qty
15 Shovel Operator
16 Crane Operator
17 Draughts man 1
18 BUS DRIVER 0
19 Site Surveyor 1
Total 2
Total 0
Done
Done
Done
Done
Done
Done
Done
Done
Done
Done
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 4-Feb-16 Weather: Sunny Temperature: 30ºC
Previous in Total in
Activity - 10 inch Current in mtr/no mtr/no mtr/no
Previous in Total
Activity - 14 inch Current inmtr/no mtr/no inmtr/no
1 Bedding 80 40 120
2 Fit up 2 47 49
3 Welding 2 44 46
4 Pipe Laying 50 100 150
5 First Layer Back Filling 50 150 200
Other Activity:
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed
Working Time: 7 am to 6:00pm
118
57
Remarks
On Progress
On Progress Total
On Progress Excavation
On Progress Completed in
Mtr
On Progress 1883
On Progress
On Progress
On Progress
Client Sign & Stamp
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 4-Feb-16
18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1
2 Site Engineer 1 10 Wheel Excavator 1
3 Safety Officer 1 11 Roller Compactor 1
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 38 Total 7
Total Manpower Total Equipments 7
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers
2 Safety barriers, safety cones and signage boards installed near to the road area
3 Pipes at ETS A near fance barricaded with warning Taypes
4 Provided signages board near road area
5 Provided mesh along with the crush barriers and safety cones beside the road
6 pipes are covered with tarpolin
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh
8 Excavation at ETS-2 are barricaded with orange Mesh
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted
10 Barricades provided near road area (Near Plant Area)
MAHAWI
Other Details
Sl No. Others Qty
Direct Manpower
20 Rigger 3
21 Pipe Fabricator 5
22 Multi Skill Helper 5
23 Electrican 1
24 Crane Operator 1
25 Tanker Driver 1
Total 16
LLC
Other Details
Sl No. Others Qty
15 Shovel Operator
16 Crane Operator
17 Draughts man 1
18 BUS DRIVER 0
19 Site Surveyor 1
Total 2
Total 0
Done
Done
Done
Done
Done
Done
Done
Done
Done
Done
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 3-Feb-16 Weather: Sunny Temperature: 30ºC
Previous in Total in
Activity - 10 inch Current in mtr/no mtr/no mtr/no
Previous in Total
Activity - 14 inch Current inmtr/no mtr/no inmtr/no
1 Bedding 80 40 120
2 Fit up 2 47 49
3 Welding 2 44 46
4 Pipe Laying 50 100 150
5 First Layer Back Filling 50 150 200
Other Activity:
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed
Working Time: 7 am to 6:00pm
118
57
Remarks
On Progress
On Progress Total
On Progress Excavation
On Progress Completed in
Mtr
On Progress 1883
On Progress
On Progress
On Progress
Client Sign & Stamp
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 3-Feb-16
18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1
2 Site Engineer 1 10 Wheel Excavator 1
3 Safety Officer 1 11 Roller Compactor 1
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 38 Total 7
Total Manpower Total Equipments 7
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers
2 Safety barriers, safety cones and signage boards installed near to the road area
3 Pipes at ETS A near fance barricaded with warning Taypes
4 Provided signages board near road area
5 Provided mesh along with the crush barriers and safety cones beside the road
6 pipes are covered with tarpolin
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh
8 Excavation at ETS-2 are barricaded with orange Mesh
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted
10 Barricades provided near road area (Near Plant Area)
MAHAWI
Other Details
Sl No. Others Qty
Direct Manpower
20 Rigger 3
21 Pipe Fabricator 5
22 Multi Skill Helper 5
23 Electrican 1
24 Crane Operator 1
25 Tanker Driver 1
Total 16
LLC
Other Details
Sl No. Others Qty
15 Shovel Operator
16 Crane Operator
17 Draughts man 1
18 BUS DRIVER 0
19 Site Surveyor 1
Total 2
Total 0
Done
Done
Done
Done
Done
Done
Done
Done
Done
Done
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 2-Feb-16 Weather: Sunny Temperature: 30ºC
Previous in Total in
Activity - 10 inch Current in mtr/no mtr/no mtr/no
Previous in Total
Activity - 14 inch Current inmtr/no mtr/no inmtr/no
1 Bedding 80 40 120
2 Fit up 2 47 49
3 Welding 2 44 46
4 Pipe Laying 50 100 150
5 First Layer Back Filling 50 150 200
Other Activity:
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed
Working Time: 7 am to 6:00pm
118
57
Remarks
On Progress
On Progress Total
On Progress Excavation
On Progress Completed in
Mtr
On Progress 1883
On Progress
On Progress
On Progress
Client Sign & Stamp
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 2-Feb-16
18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1
2 Site Engineer 1 10 Wheel Excavator 1
3 Safety Officer 1 11 Roller Compactor 1
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 38 Total 7
Total Manpower Total Equipments 7
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers
2 Safety barriers, safety cones and signage boards installed near to the road area
3 Pipes at ETS A near fance barricaded with warning Taypes
4 Provided signages board near road area
5 Provided mesh along with the crush barriers and safety cones beside the road
6 pipes are covered with tarpolin
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh
8 Excavation at ETS-2 are barricaded with orange Mesh
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted
10 Barricades provided near road area (Near Plant Area)
MAHAWI
Other Details
Sl No. Others Qty
Direct Manpower
20 Rigger 3
21 Pipe Fabricator 5
22 Multi Skill Helper 5
23 Electrican 1
24 Crane Operator 1
25 Tanker Driver 1
Total 16
LLC
Other Details
Sl No. Others Qty
15 Shovel Operator
16 Crane Operator
17 Draughts man 1
18 BUS DRIVER 0
19 Site Surveyor 1
Total 2
Total 0
Done
Done
Done
Done
Done
Done
Done
Done
Done
Done
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 1-Feb-16 Weather: Sunny Temperature: 30ºC
Previous in Total
Activity - 14 inch Current inmtr/no mtr/no inmtr/no
1 Bedding 80 40 120
2 Fit up 2 47 49
3 Welding 2 44 46
4 Pipe Laying 50 100 150
5 First Layer Back Filling 50 150 200
Other Activity:
1 Pneumatic test for Zone-1 Joint No. R4 to R31 & S4 to S31 Completed
2 Pneumatic test for Zone-1 Joint No. R39 to R62 & S39 to S62 Completed
3 Pneumatic test for Zone-1 Joint No. R1 to R31 & S1 to S31 Completed
4 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S 39 to S58 Completed
5 2 Coat Primer + 2 coat Epoxy applied in Zone-1 S4 to S31 Completed
6 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R39 to R58 Completed
7 2 Coat Primer + 2 coat Epoxy applied in Zone-1 R4 to R31 Completed
8 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S1 to S20 Completed
9 2 Coat Primer + 2 coat Epoxy applied in Zone-2 S21 to S31 Completed
10 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R1 to R20 Completed
11 2 Coat Primer + 2 coat Epoxy applied in Zone-2 R21 to R31 Completed
12 2 Coat Primer + 2 coat Epoxy applied in Zone-5 S6 to S38 Completed
Working Time: 7 am to 6:00pm
118
57
Remarks
On Progress
On Progress Total
On Progress Excavation
On Progress Completed in
Mtr
On Progress 1863
On Progress
On Progress
On Progress
Client Sign & Stamp
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
To Be Progressed
PROJECT TITLE: EXTERNAL CHILLED WATER PIPING NETWORK -- MAHAWI
PROJECT NO: AD- 16 - 4061 E
DAILY PROGRESS REPORT
Date: 1-Feb-16
18 BUS DRIVER 3
19 Carpenter 1
Total 32 Total 34
SubContractor - Emirates Engineering LLC
Manpower Details Equipment Detail
Sl No. Designation Qty Sl No. Equipments Qty
Emirates Engineering
1 Project Engineer 1 9 Mini Bus 1
2 Site Engineer 1 10 Wheel Excavator 1
3 Safety Officer 1 11 Roller Compactor 1
10 Electrican 0
11 Painter 0
12 Safety Officer 1
13 Excavator & Shovel Operator 0
Total 38 Total 7
Total Manpower Total Equipments 7
HSE Issues:
F. HSE Issues:
1 Excavation in ETS-2 was barricaded with Mesh and installed signages board and barriers
2 Safety barriers, safety cones and signage boards installed near to the road area
3 Pipes at ETS A near fance barricaded with warning Taypes
4 Provided signages board near road area
5 Provided mesh along with the crush barriers and safety cones beside the road
6 pipes are covered with tarpolin
7 Excavation at near (ETS A) area barricaded with barriers &orange mesh
8 Excavation at ETS-2 are barricaded with orange Mesh
9 Installed Crush Barriers with water beside the road side area Safety Signages were posted
10 Barricades provided near road area (Near Plant Area)
MAHAWI
Other Details
Sl No. Others Qty
Direct Manpower
20 Rigger 3
21 Pipe Fabricator 5
22 Multi Skill Helper 5
23 Electrican 1
24 Crane Operator 1
25 Tanker Driver 1
Total 16
LLC
Other Details
Sl No. Others Qty
15 Shovel Operator
16 Crane Operator
17 Draughts man 1
18 BUS DRIVER 0
19 Site Surveyor 1
Total 2
Total 0
Done
Done
Done
Done
Done
Done
Done
Done
Done
Done