Robustness
Robustness
STRUCTURAL ROBUSTNESS
DESIGN
ir azhar ahmad faculty of civil engineering
Version 2:December 2012
3
INTRODUCTION
• The collapse of Ronan Point in 1968 was a seminal event
and resulted in fundamental changes to the design
philosophy of building structures in the UK. The disaster
highlighted the need for specific consideration of the
stability of structures that have been damaged by
accidents such as a gas explosion.
• It was considered that, while localized damage was
unavoidable, complete collapse of structures had to be
prevented. Thus, the concept of disproportionate or
progressive collapse was born and structures had to be
designed in such a way that they would not be damaged to
an extent disproportionate to the initial effect of the
accident.
4
INTRODUCTION
5
INTRODUCTION
6
INTRODUCTION
Attention to progressive
collapse was initiated.
7
INTRODUCTION
8
INTRODUCTION
25th floor
1) 1D Translational-Rotational
--- "Ronan Point" type Gas
Angular momentum and shear exploded
on 18th floor
not negligible
2) 3D Compaction Front
Propagation
— will require finite Generalization of
strain simulation Progressive
Collapse
9
INTRODUCTION
10
INTRODUCTION
11
INTRODUCTION
12
INTRODUCTION
13
INTRODUCTION
14
PHASE 1: PROGRESSIVE COLLAPSE
• Introduction
• Historical Events
• Associated Hazards
15
HISTORICAL EVENTS
Alfred P. Murrah
Building, 1995,
Oklahoma City,
Oklahoma
RC frame structure
with transfer girders
designed in
accordance with ACI
318-71.
Discontinuity of
reinforcement in both
the positive and
negative moment
reinforcement.
16
HISTORICAL EVENTS
17
HISTORICAL EVENTS
1995 Federal
Murrah Building
18
HISTORICAL EVENTS
19
HISTORICAL EVENTS
4) Floors above
transfer girder fail;
collapse imminent
Commonwealth Avenue
apartment, 1971, Boston
RC flat-plate structure
Likely construction over-load, poor material
properties in cold weather, and inadequate
positioning slab top bars caused punching
shear failure at roof level.
Punching shear failure propagated to the
ground level.
Attention to progressive collapse was
initiated.
22
HISTORICAL EVENTS
1983 US Marine
Corps HQ, Lebanon -
241 dead + 60
wounded
24
HISTORICAL EVENTS
WORLD TRADE
CENTER NEW
YORK
SEPTEMBER
2011
25
HISTORICAL EVENTS
26
HISTORICAL EVENTS
27
HISTORICAL EVENTS
29
PHASE 1: PROGRESSIVE COLLAPSE
• Introduction
• Historical Events
• Associated Hazards
30
ASSOCIATED HAZARDS
32
ASSOCIATED HAZARDS
33
ASSOCIATED HAZARDS
34
ASSOCIATED HAZARDS
1.Aircraft Impact
• The majority of accidents occur in
take-off or landing operations. US
figures indicate that over half of
all such accidents occur at airport
sites and only 30 % occur at
distances greater than 8 km (5 mi)
from the airport.
Although aircraft impact does not
appear to pose a credible threat
certain key facilities within 10 km
(6 mi) of an Airport may require a
site-specific analysis.
36
ASSOCIATED HAZARDS
38
ASSOCIATED HAZARDS
39
ASSOCIATED HAZARDS
3.Fire
40
ASSOCIATED HAZARDS
4.Gas Explosions
41
ASSOCIATED HAZARDS
1. Floor lifted up by
the gas explosion
2. Dowel bar
pulled out
the grout tube
42
ASSOCIATED HAZARDS
43
ASSOCIATED HAZARDS
44
ASSOCIATED HAZARDS
7.Vehicular Collision
45
ASSOCIATED HAZARDS
8.Bomb Explosions
46
ASSOCIATED HAZARDS
47
ASSOCIATED HAZARDS
49
PHASE 1: PROGRESSIVE COLLAPSE
• Introduction
• Historical Events
• Associated Hazards
50
ROBUSTNESS IN DESIGN
51
ROBUSTNESS IN DESIGN
An extract from
the UK Building
Regulations of
1972.
52
ROBUSTNESS IN DESIGN
53
ROBUSTNESS IN DESIGN
54
ROBUSTNESS IN DESIGN
55
ROBUSTNESS IN DESIGN
• Hotels, apartments and other residential buildings • Horizontal ties and vertical ties
exceeding 4 storeys, but not exceeding 15 storeys. as described in the codes of
• Educational buildings greater than 1 storey, but not practice,
exceeding 15 storeys. OR
• Retail premises greater than 3 storeys but not exceeding • Show that the removal of a wall
2B 15 storeys. or column will cause only limited
• Hospitals not exceeding 3 storeys. damage,
• Offices greater than 4 storeys but not exceeding 15 OR
storeys. • Design as ‘key elements’.
• All buildings to which members of the pubic are admitted
and which contain floor areas exceeding
2000 m2 but less than 5000 m2 at each storey.
• Car parking not exceeding 6 storeys.
• All buildings defined above as Class 2A and 2B that • Systematic risk assessment
exceed the limits on area and/or number of storeys.
3 • All buildings, containing hazardous substances and/or
processes.
• Grandstands accommodating more than 5000
spectators.
56
ROBUSTNESS IN DESIGN
Class 1 buildings
57
ROBUSTNESS IN DESIGN
Class 2A buildings
• Class 2A buildings require horizontal ties in the floor
plates. If dedicated horizontal ties are not provided then
there must be „effective anchorage‟ of the suspended
floors to the walls. In terms of concrete elements, the use
of the effective anchorage concept is used when concrete
floors are supported on masonry walls, by reference to BS
56286.
58
ROBUSTNESS IN DESIGN
• Class 2B buildings
• There are effectively three approaches:
• 1 Compliance with tying rules
• 2 Showing that the removal of a wall or column will cause
only limited damage
• 3 Showing that key elements are „non-removable‟.
60
ROBUSTNESS IN DESIGN
Figure 1:
Recommended limit
of acceptable
damage
Legend:
a) Floor plan
b) Elevation with vertical section
(A) Local damage less than 15 % of floor area but not more than 75 m2
simultaneously in two adjacent floors
(B) Column, removed for analysis
61
ROBUSTNESS IN DESIGN
62
ROBUSTNESS IN DESIGN
• Interaction of Methods
It should be noted that Methods 2 & 3 are principally
concerned with vertical structure or elements
supporting vertical structure. When applying these
methods the designer must ensure that the horizontal
structure in both directions is robust. This is generally
achieved by providing horizontal ties.
64
ROBUSTNESS IN DESIGN
In the Tie Force approach, the building is mechanically tied together, enhancing
continuity, ductility, and development of alternate load paths.
Tie forces can be provided by the existing structural elements that have been
designed using conventional design methods to carry the standard loads
imposed upon the structure.
Loss of column
65
ROBUSTNESS IN DESIGN
Typical arrangement of
tensile ties in precast
bearing wall structures,
include typical
transverse, longitudinal,
vertical, and perimeter
arrangements.
Poor detailing-no
continuity of top &
bottom reinforcement
67
ROBUSTNESS IN DESIGN
68
ROBUSTNESS IN DESIGN
69
ROBUSTNESS IN DESIGN
To prevent the top continuous bars from tearing out of the top
of the beam, U-stirrups with 135-degree hooks, or one-piece
closed stirrups must be used around the continuous bars.
70
ROBUSTNESS IN DESIGN
A B C
Floor units are Structural topping is
gettingapart detached from the
slabs, mainly in the
floor part near to the
edge beams
D
F
Floor beams slip Large cracks in the floor
off the units due to torsion
supporting
Large cracks E
corbels
between slab units
and floor beams
71
ROBUSTNESS IN DESIGN
Projecting
stirrups from
floor beam
Transversal tie bar connecting the
floor to the supporting beam
72
ROBUSTNESS IN DESIGN
• HORIZONTAL TIES
• Ties need to be continuous (lapped or connected)
across from edge to edge or around the structure while
at the ends horizontal ties to edge columns and wall
must be satisfactorily anchored back
73
ROBUSTNESS IN DESIGN
74
ROBUSTNESS IN DESIGN
• VERTICAL TIES
• Vertical ties have 2 roles. The first is to provide
some form of minimum resistance to the
removal of vertical elements. The second is to
enable load sharing between floors above a
damaged vertical element.
75
ROBUSTNESS IN DESIGN
Fig. 1: Effects of losing an external Fig. 1: (c) alternate load path design:
column to a blast loading: (a) exterior no progressive collapse
blast loading;
76
ROBUSTNESS IN DESIGN
In the Alternate Path method, the designer must show that the structure is capable
of bridging over a removed column or section of wall and that the resulting
deformations and internal actions do not exceed the acceptance criteria.
77
ROBUSTNESS IN DESIGN
Beam-to-beam continuity is
assumed to be maintained
across a removed column,
i.e. remove the clear height
between lateral restraints.
78
ROBUSTNESS IN DESIGN
80
ROBUSTNESS IN DESIGN
81
ROBUSTNESS IN DESIGN
82
ROBUSTNESS IN DESIGN
Frame Action
Catenary Action
Horizontal restraints
Actuator
Steel roller
Compressive arching
and tensile catenary
actions in double-span
steel beam
85
ROBUSTNESS IN DESIGN
Catenary
action Cantilevering
beam
90
ROBUSTNESS IN DESIGN
91
ROBUSTNESS IN DESIGN
92
ROBUSTNESS IN DESIGN
94
ROBUSTNESS IN DESIGN
95
ROBUSTNESS IN DESIGN
96
PHASE 1: PROGRESSIVE COLLAPSE
• Introduction
• Historical Events
• Associated Hazards
97
EXAMPLE OF ROBUST
STRUCTURE
On June 25, 1996, a bomb
estimated at 9 Mg (20 000 lb)
TNT equivalent, apparently
placed in a tank truck was
detonated approximately 24 m
(80 ft) from one of the buildings.
Khobar Towers The explosion, which created a
crater 17 m (55 ft) in diameter
and 5 m (16 ft) deep, destroyed
the facing façade wall of the
closest building, and damaged
interior floors and wall
crater components.
98
EXAMPLE OF ROBUST STRUCTURE
Khobar Towers
Bombing,
Dhahran, Saudi
Arabia;
Casualties from
Debris, Not
Collapse
99
EXAMPLE OF ROBUST STRUCTURE
100
EXAMPLE OF ROBUST STRUCTURE
101
EXAMPLE OF ROBUST STRUCTURE
104
EXAMPLE OF ROBUST STRUCTURE
107
DESIGN PROCEDURES
• The BS Code defines the requirement for robustness in
Clause 2.1.4 as “a structure should be designed and
constructed so that it is inherently robust and not
unreasonably susceptible to the effects of accidents or
misuse, and disproportionate collapse.”
• BS 8110 states: "The engineer responsible for the overall
stability of the structure should ensure the compatibility
of the design and details of parts and components, even
where some or all of the design and details of those parts
and components are not made by this engineer". This is
particularly important when it comes to the robustness of
the structural frame.
108
DESIGN PROCEDURES
109
DESIGN PROCEDURES-BUILDING
LAYOUT
110
DESIGN PROCEDURES-BUILDING LAYOUT
111
DESIGN PROCEDURES-BUILDING LAYOUT
a) Improvement of
the local resistance
of the columns
Strengthening the transfer girder Strengthening the ground floor with more
columns (but, this would have conflicted
with architectural requirements)
113
DESIGN PROCEDURES-BUILDING LAYOUT
114
DESIGN PROCEDURES-BUILDING LAYOUT
115
DESIGN PROCEDURES-BUILDING LAYOUT
116
DESIGN PROCEDURES-BUILDING LAYOUT
117
DESIGN PROCEDURES-BUILDING LAYOUT
Multi storey or apartment buildings tend to have slender columns using little floor space. In addition
they require long floor spans, also minimizing the amount of columns. To minimise also the amount
of beams, the floors are made with a high profile and therefore are becoming thick and stiff
In the upper line of sketches the
building has thick and stiff floors
with slender supporting columns.
During a earthquake the bottom
columns receive the largest
forces and bend; walls crack and
the whole building will pancake.
118
DESIGN PROCEDURES-NOTIONAL
HORIZONTAL LOADS
• capable to resist notional loads simultaneously at floor
levels and roof (Cl. 3.1.4.2 of the BS 8110 Code which also
requires that applied ultimate wind loads should be greater
than these notional values)
119
DESIGN PROCEDURES-INDIRECT
METHOD
120
DESIGN PROCEDURES-INDIRECT
METHOD
121
DESIGN PROCEDURES-INDIRECT METHOD
122
DESIGN PROCEDURES-INDIRECT METHOD
123
DESIGN PROCEDURES-INDIRECT METHOD
126
EXAMPLE OF INDIRECT METHOD
Example
i. Internal Ties
127
EXAMPLE OF INDIRECT METHOD
128
EXAMPLE OF INDIRECT METHOD
iii. External
Column & Wall
Ties
129
EXAMPLE OF INDIRECT METHOD
130
DESIGN PROCEDURES: EXAMPLES
OF TIE DETAILS
131
DESIGN PROCEDURES: TIE DETAILS
132
DESIGN PROCEDURES: TIE DETAILS
133
DESIGN PROCEDURES: TIE DETAILS
Typical
Details for
Ties
134
DESIGN PROCEDURES: TIE DETAILS
137
DESIGN PROCEDURES: TIE DETAILS
Typical
Details for
Ties
138
DESIGN PROCEDURES-DIRECT
METHOD
139
DESIGN PROCEDURES-DIRECT
METHOD
140
DESIGN PROCEDURES-DIRECT METHOD
141
DESIGN PROCEDURES-DIRECT METHOD
142
•
DESIGN PROCEDURES-DIRECT METHOD
143
DESIGN PROCEDURES-DIRECT METHOD
where
DL = dead load
LL = live load.
For the load combination in Eq. 1, only 25 percent of the live load is
used since the probability of that full live load being present during a
progressive collapse event is small. An amplification factor of 2 is
applied to the load combination to account for dynamic effects.
144
DESIGN PROCEDURES-DIRECT METHOD
145
DESIGN PROCEDURES-DIRECT METHOD
• Using the DCR criteria, structural members and connections that have
DCR values greater than 2.0 are considered to be severely damaged or
collapsed [GSA 2003]. In the case of shear forces, failure is imminent
when the DCR value exceeds 1.0.
• Once the DCRs have been computed, the extent of damage or collapse
can be determined. GSA specifies that the maximum allowable area of
collapse resulting from the instantaneous removal of an exterior
column (or wall ) shall be smaller of the following two areas: (1) the
structural bay directly associated with the removed column or (2) 170
m2 (1830 ft2) at the floor level directly above the removed column.
Similar limits are given areas based on the removal of an interior
column
146
DESIGN PROCEDURES-DIRECT METHOD
Case Study
Number of stories: 12
148
DESIGN PROCEDURES-DIRECT METHOD
• Loads
• Floor Live Load = 50 psf
• Superimposed Dead Load = 30 psf
• Dead Load
• Wind Load for 70 MPH
• Seismic Load - 3 Locations (SDC D,
SDC C & SDC A)
149
DESIGN PROCEDURES-DIRECT METHOD
150
DESIGN PROCEDURES-DIRECT METHOD
Interior column
removed for parking and public space
151
DESIGN PROCEDURES-DIRECT METHOD
152
DESIGN PROCEDURES-DIRECT METHOD
153
DESIGN PROCEDURES-DIRECT METHOD
154
DESIGN PROCEDURES-DIRECT METHOD
155
DESIGN PROCEDURES-DIRECT METHOD
Column line C
Column line 1
157
DESIGN PROCEDURES-DIRECT METHOD
158
DESIGN PROCEDURES-DIRECT METHOD
159
DESIGN PROCEDURES-DIRECT METHOD
• The shear DCR‟s are shown in Table 5 for critical beams B2, B3, and
B27. The table shows that all the SDR‟s are below the GSA limit of 2
and therefore additional shear reinforcement is not needed to prevent
progressive collapse.
• Columns C13, C12, and C16 are symmetrical to the removed column
C9 and, therefore, would also be removed one at a time.
Consequently, beams B4, B17, B18, and B19 would have DCR‟s equal
to those for beams B2 and B3 and need additional reinforcement as
discussed in 2 and 3 above.
160
DESIGN PROCEDURES-DIRECT METHOD
161
DESIGN PROCEDURES-DIRECT METHOD
162
DESIGN PROCEDURES-DIRECT METHOD
Shear
Force
Diagram
164
DESIGN PROCEDURES-DIRECT METHOD
• The shear DCR‟s are shown in Table 5 for beams B6, B21, and B22. The
table shows that all the SDR‟s are below the GSA limit of 2 and
therefore additional shear reinforcement is not needed to prevent
progressive collapse.
• Columns C3, C22, and C23 are symmetrical to the removed column C2
and, therefore, would also be removed one at a time. Consequently,
beams B23, B36, B37, and B38 would have DCR‟s equal to those for
beams B21 and B22 and would need additional reinforcement as
discussed in 2 and 3 immediately above
166
DESIGN PROCEDURES-DIRECT METHOD
167
DESIGN PROCEDURES-DIRECT METHOD
Bending
Moment
Diagram
Shear
Force
Diagram
170
DESIGN PROCEDURES-DIRECT METHOD
• The shear DCR‟s are shown in Table 5 for beams B1 and B21. The table
shows that all the SDR‟s are below the GSA limit of 2 and, therefore,
additional shear reinforcement is not needed to prevent progressive
collapse.
• Columns C4, C21, and C24 are symmetrical to the removed column C1
and, therefore, would also be removed one at a time. Consequently,
beams B23, B16, B20, B9, B36 and B38 would have DCR‟s equal to
those for beams B1 and B21 and would need additional reinforcement
as discussed in 2 and 3 immediately above.
172
DESIGN PROCEDURES-DIRECT METHOD
The removal of
interior column
C6 caused
moment
reversal in the
beams
intersecting at
the removed
support in
beams B6, B7,
B24, and B25
173
DESIGN PROCEDURES-DIRECT METHOD
Bending
Moment
Diagram
Shear
Force
Diagram
A comparison of the
flexural demand
capacity ratios for the
three buildings
studied for the beams
in the vicinity of the
removed column at
beams B6, B7, B24,
and B25 for the
twelve stories is
presented in Figure 9.
The following is a
summary of the
analysis results:
176
DESIGN PROCEDURES-DIRECT METHOD
177
DESIGN PROCEDURES-DIRECT METHOD
• The shear DCR‟s are shown in Table 5 for beams B6, B7, B24, and B25.
The table shows that all the SDR‟s are below the GSA limit of 2 and
therefore additional shear reinforcement is not needed to prevent
progressive collapse.
• Columns C7, C10, C11, C14, C15, C18, and C19 are symmetrical to the
removed column C6 and, therefore, would also be removed one at a
time. Consequently, beams B8, B9, B10, B11, B12, B13, B14, and B15
would have DCR‟s equal to those for beams B6, B7, B24, and B25 and
would need additional reinforcement as discussed in 3 immediately
above.
178
DESIGN PROCEDURES-DIRECT METHOD
• COLUMNS
• BEAM FLEXURAL
• BEAM SHEAR
179
DESIGN PROCEDURES-KEY
ELEMENT DESIGN
180
DESIGN PROCEDURES-KEY
ELEMENT DESIGN
Figure 1:
Recommended limit
of acceptable
damage
Legend:
a) Floor plan
b) Elevation with vertical section
(A) Local damage less than 15 % of floor area but not more than 75 m2
simultaneously in two adjacent floors
(B) Column, removed for analysis
181
DESIGN PROCEDURES-KEY ELEMENT
DESIGN
v. Key Element
Design
Calculation
182
PHASE 1: PROGRESSIVE COLLAPSE
• Introduction
• Historical Events
• Associated Hazards
183
PRACTICAL MEANS FOR
COLLAPSE PREVENTION
• Donald O. Dusenberry
184
PRACTICAL MEANS FOR COLLAPSE PREVENTION
185
PRACTICAL MEANS FOR COLLAPSE PREVENTION
186
PRACTICAL MEANS FOR COLLAPSE PREVENTION
RC Structures
members detailed for ductility- confinement of shear links/column
with spiral links
can be designed for load reversal
can be designed for alternate path
can be designed for two way action
187
PRACTICAL MEANS FOR COLLAPSE PREVENTION
RC Beam Design
• ensure flexural failure (ductile) rather than shear failure (brittle)
• consider large deflections/rotations
• maintain continuous positive and negative reinforcement
• develop the steel anchorage - do not splice reinforcement near
connections or mid span (max. moment areas)
• Increase member sizes (enhance torsional resistance)
Enhance Connections
Provide closely spaced confining steel (improves ductility,
increases shear and torsion strength)
Design joint regions to be stronger than elements
Design for full plastic moment capacity before shear failure
188
PRACTICAL MEANS FOR COLLAPSE PREVENTION
RC Column Design
increase member sizes (enhance load sharing after loss of adjacent
column)
provide confinement
splice column reinforcement at third points
RC Slab Design
189
PRACTICAL MEANS FOR COLLAPSE PREVENTION
RC Wall Design
provide additional detailing in coupling beams and around
openings
consider adding boundary elements to serve as column
tie slabs into walls
190
PHASE 1: PROGRESSIVE COLLAPSE
• Introduction
• Historical Events
• Associated Hazards
191
ROBUSTNESS DURING
CONSTRUCTION
192
ROBUSTNESS DURING CONSTRUCTION
194
ROBUSTNESS DURING CONSTRUCTION
195
ROBUSTNESS DURING CONSTRUCTION
196
ROBUSTNESS DURING CONSTRUCTION
197
PHASE 1: PROGRESSIVE COLLAPSE
• Introduction
• Historical Events
• Associated Hazards
198
QUALITY ASSURANCE
Reinforced Concrete Buildings
during the 1999 Kocaeli Turkish
NO COLUMN STIRRUPS
Earthquake
(Non-application of standards
and poor quality
material/construction)
The collapse of many reinforced
concrete buildings during the
1999 earthquake in Turkey has
been attributed to designs which
were not carried out according to
the applicable standards and to
the poor quality of materials and
construction
199
QUALITY ASSURANCE
200
QUALITY ASSURANCE
Construction Poor material quality on site Test for quality. Reject poor quality.
Good suppliers.
Poor curing (where necessary) Good supervision and procedures. Well trained staff.
Badly applied protection Good supervision and procedures. Well trained staff .
measures
Poor connection of components Good supervision and procedures. Well trained staff
202
QUALITY ASSURANCE
Poor (too low or too high) Good supervision and procedures. Well
prestressing trained staff
203
APPENDIX
204
APPENDIX
205
APPENDIX
206
APPENDIX
207
APPENDIX
208
APPENDIX
209
•THANK YOU
210