07 - Progress Reporting Procedures
07 - Progress Reporting Procedures
FOR
SUR CONSTRUCTION PLC.
IMPLEMENTATION MANUAL
ABSTRACT……………………………………………………………………………………………..…. 1 - 1
MONITORING PERFORMANCE………………………………………………………………………...5 - 9
TREND FORECASTING….............................................................................................................. 9 - 9
ABSTRACT
TEAMS has prepared the manual on ‘Progress Reporting Procedures’ so that it can be of
assistance to SUR Construction Plc. This manual’s implementation on real time projects
would definitely result in fruitful outcomes.
It deals with vivid and easy-to-understand step-by-step progress reporting procedures for
construction projects. Care has been taken to develop all the details with respect to the
various requirements of SUR Construction Plc. Every stage of progress reporting is explained
by using a Template that is to be filled in with the help of Filling Instructions provided with it.
The template gives a perception of as to what exactly is to be done at a particular stage of
planning. The content of the template is thoroughly elaborated in Implementation Guidelines.
In order to make the project more user-friendly certain templates have also been propped up
with examples. These examples pave a way towards a better understanding and
implementation of the elements of manual.
Progress Reporting of Construction Projects can broadly be divided into two types:
1. Progress reports submitted to client (Project Management Information Reports)
2. Progress reports from site office to head office (Internal Reports)
In this manual, we covered first type (i.e. progress reports submitted to client). The manual
starts with the introduction of progress reporting system and then leads to compilation of
progress report.
Project Management Information Report can be divided into two phases
ü Performance Report this Period
ü Planned Progress next Period
Detailed templates of both phases have been explained in detail. TEAMS hopes that this
manual would fulfill the requirements of SUR Construction Plc., regarding their construction
projects, to the fullest degree.
In order to establish this reporting system you will want to look into the hundreds of
reports that are standard fare in project management software packages. Once you
decide what you want to track, these software tools will give you several suggestions and
standard reports to meet your needs. Most project management software tools allow you
to customize their standard reports to meet even the most specific needs.
(a) What are the short-term goals and long-term objectives assigned to the Responsibility
centre?
(b) What is the data needed to monitor the performance of these goals and objectives?
(c) How should this data be obtained from the initiators, viz. in a verbal or a written form?
(d) What should be the nature, format and frequency of reports to be submitted by each
control responsibility centre to the monitor?
(e) Is the data reported required for controlling the performance of other control centers?
If so, who should be asked to initiate the report?
(f) How accurate should each report be? The degree of accuracy will depend upon the
purpose of the report.
(g) Will the report initiator need additional assistance to submit the report? If so, what
and how much? (In particular, the stationery and printing requirements should also be
assessed.
(h) Can the report under consideration be eliminated, substituted, combined, rearranged
or simplified? This should be reexamined before finalization.
It is emphasized that there are no tailor-made formats for reporting the performance.
Generally, the contents of a report should show the performance goals in the form of
current and cumulative status. It should indicate variances from planned targets with
reasons. It should identify bottlenecks in achieving goals, and it should highlight the
aspects needing further action.
In particular, responsibility centers must not be loaded with paperwork. The reports
should be designed in such a manner that it reduces the recording effort. To quote an
example, the ‘daily activities time progress’ report should serve the following main
purposes:
(a) Makes the site supervisors pre-plan for the next day’s work including the allocation of
resources for each activity.
(b) Provides the following valuable data to the monitor and cost accountant in respect of
each current activity:
(1) State of time progress showing the dates of commencement and completion
activity-wise.
(2) Correlation of activity with resources deployed and consumed such as man-
day utilized for the completion of each activity and the corresponding
productivity achieved.
MONITORING PERFORMANCE
The performance monitoring process commences after the monitor receives the
appropriate performance data through site reports, personal visits and discussions. The
performance monitoring process can be divided into the following stages:
It is felt that depending upon the importance and complexity of the project, the status
evaluation of controlled parameters should be carried out immediately on receipt of the
concerned performance reports whereas the trend analysis based on the current plan can
process and it should be undertaken only when necessary.
It is important to note that effective monitoring depends upon the accurate and timely
reporting of the input data. Delays or distorted data lead to incorrect analyses. Similarly,
monitoring has no meaning if the feedback by the monitor is not given on time to the site
executives. Team spirit coupled with a sense of responsibility of all the participants can go
a long way to make monitoring effective.
As input activity managers and the project manager must report the progress made on all
of those activities that were open for work during the period of time covered by the status
report. Recall that your planning estimates of activity duration and cost were based on
little or no information. Now that you have completed some work on the activity, you
should be able to provide a better estimate of the work remaining to complete the activity.
That update information should also be provided.
b. Percent Complete
What was planned to be accomplished and what was actually accomplished are
two different things. Rather than disappoint the project manager activity
managers are likely to report that the planned work was actually accomplished.
Their hope is to catch up by the next report period. Hence, project managers
need to verify the accuracy of the reported data rather than simply accept it as
accurate.
ü Percent Complete
b. Percent Complete
Percent complete is the most common method used to record progress because
it is the way we tend to think about what has been done in reference to the total
job that is to be done. Percent complete isn’t the best method to report progress,
though because it is a subjective evaluation. What goes through someone’s mind
if you ask him or her “What percent complete are you on this activity?” The first
thing he or she thinks about this is most likely: “What percent should I be?”
followed closely by “What’s a number that we can all be happy with?”
Things actually going at the field are not exactly the same as what we planned
earlier. For example, we planned that we need 100 man-hours to complete the
activity. However; actually, 70 man-hours have already been used and activity is
only 50% complete.
d. Actual Cost
You need to update your cost too. Like resources, following four fields should be
updated:
3. Performance Analysis
The term ‘variance’ stands for the difference between the planned and the actual.
When associated with the parameter of a work -item or activity being controlled,
variances represent difference in planned and actual performance of the controlled
factors.
For example,
Sales revenue variance = Budgeted value of sales revenue - Actual revenue from sale
Variances when evaluated can be zero, plus or minus. Plus or zero value variances
are called favorable, and the minus value variances are termed unfavorable.
To quote an example, if the actual cost of a work -item is greater than the standard
cost, the work-item has an unfavorable variance.
On the other hand, the causes of variance which are beyond the control of the
management such as increase in labor wages due to labor legislation are called
uncontrollable.
(b) What are the controllable and the uncontrollable causes of variance?
(c) How to tackle controllable and uncontrollable variance and what are their
implications?
(d) Will the uncontrollable variance occur again? If so, when and what will be its
effect?
It may be noted that variance analysis presupposes that the work -item or activity
being analyzed is identifiable and measurable and therefore, each variance can be
considered an isolated item. However some of them may have interacting effects and
in such cases they should be analyzed in conjunction with others.
4. Trends forecasting
Understanding of same of the techniques and concepts given below can help in
producing a realistic forecast on future performance. There are no hard and fast rules
to state as to when and where technique will be used.
(a) Time forecasting techniques Network analysis and line-of –balance technique.
a) Updated Schedule
c) Payment Status
e) Progress Photographs
h) Equipment Deployed
a) Forecasted schedule
c) Material Requirement
d) Equipment Requirement
PROJECT BRIEF:
PROJECT SUMMARY:
PERFORMANCE OVERVIEW:
REMARKS: ________________________________________________________________
REMARKS: ________________________________________________________________
RECOMMENDATIONS:
What?
Progress overview presents status for a phase of a project, with emphasis on reporting completion
status of major tasks. This format can be used to give status on current phase or you can expand it to
include all major phases. You can reduce the level of detail in each phase and report on a smaller
number of major milestones. Some people prefer to leave out "percent complete".
This status report is a good summary for a team and functional managers. By providing planned and
actual start and end dates for the various tasks/milestones, it lets you see at a glance whether the
project is on schedule. It is not a complete picture for reporting to executives, because it does not
provide highly targeted information on issues they need to understand where to focus their attention to
assist the project. At most the Status or Comments column could be used to convey some of that
information
Why?
ü To ensure that the team has clear visibility to the true state of a project.
ü To ensure that management stays properly informed about project progress, difficulties, and
issues, by periodically getting the right kinds of information from the project manager.
ü The reports should let management know whether the project is on track to deliver its
outcome as planned, and must highlight to management any place where their decision-
making or direct help is needed.
How?
Review the included status report formats and select the one that seems most appropriate for your
needs, or create your own hybrid. Pay attention to the type and level of detail the report suggests.
Sometimes communication with management can be of low quality because too MUCH information is
provided, and busy executives can't determine what actions they need to take to help the project.
PROJECT BRIEF:
Project Name: Specify the name of project. The title should be same as mentioned in
Contract.
Project Code: Refer to Planning Procedures (Form No.CM/PBS-001)
Client Name: Specify the name of the owner/ funding agency of the project.
Consultants: Specify the name of main consultants of the project.
Project Manager: Designated Project Manager of SUR Construction Plc.
Project Cost: Specify the Contract Value of the Project
PROJECT SUMMARY:
PERFORMANCE OVERVIEW:
Project Status/ Percent Complete: Here we analyze the total performance of the project till to-
date by the bar charts and S-curves. This Percent
Complete is calculated with the weighted schedule and for
details refer CM-PRG-003 and also mention the over all
percent completion of the project by site monitoring
techniques.
Billing Status/ Work done to date: Here we analyze the billing status of the project till to date
by the bar charts and S-curves which can be as it will be
discus in detail under CM-PRG-003 and also mention the
over all billing percentage of the project by checking the
site bills
WBS: WBS stands for work breakdown standardization, in it we divide the activities of project
into several groups or in sub categories so that we can easily manage and control the
whole work. In this way the item work of project can be obtained in best and required
quality. In WBS one person is made responsible to an activity.
Deliverables: Deliverables means the main items mentioned in the BOQ (Bill of Quantities) in the
form of headings. For example if we take a road project then in it few of the possible
milestone can be excavation, embankment, sub-base preparation, base course, prime
coating, tack coat and etc. It also includes the starting and finishing of the project.
Or it can be defined as those items of works, which we have to deliver to the Clients.
Status / % Complete: The work completion data of different activities obtained by the site monitoring
is expressed in percentage (%), which would be helpful to check the work performance.
In this portion we write about the major deliverables, which are completed in this period of
time. This portion is just a summary of happenings during this period; details will be depicted
in CM-PRG-002.
In this portion we write about our planning that what we have to complete in next period. We
will list down the items / deliverables to be completed so to catch up the required progress.
This portion is just a summary for next period; details will be depicted in CM-PRG-010.
Any issue or problem faced in this period will be mention here or any pending issue will also
be discussed. The issues may be late arrival of drawings at site, poor designing, may be at
site there are unforeseen items, weather is creating hurdles, there is changing in drawings
from the Clients etc.
Issues that are pending and yet to resolve will also be mentioned under this item of progress
report. Apart of pending issues, remarks should be written,
RECOMMENDATIONS:
Here we discuss that how we can get rid of these issues. For example, if we are lagging
behind the schedule then will plan how to get rid of issues and make catch up plans.
What?
In this portion we write about the major deliverables, which are completed in this period of
time. This portion is just a summary of happenings during this period. Following documents
should be attached with progress this period;
CM-PRG-002 Updated Schedule
CM-PRG-003 Physical Work Done Status
CM-PRG-004 Updated Site Maps
CM-PRG-005 Construction Drawing Issuance Status
CM-PRG-006 Progress Photographs
CM-PRG-007 Material Consumption Status
CM-PRG-008 Equipment Deployed
CM-PRG-009 Human Resource Utilization
What?
Updated schedules are the graphical representation of project status. The actual updating technique
will vary depending upon the scheduling method selected. Bar charts provide for the recording of the
passage of time- as it passes.
How?
1. In order to update schedule on Microsoft Project, you need actual data from site. Refer to CM-
PRG-002-a (Information collection for updated schedule)
2. Update data on Microsoft Project
• If the scheduled finish date is before the date you enter, the task is considered
completed, and it is set to 100% complete.
• If the scheduled start date is before the date you enter and the scheduled finish date is
after the date you enter, the task is considered in progress. Microsoft Project calculates
the percentage of completion.
When you update task dates, Microsoft Project updates the % complete field. You can have
Microsoft Project calculate the approximate percentage of the task that has been completed as
of the date you enter in this dialog box. Alternatively, you can have it leave the percentage of
completion set to zero if the task is in progress or set it to 100 if the task is complete. Microsoft
Project also sets the actual start date, which indicates that the task is in progress.
Reschedule uncompleted work to start after Click this option to have Microsoft Project
reschedule work that remains to be done. This reschedules work by entering a new date for the
work.
If a task has not started by the specified date, the task has slipped. Microsoft Project
reschedules the work, setting the scheduled start date to your specified date and applying the
Start No Earlier Than constraint.
If the task is in progress but behind schedule, Microsoft Project schedules the remaining
duration to start on your specified date.
When you reschedule tasks with this option, Microsoft Project sets the Stop and Resume fields.
The date of last reported progress is placed into the Stop field, and your specified date for
rescheduling is placed in the Resume field.
Update actual work: You can track actual work by period using the time phased fields in
Microsoft Project. With this method, you can enter work for a particular day or week in your
schedule.
• On the View menu, click Task Usage.
• On the Format menu, point to Details, and then click Actual Work.
• In the time phased portion of the view, in the Act. Work field, type the actual work of each
assigned resource.
Update actual duration: You know the number of days a task has been in progress and if it is
progressing as planned, you can track progress by entering the duration that the resource has
been working on the task.
When you enter the actual duration of a task, Microsoft Project updates the actual start date,
the task's percentage of completion, and the duration of the task remaining in the schedule.
PROJECT BRIEF:
PROJECT SUMMARY:
What?
Physical work done status is used to measure project performance and, by tradition, uses the dollar
value of work as metric. Actual work performed is compared against planned and budgeted work
expressed in these equivalents. These metrics are used to determine schedule and cost variances for
both the current period and cumulative to date. Cost is not a good objective indicator with which to
measure performance or progress. While this is true, there is no other good indicator. Given this we
are left with dollars, which we are at least familiar working with in other contexts. Either one by itself
does not tell the whole story. We need to relate them to one another.
One drawback that these metrics have is that they report history. Although they can be used to make
extrapolated predictions for the future, they primarily provide a measure of the general health of the
project, which the project manager can correct as needed to restore the project to good health.
80
% Complete
Update Date
60
40
Variance
20
0
0 30 60 90 120 150 180
Time
Planned Work Done Curve Actual Work Done
Above figure shows an S-Curve, which represents the baseline progress curve for the original project
plan. It can be used as a reference point. You can compare your actual progress to date against the
curve and determine how well the project is doing.
By adding the actual progress curve to the baseline curve, you can now see the current status versus
the planned status. Above figure shows the actual progress curve to be below the planned curve. If
this represented dollars, we might be tempted to believe the project is running under budget.
How?
EXAMPLE CONTINUED
Today is day No. 60; following data has been collected from site office
E Compaction 0 sft NA NA 0%
F Carpeting 0 sft NA NA 0%
TOTAL 29.65 %
1 10
Site Layout Planned
1 10
Actual
11 50
Cut and Fill
11 55
Grading 31 60
31 80%
41 100
Sub Base
51 6.67%
Compaction 81 120
100 100.00
85.24
80
70.47
% Complete
60
50.26
40 38.06
Variance =8.41 %
29.65
behind schedule
20
9.18
0 -
0 30 60 90 120 150 180
Day No.
What?
As Site Maps are basic component of the Progress Report, we can easily analyze the over all project
progress by single glance.
Existing site maps which is usually drawn on Auto CAD is updated to know about the appropriate
progress of the project till this period. For example if we consider a road project then first we draw the
proposed plan road, marked the bridges, culverts and drains etc. on the CAD drawing by using single
color e.g. red for roads, blue for bridges, green for culverts and orange for drains. Each of the
respective is updated by highlighting it in yellow color.
Legend should be shown in drawing for the guidance of the reader. These legends should be at
prominent and identifiable place. The map must be on scale with proper boarders. If project is divided
into sectors then each sector must be clearly marked with its specified boundary lines. These Site
maps should be updated timely.
What?
In most of the projects (especially in fast track projects), construction drawings are submitted as work
begins. The issuance of these construction drawings is very important to execute the work. If these
drawings do not issued to contractor on-time, project will definitely get late. A separate schedule
should be prepared by consultants for issuance of construction drawings. Although, issuance of
drawings is a sole responsibility of consultants, contractor should record the dates of issuance of
construction drawings. This record may be used to defend the progress of work, if consultants fail to
issue drawings on-time.
How?
Drawing Issuance Status should record in the form of log of drawing showing the dates of issuance of
drawings. This log must also have drawing number, work package, date of submission of drawings at
site office, remarks (means if any change or amendments is made by the Client or Head office) e.g. if
we consider a building project then it can be divide into work packages like civil works, electrical
works, plumbing works etc. it became more convenient to separately deal the drawings under there
respective package and thus casing less chance of miss placing of drawings. The drawing should be
kept in files in descending order, means drawing # Civil/B –03 is to be placed over drawing # Civil/B-
02. Before issuance of drawing to any of the concerned person at site the drawing log status must be
signed by the respective person and drawing log in charge
PROJECT BRIEF:
Date of Forwarded/
S. No. Drawing No. Drawing Title Revision Status Remarks
Issue Issued to
PROJECT BRIEF:
Client Name: Specify the name of the owner/ Consultant Name: Specify the name of main Project Cost: Specify the Contract Value of the
funding agency of the project consultants of the project. Project
Date of Forwarded/
S. No. Drawing No. Drawing Title Revision Status Remarks
Issue Issued to
Specify if
this
drawing is
a new one Specify if this
Specify the or a drawing is
As written on
date of revised “for review”,
the bottom of
issue. version of “for
drawing. Specify if you
Ensure that previously construction”,
Usually issue the copy
As written in the title block of the date on issued “Tender
e.g. consultants of drawing to
drawing. E.g. Master Plan, receiving drawing. drawing” etc.
1,2,3 have their vendor,
Pavement Area etc. stamp For New This
own subcontractor,
should Drawing information is
nomenclature. etc.
match the write- also written
E.g.
date of “Rev 0” on the bottom
# Civil/B –03
issue and of each
increase it drawing.
as
revision
increases.
What?
The job photo record begins with the preconstruction photo survey. Ongoing construction photographs
are the subject of this section. They are divided into regular progress photos and those required in
special situations. There should always be a camera on-site and ready. Whenever there is any
situation involving a significant question or the potential for changes, problems, etc., taking a photo of
the area before any further discussion and certainly before the area becomes further disturbed must
become the habit of the field staff. Film will always be the least expensive but most powerful agent of
every negotiation, resolution, and settlement effort.
Resist the temptation to use wide-angle lenses in all photographs. While they make it easier to get
more into the picture, they distort shapes, relative sizes, and perspectives. Remember that the
objective is to provide an accurate record. Use lenses with "normal" focal lengths, and your photos will
remain truer representations of reality.
As the use of digital photography has become more common, so too has the proliferation of various
electronic record keeping systems that can best make use of the digital technology. In such systems,
the regular project photographs and special photographs can be stored and organized in easily
retrievable electronic systems. The photo record for the entire project can in many cases be burned
onto a single CD. The photos can then be keyed either directly or through some database program
linking the photographs to other key project information. Such links can include correlations between
photographs and electronically filed Daily Field Reports, Meeting Minutes, and almost any other
component of the official project record.
The major problem with digital photography may rest in the photographic resolution of the
photographs themselves. If digital cameras are used that have relatively moderate to low levels of
photographic resolution, the use of the photographs may become limited. If, for example, a 400-dpi
format is used, 3" x 5" or 5" x 7" digital photographs would probably be of an acceptable resolution for
documentation and even presentation. If, however, that same photograph is to be significantly
enlarged (as would be desirable for presentation in litigation or arbitration), the low level of resolution
may quickly render the photographs unusable for such a purpose. Because of this, reconsider any
thought of using a moderately priced digital camera that does not create photographs with an
acceptable resolution. Spend the money up front on the proper equipment that will produce
photographs with the highest possible resolution, and the equipment will pay large dividends in many
forms for a very long time.
How?
The remainder of this section discusses photographs in conventional (film/print) format. Given your
decision on the use of digital photographic equipment, the entire section can be applied as it is in
either case.
In these kinds of events, fast action is necessary to gain the maximum advantage possible. A
"precondition" photo or series of photos will be the best record to confirm the actual state of affairs
prior to a changed work sequence.
If the duration of the anticipated sequence or activity is relatively long, progress photos of the specific
sequence should be taken.
An "instant" camera may prove to be a valuable addition to the project photo effort. Again, it is to be
used as a supplement and can only become a substitute for better-quality photos in the simplest of
situations (a cleanup back charge?).
The principal advantages of instant pictures are that they immediately display the specific information
that has been recorded in the photo. It is therefore immediately evident if your photos indicate
everything intended, or if additional photos, perhaps from other angles, will be necessary. This may
be particularly important if conditions are likely to change quickly, leaving little time for conventional
photos to be reviewed. Even so, one-hour developing is becoming readily available.
Special photographs are, however, taken for a specific purpose and must be so identified. In the worst
conditions of arbitration or litigation, each photo must be properly and completely identified along strict
criteria. If it is not, even the best photo will not be allowed consideration. Even if the photo's uses will
not become so extreme, references to special photos most often come at points in time long after the
original incident. Memories fade, orientations get confused, and so on.
It is therefore important that each significant photo be properly identified if it is to be used to support a
charge, contention, or any special circumstance.
Using the Sample Photograph layout Form (Template- CM-PRG-006) that follows will guarantee that
each photo that will immediately or eventually be used in any presentation or as support for any kind
of charge or contention will be correctly identified with:
1. Name of project and Owner, Company project number
2. Photo location, area identification
3. Photo orientation, direction of view
4. References to any appropriate correspondence, field reports, or anything else that ties it
directly to the detailed project record
PROJECT BRIEF:
Location_______________________________________________________________________
Remarks: _____________________________________________________________________
_____________________________________________________________________________
Place Photos / Assign numbers to multiple photos / Attach this form to large photos.
What?
Material accounting system documents the material data. It provides the material consumption status.
Project stakeholders are especially concerned with material-data for ensuring the timely procurement
of materials, and site availability of materials of right quantity and quality at the required time and
place. They also aim at minimizing wastage during usage, evaluating implications of variation from the
acceptable wastage standard, updating cost estimates and expenditure of materials, and formulating
materials costing norms for future works.
The materials accounting process from the demand initiation till its consumption stage involves
maintenance of up-to-date record of receipts and issues at the project central store, monthly stock
checking of materials in the store and at the work site, and the return of the unused materials after
completion of the intended job.
How?
PROJECT BRIEF:
PROJECT BRIEF:
Client Name: Specify the name of the owner/ Cons ultant Name: Specify the name of main
funding agency of the project consultants of the project.
Project Manager : Designated Project Manager Project Cost: Specify the Contract Value of the
of SUR Construction Plc. Project
Work Period : From Start date of this period to Finish date of this period
What?
In construction, some tasks are labor intensive, some predominantly employ equipment, and some
use a combination of both, i.e. labor and equipment. While the actual work done and associated labor
is accounted for by the foreman concerned, the equipment productivity control is undertaken to
determine its employment time, the output achieved, and its productivity at site.
This information must be a part of progress report. From this information, we can easily evaluate the
progress of work done and the reason of delays.
How?
PROJECT BRIEF:
PROJECT BRIEF:
Client Name: Specify the name of the owner/ Cons ultant Name: Specify the name of main
funding agency of the project consultants of the project.
Project Manager : Designated Project Manager Project Cost: Specify the Contract Value of the
of SUR Construction Plc. Project
Work Period : From Start date of this period to Finish date of this period
Total Days: Specify the total days of period, e.g. in a month there are 30 days
PROJECT BRIEF:
MANAGEMENT STAFF:
Present at
S.
Name of Personnel Designation Site Remarks
No.
(Days)
LABOR/ OPERATORS:
Deployed
S. Total
Type of Labor Qty Remarks
No. Man days
(Nos.)
PROJECT BRIEF:
Client Name: Specify the name of the owner/ Cons ultant Name: Specify the name of main
funding agency of the project consultants of the project.
Project Manager : Designated Project Manager Project Cost: Specify the Contract Value of the
of SUR Construction Plc. Project
Work Period : From Start date of this period to Finish date of this period
MANAGEMENT STAFF:
Present at
S.
Name of Personnel Designation Site Remarks
No.
(Days)
Specify the Specify the reason of absence
designation
of person. Attendance
Surveyor, period
Supervisor,
Foreman etc
LABOR/ OPERATORS:
Deployed
S. Total
Type of Labor Qty Remarks
No. Man days
(Nos.)
Specify the
calculated
man days of
labor. E.g. 2
masons were
present for
first 10 days,
Specify
4 masons
average
were present
Specify the type of labor/ numbers of
for next 10
operator. E.g. Mason, Helper, labors
days and 5
Mixer Operator, etc. deployed
masons were
during this
present for
period
last 10 days
of month.
days are
10*2 + 10*4 +
10 *5 = 110
Man days
What?
In this portion we write about the major deliverables, which we plan to complete next period.
This portion will be a summary of happenings next period. Following documents should be
attached with forecasting;
CM-PRG-010 Forecasted Schedule
CM-PRG-011 Material Requirement
CM-PRG-012 Equipment Requirement
CM-PRG-013 Human Resource Requirement
What?
Forecasted schedules are the graphical representation of anticipated project finish date. In this bar
chart, planned bars are compared with the actual bars and forecasted bars.
How?
Today is day No. 60; following data has been collected from site office
E Compaction 0 sft NA NA 0%
F Carpeting 0 sft NA NA 0%
TOTAL 29.65 %
1 10
Site Layout Planned
1 10
Actual
11 50
Cut and Fill
11 55
Grading 31 60
31 80%
41 100
Sub Base
51 6.67%
Compaction 81 120
Total Quantity “A” Job 10,000 cft 15,000 cft 15,000 cft
Achieved Quantity “B” 100 % 10,000 cft 12,000 cft 1,000 cft
Total Duration 40 80
1 10
Site Layout Planned
1 10
Actual
11 50
Cut and Fill Forecasted
11 55
Grading 31 60
31 80%
68
41 100
Sub Base
51 6.67%
200
Compaction 81 120
181 220
PROJECT BRIEF:
PROJECT BRIEF:
PROJECT BRIEF:
MANAGEMENT STAFF:
S.
Name of Personnel Designation Responsibilities
No.
LABOR/ OPERATORS:
What?
Forecasted work done graph is the comparison of Actual work performed against planned and
budgeted work and extrapolation of behavior of project’s progress.
100
Update Date
80
% Complete
60
40
20
0
0 30 60 90 120 150 180 210 240 270 300
Time
Planned Work Done Curve Actual Work Done Forecasted Graph
Above figure shows an S-Curve, which represents the baseline progress curve for the original project
plan. It can be used as a reference point. You can compare your actual progress to date against the
curve and determine how well the project is doing.
By adding the actual progress curve to the baseline curve, you can now see the current status versus
the planned status. Above figure shows the actual progress curve to be below the planned curve. If
this represented dollars, we might be tempted to believe the project is running under budget.
How?
EXAMPLE CONTINUED
Today is day No. 60; following data has been collected from site office
E Compaction 0 sft NA NA 0%
F Carpeting 0 sft NA NA 0%
TOTAL 29.65 %
1 10
Site Layout Planned
1 10
Actual
11 50
Cut and Fill Forecasted
11 55
Grading 31 60
31 80%
68
41 100
Sub Base
51 6.67%
200
Compaction 81 120
181 220
DAY 60 DAY 90 DAY 120 DAY 150 DAY 180 DAY 210 DAY 240 DAY 270 DAY 280
TOTAL 26.5 % 36.74 % 40.67 % 44.6 % 48.54 % 63.17 % 80.3 % 95.06 % 100 %
100
Update Date 100
95.06
80
80.3
% Complete
60
63.17
48.54
40 44.6
40.67
36.74
20 26.5
0
0 30 60 90 120 150 180 210 240 270 300
Time
Planned Work Done Curve Actual Work Done Forecasted Work Done