Company IREKA ENGINEERING AND CONSTRUCTION Prepared by : Mohd NOORHISHAM BIN MOHD RAMLI
SDN BHD. (Safety and Health Officer).
Process / Location OT2 PARCEL C
Approved by: MR CHAN HUAN CHOONG Date: 20 SEPTEMBER 2016
(Name , designation) Project Manager
Date 20 SEPTEMBER 2016 Reviewed date: Rev. :
WORKPLACE : OT2 PARCEL C KL ECOCITY
ACTIVITY : AIR CONDUCTIONING & MECHANICAL VENTILATION (ACMV)
RISK RATING
SEQUENCE OF JOB HAZARD POTENTIAL RISK CONTROL MEASURE/
GROUP & POTENTIAL HAZARD Prob Sev. Total RECOMMENDATION
(P x S)
Delivery of Material * Mechanical -Minor injury -Workers stay away from moving vehicle/ lorry.
Loading and unloading material Struck by moving part of vehicle. -Damage to property 2 2 4
* Physical -Minor injury -Supervised by designated person during shifting of
Struck/ hit by moving part of 2 2 4 material.
material during shifting activity
(manual handling)
*Physical (Ergonomic) -Negligible injury -Manual handling/lifting should be carry out with
Spine injury - Improper method 2 2 4 correct method.
of handling (refer to method statement)
* Physical -Minor injury -Supervised by designated person during lifting of
Struck/ hit by moving part of 2 2 4 material.
material during lifting activity
(by tower crane)
Stacking/ Storing material. * Physical -Fatality/serious injury -Workers stay away from lifting area.
Falling object (during lifting of -Damage to property 2 4 8
material)
* Physical -Fatality/serious injury -Supervised by designated person during stacking of
Slip/ fall/ collapse of material due -Damage to property 2 4 8 material.
to poor material arrangement. - Routine checking to ensure stability of material.
-To ensure material not obstructing any access way.
-To provide wedge.
Erection of working platform *Physical (Ergonomic) -Negligible injury -Manual handling/lifting should be carry out with
Improper method of handling 2 2 4 correct method.
activity -Scaffolding for working platform are erecting by
experience workers.
-Proper mobile scaffold i.e. stopper for tyre, G.I pipe
for mobile support.
* Physical -Serious injury -Provide proper working platform for workers.
Workers slip and fall 2 3 6 -Plank min. 600mm wide/ cat walk.
Fabrication of pipe * Physical -Serious injury -To ensure hand-tool in good condition.
(Ducting work) Hit by hand-tool 2 3 6
Installation of support bracket and pipe * Physical -Fatality/ serious injury -Provide proper working platform for workers.
Workers slip and fall 2 4 8 -No worker shall be allowed to be on the working
platform while shifting/ mobilise the mobile scaffold.
* Physical -Fatality/ serious injury -To ensure power tool in good condition before used.
Electrical shock (drilling activity) 2 4 8 -Electrical wire shall hang-up and not obstruct
walkway.
* Chemical -Serious injury (long term -Provide dust collector/ dust mask
Inhalation of cement dust during can impair workers lung) 3 3 9
drilling activity.
Painting work * Chemical -Serious injury -Workers must wear suitable PPE i.e air protector etc.
Inhalation (long term can effect 3 3 9
human respiration system)
* Chemical -Serious injury (long tern -Workers must wear suitable PPE i.e glove.
Skin contact with paint/ thinner can impair worker skin/ 3 3 9
dermatitis)
* Physical (Ergonomic) -Negligible injury -Material handling should be carried out with correct
Redundant repeated working 3 1 3 method.
behavior. -Take a 2-3 minutes rest after every 2(two) hours.
Activity carried out by : Prepared by : Approved by :
Location of activity : Name :
Date :