Concurrent Delays and Time Extension in Construction Contracts Claims
Concurrent Delays and Time Extension in Construction Contracts Claims
FACT OR FICTION?
LINA ZUREIKAT
Manager – Claims and Disputes Resoltuion
Construction Management Associates (CMA)
MSc C.E, LLM, MRICS, FCIArb, FCIOB
EXPERIENCE
14 years experience
Contract Administration
Claims Preparation and Response to Claims/ Claims Rebuttal
Provide Expertise in Delay Analysis/Quantum in Arbitration
RECENT PROJECTS
EXPO 2020
King Abdulaziz International Airport –Jeddah
King Khaled International Airport - Riyadh
Shangri La Hotel Tower –Jeddah
CONCURRENT DELAYS AND TIME EXTENSION IN CONSTRUCTION
CONTRACTS CLAIMS
TIME IN CONSTRUCTION
Delay is the time during which some part of a construction has been extended
beyond what was originally planned due to circumstance impacting on the
project.
CONCURRENT DELAYS AND TIME EXTENSION IN CONSTRUCTION
CONTRACTS CLAIMS
Liability Timing
Third
Employer Contractor
Party Concurrent Non-Concurrent
Type Compensability
The occurrence of two or more delay events at the same time, and
One is the responsibility of the Contractor and the other is the responsibility of
the Employer, and
For concurrent delay to exist each of the Employer Risk Event and the Contractor
Risk Event must be an effective cause of delay to completion.
Period of project overrun caused by two or more effective causes of delay (one is
caused by the Employer and one is caused by the Contractor) of approximately equal
causative potency.
True concurrent delay is the occurrence of two or more delay events at the same
time, one an Employer Risk Event, the other a Contractor Risk Event and the effects
of which are felt at the same time.
a) The first Relevant Event is assessed to determine whether it was critical, and
b) The second Relevant Event is similarly assessed ignoring the existence of the
first one.
2. The critically of the two events is assessed taking into consideration all
circumstances.
CONCURRENT DELAYS AND TIME EXTENSION IN CONSTRUCTION
CONTRACTS CLAIMS
Scenario 1
As-Built
Contractor Delay
As-Built ''but for'' Contractor Delay
Employer Delay
No Concurrency
CONCURRENT DELAYS AND TIME EXTENSION IN CONSTRUCTION
CONTRACTS CLAIMS
Scenario 2
Plan Time For Completion
As-Built
Critical Delay
As-Built ''but for'' Employer Delay
Contractor Delay
As-Built ''but for'' Contractor Delay
Employer Delay
Scenario 3
As-Built
Critical Delay
As-Built ''but for'' Employer Delay
Contractor Delay
As-Built ''but for'' Contractor Delay
Employer Delay
period of concurrency
Concurrency Exists
CONCURRENT DELAYS AND TIME EXTENSION IN CONSTRUCTION
CONTRACTS CLAIMS
Example 1:
Example 2:
Example 3:
Contractor would
Contractor be entitled
Entitled to a one-week
to a Two-Week Extension of Time
extension of time
CONCURRENT DELAYS AND TIME EXTENSION IN CONSTRUCTION
CONTRACTS CLAIMS
Example 4:
Example 5:
Malmaison Approach
“if there are two concurrent causes of delay, one of which is a Relevant Event and
the other is not, the contractor is entitled to an extension of time for the period of
delay caused by a Relevant Event notwithstanding the concurrent effect of the other
event”.
FACTUAL CAUSATION
The breach by the defendant must in fact be the cause of the harm suffered by
the claimant. Otherwise the claim will fail.
It has to be established that but for the breach the harm would not have
occurred.
CONCURRENT DELAYS AND TIME EXTENSION IN CONSTRUCTION
CONTRACTS CLAIMS
Requires a claimant to show what part of the claimed loss has been caused
solely by the defendant in order for substantial damages to be recovered in
respect of it.
Chances for the contractor to be compensated for damages are very low.
CONCURRENT DELAYS AND TIME EXTENSION IN CONSTRUCTION
CONTRACTS CLAIMS
Approach was approved in City Inn Ltd v Shepherd Construction Ltd [2007]
C.S.O.H. 190
If there are two concurrent causes of loss, the Claimant succeeds if he establishes
that the cause for which the Defendant is responsible is the dominant cause.
A contractor must show causation in the sense that on the balance of probabilities,
and by using common sense, the relevant matter relied upon was the “dominant”
cause of the postulated loss.
Does not resolve the problem where there is no one dominant cause.
CONCURRENT DELAYS AND TIME EXTENSION IN CONSTRUCTION
CONTRACTS CLAIMS
Concurrency Under
United Arab Emirates Civil Code
CONCURRENT DELAYS AND TIME EXTENSION IN CONSTRUCTION
CONTRACTS CLAIMS
Article 290
“it shall be permissible for the judge to reduce the level by which an act has
to be made good or to order that it need not be made good if the person
suffering harm participated by his own act in bringing about or aggravating
the damage”.
Article 291
“If a number of persons are responsible for a harmful act, each of them shall
be liable in proportion to his share in it, and the judge may make an order
against them in equal shares or by way of joint or several liability”.
Article 246(1)
“The contract must be performed in accordance with its contents, and in a
manner consistent with the requirements of good faith.”
CONCURRENT DELAYS AND TIME EXTENSION IN CONSTRUCTION
CONTRACTS CLAIMS
Article 106
“A person shall be held liable for an unlawful exercise of his rights.”
Article 390(2)
“The judge may in all cases, upon the application of either of the parties, vary
such agreement so as to make the compensation equal to the loss, and any
agreement to the contrary shall be void.“
CONCURRENT DELAYS AND TIME EXTENSION IN CONSTRUCTION
CONTRACTS CLAIMS
Delays must occur at the Same time Delays need only occur within the
same period of analysis
More compensation for both parties Less compensation for both parties
CONCURRENT DELAYS AND TIME EXTENSION IN CONSTRUCTION
CONTRACTS CLAIMS
FUNCTIONAL APPROACH
Two or more delays that are unrelated, independent, and on the critical path of
the project;
Two or more delays that are the contractual responsibility of different parties,
but one may be a force majeure event;
Impacted As Planned
CONCURRENT DELAYS AND TIME EXTENSION IN CONSTRUCTION
CONTRACTS CLAIMS
An Additive/Modelled Technique
1. List all identified delay events in a table with the start and end dates,
durations, predecessors and successors.
2. Assess the liability for each delay event based on circumstances and contractual
obligations.
4. Tabulate the data-dates and the projected completion date of each of the base
programs prior to inserting any of the delay events.
5. Convert each delay event to a new subset of activities, or ‘fragnet’, complete with
estimated durations and identified predecessor and successor activities in the
base program.
7. The calculated change to the completion date (loss or gain) for each
successive delay event is tabulated and inserted chronologically into the table.
Event
Event
Finish Impacted
Completion Event Event Event start date
Window Data Date date in Duration Completion Loss/Gain
Date Description Start date finish date in current
current Date
window
window
CONTRACTOR CAUSED DELAYS
UD01
UD02
UD03
EMPLOYER CAUSED DELAYS
UD01
UD02
UD03
CONCURRENT DELAYS AND TIME EXTENSION IN CONSTRUCTION
CONTRACTS CLAIMS
8. Cumulative loss, or gains, are determined for EDE, CDE and concurrent periods.
B aseline Plan
Delay is a direct result of keeping pace with delays caused by the other party,
thus triggering a claim for a compensable extension of time.
CONCURRENT DELAYS AND TIME EXTENSION IN CONSTRUCTION
CONTRACTS CLAIMS
DIRECT PACING
Conduit Installation
FF 5
Wire Pulling
As-Planned SS 5
Conduit Installation
As-Built FF 5
Wire Pulling
SS 5
INDIRECT PACING
Original Completion
Data Date As Planned Schedule - Duration 55 W Date
20W Ducting
15W
INDIRECT PACING
Actual Completion
Data Date As- Built Schedule - Duration 70 W Date
15W