MSC Dissertation
MSC Dissertation
net/publication/272790556
CITATIONS READS
0 784
1 author:
Bélal Almassri
Palestine Polytechnic University
16 PUBLICATIONS 64 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
A FEM model to study the behaviour of corroded RC beams shear-repaired by ETS FRP rods technique View project
Experimental and Numerical study of strengthening and repairing of continuous RC beams using Near Surface Mounted Reinforcement (NSM) View project
All content following this page was uploaded by Bélal Almassri on 25 February 2015.
Signature: Date:
I
ACKNOWLEDGEMENTS
I want to express my sincere gratitude to my supervisor Dr. Songdong Shao for his valuable,
professional supervising and guiding my research. In particular, I have appreciated that he let
me to follow my own path during my research project.
II
ABSTRACT
Numerical Modelling is one of the most information-dependent researches compared to other
sectors. Computers have been used to improve the efficiency of management in most of the
engineering projects including the disaster recovery processes. Treating information
efficiently is the key to maintain a high degree of the security for all of the engineering
projects.
This research presents the numerical analysis of different simulation cases related to different
types of modelling tests using two of the leading softwares in the river modelling field which
are the ISIS and the HEC-RAS, these cases present two of the dam failure tests, the
simulation of the river flood, the dry bed river and the sinusoidal oscillation case. This
research gives also fully understanding steps for the two softwares from the starting up of the
programs and finishing with the results and the discussions. The research also highlights a
comparison of the results of this research and other results from previous researches then it
highlights a comparison between the ISIS and the HEC-RAS in order to decide which one is
more efficient, faster and more reliable than the other.
From the simulation analysis done in this research it presents some more advantages in the
HEC-RAS which they are not exist in the ISIS however the ISIS can be more efficient and
gives more reliable results if a different type of simulation cases were applied or different
size of data has been inserted into the programs so for these reasons this research suggests
more investigations to be done in the future studies before carrying on the simulation
processes with different types of cases and large amounts of data in order to decide which
software is more efficient than the other.
Keywords: ISIS; HEC-RAS; Steady State Analysis; Unsteady State Analysis; Upstream
Boundary Condition; Downstream Boundary Condition; Flow Hydrograph; Stage
Hydrograph.
III
Table of Contents
STATEMENT OF ORIGINALITY…………………………………………………………………... .. I
ACKNOWLEDGEMENT …………………………………………………………….. .......................II
ABSTRACT………………………………………………………………………… ......................... III
Table of Contents………………..…………………….………………………… .............................. IV
List of Abbreviations …………………………………………………………. .................................. VI
List of Tables…………………..………………………………………………. ................................. VI
List of Figures…………………………………………………………...……... ............................... VII
Chapter 1: Introduction ......................................................................................................................... 1
1.1 General Introduction ....................................................................................................................... 1
1.2 Research problem ........................................................................................................................... 1
1.3 Research aims ................................................................................................................................. 1
1.4 Research layout ............................................................................................................................... 2
Chapter 2: Literature Review ................................................................................................................ 4
2.1 River flood events and factors causing floods ................................................................................. 4
2.1.1 River flooding factors .............................................................................................................. 4
2.1.2 Maximum floods records around the world.............................................................................. 5
2.1.3 Sample of the flood hazard assessment (United Kingdom) ...................................................... 5
2.2 Dam failure background.................................................................................................................. 6
2.2.1 Definitions and meanings ......................................................................................................... 6
2.2.2 Historical background of dam failures ..................................................................................... 9
2.2.3 Factors of dam failures ........................................................................................................... 10
2.2.4 Risk study assessment ............................................................................................................ 12
2.3 Benefits of numerical model ......................................................................................................... 15
2.4 Selection of the software and its user guide .................................................................................. 16
2.4.1 Starting ISIS and basic concepts ............................................................................................ 16
2.4.1.1 Introduction to ISIS ......................................................................................................... 16
2.4.1.2 Basic concepts of ISIS..................................................................................................... 18
2.4.1.3 Design simple single river channel and view the results ................................................. 19
2.4.1.4 Dam breaks analysis using ISIS application .................................................................... 24
2.4.2 Starting HEC-RAS and basic concepts .................................................................................. 25
2.4.2.1 Introduction to HEC-RAS ............................................................................................... 25
2.4.2.2 Basic concepts of HEC-RAS........................................................................................... 25
2.4.2.3 Design simple single river channel and view the results ................................................. 26
Chapter 3: Methodology ..................................................................................................................... 30
IV
3.1 Research Methodology ................................................................................................................. 30
3.2 Simulation Cases Selection ........................................................................................................... 30
3.3 Research Methodology Flowchart ................................................................................................ 31
3.4 Dual Software System Selection ................................................................................................... 32
3.5 Verification of the Simulation Results .......................................................................................... 32
3.6 Methodology of the Flow Analysis and Results ............................................................................ 33
Chapter 4: Simulation Analysis & Discussion .................................................................................... 34
4.1 Case 1: Simulation of the dam breaks as a sluice gate opening abruptly through the dam ............ 34
4.1.1 General description ................................................................................................................ 34
4.1.2 Test case 1 using the ISIS ...................................................................................................... 35
4.1.3 Toce river dam break test using ISIS ..................................................................................... 42
4.1.4 Test case 1 using the HEC-RAS............................................................................................. 45
4.2 Case2: Malpasset dam-break test .................................................................................................. 54
4.2.1 General description ................................................................................................................ 54
4.2.2 Test case 2 using ISIS ............................................................................................................ 55
4.2.3 Test case 2 using HEC-RAS .................................................................................................. 60
4.2.4 Comparison between the results obtained from the ISIS, the HEC-RAS and the results
obtained from the journal ................................................................................................................ 63
4.3 Case 3: Sinusoidal Oscillation ...................................................................................................... 64
4.3.1 General description ................................................................................................................ 64
4.3.2 Test case 3 using ISIS ............................................................................................................ 65
4.3.3 Test case 3 using HEC-RAS .................................................................................................. 72
4.3.4 Comparison between ISIS and HEC-RAS ............................................................................. 77
4.4 Case4: Dry River with constant flow discharge ............................................................................ 78
4.4.1 General description ................................................................................................................ 78
4.4.2 Test case 4 using ISIS ............................................................................................................ 78
4.4.3 Test case 4 using HEC-RAS .................................................................................................. 85
4.4.4 Comparison between ISIS and HEC-RAS ............................................................................. 88
4.5 Case 5: Simplified dynamic model for flood routing in rectangular cross sections channels ........ 89
4.5.1 General description ................................................................................................................ 89
4.5.2 Test case 5 using ISIS ............................................................................................................ 90
4.5.3 Test case 5 using HEC-RAS .................................................................................................. 95
4.6 Comparison highlight between ISIS and HEC-RAS ..................................................................... 99
4.6.1 Comparison highlight between ISIS and HEC-RAS according to the cases observations ...... 99
4.6.2 Comparison between ISIS and HEC-RAS according to the CPU time ................................ 100
Chapter 5: Conclusions, Recommendations and Future work ........................................................... 101
V
5.1 Conclusions................................................................................................................................. 101
5.1 Recommendations and future work ............................................................................................. 102
List of Abbreviations:
EDF: Electricite de France.
EPRI: Electric Power Research Institute.
FERC: Federal Energy Regulatory Commission’s.
HEC-RAS: Hydrologic Engineering Centres River Analysis System.
ICOLD: International Commission on Large Dams.
NRCS: Natural Resources Conservation Service.
PMF: Probable Maximum Flood.
PRA: Portfolio Risk Assessment Methodology.
RAM-D: Risk Assessment Methodology of Dams.
List of Tables:
Table 2. 1 Historical dams failures (Chanson, 2009) .......................................................................... 10
Table 2. 2 Files Types in ISIS ............................................................................................................. 19
Table 4. 1 Dam Information ................................................................................................................ 37
Table 4. 2 Upstream boundary conditions ........................................................................................... 42
Table 4. 3 Gate data ............................................................................................................................ 56
Table 4. 4 Assumed parameters .......................................................................................................... 64
Table 4. 5 Assumed parameters .......................................................................................................... 78
Table 4. 6 Distances between sections ................................................................................................ 89
Table 4. 7 CPU Elapsed Time ........................................................................................................... 100
VI
List of Figures:
Figure 1.1 Research Layout .................................................................................................................. 3
Figure 2. 1 Dam Classification ............................................................................................................. 8
Figure 2. 2 Dam Failure Causes .......................................................................................................... 12
Figure 2. 3 Dams Risk Assessment ..................................................................................................... 14
Figure 2. 4 Implicit method (Anderson, 1995) .................................................................................... 16
Figure 2. 5 Implicit method matrix (Anderson, 1995)......................................................................... 17
Figure 2. 6 ISIS main interface ........................................................................................................... 18
Figure 2. 7 Node Label Editor ............................................................................................................ 19
Figure 2. 8 Upstream boundary condition ........................................................................................... 20
Figure 2. 9 Connect the labels (ISIS) .................................................................................................. 20
Figure 2. 10 River Section Details ...................................................................................................... 21
Figure 2. 11 Downstream boundary condition .................................................................................... 22
Figure 2. 12 ISIS Visuilizer ................................................................................................................ 22
Figure 2. 13 Simulation Analysis (ISIS) ............................................................................................. 23
Figure 2. 14 Time Sereis Sample (ISIS).............................................................................................. 24
Figure 2. 15 HEC-RAS main interface ............................................................................................... 26
Figure 2. 16 Open a new project (HEC-RAS) ..................................................................................... 26
Figure 2. 17 Enter the geometric Data Button ..................................................................................... 27
Figure 2. 18 Enter the geometric data window .................................................................................... 27
Figure 2. 19 River section details (HEC-RAS) ................................................................................... 28
Figure 2. 20 XS Interpolation ............................................................................................................. 28
Figure 2. 21 Unsteady Analysis Window ............................................................................................ 29
Figure3. 1 Flowchart of Methodology ................................................................................................. 31
Figure3. 2 Process of the Verification of Results ................................................................................. 32
Figure 4.1 Sluice Gate Shape .............................................................................................................. 34
Figure 4.2 Upstream Boundary ........................................................................................................... 35
Figure 4.3 The River Profile for Test Case 1 ...................................................................................... 35
Figure 4.4 River Cross Section ........................................................................................................... 36
Figure 4.5 Weir data ........................................................................................................................... 37
Figure 4.6 Gate Data ........................................................................................................................... 38
Figure 4.7 Gate opening data .............................................................................................................. 38
Figure 4.8 The last River Section ........................................................................................................ 39
Figure 4.9 The Downstream Boundary ............................................................................................... 39
Figure 4.10 The Steady State Flow Simulation ................................................................................... 40
Figure 4.11 Steady Simulation Results ............................................................................................... 40
Figure 4.12 Unsteady simulation completed ....................................................................................... 41
Figure 4.13 Longitudinal Profile ......................................................................................................... 41
Figure 4.14 Flow Vs Time .................................................................................................................. 42
Figure 4.15 steady state results ........................................................................................................... 43
Figure 4.16 Unsteady state (fixed time step) results............................................................................ 43
Figure 4.17 Time series for unsteady adaptive time step .................................................................... 44
Figure 4.18 Stage plot for test case 1 .................................................................................................. 44
Figure 4.19 starting new project in the HEC-RAS .............................................................................. 45
Figure 4.20 Entering the geometric data into the HEC-RAS............................................................... 45
Figure 4.21 cross sections details ........................................................................................................ 46
Figure 4.22 cross sections interpolation .............................................................................................. 47
VII
Figure 4.23 XS interpolation between river stations ........................................................................... 47
Figure 4.24 gate opening information ................................................................................................. 48
Figure 4.25 weir stations & elevations ................................................................................................ 49
Figure 4.26 Inline Structure Data ........................................................................................................ 49
Figure 4.27 River channel profile ....................................................................................................... 50
Figure 4.28 Gate openings information ............................................................................................... 50
Figure 4.29 define the boundary conditions ........................................................................................ 51
Figure 4.30 Steady state analysis complete ......................................................................................... 52
Figure 4.31 Results of the steady state analysis .................................................................................. 52
Figure 4.32 General profile plot .......................................................................................................... 53
Figure 4.33 Stage Hydrograph (ISIS Vs HEC-RAS) .......................................................................... 53
Figure 4.34 Outflow hydrograph, (Ahmed and Morris, 1997) ............................................................ 54
Figure 4.35 upstream boundary condition ........................................................................................... 55
Figure 4.36 Downstream boundary condition ..................................................................................... 55
Figure 4.37 Sluice radial gate information .......................................................................................... 56
Figure 4.39 Flow hydrograph (ISIS) ................................................................................................... 57
Figure 4.38 Steady state analysis results ............................................................................................. 57
Figure 4.40 Outflow hydrograph comparison ..................................................................................... 58
Figure 4.41 Outflow hydrograph ISIS Vs EDF ................................................................................... 59
Figure 4.42 Gate information .............................................................................................................. 60
Figure 4.43 Weir embankment data .................................................................................................... 60
Figure 4.44 Cross section details ........................................................................................................ 61
Figure 4.45 Unsteady flow boundary conditions................................................................................. 61
Figure 4.46 Flow hydrograph (HEC-RAS) ......................................................................................... 62
Figure 4.47 Comparison of outflow hydrograph ................................................................................. 63
Figure 4.48 Upstream boundary condition .......................................................................................... 65
Figure 4.49 Cross section details ........................................................................................................ 65
Figure 4.50 Downstream boundary condition ..................................................................................... 66
Figure 4.51 Steady state analysis results ............................................................................................. 66
Figure 4.52 Unsteady state analysis .................................................................................................... 67
Figure 4.53 Longitudinal profile after 0 hours .................................................................................... 67
Figure 4.54 Longitudinal profile after 1 hours .................................................................................... 68
Figure 4.55 Longitudinal profile after 2 hours .................................................................................... 68
Figure 4.56 Longitudinal profile after 3 hours .................................................................................... 69
Figure 4.57 Longitudinal profile after 4 hours .................................................................................... 69
Figure 4.58 Longitudinal profile after 5 hours .................................................................................... 70
Figure 4.59 Stage hydrograph (ISIS) .................................................................................................. 71
Figure 4.60 Velocity hydrograph (ISIS).............................................................................................. 71
Figure 4.61 Reach river....................................................................................................................... 72
Figure 4.62 Cross section details ........................................................................................................ 72
Figure 4.63 Steady flow boundary condition ...................................................................................... 73
Figure 4.64 Steady state results ........................................................................................................... 73
Figure 4.65 Unsteady state boundary conditions................................................................................. 74
Figure 4.66 Unsteady flow analysis .................................................................................................... 74
Figure 4.67 Stage hydrograph ............................................................................................................. 75
Figure 4.68 Flow hydrograph.............................................................................................................. 75
Figure 4.69 Longitudinal profile at different simulation times ............................................................ 76
Figure 4.70 Outflow hydrograph comparison ..................................................................................... 77
VIII
Figure 4.71 Stage hydrograph comparison .......................................................................................... 77
Figure 4.72 Upstream boundary condition .......................................................................................... 79
Figure 4.73 Cross section details ........................................................................................................ 79
Figure 4.74 Downstream boundary condition ..................................................................................... 80
Figure 4.75 Steady flow results after 0 hours ...................................................................................... 80
Figure 4.76 Steady flow results after 1 hours ...................................................................................... 81
Figure 4.77 Unsteady flow analysis .................................................................................................... 81
Figure 4.78 Unsteady state flow analysis completed........................................................................... 82
Figure 4.79 Cross section plot............................................................................................................. 82
Figure 4.81 Stage hydrograph (ISIS) .................................................................................................. 83
Figure 4.80 Longitudinal profile after 0 hours .................................................................................... 83
Figure 4.82 Flow hydrograph (ISIS) ................................................................................................... 84
Figure 4.83 Steady flow results after 0 hours ...................................................................................... 85
Figure 4.84 Steady flow analysis after 1 hours ................................................................................... 85
Figure 4.85 Profile plot ....................................................................................................................... 86
Figure 4.86 Stage Vs Flow (HEC-RAS) ............................................................................................. 86
Figure 4.87 Stage hydrograph (HEC-RAS) ........................................................................................ 87
Figure 4.88 Flow hydrograph (HEC-RAS) ......................................................................................... 87
Figure 4.89 Flow hydrograph comparison .......................................................................................... 88
Figure 4.90 Stage hydrograph comparison .......................................................................................... 88
Figure 4.91 Upstream boundary condition .......................................................................................... 90
Figure 4.92 Cross section details ........................................................................................................ 90
Figure 4.93 Downstream boundary condition ..................................................................................... 91
Figure 4.94 Steady flow results ........................................................................................................... 91
Figure 4.95 Unsteady state flow analysis ............................................................................................ 92
Figure 4.96 Unsteady flow analysis completed ................................................................................... 92
Figure 4.97 Flow hydrograph (ISIS) ................................................................................................... 93
Figure 4.98 Flow hydrograph, (Keskin and Aǵiralioǵlu, 1997) .......................................................... 93
Figure 4.99 Flow hydrograph (ISIS Vs SDM) .................................................................................... 94
Figure 4.100 Cross section details ...................................................................................................... 95
Figure 4.101 Unsteady flow boundary conditions............................................................................... 95
Figure 4.102 Flow hydrograph (HEC-RAS) ....................................................................................... 96
Figure 4.103 Flow hydrograph (ISIS Vs HEC-RAS) .......................................................................... 96
Figure 4.104 Flow hydrograph (ISIS Vs HEC-RAS Vs SDM) at S1 .................................................. 97
Figure 4.105 Flow hydrograph (ISIS Vs HEC-RAS Vs SDM) at S3 .................................................. 97
Figure 4.106 Flow hydrograph (ISIS Vs HEC-RAS Vs SDM) at S5 .................................................. 98
Figure 4.107 ISIS Vs HEC-RAS....................................................................................................... 100
IX
Chapter 1: Introduction
1
1.4 Research layout
The research project consists of five chapters. Figure 1.1 shows the relationship between the
chapters. The first chapter gives a general introduction and a sample of the layout of the
research. The other chapters will be divided as the following:
Chapter two is the literature review that covers the following areas:
Chapter three explains the methodology which covers the following areas:
Dam failure simulation cases selection.
Other simulation cases selection.
The methodology of the analysis of the simulation cases.
Reliability check of the results of the analysis.
Chapter four which is the biggest chapter in this research illustrates the procedure of different
five simulation cases and the findings of the simulation analysis of each case using both the
ISIS and the HEC-RAS and then conducting comparisons between the two softwares in order
to tell which is the best. Chapter five is the last chapter; it includes the conclusions and
recommendations of the researcher.
2
Figure 1.1 Research Layout
3
Chapter 2: Literature Review
Other reasons which cause the river flooding as listed in (Loh, 2011) are listed below:
4
2.1.2 Maximum floods records around the world
When the maximum floods take a place the most dangerous disasters will happen so for that
reason so many researchers have studied the maximum floods records around the world, as
141 rivers were selected around the world with maximum floods carry a flow of water equals
or greater than 10,000 𝑚3 /𝑠 it has been found that China had the most dangerous floods
percentage around the world with 32.14% which means 45 rivers between the 141 rivers had
the maximum floods in the world and the maximum floods in Asia which had the highest
percentage of the maximum floods through the all continents with 54.61%. The second
highest country in the world is the USA with 12.86% which means that 18 rivers between the
141 had the maximum floods in the world. Around 80% of the maximum floods around the
world relate usually to the solar activity and it is related especially to the relative solar
number R where it has been found that the maximum floods occur when the value of R is
around 24.73 or around 110.2 (Yongquan, 1993)
5
2.2 Dam failure background
(NRCS, 2003) mentioned that the dams are built in order to maintain two different major
purposes; the first one is to encounter the water and make flood management for the river
stream or any other water stream. The other type of dams is the diversion dam which is a
structure built in order to divert all or part of the river or water stream then that water stream
can be controlled effectively and used for different purposes, these purposes mentioned in
(Nuera, 2005) as the following:
1. Saddle dam: the saddle dam is built at the edge of the water stream in order to protect
the land next to that water stream from flood risk.
2. Dry dam: the dry dam is very important in the heavy rainy areas so the flow of the
river or the water stream is very big.
3. Overflow dam: the overflow dam is used to increase the level of water inside the river
then different sizes of weirs can be used at different levels in order to generate
electricity.
4. Check dam: the check dam is that type of dams used to ensure that the soil erosion not
take place and try to reduce the velocity of water flow in the river.
According to the material used to build the dams, the dams have been divided into two major
types, the first one is the embankment dam and the other one is the masonry dam. The
embankment dam is built out of fill materials, those materials are less dense than concrete so
6
it is expected that the embankment dam will need more material of loose rock or earth or a
combination.
The embankment dam has been divided into three different types of dams regarding the fill
material used in the construction of the dam as the following:
1. Rock-fill embankment: filled with loose rocks covered with a crest of concrete to
prevent the water seepage inside the fill, that crest can be made from any other
material prevent the passage of the water inside the fill.
2. Earth-fill embankment: made from well-compacted soil layers (more than 50% of the
fill material consists of soil) covered with waterproof layer as the rock-fill
embankment, sometimes a clay layer inserted inside the fill or outside the fill on the
upstream face.
3. Zoned embankment: used in modern dams which the core is made from water
resistant material and then covered with rock or soil in order to prevent the water to
go through the dam material. So that different degrees of permeability will be exist in
these types of dams.
On the other hand the masonry dam consists of stone, brick or concrete joined together with
mortar which is a mixture of sand, cement powder and water, the masonry dam has been
divided into three different types of dams which are the Arch dam, the Gravity dam and the
Buttress dam (NH Department of Environmental Services, 2006).
1. Arch dam: the arch dam is made of concrete or stone-brick material has the shape of
curve across the river, the main design purpose of the arch dam is to move the water
pressure onto the narrow walls of the river. This type of dams doesn’t depend on its
self-weight as the following type so it is not expected to be heavy. The arch dam can
be formed into eggshell shape or multiple arch shapes.
2. Gravity dam: this type of dams depends on its own weight to hold the water pressure
of the reservoir, the gravity dam is much heavier in weight than the arch dam and it is
made from concrete because concrete is known of its water resistance, heavy weight
and easy formation into so many different shapes.
3. Buttress dam (hollow dams): the buttress dam consists of concrete wall supported
with buttresses placed on the downstream face and made from steel bars, the buttress
dam used usually in the wide rivers like the gravity type of dams and not like the arch
7
dams which used in the narrow type of dams (NH Department of Environmental
Services, 2006).
The previous types of dams are considered the most common types of dams according to the
material used in the construction process, the following figure summarize the different types
of dams according to different kind of divisions.
8
2.2.2 Historical background of dam failures
One of the oldest manmade structures on the earth are the dams which have been used for the
first time in the Roman Empire in the first century in order to encounter the river water near
the Mediterranean Sea (Nuera, 2005). The construction of dams for many different purposes
continued until the modern age when the fluid mechanics science has become deeper and
more professional even though the failures and the breaks of the dams still one of the
important issues which concern the engineers and the designers all over the world. There are
many different causes of the dam failure, one third of those causes globally are because of the
Overtopping, and another one third of the dam failures globally are because of the foundation
defects, other reasons like piping, seepage and inadequate materials has took a place also
along the previous years (Probe international, 2008)
One of the dramatic historical dam failure cases which happened in 1959 in the Malpasset
dam in France and killed 500 people just after few weeks of the crack notice, the main reason
of the crack happened is the tectonic fault which has been realized to be exist after the crack
took a place, the existence of the tectonic plate under the downstream face built non uniform
pressure under the dam and when the heavy rains came, the level of the reservoir had
increased and helped in the Malpasset dam break ( Ahmed and Morris, 1999).
Another famous dam break happened in the kolnbrein in Austria in 1979, the cracks and the
seepage of the water were noticed after the second partial filling, they tried to drain the water
at that time but that wasn’t applicable and the problem still exists. In 1989 the engineers
decided to support the dam with buttresses from the downstream side in order to hold the dam
and prevent the failure but the repair cost was about 190 million $ and that was a case studied
and simulated by the engineers again and again in order to prevent some similar cases in the
future (Robinson et al., 2002).
Another two important historical cases in the dam failures issue were the Fontana dam in
USA and El Atazar Dam in Spain, the major problem of Fontana dam was the chemical
reaction between the aggregate and the cement inside the dam and that resulted in a
significant cracks. About El Atazar dam break the main reason behind that was the different
deformation between the left and the right side of the dam and that resulted in a significant
settlement in the foundations (Robinson et al., 2002).
9
A table illustrates some of the other historical dam failures cases happened is shown below
with the dates, names and the causes of the failures:
10
Overtopping: as mentioned before that the reason of overtopping is considered to be
behind one third of the dam failures globally, the overtopping happened when the
level of the reservoir reach its limit and exceed this limit so the capacity of the water
inside the dam exceeds its limit. This reason happened when the spillway became
insufficient or the settlement of the dam crest exceeds its limit. The heavy rains
usually plays the facilitator of the dam failures because when the heavy rains come it
is expected to increase the capacity of the reservoir and then the level of the water
inside the reservoir exceeds the limit and so the failure take a place. (Probe
International, 2008).
Failure of the dam foundations: another one third of the all dam failures happened due
to the large defects of the foundations supporting the dam. The major reason behind
that is a design mistake when the weight of the dam hasn’t taken into consideration
very well then a differential settlement will occur underneath the dam that will result
in a non uniform pressure, this pressure will cause instability and landslide under the
dam so at that time if any seepage for water happened or any land shake took a place
it is expected that will dramatically compromise the structure. (Probe International,
2008).
Piping and internal erosion of soil: about one fifth of the all dam’s failures happened
due to the piping and seepage problems and that is considered very famous in the
embankment type of dams which considered semi-permeable. The seepage of water
through the dam reduce the strength of the dam and result in large cracks and
settlements through the dam, those cracks will play as water pipes through the dam
which will make the dam weaker and weaker and will compromise the dam in any
instant. (Probe International, 2008).
Other reasons: inadequate maintenance, insufficient in the materials used in the
construction and/or improper design for the dam. (Federal Emergency Management
Agency, 2006).
11
Dam Failure
There are so many available methods for estimating the probabilities of the dam safety risk
analysis, one of those methods is the historical performance method which study a similar
cases and dams as the dam which being studied and analysed then try to assume that this dam
will behave as the same old dams in the future, the historical method is considered to be
applicable for the initial stages of the risk assessment because it is not detailed and the
analysis of the dam safety can’t be relied only on it. Other method for estimating the
probability is the event tree method which simulates and models the dam failure process from
the beginning until the end with all the details of the dam and the foundation and can be
connected sometimes to the historical performance data in order to give a check for the
results of the assessment. (Hill et al, 2003).
Combining probabilities:
In this stage there are two different cases should be discussed, the first one is the common
cause failure modes which can happen at the same time at any single section in the dam
should be studied and then it should be assumed that the failure of the dam will happen due to
12
a combination of those probabilities, the second case is the study of the single failure cause
probability at different number of sections in the dam. (Hill et al, 2003).
This theorem produce a method of how the probabilities of the dam failure causes at every
section inside the dam which they are not mutually exclusive can be modified and adjusted in
order to reflect the actual physical condition of the dam in on the modelling process. (Hill et
al, 2003).
There are some methods and procedures consider the dam safety and try to make
methodologies in order to reduce the risk of the dam failures, one of those methodologies is
the RAM-D risk assessment methodology which was invented in order to evaluate the
security level of the dams, the RAM-D risk assessment methodology based on the following
equation (Harrald et al, 2004):
This risk methodology designed especially for the dam owners and the security managers,
away from the previous equation, the RAM-D use different types of equations and
worksheets in order to calculate the risk of the dam failure. To sum up the most important
objective of the RAM-D is to understand and identify the most critical risks which are
considered to be undesired then try to analyse the potential hazards of those risks and finally
suggest and recommend some steps to increase the emergency and security level. (Harrald et
al, 2004).
Other risk methodologies like the Portfolio Risk Assessment Methodology (PRA) which
produced by team of engineers, safety managers and decision makers, the risk assessment
steps include identification of the hazards then make an engineering assessment after that a
decision making will take a place and finally the prioritization and the recommendations will
be provided by the team who responsible for the methodology. (Harrald et al, 2004).
Another assessment tool for the dam safety has been produced by the Electric Power
Research Institute (EPRI) which works with the U.S. Federal Energy Regulatory
Commission’s (FERC) Division of Dam Safety and Inspections in order to produce a
13
hydropower security assessment tool which will be used after that in the studies of the dam
safety related to the FERC. The tool aims at producing a security-planning program which
will facilitate the self-assessment of the dam and will produce applicable results which meets
the standards regulations of the dam safety for so many different purposes. (Harrald et al,
2004).
Estimating
Prpbabilities
Using Uni-
bound theorem
14
2.3 Benefits of numerical model
The numerical model of the rivers is considered one of the most important branches in the
hydraulics science because of the following reasons as mentioned in (Abdullah et al, 2009):
1. It performs a large testing operation for the hydraulic case and can evaluate the dam
break analysis.
2. It also gives a good prediction of the inflow and outflow hydrograph for any required
dam.
3. Calculate the magnitude of the flooding due to the dam and then that magnitude can
be compared with the PMF inflow capacity and then the failure risk on a specific
section of the dam can be determined.
4. An emergency response plans can be produced in order to prevent the failure of the
dams.
5. Determine the flood hydrograph, peak discharge, flood wave propagation time and so
on, this concerning with the type of the dam structures, mechanisms and size of the
break.
There are different models have been designed in order to manage the water resources. Those
models are ISIS, MIKE11, HEC-RAS, HYDRO-1D and Info Works RS (River Simulation).
Those programs have been designed to analyse the dam break and consider so many practical
hydraulic cases. Those programs can be used as empirical model, analytical model,
parametrical model and numerical model. (Abdullah et al, 2009).
In general and to sum up, the failures of the dams can’t be totally prevented by using the
numerical modelling but the numerical modelling gives a complete methodology in order to
reduce the failure risk. There are two ways to reduce the risk the first way is to decrease the
probability of the dam break and the second way is to reduce the impact on it. Before the dam
break occurs, the process of the flood forecasting should be completed at the fore stage.
15
2.4 Selection of the software and its user guide
There are wide range of available softwares can compute and predict the flooding but as
mentioned before that the biggest concern in this research is to conduct the flow simulation
process through the ISIS and the HEC-RAS and compare them together. In this part of this
chapter a briefly description of each software, how it works and a simple user guide have
been provided to this research.
The numerical brain of the ISIS software is based on the Preissmann Implicit Scheme or 4-
point Box Scheme. In the implicit approach, three unknown future values (j-1,n+1), (j,n+1),
(j+1,n+1) will be used with other three known present values (j-1,n), (j,n), (j+1,n). All the
unknown values will be linked and solved together using the matrix principle approach
(Anderson, 1995).
16
The three known values with the three unknown values will be used in the following equation
in order to form the matrix then after the matrix being solved the ISIS program can get the
future values (Vasilyev, 2007).
1 𝑛 1 𝑛+1
𝑇𝑖𝑛 +1 − 𝑇𝑖𝑛 𝑇𝑖+1 − 2𝑇𝑖𝑛 + 𝑇𝑖−1
𝑛
+ 2 𝑇𝑖+1 − 2𝑇𝑖𝑛+1 + 𝑇𝑖−1
𝑛+1
=∝ 2
∆𝑡 (∆𝑥)2
The ISIS software gives the choice for the user either to run steady or unsteady simulations, if
the user is doing steady run then he has the choice either to do a direct run or timestepping
run, the direct choice is considered to be faster and more accurate than the second choice. If
the user is doing unsteady run then he has the choice also to choose between two different
types of runs, the first one is fixed timespan and the second one is the adaptive timespan. ISIS
gives the ability to do one dimensional modelling for the structures and the channels, all the
section including the weirs, the spills, the reservoirs and everything can be input into the ISIS
in order to find the results which depends on the data input quality and the skill of the user
not only the one dimensional modelling can be applied but also the ISIS gives the ability to
do two dimensional modelling based on the topography of the area, the hydrological data, the
roughness and the floodplain and channel locations (Vasilyev, 2007).
Finally all the results can be obtained from the ISIS software, all the water profiles and the
tables including all the information. Output numerical data may be plotted by ISIS by
Halcrow software or Microsoft Office Excel. The graphs of the river sections at different time
intervals can be plotted, the maximum water level and the maximum reservoir capacity can
be calculated then the output data can be analyzed and investigated considering different case
in order to form a good decision about the case which being studied (Vasilyev, 2007).
17
2.4.1.2 Basic concepts of ISIS
In addition to the modelling of the flows and water levels in open channels, ISIS can be used
for different types of structures as bridges, sluices, weirs, culverts and pumps which can be
modelled easily in the simulation analysis process. The majority of the information in this
section has been retrieved from the ISIS by Halcrow User Manual through the software’s
website. The main concept in the simulation process consists of three main points:
1. The upstream boundary condition which represents a flow of water entering the river.
2. The downstream boundary condition which represents the flow of water getting out
from the river.
3. The river channel which will be represented by number of river sections (at least two
sections).
The main interface of ISIS is the Network Properties Window, which opens automatically
every time ISIS is opened. The Network Properties Window is used to insert the components
of the river model such as river sections and weirs. This interface consists of multiple icons
for different purposes some of them are related to the boundary conditions, the river cross
sections, the junctions through the river mode and the different types of the structural units
such as bridges, weirs, sluices and others as shown in the following figure:
18
ISIS deals with a large range of different types of files in order to control the model data and
the results. The most important file types are listed below in the following table:
2.4.1.3 Design simple single river channel and view the results
In this part a simple river channel will be designed in order to explain the major steps which
needed to design a river channel using the ISIS, most of the data used in this part with the
help of the ISIS Free & the ISIS profession quick start guide. As mentioned in the previous
part that there are three major considerations needed to design the river channel and to run the
simulation process successfully those parameters are the upstream boundary, the downstream
boundary and a minimum of 2 cross sections. The following points show the major steps
needed to build the river channel and to run the simulation analysis:
Begin a new blank model by clicking on >File >New in the network properties
window or by clicking on the icon of New from the main window of icons.
Define the upstream boundary condition by clicking on the icon of Flow Time
Boundary then the node label editor has been appeared and the label has been
assumed to be S1 as shown in the following figure:
19
After the label of the upstream boundary has been inserted the data of the flow time
table need to be inserted through double click on the S1 (QTBDY), it has been
assumed that the peak flow is 20 𝑚3 /𝑠, the base flow is 10 20 𝑚3 /𝑠 and the peak
time is 12 hours as shown in the following figure:
Now at least two cross sections have been inserted by clicking on the river section
icon then the node label editor has been appeared and in order to link the first
cross section with the upstream boundary it has been labelled with the same label of
the upstream boundary condition S1 as shown in the following figure:
20
After the cross section has been labelled the geometric details of the cross section
need to be inserted by double clicking on the S1 (RIVER) then a new window which
shown in the following figure and it has been assumed to be filled with the following
data:
The shape of the river section can be checked easily by clicking on Plot in the
previous figure, the following steps will be the same as the previous step but in the
last river section it should be noticed that the distance to the next section should be set
to be zero.
The last major step in order to complete the channel design is the downstream
boundary condition which must be satisfied by clicking on HTBDY boundary
condition icon which should be labelled with the same label of the last river
section in order to be linked as one river channel and the details of the downstream
boundary condition which include table of the stage head against the time values have
been assumed in this sample example to be filled as in the following figure:
21
Figure 2. 11 Downstream boundary condition
After completing the single channel the river channel can be visualised by clicking on
the icon of the visualiser icon and this icon will enable to see the all river channel
with the all links as shown in the following figure:
22
Once all of the design criteria has been met the simulation analysis can be run at this
time which will generate flow output results which can be checked at the end of the
simulation process, by clicking on the simulation icon a new window will appear
which include 5 types of the simulation analysis’s where the steady (direct) type
should be run first in order to make the initial conditions ready to the simulations
analysis, in the unsteady (Fixed timestep) and (Adaptive timestep) the finish time
should be larger than the start time and if the timestep was very small the software
will take more time to converge and the results will be more accurate.
The results of the steady flow analysis appeared once the simulation completed as
word file contain the flow values, velocity values, Froude number and other
parameters at different river sections, the results of the unsteady state analysis can be
obtained by clicking on the tabular CSV command icon which give the ability to
obtain the values of velocity, flow, stage and other parameters for the unsteady flow
analysis.
23
Other results as the longitudinal profile for the river channel can be obtained by
clicking on the longitudinal section icon , the plot of the time series can be drawn
by clicking on the time series icon as shown in the following figure:
24
2.4.2 Starting HEC-RAS and basic concepts
1. Drawing the river reach line which shows the direction of the flow from the upstream
boundary to the downstream one.
2. Define the river station and as mentioned above that the upstream boundary is
labelled with 10 and the downstream with 0.
3. At least two river cross sections are needed to define the geometric data for the reach
river.
4. Finally and before running the flow analysis the initial conditions plus the boundary
conditions must be defined.
The main interface of the HEC-RAS is shown in the following figure which contains so many
icons related to different tasks and purposes, for example from this interface a new project
can be created or an old one can be opened from File tap, the initial and the boundary
conditions can be inserted into the project from the Edit tap, running the steady or the
25
unsteady flow analysis can be done from the Run tap and other options and views of the
results for the simulation of the projects can be seen from View and Options taps.
2.4.2.3 Design simple single river channel and view the results
In this part a simple river channel will be designed in order to explain the major steps which
needed to design a river channel using the HEC-RAS, most of the data used in this part with
the help of the HEC-RAS manual. The following points show the major steps needed to build
the river channel and to run the simulation analysis:
A new project can be created by going to >File >New project in the main interface of
the software, after doing that the HEC-RAS will ask for the name of the new project
as shown in the following figure:
26
After saving the new project then it is the time to enter the geometric data of the
project by clicking on the icon of Edit/Enter geometric data as shown in the following
figure:
In the following step a new window will appear and the river reach needs to be drawn
now by clicking on the icon of River Reach and by clicking on that icon and drawing
the beginning and the end of the river the HEC-RAS will ask for the name of the river
and the reach which can be named with any name as shown in the following figure:
From the geometric data window by pressing on cross-section button to enter the
details of the river cross section and from the new window appeared by going to
>Options >Add a new cross section then the geometric details can be easily inserted
into the new window where these details include the cross section coordinates (x-
27
direction and y-direction), manning values, the distance to the next section and the
slope of the river bed. The following figure shows the cross section data window:
Once >add new cross section pressed the HEC-RAS asks for the river station of the
cross section which should be 10 for the upstream boundary and 0 for the downstream
boundary. Since the same geometry data will be used in the following river sections
HEC-RAS gives the ability to copy the details of the current cross section by pressing
>Options >Copy current cross section, another important command gives the ability
to interpolate the rest of cross sections which can save the time by going to >Tools
>XS Interpolation as shown in the following figure:
Figure 2. 20 XS Interpolation
28
The last step before running the flow analysis is to define the initial conditions, the
upstream and the downstream boundary conditions of the reach river by going to
>Edit >Steady Flow Data and that if the flow analysis is steady state, if it is unsteady
state it will be >Edit >Unsteady Flow Data. According to the available data the reach
boundary conditions will be defined but the usual definition of the boundary
conditions as the following:
1. The upstream boundary condition is being defined as flow hydrograph.
2. The downstream boundary condition is being defined as stage hydrograph.
3. The sluice gates structures are being defined as T.S. gate openings.
The steady flow analysis and the unsteady flow analysis can be run by going to >Run
>Steady flow analysis >Compute or >Run >Unsteady flow analysis >Compute. The
starting, the ending time and the time step for the unsteady flow analysis should be
inserted into the new opened window as shown in the following figure:
29
Chapter 3: Methodology
30
4. The last simulation case shows how the flood routing for a rectangular channel can be
simulated and this case has been chosen according to a previous report used the
simplified dynamic model to describe the case; the results from both the SDM and the
two applications have been compared together at the end.
Topic selection
Define the problem
Develop
Research
Establish Objectives
plan
Literature review
Conducting Cases on
ISIS
Regenerate more
Conducting Cases on
HEC-RAS cases
survey
Check the validity by
doing comparisons
Results and
comments
Conclusions &
Recommendations
Figure3. 1 Flowchart
surveyof Methodology
31
3.4 Dual Software System Selection
The decision of the selection of the two softwares which have been used in this research has
been made according to the following points:
The ISIS and the HEC-RAS are considered to be the most popular softwares in the
river modelling field in so many countries around the world and especially in the
United Kingdom.
The modern features which have been developed in the ISIS and the HEC-RAS as the
model health checker, the results extractor, the 1D modelling, the 2D linked
modelling and the friendly user interface all these productivity tools increased the
degree of professionalism for the two softwares.
Although there are main competitors to the ISIS and the HEC-RAS as the Mike 11
and the Infoworks RS the ISIS and the HEC-RAS are still considered to be the
simplest and the most accurate softwares in the river modelling area.
1. The first check by using the dual system software and compare the results together.
2. The second check by comparing the results from the softwares to the results of the
previous reports.
Results
Results Results
Checked with
obtained from Checked with
the reports
the ISIS the HEC-RAS
results
32
3.6 Methodology of the Flow Analysis and Results
The flow analysis of each simulation case has passed two main stages the first one was the
steady flow analysis and the second one was the unsteady state flow analysis, as mentioned
before it is very necessary to conduct the steady flow analysis before the unsteady analysis in
order to prepare the initial conditions for the flow analysis process. In each simulation case
the results of the steady state flow analysis appeared once the simulation is completed but in
the unsteady flow analysis it is necessary to extract the results using some commands in the
softwares in order to get the following important results:
The flow Hydrograph which include the flow values at each river section for every
time step until the simulation time is finished.
The stage Hydrograph which include the stage values against the simulation time
values.
Other results could be very useful as the velocity values and Froude number values.
Although the ISIS and the HEC-RAS give the ability to draw the flow and the stage
hydrographs for each case the results have been extracted as tables and then moved to the
Microsoft Excel in order to compare those values with other values extracted from other
softwares or other reports.
33
Chapter 4: Simulation Analysis & Discussion
4.1 Case 1: Simulation of the dam breaks as a sluice gate opening abruptly
through the dam
34
4.1.2 Test case 1 using the ISIS
In this section the test case 1 has been simulated through number of steps using the ISIS
software.
The upstream boundary has been defined by clicking on the Flow-Time Boundary
picture button in the tools bar or select > Edit > Insert >Boundaries > Hydrographs >
Flow/Time from the main menu and then the data has been filled into the window
appeared as shown in figure 1:
The river sections have been inserted using the picture button of the river section from
the tools bar or by select > Edit > Insert > Channels > River > River Section from the
main menu by entering the label of the cross section as S1 then the details of the river
cross section which has been assumed to be as in the figure 2:
35
Figure 4.4 River Cross Section
The second step has been repeated for S2, S3 and S4up. The only difference in S4up
is the distance to the next section which is S4dn which has been inserted as zero as
shown in the figure 3:
36
Between sections S4up and S4dn the sluice gate has been inserted by clicking on the
vertical sluice button picture in the tools bar then all assumed data of the weir and the
gate has been inserted into the windows appeared which are shown in figures 4, 5 and
6. The dam data has been assumed to be as the following table 1. After the weir
geometry has been edited the calculation method in the coefficients tap has been
changed to variable mode:
37
Figure 4.6 Gate Data
38
The rest of the river sections S4dn, S5, S6, S7 and S8 have been inserted with the
same previous way as shown in figure 7 and the only difference in S8 is the distance
to the next station which has been inserted as zero because it is the last section of the
river profile. Then the downstream boundary of the river has been defined by clicking
on the Head-Time Boundary button picture in the tools bar as shown in figure 8:
39
The steady state simulation flow has been run by clicking on Run Flow Simulation
button picture in the tools bar and it has been found that the free gate flow (UMODE)
is 5 and the opening of the gate (USTATE) is 5 as shown in the following figures 10
and 11:
40
The unsteady state simulation flow has been run by clicking on Run Flow Simulation
button picture in the tools bar and then select the unsteady (fixed time step), and if the
time step changed to 3 and save interval into 60 and the finish time at 24 hrs, it has
been found that flow stage decreases at the gate break location (Section 4) and the
water volume below 3.003 meters can be neglected because 3.003 meters is
considered as the minimum stage level and the 3.05 is the maximum stage record at
the beginning of the river.
3.05 S1
S2
3.04 S3
Stage (meters)
S4up
3.03
3.02 S4dn
S5
3.01 S6
S7
3 S8
2.99
0 50 100 150 200 250 300 350 400
Length (meters)
41
4.1.3 Toce river dam break test using ISIS
The test case 1 has been repeated according to the research paper on the Toce valley dam
break analysis so the data of the upstream boundary conditions has been changed to be
similar to that case by changing the values of the flow with time to be similar to the following
values:
Table 4. 2 Upstream boundary conditions
42
By running the steady state simulation first the following results have been appeared, the free
gate flow (UMODE) is 4 and the opening of the gate (USTATE) is 0.25 as shown in the
following figure:
The main purpose of the steady state simulation is to make the boundary conditions ready to
the simulation process so for that reason the steady state simulation should be run first, when
the unsteady (fixed time step) has been run by selecting the time step to be 3 and the interval
to be 60 so the simulation process completed successfully and the longitudinal section of the
river through the river sections from S1 to S8 has been found to be in the following shape:
43
At the river section S4dn if the time series plot has been drawn in the unsteady (fixed time
step), the plot will be as in the following figure:
Figure
Figure 4.17
4.17 Time
Time series
series forfor unsteady
unsteady adaptive
adaptive time
time step
step
stage plot
8
stage…
7
0
0 50 100 150 200 250 300 350 400 450
As shown in the figure above that the stage plot of the eight sections, by changing the
distance it has been found that the stage is changing but the inflection point is between 120
and 220 meters.
44
4.1.4 Test case 1 using the HEC-RAS
In this section the test case 1 has been simulated through number of steps using the HEC-
RAS software.
A new project has been started by opening the HEC-RAS window then from the file
tap a new project can be started and titled then it can be saved as a file in any
directory as shown in the following figure:
After the new project has been created in the HEC-RAS main window, the geometric
data of the new project needs to be entered by clicking on the geometric data button
picture from the main menu in the software, a new window has been appeared from
this window a new river reach has been defined by drawing the upstream and the
downstream boundaries of the river.
The cross sections of the rivers have been inserted into the new project by pressing
the cross section button picture from the left hand side in the new project window
then a new window has been appeared and then the software asked for adding a new
cross section in order to give the ability to put all the details of the cross sections of
the river which have been assumed and inserted in there as shown in the following
figure:
The previous cross section has been described to be the upstream river station which has been
assumed to be 10 and with a distance equals 50 meters from the next cross section and the
manning coefficient has been assumed to be 0.01 as shown in the figure above.
The cross section at the downstream river station has been defined with the same way
of the upstream but this time the downstream river station has been assumed to be 0
and the other parameters have been left to be the as the same in the upstream river
station.
46
The river cross sections between the upstream and the downstream river stations have
been inserted into the project by using the interpolation tool which gives the ability to
interpolate the distance between the upstream and the downstream boundaries because
of the uniform river sections as shown in the following figures:
47
The maximum interpolated distance has been assumed to be 50 meters and then the button
“Interpolate New XS’s” has been pressed to give the river channel with different stations
between the upstream and the downstream boundaries as shown in figure 27.
In this step the dam has been inserted as a vertical sluice gate between the fourth and
the fifth sections of the river channel by clicking on the “Inline Structure” button
picture from the left hand side tap then a new window has been appeared and press
ass inline structure from the options menu, the river station of the inline structure has
been assumed to be 4.5 (which is approximately the mid distance between the fourth
and the fifth sections of the river channel), then the geometric information of the gate
and the weir embankment has been added as shown in the following figures:
The number of gate openings has been assumed to be 2 times as shown in the figure above,
the gate height has been assumed to be 12, the width is 5 and the invert is 2. It has been
assumed two elevations coordinates for two different weir stations as shown in the following
figure:
48
Figure 4.25 weir stations & elevations
49
Figure 4.27 River channel profile
In this step some more information has been added to the project before running the
simulation process: The gate opening information: it has been added by pressing the
“steady flow data” button from the edit menu then >options >gate openings, the open
height has been assumed to be 5 meters as shown in the following figure:
50
Before running the steady state and the unsteady state analysis the reach conditions
for the upstream and the downstream should be defined, there are different ways to
define the reach conditions as the following:
Steady state analysis:
For the upstream boundary and the downstream boundary conditions, they can be defined
using one of the following methods (go to >edit >steady flow data):
a. Enter the rating curve (by inserting the changes in values of stage against the flow).
b. Enter the downstream slope for normal depth computation.
c. Set the condition to be a critical depth (unknown value).
d. Enter the water surface elevations for different values of flow.
Unsteady state analysis:
In the unsteady state analysis the upstream boundary can be defined using one of the
followings parameters (go to >edit >unsteady flow data):
a. Stage hydrograph.
b. Flow hydrograph.
c. Stage/flow hydrograph.
The downstream boundary condition can be defined in the same parameters of the
upstream boundary plus the rating curve and the normal depth. So from those parameters
one of them is enough to define the boundary conditions which have been chosen to be
the stage hydrograph in this test case
51
In this step the steady state analysis has been run and the information of the gate
opening has been provided through the HEC-RAS tables from the main menu and it
was as in the following figures:
From the results of the steady state analysis, it has been found that the flow of the river at the
gate equals 10.37 𝑚3 /𝑠 and the elevation of the gate is around 3.15 meters. The general
profile of the river and the water surface profile have been shown in the following figure:
52
Figure 4.32 General profile plot
The last step in this analysis is to run the unsteady state analysis in the HEC-RAS
software then compare its results with the results obtained from the ISIS, the results
have been grouped in the following graph to compare between the two softwares:
ISIS Vs HEC-RAS
3.06
3.05
3.04
Stage (meters)
3.03 ISIS
3.02
HEC-RAS
3.01
2.99
0 100 200 300 400
Length (meters)
From the figure above it has been noticed that the HEC-RAS is higher than the ISIS stage
values but both values still acceptable and close to each other.
53
4.2 Case2: Malpasset dam-break test
A comparison has been made between the ISIS numerical model results and the physical
model results by (Ahmed and Morris, 1999) throughout simulating the Malpasset dam failure
using the ISIS software by considering the dam failure as 3 sluice gates opening 10 seconds
per each one and then drawing the outflow hydrograph with the hydrograph resulted from the
physical model in one graph in order to watch the difference between the two curves. The
journal run two simulations; the first one used the EDF hydrograph data and the second one
used the computed hydrograph and in order to have this process done in the ISIS the two
simulation processes have been done separately. The following graph shows the difference
between the ISIS hydrograph and the EDF hydrograph where the ISIS hydrograph has been
found to be longer than the physical one.
54
4.2.2 Test case 2 using ISIS
The simulation process steps of this test case are totally similar to the first test case with only
some changes listed below:
Data values
Height of the gates 9.7 meters
Radius of gates 15 meters
Height of the pivot 14.7 meters
Elevation of the crest 56.8 meters
As mentioned before that the ISIS cannot run two different models at the same time so the
two different models should be run separately then the results of the two models will be
combined together in one Excel graph as shown in the following steps:
56
The first step in the dam break analysis process is to run the steady state flow analysis
and the results of that analysis have been found in the following form which shows
the big difference in the velocity values before and after the dam location point :
Secondly the unsteady fixed time step flow analysis has been run and the flow values
for the river sections have been computed through the CSV tabular command in the
ISIS and the following graph has been drawn using Excel:
Flow hydrograph
(ISIS)
7000
6000
S1
5000
S2
Flow (m3/s)
4000 S3
3000 S4up
2000 S4dn
1000 S5
S6
0
S7
0 0.2 0.4 0.6 0.8 1 1.2
Time (hours)
57
As noticed from the previous flow hydrograph that the maximum flow point is around 6000
𝑚3 /𝑠 and it has been reached after some time from the beginning of the simulation process
then it decreased gradually until it reached zero by the end of the simulation time, it is very
clear also that the highest flow hydrograph curve is at the first section then it decreased in the
next following sections.
The following graph shows the comparison between the outflow hydrograph obtained by the
journal and the one obtained from this analysis in one graph which shows that there is a slight
difference in the maximum flow point which has been found in the journal to be around 7000
𝑚3 /𝑠 and this might happen due to rounding decimal or human error.
Outflow hydrograph
ISIS Vs ISIS (journal)
8000
7000
6000
ISIS
Flow (m3/s)
5000
4000
ISIS(journal)
3000
2000
1000
0
0 0.2 0.4 0.6 0.8 1 1.2
Time (hours)
The second graph shows the difference in the starting value of the flow which has been found
around 5000 𝑚3 /𝑠 and the other difference is the maximum flow point which has been found
to be less than 7000 𝑚3 /𝑠 with a little value:
58
Outflow hydrograph
ISIS Vs EDF (journal)
8000
7000
6000
Flow (m3/s)
5000 S1
4000 EDF (journal)
3000
2000
1000
0
0 0.5 1 1.5
Time (hours)
59
4.2.3 Test case 2 using HEC-RAS
The same procedure followed in the previous part has been applied here with some
differenced related to the HEC-RAS; the major steps of the simulation process for this test
case using the HEC-RAS software are listed below:
The same gate information has been used to describe the Malpasset dam as a radial
sluice gate with three openings, the following figures describe the shape of the weir,
the information of the gate and the openings information:
The initial flow condition has been set to be 10 𝑚3 /𝑠 , the upstream boundary
condition has been defined as a flow hydrograph using the same details which used in
the previous section, the downstream boundary condition has been defined as a stage
hydrograph with the same data as well and the last boundary condition was the
opening times of the sluice gate as shown in the following figure:
61
The last step in this process was conducting the steady flow analysis followed by the
unsteady one and then the flow hydrograph values can be obtained using the
computation level output which give the spatial time series plot for each section
separately, those flow hydrographs have been grouped altogether in one flow
hydrograph as shown below:
Flow Hydrograph
(HEC-RAS)
8000
S1
7000
S2
6000 S3
Flow (m3/s)
5000 S4up
4000 S4dn
3000 S5
2000 S6
S7
1000
0
0 500 1000 1500 2000 2500 3000 3500
Time (Seconds)
It has been noticed that the maximum flow value obtained by the HEC-RAS was around 7200
𝑚3 /𝑠 and this value decreased in the following sections until it reached around 4000 𝑚3 /𝑠 in
the last section. The flow curve between 1000 seconds and 2000 seconds grew again until it
reached a maximum local value which was 2800𝑚3 /𝑠 which describe some instability of the
software at the last river sections.
62
4.2.4 Comparison between the results obtained from the ISIS, the HEC-RAS and
the results obtained from the journal
The following outflow hydrograph includes the following curves:
It is obvious that the outflow hydrograph obtained from the HEC-RAS and the ISIS (journal)
are coinciding on each other in most of the graph points and the dam failed when the
discharge was 7200 𝑚3 /𝑠 in both of them, as seen from the ISIS hydrograph that the dam
failed when the discharge was 6000 𝑚3 /𝑠 which is not the same of the ISIS (journal) as said
before that the reason behind that could be the rounding decimal or a human error. The EDF
hydrograph recorded 6800 𝑚3 /𝑠 flow value when the dam failed which is still a quite closer
to the value obtained from the HEC-RAS and the ISIS (journal).
7000
6000
ISIS
5000
Flow (m3/s)
HEC-RAS
4000
ISIS(journal)
3000
EDF (journal)
2000
1000
0
0 0.2 0.4 0.6 0.8 1 1.2
Time (hours)
63
4.3 Case 3: Sinusoidal Oscillation
Parameter Value
Number of sections 8
Channel base width (meters) 5
Channel deep (meters) 5
Manning coefficient 0.0300
Slope for normal depth 0.0003
Simulation time (hrs) 48
Time step (secs) 60
Save interval (secs) 300
64
4.3.2 Test case 3 using ISIS
The previous data has been inserted into the ISIS as the same steps of the previous cases as
shown below:
1. Define the upstream boundary condition by setting the flow discharge as 2 𝑚3 /𝑠 as
shown in the following figure:
2. The 8 river cross sections details have been inserted to be as in the following:
65
3. The details of the downstream boundary condition have been inserted to be oscillating
over the time as shown in the following figure:
4. Conduct the steady state simulation first in order to allow the ISIS prepare the initial
conditions, the steady state simulations results has been found to be as in the
following figure:
66
5. Run the unsteady state (fixed timestep) simulation by setting the timestep to be 60
seconds, the save interval to be 300 seconds and the finish time to be 48 hours as
shown in the following figure:
6. The long section of the river water surface has been found to be sinusoidal oscillated
each different hour because of the continuos change of the river surface height each
different hour as shown in the following figures:
67
Figure 4.54 Longitudinal profile after 1 hours
68
Figure 4.56 Longitudinal profile after 3 hours
69
Figure 4.58 Longitudinal profile after 5 hours
7. The results of the unsteady state analysis have been taken through the CSV tabular
command which gives all the variables including the velocity, the stage, the flow etc.
So the stage and the velocity information for this case have been taken throughout this
command the then plotted against the time in order to see the backwater tidal
oscillations which have been found that those oscillations started from the last section
S8 to the first one S1 from those following graphs it has been found that the more
distance from the start of the river till the higher wave height it becomes for the
velocity and the lower wave height it becomes for the stage and that proves the wave
energy decreases as it travels due to the losses of the velocities and the friction forces
from the channel bed and the river walls from the upstream boundary to the
downstream boundary. The following figures show the wave oscillations for the stage
and the velocity against the change of the time:
70
Stage Vs Time
3.5
2.5
Stage(m)
2 S1
1.5 S4
1 S8
0.5
0 0 5 10 15 20 25
Time(hr)
Velocity Vs Time
1.5
1
Velocity(m/s)
0.5
S1
S4
0
S8
0 5 10 15 20 25
-0.5
-1
Time(hr)
71
4.3.3 Test case 3 using HEC-RAS
The river reach has been defined using 8 cross section starting from the river station
10 at the upstream boundary to the river station 0 at the downstream boundary as
shown in the following figure:
The cross section details have been assumed to be as the same information inserted in
the ISIS for this test case where the distance between the cross sections is kept to be
500 meters and the manning coefficient to be 0.03 and any other details are shown in
the following figure:
72
In order to run the steady state simulation analysis a pre step has been done which is
defining the steady flow data from: >edit >steady flow data, then the flow discharge
set to be 2 𝑚3 /𝑠 and the boundary conditions have been defined using the rating
curve option for both the upstream and the downstream boundaries:
The steady state analysis has been computed then the following results from the output
summary tables for the steady state analysis have been extracted as shown below:
73
The last step is to run the unsteady state analysis but before doing that step the
unsteady state flow data needs to be defined using the same way of the steady state
flow data but this time the only difference is how to show the sinusoidal case in the
reach river using the same information used in the ISIS. The same information has
been inserted into the downstream boundary condition as a stage hydrograph and for
the upstream boundary condition as a flow hydrograph as shown below:
All the information needed from the unsteady analysis can be extracted through an
important option in the following window which allows showing details about the
stage and the flow at every section in the river. This option can be activated by tick
the box in front of computation level output sentence as shown below:
74
As soon as the unsteady state analysis finished all the information needed to draw the graphs
of the stage and the flow against time can be extracted from >view >unsteady state flow time
series plot, so all the information needed has been extracted and moved to the Excel to draw
the following graphs as shown below:
75
From the graphs above the backwater tidal oscillations are obviously exist in the stage and
the flow graphs at different sections of the river and it has been noticed also the further from
the beginning of the river reach the lower in the water surface and the more unstable in the
flow of the water.
The followning figure shows the water surface of the river at different times during the
simulation process and it has been noticed that the largest level of water reached 3 meters
after 2 hours from the beginning of the simulation process:
76
4.3.4 Comparison between ISIS and HEC-RAS
The following graph shows the difference between the two softwares in the flow hydrograph
where the ISIS has been found to be similar to the HEC-RAS at the first section of the river
but at the other sections there is a slight difference between the two graphs as shown below, it
is noticed that the HEC-RAS is quicker than the ISIS in reaching the maximum and minimum
flow values:
6
S1 (ISIS)
4
Flow (m3/s)
S4 (ISIS)
2
S8 (ISIS)
0
S1 (HEC-RAS)
0 5 10 15
-2 S4 (HEC-RAS)
-4 S8 (HEC-RAS)
-6
Time (hours)
The second graph shows the difference between the two softwares in the stage hydrograph
where the ISIS has been found to the same as the HEC-RAS in the stage values with some
difference in the timing between them:
S1 (ISIS)
2 S4 (ISIS)
1.5 S8 (ISIS)
1 S1 (HEC-RAS)
0.5 S4 (HEC-RAS)
0 S8 (HEC-RAS)
0 5 10 15
Time (hours)
77
4.4 Case4: Dry River with constant flow discharge
Parameter value
Base flow (m3/s) 10
Distance between cross sections (m) 50
Cross section (m*m) 5*5
Slope of the channel 0.0001
Simulation time (hrs) 48
Time step (secs) 20
Save interval (secs) 300
Manning coefficient 0.03
78
Figure 4.72 Upstream boundary condition
The second step is to define 8 cross sections of the river (S1 to S8) with the details
shown in the following figure:
79
Finally and before running the simulation analysis, the downstream boundary
condition should be defined as a constant stage 1 meter over the change of the
simulation time as shown in the figure:
The steady state simulation has been run, the results of the steady state analysis at
zero hour time show the dry river bed simulation where the values of the velocity, the
Froude number and the flow values are equal zero as shown in the figure:
80
The results of the steady state simulation analysis after one hour of the simulation show the
change of the river bed from the dry case to the wet case as the velocity values start to
increase, the Froude number and the stage as well, the following figure shows the change
from the dry to the wet:
In the last step of simulating the dry river bed is to run the unsteady state flow
simulation fixed time step where the time step has been set to be 20 seconds and the
simulation time assumed to be 12 hours:
81
Figure 4.78 Unsteady state flow analysis completed
The following figures show the maximum surface of the water in the river which reaches
1.813 meters in section 1 and from the longitudinal river section it is obvious the increase of
the height of the water by the time from section 8 to section 1 (from left to right):
82
Figure 4.80 Longitudinal profile after 0 hours
The values of the stage against time have been run through the tabular CSV command and
then plotted to be as shown in the following figure which indicates the maximum height of
the river at 1.8 meters and the more distance from the first section the lower in the stage
against time:
Stage Vs Time
1.9
1.8
1.7 S1
1.6 S2
Stage(m)
1.5 S3
1.4 S4
1.3
S5
1.2
S6
1.1
S7
1
0 2 4 6 8 10 12 14 S8
Time(hrs)
83
The last figure shows the flow values against the time values which indicate the dry river bed
at the beginning of the simulation time and then the increase of the flow and the height of the
water surface until it reach the constant value for all of the river cross sections.
Flow Vs Time
12
10 S1
8 S2
Flow(m3/s)
S3
6
S4
4
S5
2
S6
0
S7
0 2 4 6 8 10 12 14
S8
Time(hrs)
84
4.4.3 Test case 4 using HEC-RAS
The first steps are exactly the same of the previous case and the only difference in the
boundaries of the reach river and they will affect the result only in the unsteady state
analysis, so before running the steady state analysis, the boundaries of the reach river
have been assumed using the rating curves then the value of the flow discharge has
been assumed to be 0.001 then to be increased suddenly on the next hour of
simulation to be 10 and this will reflect the change from dry case to wet case.
In order to simulate the dry bed of a river through the HEC-RAS, the flow discharge
of the water should be assumed to be very small value at the beginning of the
simulation time then the change of the state from dry to wet will be through
increasing the value of the discharge in the river over the time, the next graph show
the dry bed condition in the steady state analysis where the values of the velocity and
Froude number equals zero:
85
The maximum level of water has been found to be 3.5 meters as shown in the
following figure where the level of water started to increase from 1 meter and stopped
at 3.5 meters at the end of simulation time :
The stage and flow hydrographs can be plotted either using the HEC-RAS or the
Excel, the following figure shows the flow and the stage plots for the 10 station :
86
Finally the values of the stage and the flow can be extracted from the tables of the
unsteady state spatial time series then those values can be transferred into Excel to
plot the stage and the flow hydrograph for each river section altogether in one plot as
shown in the following plots:
Stage Vs Time
4
3.5 10
3
Stage (meters)
8.5
2.5
7.1
2
1.5 5.7
1 4.2
0.5 2.8
0
1.4
0 200 400 600 800
0
Time (minutes)
The previous plot show the decrease in the water level by moving away from the upstream
boundary of the river until it reach the downstream boundary where the value of the stage is
constant and equals 1 meter, the next graph shows the change of flow over time for all river
sections and it is obvious that the flow at the beginning of the river (upstream boundary) is
higher than the flow at the end of the river (downstream boundary):
Flow Vs Time
1.20E+01
10
1.00E+01
8.5
8.00E+00
Flow (m3/s)
7.1
6.00E+00
5.7
4.00E+00
4.2
2.00E+00
2.8
0.00E+00
1.4
-2.00E+00 0 200 400 600 800
0
Time (minutes)
87
4.4.4 Comparison between ISIS and HEC-RAS
There is no big difference in simulating the dry bed river between the two softwares and the
only difference is in the beginning of the simulation time where the hydrograph in ISIS takes
some time to start increasing but in the HEC-RAS it started to increase at (0,0) point as
shown in the following figures:
10
8 S1 (ISIS)
Flow (m3/s)
S4 (ISIS)
6
S8 (ISIS)
4
S1 (HEC-RAS)
2
S4 (HEC-RAS)
0
S8 (HEC-RAS)
0 5 10 15
Time (hours)
1.6
1.5
1.4
S1 (ISIS)
1.3
1.2 S1 (HEC-RAS)
1.1
1
0 5 10 15
Time (hours)
88
4.5 Case 5: Simplified dynamic model for flood routing in rectangular cross
sections channels
The cross section details have been assumed to be the same rectangular section used in the
previous test case and the distances between the sections have been assumed as the same
assumed by (Keskin and Aǵiralioǵlu, 1997); the following table show the detailed distances
between the cross sections of the river:
89
4.5.2 Test case 5 using ISIS
The first step is to define the upstream boundary condition to be as the same in the
following figure which meets the design criteria for (Keskin and Aǵiralioǵlu, 1997):
The number of cross sections have been assumed to be 5 identical cross sections and
their details have been assumed to be as in the following figure with the specified
distances which have been used in the simplified dynamic model method:
90
The downstream boundary condition has been assumed to be a constant stage with 1
meter value over the change of time as shown in the following figure :
The results of the steady state flow analysis are shown below and it shows the values
of the stage which are around 1 meter according to the base flow 3 𝑚3 /𝑠 :
91
The last step is to run the unsteady fixed time step analysis with time step equals to 3
seconds and interval of time equals to 10 seconds as shown in the following graph:
The unsteady state flow analysis has been completed and then the values of flow over time
can be extracted through the CSV tabular command in the ISIS which gives the values of
velocity, stage, flow and others in a table over the change of time:
92
The following figure shows the change of flow values over the time for the five different
sections through the river, it is obvious that the highest value of flow exist in the first section
and it becomes lower and lower at the following sections, the shape of the flow over time at
the first two sections is stable triangle and it becomes more unstable at the following sections:
Flow Vs Time
14
12
10
Flow (m3/s)
8 S1
S2
6
S3
4
S4
2 S5
0
0 0.2 0.4 0.6 0.8 1 1.2
Time (hours)
The following figure shows the inflow hydrograph using the simplified dynamic model
approach which has been found to be similar to the previous graph with some small changes
in the stability and the smoothness of the last two curves for the last two sections:
93
The values of the inflow hydrograph at the first section using the simplified dynamic model
approach and the ISIS have been drawn together in one graph in order to see the difference
between the ISIS and the SD model:
1. The curve of the SD model hit the peak flow value which is 12 𝑚3 /𝑠 but the curve of
the ISIS can’t hit that point but they are still very close to each other.
2. The ISIS is much quicker than the SD model in reaching the peak value and the base
value as shown in the figure.
12
10 SD Model
Flow (m3/s)
8 ISIS
0
0 10 20 30 40 50 60
Time (minutes)
94
4.5.3 Test case 5 using HEC-RAS
Five sections have been inserted using the same details as used in the ISIS as shown
in the following figure:
Before running the simulation analysis, the upstream and the downstream boundaries
have been defined using the same stage and flow hydrographs which have been used
in the ISIS as shown in the following figures:
95
The values of the flow discharge over the change in time have been found using the
unsteady flow time series command in the HEC-RAS and then those values have been
moved to the Excel to draw the flow hydrograph for the different river sections:
Flow Vs Time
14
12
S1 (HEC-RAS)
10
S2 (HEC-RAS)
Flow (m3/s)
8 S3 (HEC-RAS)
6 S4 (HEC-RAS)
4 S5 (HEC-RAS)
0
0 0.2 0.4 0.6 0.8 1
Time (minutes)
The flow hydrograph of the ISIS and the HEC-RAS for S1, S3 and S5 have been
drawn together in one graph and from the graph it can be noticed that the flow
hydrograph of the HEC-RAS is quicker than the flow hydrograph of the ISIS and that
means the HEC-RAS reaches the peak flow value before the ISIS. One other point can
be noticed where the values of the flow hydrograph of the ISIS at the end of the river
(at section 5) are higher than the values of the flow hydrograph of the HEC-RAS.
ISIS Vs HEC-RAS
14
S1 (HEC-RAS)
12
S3 (HEC-RAS)
10
Flow (m3/s)
S5 (HEC-RAS)
8
6 S1 (ISIS)
4 S3 (ISIS)
2 S5 (ISIS)
0
0 0.2 0.4 0.6 0.8 1 1.2
Time (hours)
96
The comparison of the flow hydrographs between ISIS, HEC-RAS and the simplified
dynamic model can be noticed after drawing all of the flow hydrographs in one graph and in
order to make the comparison very clear the graphs have been divided into 3 graphs each one
describe the comparison at different section through the river:
8 S1 (ISIS)
6
S1 (SDM)
4
2
0
0 0.2 0.4 0.6 0.8 1 1.2
Time (hours)
10
S3 (HEC-RAS)
8
Flow (m3/s)
6 S3 (ISIS)
4 S3 (SDM)
2
0
0 0.2 0.4 0.6 0.8 1 1.2
Time (hours)
97
ISIS Vs HEC-RAS Vs SDM
(AT S5)
10
9
8
7 S5 (HEC-RAS)
Flow (m3/s)
6
5 S5 (ISIS)
4
3 S5 (SDM)
2
1
0
0 0.2 0.4 0.6 0.8 1 1.2
Time (hours)
1. At the first section of the river the three methods are very close to each other even
though the HEC-RAS is quicker than the other two methods.
2. At the third section S3, the values of the flow hydrograph for the HEC-RAS are the
highest followed by the ISIS flow hydrograph values followed by the SDM method.
3. At the end of the river there is a clear instability in the ISIS and the HEC-RAS but in
the SDM maintained its stability and the values are smoother than the other two
methods.
98
4.6 Comparison highlight between ISIS and HEC-RAS
4.6.1 Comparison highlight between ISIS and HEC-RAS according to the cases
observations
By looking at the comparisons which have been done between the two softwares during the 5
previous cases some major points can summarize the observed difference between the ISIS
and the HEC-RAS, those differences are listed below in the following points:
The ISIS and the HEC-RAS have resulted in the same stage hydrograph and the same
output values for the first test case and the only difference between the two softwares
were the two following points:
1. The HEC-RAS can reach higher maximum stage value than the ISIS.
2. The difference in stage values between the upstream and the downstream levels for
the ISIS was larger than the one resulted from the HEC-RAS.
In the comparison of the outflow hydrographs which have done in the second test case
it has been found that the HEC-RAS recorded higher flow value than the ISIS at the
time of the Malpasset dam break which was 7200 𝑚3 /𝑠 but the ISIS recorded 6000
𝑚3 /𝑠 , this means that the ISIS give a higher factor of safety than the HEC-RAS.
In the third test case the two softwares have been noticed to be very close to each
other and the only difference noticed is the time needed for the ISIS to reach to the
maximum flow value and the same thing has been found in the stage hydrograph and
from this point it can be concluded that the ISIS is slower than the HEC-RAS in most
of the points.
There is an obvious problem can be noticed in the ISIS when the dry bed river has
been simulated because it needed some time to start the increasing in the flow and the
stage hydrograph but the HEC-RAS started to increase at the (0,0) point and didn’t
need much simulation time to do that.
There is no much difference between the two softwares in the last test case where the
flow hydrographs at different river sections have been found to be similar to each
other with a slight difference in the maximum flow value at the end of the river and
some instability of the two softwares at the simulation of the end of the river.
The HEC-RAS give the user the choice to enter the reach boundaries but in the ISIS it
should be as a flow hydrograph or stage hydrograph only.
99
4.6.2 Comparison between ISIS and HEC-RAS according to the CPU time
The CPU required time to converge or to find the results in each software has been calculated
for each simulation case and then showed in the following table:
From the table above it is very obvious that the CPU elapsed time by the HEC-RAS in both
the steady and the unsteady flow analysis is much less than the CPU elapsed time by the ISIS
and this is considered as an advantage to the HEC-RAS in the race between the two
softwares. The following figure summarizes also the difference in the CPU elapsed time
between the two softwares:
2.5
1.5 ISIS
HEC-RAS
1
0.5
0
Case1 Case2 Case3 Case4 Case5
100
Chapter 5: Conclusions, Recommendations and Future work
5.1 Conclusions
After five simulation cases have been done through the ISIS and the HEC-RAS, detailed
comparisons have been conducted also so the best software can be recommended, there are
many difficulties have been experienced from the simulation results while using the ISIS but
on the other hand the HEC-RAS doesn’t have these troubles, the following points conclude
the differences between the two softwares:
In simulating the dry river bed conditions the ISIS consumes some of the simulation
time before starts to increase the flow and the stage values in both the flow and the
stage hydrographs which will cause sort of replicating problem and this happens in
the ISIS free edition because it is 1D limited package which doesn’t have the ability
to simulate the case of the dry river bed accurately on the other hand the HEC-RAS
doesn’t consume any time in simulating the dry river bed conditions and it starts to
simulate the flow hydrograph from the first part of the second.
In simulating the dam break test the ISIS gives a higher factor of safety than the HEC-
RAS while the HEC-RAS gives values and results closer to the numerical physical
models which have been done in previous reports.
As mentioned before that the ISIS gives the ability to enter only one option to define
the boundary conditions which are the stage and the flow hydrographs but the HEC-
RAS gives more options to define that as the critical depth, the stage/flow hydrograph
which gives the ability to insert the two values simultaneously.
From the comparison of the CPU consumed time in both softwares it is very clear that
the ISIS consumes more CPU time in order to find the results than the HEC-RAS.
Finally and from this research it has been found that both of the HEC-RAS and the ISIS are
considered as very efficient softwares in the field of the numerical simulation analysis for the
river floods and the dam break simulation tests but from the differences listed above it can be
stated that the HEC-RAS is faster, more accurate, more reliable, more flexible and can
simulate any test case without any difficulty however the ISIS could be similar in the
processing speed yet a rather expanded range of values should be tried and tested at inputs to
further validate a broad spectrum for the simulation outputs.
101
5.1 Recommendations and future work
In this part some points have been recommended to be applied and studied in the future
studies:
It should test both softwares ISIS and HEC-RAS with large amount of data input to
study the processing time for the response that the simulations could give for these
data and further validate which software could be more appropriate for the data type
and ranges acquired through research.
It should work out a complete investigation about the topics and collect more data to
be inserted in the simulations so more reliable results will get out from the softwares.
More improvements are needed in the next studies should be made on the simulations
model and their limitations and try to solve the problems appeared in the previous
studies such as the dry bed simulations in the 1D package.
The future studies should propose an emergency response plans in the cases of dam
breaks and river flooding.
It should test which is the most suitable software for river flood simulations between
the ISIS and the HEC-RAS throughout changing the types of the simulation cases and
increase the size of each case.
102
REFERENCES
Abdullah R., Berhad S., Pengeluaran J. (2009). Dam Break Analysis: A Case Study at Durian
Tunggal Dam, Mesyuarat Tahunan JTJAD Kali Ke 22 & Mesyuarat Exco JTJAD Bil 8 Sesi
2007-2010.
Ahmed M., Morris M. (1999), Malpasset Dam-Break Test Case A Comparison between the
ISIS Numerical Model Results and the Field and Physical Model Data. ISIS, pp. 219-226.
Ahmed M., Morris M. (1999), Toce River Dam-Break Test Case Revisited. ISIS, pp. 207-
218.
Anderson, J., (1995). Computational Fluid Dynamics. 1st Ed. London: McGraw-Hill
Science/Engineering/Math.
Brown J., Damery S. (2002), Managing Flood Risk in the UK: Towards an Integration of
Social and Technical Perspectives. Transactions of the Institute of British Geographers, New
Series, Vol. 27, No. 4, pp. 412-426.
Chanson H. (2009), Embankment Overflow Protections System and Earth Dam Spillways. in
"Dams: Impact, Stability and Design", Nova Science Publishers, Hauppauge NY, USA, Ed.
W.P. Hayes and M.C. Barnes, Chapter 4, pp. 101-132. ISBN 978-1-60692-618-5.
Coface (2003), Hydroelectric power stations and large dams. Environmental Guidelines,
available on [www.adb.org/water/topics/dams/pdf/barragesgb.pdf], accessed on 12/06/2011.
103
Federal Emergency Management Agency (2006), “Why Dams Fail?”, available on
[www.fema.gov/hazard/damfailure/why.shtm], accessed on 17/06/2011.
Harrald J., Renda-Tanali I., Shaw G., Rubin, C. B., Yeletaysi, S. (2004). Review of Risk
Based Prioritization Decision Making Methodologies for Dams. Risk Management. The
George Washington University. Institute for Crisis, Disaster, and Risk Management.
Hill P., Bowles D., Jordan P., Nathan, R. (2003). Estimating Overall Risk of Dam Failure:
Practical Considerations in Combining Failure Probabilities. Introduction Estimating
Probabilities in Dam, ANCOLD Risk Workshop.
Keskin, M. E., Ag, N. (1997), A simplified dynamic model for flood routing in rectangular
channels, Journal of Hydrology, vol 202, issues (1-4), pp. 302-314, doi:10.1016/S0022-
1694(97)00072-3.
NRCS (Natural Resources Conservation Service) (2003), Dam, Diversion, (No. Or Ft.) Code
348, pp. 1-2.
104
Nuera A. (2005), The Asian Development Bank And Dams. NGO Forum on ADB
Guidebook Series, First Edition, pp. 3-10. Philippines.
Robinson R., Kerr J., Noschese F., Klein N., Belasen A. (2002), Cracking Dams. Syracuse
University, available on [http://simscience.org/cracks/index.html], accessed on 11/06/2011.
Rosu C., Ahmed M. (1999), Toce River dam-break test case: A comparison between the ISIS
numerical model and the Physical Model, ISIS, pp. 207-218.
Rowsell E., Handmer J. (1988), Flood Hazard Management in Britain: A Changing Scene
The Geographical Journal, Vol. 154, No. 2, pp. 209-220.
Samuels P. (2003), Flood risk and flood forecasting – the state-of-the-art in EU research, EU-
MEDIN on disaster research, available on [http://eprints.hrwallingford.co.uk/37/], accessed
on 10/06/2011.
US Army Corps of Engineers, Institute for Water Resources Hydrologic Engineering. 2010.
HEC-RAS River Analysis System Applications Guides. [online]. Available on
[http://www.hec.usace.army.mil/software/legacysoftware/hec1/hec1-documentation.htm],
accessed on 05/07/2011.
105
Yongquan W. (1993), Solar activity and maximum floods in the world. Extreme
Hydrological Events: Precipitation, Floods and Droughts. Proceedings of the Yokohama
Symposium, IAHS Publ. no. 213.
106