0% found this document useful (0 votes)
42 views

SMC Assignment 6 Corrected 1

This document provides information to calculate points earned for sustainable material and construction categories for a 4-story building under construction. It finds that 67.54% of structural elements were reused, earning 1 point under MRC 1.1 for Building Reuse. It also finds that the recycled content of materials used is 1.8147% of total material cost, less than the 10% required to earn points under MRC 1.3 for Recycled Content. Therefore, no points will be earned for Recycled Content.

Uploaded by

gautham
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
42 views

SMC Assignment 6 Corrected 1

This document provides information to calculate points earned for sustainable material and construction categories for a 4-story building under construction. It finds that 67.54% of structural elements were reused, earning 1 point under MRC 1.1 for Building Reuse. It also finds that the recycled content of materials used is 1.8147% of total material cost, less than the 10% required to earn points under MRC 1.3 for Recycled Content. Therefore, no points will be earned for Recycled Content.

Uploaded by

gautham
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

SUSTAINABLE

MATERIALS AND
CONSTRUCTION
SUBMITTED BY
ASSIGNMENT 6 GOUTHAM M
2019PCS5488
STRUCTURAL ENGG

SUBMITTED TO
PROF.SANDEEP
SHRIVASTAVA
DEPT OF CIVIL
ENGINEERING
MNIT ,JAIPUR
GIVEN

Number of storeys=4

Height of each storey =4m

Total cost of construction=20L

Percentage of material cost=45%=9 L

Waste for landfill=25 tons

Density of waste =900 kg/m3

Percentage of bricks reused =25%

Rest 75% new bricks which has 30% fly ash content

Price of 1 fly ash brick=6rs

Price of 1 conventional brick =3rs

Sl particulars Reused part Demolished part Total


no
1 SLAB +ROOF AREA 6x4x5=120 m2 4x3x5=60 m2 180 m2

2 Wall area [(6.6+4)X2X4X4]=339.2m2 [(4.6+3+3)X4X4]=169.6 508.8 m2


m2
3 Door and window [(1.5x2)+(1.5x2.3)]x4=25.8 m2 [(1.5x2.3)+(1x2)]x4= m2 47.6 m2
deduction
4 Net masonry area 339.2-25.8=313.4 m2 169.6-21.8=147.8 m2 461.2 m2

5 Foundation plan area 6x4=24 m2 4x3=12 m2 36 m2

6 A. MRC1=

7 Fly ash bricks cost

8 RCV

9 B. MRC4=

1
As per IGBC Material and Resource category:

How many points the team may get under MRC 1.1: Building Reuse

Total area of including slab + roof area, net masonry area and foundation plan area=180+461.2+36

=677.2 m2

Area of sturctural elements Retained (re-used) =120+313.4+24

[ Slab area + roof area+ net masonry area + foundation plan area] = 457.4 m2

Percentage of retained = [ 457.4/677.2]x100 = 67.54% which is greater than 50%

Ensure at least 50% (by area) of the structural and/or at least 25% (by area) of the non-structural
(interiors) elements of the existing building are retained.

SL PARTICULARS PERCENTAGE RETAINED POINTS


NO AWARDED
1 Structural elements 67.54% > 50% 1

Total points earned under MRC 1.1: Building reuse = 1 points

2
How many points may be achieved under MRC 1.3: Recycled content

Total cost of construction=20L Rs

Percentage of material cost=45%=9 L Rs

Cost of total recycled content = RCV = 147.8x0.3x500x0.25x3

=16627.5 Rs

Percentage of Materials with Recycled Content = [16627.5/900000]x100 = 1.847%

Use materials with recycled content in the building (as per owner / developer’s scope) such that
the total recycled content constitutes at least 10% of the total cost of building materials.

SL PARTICULARS PERCENTAGE POINTS


NO AWARDED
1 Total recycled content 1.8147% < 10% 0

Total points awarde under MRC 1.3: Recycled Content = 0 points