VISAKH REFINERY
FORMAT OF INSPECTION WORK LIST
TECHNICAL DEPARTMENT Doc. No. OCP/TSD/FR/305/Rev.2
Rev. Date : 16-Jan-02
(Ref. Pro.:OCP/TSD/PR/204)
Page 1 of 1
WORK LIST No. : 17-673520 IWL.DESC.: CCR: IWL for CCR Reactor Reduction zone gasket Date:
LOCATION : CCR_REAC LOC.DESC.: CCR Reactors INSP. BY: B M JEELANI
Equipment : REF:
Reduction Zone/Reactor-I gasket was replaced in July 2015 with new Kammprofile
gasket and a weather shield was provided at the flange joint. The joint previously had
developed leak on two instances due to gasket failure. Keeping in view of criticality &
long term reliability of the joint and forthcoming T&I of the unit in 2018, a new gasket
of M/s Flexitalic gasket is recommended to be kept as spare. The usage of Flexitallic
thermiculite 845 Flexpro (Kamprofile style ZA) or equal is specified by M/s UOP. The
similar gasket of Flexitalic make has been procured at MR also. Refer Item No. 107,
Drawing No. PPPV-2299-01-A-000.
Sl No. LOCATION/ITEM OBSERVATION RECOMMENDATION
10 Gasket for flange joint between Frequent leaks and fire incidents were reported at the flange joint 1. Procure and keep as spare, 1 no.
Reactor #1 and Reduction zone between Recator No. 1 (74R-01) and Reduction zone. Presently Flexitallic thermiculite 845 Flexpro
Kammpofile graphite with graphite withstanding up to temperatures of (Kamprofile style ZA) make gasket. The
550 deg.C. was provided in July 2015. A weather shield has been gasket can be replaced in T&I -2018.
provided at the flange joint as per UOP recommendations.
As per UOP advisory for Platforming process unit-Reactor external
flange, in order to minimize the chances of reactors external leaks,
usage of Flexitallic thermiculite 845 Flexpro (Kamprofile style ZA) or
equal is specified for the gasket between Reactor 1 and Reduction
Zone flange joint.
____________________________
HEAD-INSPECTION