The document provides installation guidelines for an analyzer system. It instructs to inspect received goods for damage, prepare the site with a level cement platform in a ventilated room away from heat and weather, and install the wet panel/dry panel accordingly. It also provides guidelines for laying sample tubes and cables, with instructions on routing, materials, and terminations. Drain should be connected to a suitable pit.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
79 views

Install Swas

The document provides installation guidelines for an analyzer system. It instructs to inspect received goods for damage, prepare the site with a level cement platform in a ventilated room away from heat and weather, and install the wet panel/dry panel accordingly. It also provides guidelines for laying sample tubes and cables, with instructions on routing, materials, and terminations. Drain should be connected to a suitable pit.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

INSTALLATION

GUIDELINES
INSTALLATION GUIDELINES

 On receipt of consignment

1. Please inform us so that we can send our engineer for pre-commissioning visit.
Our engineer will visit the site for verification of goods received and discuss with
your engineers regarding site preparation and installation work.

2. Examine the unit for any shipping damage. If in doubt, please take picture of the
damaged items. Examine for any visible damage. Report damage to insurance
agency and lodge the claim.

3. Dispatch documents contain packing list.

4. If commissioning is delayed because of any reason, Please repack the system


with the same packing material and keep in store, away from direct sun and rain.

♦ Installation

Installation and regular maintenance are the two major aspects apart from
engineering for getting best performance from analyser system.

Following are the important guideline for installation of the system.

♦ Installation of wet panel/dry panel

Wet panel/dry panel should be installed in well ventilated room away from direct sun
and rain.

Wet panel/dry panel should be installed on a cement platform which is free from
vibration and has level surface and properly grouted in the platform.

By the means if it is not possible to mount wet panel/dry panel in a room, suitable
covering should be provided to protect the wet panel/dry panel from sunlight / rain.
Wet panel/dry panel front should be directed towards north or South.

Analyser and any other LCD displays should not be exposed to direct sunlight. We
strongly recommend not mounting the panel near boiler or any other heat dissipating
area.
♦ Tube laying

Sample tube material should be selected based on constituents of the sample.


SS316 tube is generally accepted material for sample tube.

The sample tubing should be easily accessible to rectify leak. Sample tube size
preferred is 1/4” OD.

♦ Cable laying

Lateral frame at the base of around 500MM should be given for cable connections.

Signal cable should never be laid with the high tension lines. Also route the signal
cable such that distance between panel and control room get minimized. Cable
should always be drawn into the panel after proper glanding. Ferruling, lugging and
dressing is required before terminating the cable to the terminal blocks.

Earth pit should be checked properly and provided in the vicinity of the wet panel/dry
panel/chiller unit earthing should be provided on the first priority before terminating
the power cables.

Always make the power supply connection last with the main switch turned off.

♦ Drain

Drain should be connected to suitable drain pit.