Block-C: SL Activity Dur. (Days) Start Finish Remarks Toilet+Store Area

The document outlines a schedule for construction activities across multiple blocks (A, B, C) with details on duration, start and finish dates for each activity. It includes activities like plastering, tiling, painting, mechanical, electrical and plumbing works. The schedule spans from December to March with various activities in the different blocks running in parallel following dependencies between start and finish dates of preceding activities.

Uploaded by

Peter Odhiambo
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
86 views7 pages

Block-C: SL Activity Dur. (Days) Start Finish Remarks Toilet+Store Area

The document outlines a schedule for construction activities across multiple blocks (A, B, C) with details on duration, start and finish dates for each activity. It includes activities like plastering, tiling, painting, mechanical, electrical and plumbing works. The schedule spans from December to March with various activities in the different blocks running in parallel following dependencies between start and finish dates of preceding activities.

Uploaded by

Peter Odhiambo
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 7

Block-C

Sl Activity Dur. (Days) Start Finish Remarks


Toilet+Store Area
1 Col. Casting for store and toilets 5 26-Dec 31-Dec
2 Slab casting for store and toilets 21 31-Dec 21-Jan
3 Block Work 8 14-Jan 22-Jan Finish=Slab Finish+1
4 MEP Conduits 3 21-Jan 24-Jan Block Finish+2
5 Internal Plastering Works 10 22-Jan 1-Feb MEP Start+1
6 Plastering Inspection 1 2-Feb 2-Feb Plaster Finish + 1
7 False ceiling 4 3-Feb 7-Feb Plaster Finish + 1
8 Door Frame 2 4-Feb 6-Feb Plaster Finish + 2
9 Window Fixing 2 4-Feb 6-Feb Plaster Finish + 2
10 Internal Painting 10 3-Feb 13-Feb Plaster Insp + 1
11 Tiling (Wall&Floor) 10 26-Jan 5-Feb Block Finish+4
12 MEP Fixtures 5 10-Feb 15-Feb Int.paint finish-3 to start
13 External Plaster works 5 24-Jan 29-Jan Block Finish+2
14 External painting 8 31-Jan 8-Feb Ext. Plaster finish +2
15 Wall Cladding for Shed 2 31-Jan 2-Feb Ext. Plaster finish +2

Shed and Mezannain Area


1 Block Work 15 25-Dec 9-Jan Start +15
2 MEP Conduits 8 3-Jan 11-Jan Block Finish+2
3 Internal Plastering Works 15 4-Jan 19-Jan MEP Start+1
4 Plastering Inspection 1 20-Jan 20-Jan Plaster Finish + 1
5 False ceiling 8 21-Jan 29-Jan Plaster Finish + 1
6 Door Frame 2 22-Jan 24-Jan Plaster Finish + 2
7 Window Fixing 2 22-Jan 24-Jan Plaster Finish + 2
8 Internal Painting 15 21-Jan 5-Feb Plaster Insp + 1
9 Floor Tiling 8 21-Jan 29-Jan Start=Plaster Finish+2
10 MEP Fixtures 3 2-Feb 5-Feb Int.paint finish-3 to start
11 External Plaster works 8 11-Jan 19-Jan Block Finish+2
12 External painting 8 21-Jan 29-Jan Ext. Plaster finish +2
13 Wall Cladding for Shed 3 21-Jan 24-Jan
Block-A
Sl Activity Dur. (Days) Start Finish Remarks

1 Internal Plastering Works 30-Dec Ongoing


2 Plastering Inspection 1 2-Jan 2-Jan Fixed
3 Wall Tiling 25 20-Jan 14-Feb
4 Wall Painting (upto pre-final) 25 3-Jan 28-Jan Plaster inspection+1
5 Floor tiling and threshold 22 9-Feb 3-Mar Wall tile finish-5
GROUND FLOOR

6 Gyp. False ceiling installation 25 13-Jan 7-Feb Wall paint start+10


7 Ceiling Painting C1 (upto pre-final) 20 31-Jan 20-Feb Start=Flase ceiling finish-7
8 Sanitarywares and toilet fittings & Accessories 25 15-Feb 12-Mar Wall Tiling Finish+1
9 Skirting 8 28-Feb 8-Mar Floor Tile Finish-3
10 Door Installation 14 9-Feb 23-Feb
11 Al. False ceiling installation 8 15-Feb 23-Feb Wall Tile Finish+1
12 Painting-Final Coat 14 9-Mar 23-Mar Skirting Finish+1
13 MEP- Wiring, A/C and Fire fighting works 40 31-Dec 9-Feb Plaster finish+1
14 MEP-Final Fix switches and light fixtures etc… 25 29-Jan 23-Feb Paint (pre-final)+1

1 Block Work 7 27-Dec 3-Jan


2 Internal Plastering Works 10 4-Jan 14-Jan Block Finish+1
3 Plastering Inspection 1 16-Jan 16-Jan Fixed
4 Wall Tiling 25 25-Jan 19-Feb
5 Wall Painting (upto pre-final) 18 17-Jan 4-Feb Plaster inspection+1
6 Floor tiling andd threshold 18 14-Feb 4-Mar Wall tile finish-5
FIRST FLOOR

7 Gyp. False ceiling installation 25 27-Jan 21-Feb Wall paint start+10


8 Ceiling Painting C1 18 14-Feb 4-Mar Start=Flase ceiling finish-7
9 Sanitarywares and toilet fittings&Accessories 25 20-Feb 17-Mar Wall Tiling Finish+1
10 Skirting 8 1-Mar 9-Mar Floor Tile Finish-3
11 Door Installation 6 14-Feb 20-Feb
12 Al. False ceiling installation 8 20-Feb 28-Feb Wall Tile Finish+1
13 Wall Painting-Final Coat 10 10-Mar 20-Mar Skirting Finish+1
14 MEP- Wiring, A/C and Fire fighting works 40 15-Jan 24-Feb Plaster finish+1
15 MEP-Final Fix switches and light fixtures etc… 25 9-Feb 6-Mar Paint (pre-final)+1

1 Plinth for A/C Machines Casting 10 10-Jan 20-Jan


2 Water Proofing Work 14 22-Jan 5-Feb 2+Upstand casting
ROOF

3 Tiling 10 6-Feb 16-Feb After Water Proofing


4 Plastering Works 6 17-Feb 23-Feb After Tiling
5 Painting 10 26-Feb 8-Mar Plastering Finish+3
6 Chiller Installation and commissioning 40 24-Jan 5-Mar 4Days after casting plinth
EXTERNAL WORKS

1 External Plastering 16 8-Jan 24-Jan FF Block work finish+5


2 External Painting 21 18-Jan 8-Feb Plaster start+10
3 Aluminum windows 15 23-Jan 7-Feb Ext. paint start+5
4 Ext. light fittings 6 9-Feb 15-Feb Ext. Paint+1
Block-B
Sl Activity Dur. (Days) Start Finish Remarks

1 Plastering Inspection 1 29-Dec 29-Dec Fixed


2 Wall Tiling 28 20-Jan 17-Feb
3 Wall Painting (upto pre-final) 25 7-Jan 1-Feb
4 Floor tiling and threshold 16 15-Feb 3-Mar Wall tile finish-2
GROUND FLOOR

5 Ceiling Painting C1 (upto pre-final) 20 5-Jan 25-Jan


6 Sanitarywares and toilet fittings & Accessories 25 18-Feb 15-Mar Wall Tiling Finish+1
7 Skirting 6 28-Feb 6-Mar Floor Tile Finish-3
8 Window Fixing 10 23-Jan 2-Feb Plaster Finish+25
9 Door Installation 14 15-Feb 1-Mar
10 False ceiling installation 15 18-Feb 5-Mar Wall Tile Finish+1
11 Painting-Final Coat 14 7-Mar 21-Mar Skirting Finish+1
12 MEP- Wiring, A/C and Fire fighting works 40 30-Dec 8-Feb Plaster Insp.+1
13 MEP-Final Fix switches and light fixtures etc… 25 2-Feb 27-Feb Paint (pre-final)+1

1 Block Work 7 25-Dec 1-Jan


2 Internal Plastering Works 10 2-Jan 12-Jan Block Finish+1
3 Plastering Inspection 1 14-Jan 14-Jan Fixed
4 Wall Tiling 25 25-Jan 19-Feb
5 Wall Painting (upto pre-final) 18 15-Jan 2-Feb Plaster inspection+1
6 Floor tiling andd threshold 18 14-Feb 4-Mar Wall tile finish-5
FIRST FLOOR

7 Ceiling Painting C1 18 19-Jan 6-Feb


8 Sanitarywares and toilet fittings&Accessories 25 20-Feb 17-Mar Wall Tiling Finish+1
9 Skirting 8 1-Mar 9-Mar Floor Tile Finish-3
10 Door Installation 6 14-Feb 20-Feb
11 Window Fixing 15 27-Jan 11-Feb Plaster Finish+15
12 False ceiling installation 15 20-Feb 7-Mar Wall Tile Finish+1
13 Wall Painting-Final Coat 10 10-Mar 20-Mar Skirting Finish+1
14 MEP- Wiring, A/C and Fire fighting works 40 13-Jan 22-Feb Plaster finish+1
15 MEP-Final Fix switches and light fixtures etc… 25 7-Feb 4-Mar Paint (pre-final)+1

1 Plinth for Split Units Casting 4 10-Jan 14-Jan


2 Water Proofing Work 14 16-Jan 30-Jan 4+Upstand casting
3 Tiling 10 31-Jan 10-Feb After Water Proofing
ROOF

4 Plastering Works 6 11-Feb 17-Feb After Tiling


5 Painting 10 20-Feb 2-Mar Plastering Finish+3
6 Split units Installation and commissioning 20 18-Jan 7-Feb 4Days after casting plinth
7 Pump and piping works 15 18-Jan 2-Feb 4Days after casting plinth
EXTERNAL WORKS

1 External Plastering 16 6-Jan 22-Jan FF Block work finish+5


2 External Painting 21 16-Jan 6-Feb Plaster start+10
3 Aluminum windows 15 21-Jan 5-Feb Ext. paint start+5
4 Ext. light fittings 6 7-Feb 13-Feb Ext. Paint+1
EXTERNAL WORKS, COMMISSIONING & HAND OVER
Sl Activity Dur. (Days) Start Finish Remarks

1 Drainage Pipes and Manholes 16 15-Jan 31-Jan Depend on Municipality Approval


2 Water Supply piping 21 25-Jan 15-Feb Plaster start+10
EXTERNAL WORKS

3 Drainage Connection 15 30-Jan 14-Feb Ext. paint start+5


4 Foot path pasco 10 16-Feb 26-Feb Ext. Paint+1
5 Water SupplyConnection 0 20-Feb 20-Feb
6 Boundary Wall 15 5-Feb 20-Feb Date as per Base Line
7 Gates and Luvers 9 2-Mar 11-Mar Date as per Base Line
8 Substation Completion 0 15-Jan 15-Jan Fixed

1 Power On 0 20-Mar 20-Mar Bldg. completion certification+5


COMMISSIONING

2 LV Commissioning 14 9-Mar 23-Mar start=Block B FF MEP Final+5


3 Fire System 5 9-Mar 14-Mar start=Block B FF MEP Final+5
4 HVAC 15 6-Mar 21-Mar Chiller instal finish+1
5 Plumbing 14 5-Mar 19-Mar MEP Final -B +1
6 Communication 9 9-Mar 18-Mar MEP Final -B +5

1 As Built Structural 21 15-Feb 8-Mar


2 As Built MEP 21 20-Feb 13-Mar
3 As Built Architectural 21 25-Feb 18-Mar
HAND OVER

4 ADDC Final Insp. - NOC Power on 0 11-Mar 11-Mar Block B FF MEP Final+5
5 Substation insp. and approval 0 18-Jan 18-Jan Substation Completion+3
6 Estimation and payment by client 7 19-Jan 26-Jan Aubstation Approval + 1
7 Building completion Certificate - ADM 10 5-Mar 15-Mar start=Block B FF MEP Final+1
8 Snagging Desnagging 23 5-Mar 28-Mar start=Block B FF MEP Final+1
9 Hand Over 0 30-Mar 30-Mar