Block-C
Sl Activity Dur. (Days) Start Finish Remarks
Toilet+Store Area
1 Col. Casting for store and toilets 5 26-Dec 31-Dec
2 Slab casting for store and toilets 21 31-Dec 21-Jan
3 Block Work 8 14-Jan 22-Jan Finish=Slab Finish+1
4 MEP Conduits 3 21-Jan 24-Jan Block Finish+2
5 Internal Plastering Works 10 22-Jan 1-Feb MEP Start+1
6 Plastering Inspection 1 2-Feb 2-Feb Plaster Finish + 1
7 False ceiling 4 3-Feb 7-Feb Plaster Finish + 1
8 Door Frame 2 4-Feb 6-Feb Plaster Finish + 2
9 Window Fixing 2 4-Feb 6-Feb Plaster Finish + 2
10 Internal Painting 10 3-Feb 13-Feb Plaster Insp + 1
11 Tiling (Wall&Floor) 10 26-Jan 5-Feb Block Finish+4
12 MEP Fixtures 5 10-Feb 15-Feb Int.paint finish-3 to start
13 External Plaster works 5 24-Jan 29-Jan Block Finish+2
14 External painting 8 31-Jan 8-Feb Ext. Plaster finish +2
15 Wall Cladding for Shed 2 31-Jan 2-Feb Ext. Plaster finish +2
Shed and Mezannain Area
1 Block Work 15 25-Dec 9-Jan Start +15
2 MEP Conduits 8 3-Jan 11-Jan Block Finish+2
3 Internal Plastering Works 15 4-Jan 19-Jan MEP Start+1
4 Plastering Inspection 1 20-Jan 20-Jan Plaster Finish + 1
5 False ceiling 8 21-Jan 29-Jan Plaster Finish + 1
6 Door Frame 2 22-Jan 24-Jan Plaster Finish + 2
7 Window Fixing 2 22-Jan 24-Jan Plaster Finish + 2
8 Internal Painting 15 21-Jan 5-Feb Plaster Insp + 1
9 Floor Tiling 8 21-Jan 29-Jan Start=Plaster Finish+2
10 MEP Fixtures 3 2-Feb 5-Feb Int.paint finish-3 to start
11 External Plaster works 8 11-Jan 19-Jan Block Finish+2
12 External painting 8 21-Jan 29-Jan Ext. Plaster finish +2
13 Wall Cladding for Shed 3 21-Jan 24-Jan
Block-A
Sl Activity Dur. (Days) Start Finish Remarks
1 Internal Plastering Works 30-Dec Ongoing
2 Plastering Inspection 1 2-Jan 2-Jan Fixed
3 Wall Tiling 25 20-Jan 14-Feb
4 Wall Painting (upto pre-final) 25 3-Jan 28-Jan Plaster inspection+1
5 Floor tiling and threshold 22 9-Feb 3-Mar Wall tile finish-5
GROUND FLOOR
6 Gyp. False ceiling installation 25 13-Jan 7-Feb Wall paint start+10
7 Ceiling Painting C1 (upto pre-final) 20 31-Jan 20-Feb Start=Flase ceiling finish-7
8 Sanitarywares and toilet fittings & Accessories 25 15-Feb 12-Mar Wall Tiling Finish+1
9 Skirting 8 28-Feb 8-Mar Floor Tile Finish-3
10 Door Installation 14 9-Feb 23-Feb
11 Al. False ceiling installation 8 15-Feb 23-Feb Wall Tile Finish+1
12 Painting-Final Coat 14 9-Mar 23-Mar Skirting Finish+1
13 MEP- Wiring, A/C and Fire fighting works 40 31-Dec 9-Feb Plaster finish+1
14 MEP-Final Fix switches and light fixtures etc… 25 29-Jan 23-Feb Paint (pre-final)+1
1 Block Work 7 27-Dec 3-Jan
2 Internal Plastering Works 10 4-Jan 14-Jan Block Finish+1
3 Plastering Inspection 1 16-Jan 16-Jan Fixed
4 Wall Tiling 25 25-Jan 19-Feb
5 Wall Painting (upto pre-final) 18 17-Jan 4-Feb Plaster inspection+1
6 Floor tiling andd threshold 18 14-Feb 4-Mar Wall tile finish-5
FIRST FLOOR
7 Gyp. False ceiling installation 25 27-Jan 21-Feb Wall paint start+10
8 Ceiling Painting C1 18 14-Feb 4-Mar Start=Flase ceiling finish-7
9 Sanitarywares and toilet fittings&Accessories 25 20-Feb 17-Mar Wall Tiling Finish+1
10 Skirting 8 1-Mar 9-Mar Floor Tile Finish-3
11 Door Installation 6 14-Feb 20-Feb
12 Al. False ceiling installation 8 20-Feb 28-Feb Wall Tile Finish+1
13 Wall Painting-Final Coat 10 10-Mar 20-Mar Skirting Finish+1
14 MEP- Wiring, A/C and Fire fighting works 40 15-Jan 24-Feb Plaster finish+1
15 MEP-Final Fix switches and light fixtures etc… 25 9-Feb 6-Mar Paint (pre-final)+1
1 Plinth for A/C Machines Casting 10 10-Jan 20-Jan
2 Water Proofing Work 14 22-Jan 5-Feb 2+Upstand casting
ROOF
3 Tiling 10 6-Feb 16-Feb After Water Proofing
4 Plastering Works 6 17-Feb 23-Feb After Tiling
5 Painting 10 26-Feb 8-Mar Plastering Finish+3
6 Chiller Installation and commissioning 40 24-Jan 5-Mar 4Days after casting plinth
EXTERNAL WORKS
1 External Plastering 16 8-Jan 24-Jan FF Block work finish+5
2 External Painting 21 18-Jan 8-Feb Plaster start+10
3 Aluminum windows 15 23-Jan 7-Feb Ext. paint start+5
4 Ext. light fittings 6 9-Feb 15-Feb Ext. Paint+1
Block-B
Sl Activity Dur. (Days) Start Finish Remarks
1 Plastering Inspection 1 29-Dec 29-Dec Fixed
2 Wall Tiling 28 20-Jan 17-Feb
3 Wall Painting (upto pre-final) 25 7-Jan 1-Feb
4 Floor tiling and threshold 16 15-Feb 3-Mar Wall tile finish-2
GROUND FLOOR
5 Ceiling Painting C1 (upto pre-final) 20 5-Jan 25-Jan
6 Sanitarywares and toilet fittings & Accessories 25 18-Feb 15-Mar Wall Tiling Finish+1
7 Skirting 6 28-Feb 6-Mar Floor Tile Finish-3
8 Window Fixing 10 23-Jan 2-Feb Plaster Finish+25
9 Door Installation 14 15-Feb 1-Mar
10 False ceiling installation 15 18-Feb 5-Mar Wall Tile Finish+1
11 Painting-Final Coat 14 7-Mar 21-Mar Skirting Finish+1
12 MEP- Wiring, A/C and Fire fighting works 40 30-Dec 8-Feb Plaster Insp.+1
13 MEP-Final Fix switches and light fixtures etc… 25 2-Feb 27-Feb Paint (pre-final)+1
1 Block Work 7 25-Dec 1-Jan
2 Internal Plastering Works 10 2-Jan 12-Jan Block Finish+1
3 Plastering Inspection 1 14-Jan 14-Jan Fixed
4 Wall Tiling 25 25-Jan 19-Feb
5 Wall Painting (upto pre-final) 18 15-Jan 2-Feb Plaster inspection+1
6 Floor tiling andd threshold 18 14-Feb 4-Mar Wall tile finish-5
FIRST FLOOR
7 Ceiling Painting C1 18 19-Jan 6-Feb
8 Sanitarywares and toilet fittings&Accessories 25 20-Feb 17-Mar Wall Tiling Finish+1
9 Skirting 8 1-Mar 9-Mar Floor Tile Finish-3
10 Door Installation 6 14-Feb 20-Feb
11 Window Fixing 15 27-Jan 11-Feb Plaster Finish+15
12 False ceiling installation 15 20-Feb 7-Mar Wall Tile Finish+1
13 Wall Painting-Final Coat 10 10-Mar 20-Mar Skirting Finish+1
14 MEP- Wiring, A/C and Fire fighting works 40 13-Jan 22-Feb Plaster finish+1
15 MEP-Final Fix switches and light fixtures etc… 25 7-Feb 4-Mar Paint (pre-final)+1
1 Plinth for Split Units Casting 4 10-Jan 14-Jan
2 Water Proofing Work 14 16-Jan 30-Jan 4+Upstand casting
3 Tiling 10 31-Jan 10-Feb After Water Proofing
ROOF
4 Plastering Works 6 11-Feb 17-Feb After Tiling
5 Painting 10 20-Feb 2-Mar Plastering Finish+3
6 Split units Installation and commissioning 20 18-Jan 7-Feb 4Days after casting plinth
7 Pump and piping works 15 18-Jan 2-Feb 4Days after casting plinth
EXTERNAL WORKS
1 External Plastering 16 6-Jan 22-Jan FF Block work finish+5
2 External Painting 21 16-Jan 6-Feb Plaster start+10
3 Aluminum windows 15 21-Jan 5-Feb Ext. paint start+5
4 Ext. light fittings 6 7-Feb 13-Feb Ext. Paint+1
EXTERNAL WORKS, COMMISSIONING & HAND OVER
Sl Activity Dur. (Days) Start Finish Remarks
1 Drainage Pipes and Manholes 16 15-Jan 31-Jan Depend on Municipality Approval
2 Water Supply piping 21 25-Jan 15-Feb Plaster start+10
EXTERNAL WORKS
3 Drainage Connection 15 30-Jan 14-Feb Ext. paint start+5
4 Foot path pasco 10 16-Feb 26-Feb Ext. Paint+1
5 Water SupplyConnection 0 20-Feb 20-Feb
6 Boundary Wall 15 5-Feb 20-Feb Date as per Base Line
7 Gates and Luvers 9 2-Mar 11-Mar Date as per Base Line
8 Substation Completion 0 15-Jan 15-Jan Fixed
1 Power On 0 20-Mar 20-Mar Bldg. completion certification+5
COMMISSIONING
2 LV Commissioning 14 9-Mar 23-Mar start=Block B FF MEP Final+5
3 Fire System 5 9-Mar 14-Mar start=Block B FF MEP Final+5
4 HVAC 15 6-Mar 21-Mar Chiller instal finish+1
5 Plumbing 14 5-Mar 19-Mar MEP Final -B +1
6 Communication 9 9-Mar 18-Mar MEP Final -B +5
1 As Built Structural 21 15-Feb 8-Mar
2 As Built MEP 21 20-Feb 13-Mar
3 As Built Architectural 21 25-Feb 18-Mar
HAND OVER
4 ADDC Final Insp. - NOC Power on 0 11-Mar 11-Mar Block B FF MEP Final+5
5 Substation insp. and approval 0 18-Jan 18-Jan Substation Completion+3
6 Estimation and payment by client 7 19-Jan 26-Jan Aubstation Approval + 1
7 Building completion Certificate - ADM 10 5-Mar 15-Mar start=Block B FF MEP Final+1
8 Snagging Desnagging 23 5-Mar 28-Mar start=Block B FF MEP Final+1
9 Hand Over 0 30-Mar 30-Mar