0% found this document useful (0 votes)
293 views1 page

Form For Calculation of Cost Index at PAR 2012

This document contains a form for calculating a cost index as per PAR 2012. It lists 13 components of construction costs including materials like bricks, cement, steel, and aggregates. It provides the unit of measurement, rate as of October 2012, weightage assigned, and space to enter revised rates. The purpose is to track changes in construction material costs over time to adjust government rates using a cost index.

Uploaded by

sintu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
293 views1 page

Form For Calculation of Cost Index at PAR 2012

This document contains a form for calculating a cost index as per PAR 2012. It lists 13 components of construction costs including materials like bricks, cement, steel, and aggregates. It provides the unit of measurement, rate as of October 2012, weightage assigned, and space to enter revised rates. The purpose is to track changes in construction material costs over time to adjust government rates using a cost index.

Uploaded by

sintu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Form for calculation of cost index as per PAR 2012

Enter new rates in rupees at the time of revision of cost index


S No Description Component Unit Rate as on Weightage Rate as on Cost index
01.10.2012 dd.mm.yyyy
1 Bricks 1000 no 3867.00 8.00 0.00
2 Ordinary Portland cement quintal 587.00 14.50 0.00
3 Steel quintal 4669.00 19.50 0.00 0.00
(a) 8 and 10 mm (TOR steel) 50%
(b) 12 and 16 mm (TOR steel) 50%
4 Aggregate 20 mm size cum 1350.00 6.50 0.00
5 Sand (coarse sand) cum 1293.00 3.00 0.00
6 Flooring items sqm 467.00 3.00 0.00 0.00
(a) Mosaic tiles 40%
(b) Ceramic tiles 40%
(c) Kota stone 10%
(d) Granite stone 10%
7 Paints litre 151.00 3.00 0.00 0.00
(a) Synthetic enamel paint 33.33%
(b) Oil bound distemper 33.33%
(c ) Plastic emulsion paint 33.33%
8 Ply and commercial wood 1476.00 5.00 0.00 0.00
(a) 12 mm thick particle board 33.33%
(b) Steel window of standard Z section 33.33%
(c) Aluminium window 33.33%
9 Pipes metre 300.00 2.50 0.00 0.00
(a) 15 mm GI pipe 33.33%
(b) 100 mm SCI pipes 33.33%
(c) 20 mm black conduit 33.33%
10 Lamps and fans each 1024.00 3.50 0.00 0.00
(a) Ceiling fans 1200 mm 50%
(b) 1.20 m fluorscent tube with fittings 50%
Electrical machinery fitting: 7.5 HP motor each 30380.00 2.50 0.00
11
(pump set) 1500 rpm (Kirloskar)
12 Wires and cables: Copper wires 100 metre 1790.00 4.00 0.00 0.00
(a) 1.5 sqmm 70%
(b) 4.0 sqmm 30%
13 Labour each 309.38 25.00 0.00 0.00
(a) Skilled 50%
(b) Unskilled 50%