04.1 - Test Format For MV Switchgear (PCT-01)

1. The document provides a test procedure and record sheet for pre-commissioning tests of medium voltage switchgear for the Midfield Terminal Building at Abu Dhabi International Airport. 2. The tests include mechanical checks, visual inspections of components and connections, verification of ratings, sizes, and sequences, and checks of operations, indicators, and padlock arrangements. 3. Eighteen test items are listed to be checked off as part of the pre-commissioning test with signatures and dates required from performing technicians, supervisors, witnesses and approvers.

Uploaded by

Gajendran Sriram
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
927 views2 pages

04.1 - Test Format For MV Switchgear (PCT-01)

1. The document provides a test procedure and record sheet for pre-commissioning tests of medium voltage switchgear for the Midfield Terminal Building at Abu Dhabi International Airport. 2. The tests include mechanical checks, visual inspections of components and connections, verification of ratings, sizes, and sequences, and checks of operations, indicators, and padlock arrangements. 3. Eighteen test items are listed to be checked off as part of the pre-commissioning test with signatures and dates required from performing technicians, supervisors, witnesses and approvers.

Uploaded by

Gajendran Sriram
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
  • General Data & Information
  • Test Procedure for MV Switchgear

TAV-CCC-ARABTEC JOINT VENTURE

Midfield Terminal Building - Abu Dhabi


International Airport
Test Procedure for MV Switchgear
Doc No: COM-0401-AN-PR-0003 Rev: 1 Checklist No: TR-ANEL-MV-PCT-01

PRE-COMMISSIONING TEST RECORD SHEET


Module Tag Ref.: CLP6-A ___
1. General Data & Information:

Feeder
Sub-System: MV Switchgear J01 J02 J03
Designation:
TK942162- TK942203-
Temperature: 26.4⁰ C Serial No.: TK942243-1
1 1
Humidity: 35% Manufacturer: Schneider
Equipment Tested: MV Switchgear Type: WSA6/42-2/623
Location / Level: CP1/L0.0 Rated Voltage: 24KV
Room No.: 394 Rated Current: 630 A
TH
Switchgear: CLP6-A Date: 13 FEB 2016
2. Mechanical Checks & Visual Inspection:

S. No. Description Checked


Verify appropriate anchorage, fixation, required area clearances, physical
1 [ Y ]
damage, and correct alignment and cleanliness.
Inspect all doors, panels, and sections for paint, dents, scratches, misfits, and
2 [ N ]
missing hardware.
Verify that the main busbar connections between the cells have been checked
3 [ Y ]
during installation (Refer ITP Reports – [Section 5: References]).
4 Inspect the earth bar connections between the cells. [ Y ]

Verify that the tightness of accessible bolted connections have been checked
5 with a torque wrench during installation (Refer ITP Reports – [Section 5: [ Y ]
References]).
6 Check earthingcontinuity between the earth connection and the metal frame. [ Y ]

7 Verify that the circuit breaker sizes and types correspond to drawings. [ Y ]
8 Verify that current and potential transformer ratios correspond to drawings. [ Y ]
9 Verify that all protection and measuring devices correspond to drawings. [ Y ]

Performed By: Sup. / Cert. By: Witnessed By: Approved By: Witnessed By: Cx Approved By:
Alpha Power Schneider TCA-JV AECOM Authority ADDC
Name: ABDULLAH
Name:T.RAJA Name:IBRAHEEM Name: Name: Name:
KARA KAYA

Signature: Signature: Signature: Signature: Signature: Signature:

Date: Date: Date: Date: Date: Date:


COM-0401-AN-PR-0003
TAV-CCC-ARABTEC JOINT VENTURE

Midfield Terminal Building - Abu Dhabi


International Airport
Test Procedure for MV Switchgear
Doc No: COM-0401-AN-PR-0003 Rev: 1 Checklist No: TR-ANEL-MV-PCT-01

10 Inspect insulators for evidence of physical damage or contaminated surfaces. [ Y ]


11 Inspect all mechanical indicating devices for correct operation. [ Y ]

Module Tag Ref.: CLP6-A ___

S. No. Description Checked


Verify that customer connections to remote power, operators, interlocks, and
13 [ N ]
indicators have been made.
Verify that all interconnection control wires between the cells have been done
14 [ Y ]
correctly referred to the control drawings.
Verify that the earth bar is connected to the earth electrode and check the
15 [ Y ]
earthing continuity.
Verify that all the incoming cables to the switchgear are connected with the
16 [ N ]
correct phase sequence.
17 Check gas leakage indicators. [ Y ]
18 Verify the Padlock arrangements on the Panel [ Y ]

Performed By: Sup. / Cert. By: Witnessed By: Approved By: Witnessed By: Cx Approved By:
Alpha Power Schneider TCA-JV AECOM Authority ADDC
Name: ABDULLAH
Name:T.RAJA Name:IBRAHEEM Name: Name: Name:
KARA KAYA

Signature: Signature: Signature: Signature: Signature: Signature:

Date: Date: Date: Date: Date: Date:


COM-0401-AN-PR-0003

TAV-CCC-ARABTEC JOINT VENTURE
Midfield Terminal Building - Abu Dhabi
International Airport
Test Procedure for MV Switchgear
D
TAV-CCC-ARABTEC JOINT VENTURE
Midfield Terminal Building - Abu Dhabi
International Airport
Test Procedure for MV Switchgear
D