TAV-CCC-ARABTEC JOINT VENTURE
Midfield Terminal Building - Abu Dhabi
International Airport
Test Procedure for MV Switchgear
Doc No: COM-0401-AN-PR-0003 Rev: 1 Checklist No: TR-ANEL-MV-PCT-01
PRE-COMMISSIONING TEST RECORD SHEET
Module Tag Ref.: CLP6-A ___
1. General Data & Information:
Feeder
Sub-System: MV Switchgear J01 J02 J03
Designation:
TK942162- TK942203-
Temperature: 26.4⁰ C Serial No.: TK942243-1
1 1
Humidity: 35% Manufacturer: Schneider
Equipment Tested: MV Switchgear Type: WSA6/42-2/623
Location / Level: CP1/L0.0 Rated Voltage: 24KV
Room No.: 394 Rated Current: 630 A
TH
Switchgear: CLP6-A Date: 13 FEB 2016
2. Mechanical Checks & Visual Inspection:
S. No. Description Checked
Verify appropriate anchorage, fixation, required area clearances, physical
1 [ Y ]
damage, and correct alignment and cleanliness.
Inspect all doors, panels, and sections for paint, dents, scratches, misfits, and
2 [ N ]
missing hardware.
Verify that the main busbar connections between the cells have been checked
3 [ Y ]
during installation (Refer ITP Reports – [Section 5: References]).
4 Inspect the earth bar connections between the cells. [ Y ]
Verify that the tightness of accessible bolted connections have been checked
5 with a torque wrench during installation (Refer ITP Reports – [Section 5: [ Y ]
References]).
6 Check earthingcontinuity between the earth connection and the metal frame. [ Y ]
7 Verify that the circuit breaker sizes and types correspond to drawings. [ Y ]
8 Verify that current and potential transformer ratios correspond to drawings. [ Y ]
9 Verify that all protection and measuring devices correspond to drawings. [ Y ]
Performed By: Sup. / Cert. By: Witnessed By: Approved By: Witnessed By: Cx Approved By:
Alpha Power Schneider TCA-JV AECOM Authority ADDC
Name: ABDULLAH
Name:T.RAJA Name:IBRAHEEM Name: Name: Name:
KARA KAYA
Signature: Signature: Signature: Signature: Signature: Signature:
Date: Date: Date: Date: Date: Date:
COM-0401-AN-PR-0003
TAV-CCC-ARABTEC JOINT VENTURE
Midfield Terminal Building - Abu Dhabi
International Airport
Test Procedure for MV Switchgear
Doc No: COM-0401-AN-PR-0003 Rev: 1 Checklist No: TR-ANEL-MV-PCT-01
10 Inspect insulators for evidence of physical damage or contaminated surfaces. [ Y ]
11 Inspect all mechanical indicating devices for correct operation. [ Y ]
Module Tag Ref.: CLP6-A ___
S. No. Description Checked
Verify that customer connections to remote power, operators, interlocks, and
13 [ N ]
indicators have been made.
Verify that all interconnection control wires between the cells have been done
14 [ Y ]
correctly referred to the control drawings.
Verify that the earth bar is connected to the earth electrode and check the
15 [ Y ]
earthing continuity.
Verify that all the incoming cables to the switchgear are connected with the
16 [ N ]
correct phase sequence.
17 Check gas leakage indicators. [ Y ]
18 Verify the Padlock arrangements on the Panel [ Y ]
Performed By: Sup. / Cert. By: Witnessed By: Approved By: Witnessed By: Cx Approved By:
Alpha Power Schneider TCA-JV AECOM Authority ADDC
Name: ABDULLAH
Name:T.RAJA Name:IBRAHEEM Name: Name: Name:
KARA KAYA
Signature: Signature: Signature: Signature: Signature: Signature:
Date: Date: Date: Date: Date: Date:
COM-0401-AN-PR-0003