S-41-1224-001WR - Rev 1
S-41-1224-001WR - Rev 1
Project: Engineering Design & Bid Package For Replacement Of Submarine Pipeline For Crude SPM RU VI Balongan
Job No: 140048.01 Date: 17/06/10
Document Title: Requisition – Linepipe
Document Number: 14-0048-01-P-7-101R
Issue / Revision: 1
S-41-1224-001WR Rev. 1
14-0048-01-P-7-101R
REQUISITION – LINE PIPE
Table of Contents
1.0 INTRODUCTION 3
1.1 General 3
1.2 Scope 3
1.3 Definitions and Abbreviations 3
2.0 QUANTITY 4
3.0 REQUIREMENT 4
4.0 INSPECTION AND TEST/CERTIFICATION 4
5.0 SERVICES 4
6.0 SPARE PARTS 5
7.0 WARRANTY 5
8.0 LIST OF APPLICABLE DOCUMENT FOR REQUIREMENT 5
8.1 Bill of Material 5
8.2 Specification and Data Sheet 5
9.0 ATTACHMENT 6
ATTACHMENTS
Attachment A Bill of Material
Attachment B Specification
Attachment C Data Sheet
14-0048-01-P-7-101R
REQUISITION – LINE PIPE
1.0 INTRODUCTION
1.1 General
PT Pertamina Persero RU VI Balongan (Company), as operator plans to replace the existing SPM
with new SPM located further offshore at deeper water depth. The new SPM 250,000 DWT will be
located offshore off the North-East coast of West Java approximately 17 km of Balongan Refinery,
Indonesia. The new SPM will have 250,000 DWT capacities. The new SPM and its pipeline to
onshore are intended to unload crude oil from oil tanker to the storage tanks Balongan Refinery.
PT Wood Group Indonesia has been awarded the Contract for the Engineering Design and Bid
Package for Replacement of Submarine Pipeline for Crude SPM RU VI Balongan.
1.2 Scope
This document defines the Linepipe requisition for Replacement of Submarine Pipeline for Crude
SPM RU VI Balongan. Manufacturer shall supply the 36" DSAW Line Pipe, API 5L X65, 22.2mm
thickness according to Specification for Linepipe Material, Doc. No. S-41-1220-002W .
For detailed material specification shall be in accordance with Linepipe & Bends Datasheet,
Doc.No. S-41-1224-002WR while quantity requirements as detailed in Bill of Material attached in
this document.
1.3.1 Definitions
Company PT Pertamina (Persero) RU VI Balongan
Contractor The party responsible for delivering the submarine pipeline.
Manufacturer The party which manufacturers or supplies the equipment/materials
specified and ordered by Contractor.
1.3.2 Abbreviations
API American Petroleum Institute
ASME American Society of Mechanical Engineers
ASTM American Society for Testing and Material
BS British Standard
EPC Engineering Procurement and Construction
MPS Manufacturing Procedure Specification
PQT Procedure Qualification Trial
RU Refinery Unit
SPM Single Point Mooring
14-0048-01-P-7-101R
REQUISITION – LINE PIPE
2.0 QUANTITY
The material quantities shall refer to Attachment A – Linepipe Quantity, attached in this document.
3.0 REQUIREMENT
The requirement for Line Pipe shall refer to Specification for Linepipe Material, Doc. No. S-41-
1220-002W. Manufacturer shall supply all new fabricated linepipe, hence stock pipe is not
acceptable.
Inspection and testing for the Contractor’s QC programme shall be included in the Contract Price.
Forms, records, procedures, and documentation shall be submitted to and approved by Company
and shall comply with applicable codes and standards and Company specifications / procedures.
Contractor shall liaise with Certifying Authority to obtain certification approval, where required by
the Indonesian regulations and in accordance with the requirements of this Scope of Work.
5.0 SERVICES
Manufacturer shall furnish all the necessary services for design, fabrication, and
documentations/correspondences submission in associates with:
- Proposal documents, which are inevitable for bid evaluation. Lack of any of these documents
may cause the rejection of Manufacturer’s offer by Company.
- Manufacturer shall submit periodically time schedule or status reports including fabrication,
tests and inspections, ready for shipment at factory and port of export, etc.
- Any of measurement documents. Specific for nominal pipe size measurement, imperial system
unit shall be applied.
- Bevel ends shall be protected with plastic end closures and bevel protector. The end caps
shall be of the recessed closed types that allow the use of lifting hooks. 10% spares shall be
provided. The use of the mill's standard plastic end cap shall be detailed in the MPS.
Manufacturer shall ensure the pipes are internally dry before fitting the end caps.
14-0048-01-P-7-101R
REQUISITION – LINE PIPE
- Spare parts for miscellaneous requirements i.e. route and buckle contingency, PQT 1
requirement for coating and burst testing, welding test pipe, and spare for construction aids.
The cost of the spare parts shall be indicated separately and included in the tender price.
7.0 WARRANTY
All linepipe materials shall meet the requirement of Company’s standard testing and inspection,
which included at any certificate of acceptance provided from Manufacturer as per Company
approval. Company shall be entitled to refuse acceptance of linepipe whether any subjected to
rejection criteria refer to Specification for Linepipe Material, Doc. No. S-41-1220-002W.
Manufacturer shall provide warranty of 1 year/2 years for satisfactory service after installation.
Manufacturer shall replace defective materials or workmanship free of charges during the warranty
period.
14-0048-01-P-7-101R
REQUISITION – LINE PIPE
9.0 ATTACHMENT
Line Pipe Quantity, Refer to Attachment A.
14-0048-01-P-7-101R
REQUISITION – LINE PIPE
ATTACHMENT A
S-41-1224-001WR Rev. 1
14-0048-01-P-7-101R
ENGINEERING DESIGN AND BID PACKAGE
REPLACEMENT OF SUBMARINE PIPELINE FOR CRUDE SPM RU VI BALONGAN
A. 36" Piping
D-41-136A-104WR
A1 Onshore Piping Linepipe Pipeline Linepipe 914.4mm 22.2mm API 5L-X65 DSAWL 82 7 41,713 S-41-1220-002W & S-41-1224-002WR
A. 24" Piping
Notes:
1. Offshore material to refer to Bill of Material - Offshore and Onshore Pipeline Facilities, Document No. B-41-1280-001W.
2. PLEM material including piping/valve, etc. refer to Bill of Material - PLEM, Document No. B-41-1280-003W.
3. Average pipe joint length is 12.2m.
4. For pipe with anodes attached at the end of pipe coating (i.e near to field joint).
5. Dimension, Type and Quantity shall be finalised/verified by contractor or vendor during detail design.
6. Unit weight of pipe is 5959 kg/joint for 36" pipe and 2281 kg/joint for 24".
Project Specification/Datasheets/Drawings:
1. S-41-1220-002W - Specification for Linepipe Material
2. S-41-1224-002WR - Datasheet - Linepipe and Bends
PERTAMINA RU-VI BALONGAN REPLACEMENT OF SUBMARINE PIPELINE 250,000 DWT
D-41-136A-001W
A2 Offshore (KP 0 - KP 4) Linepipe Pipeline Linepipe 914.4mm 22.2mm API 5L-X65 DSAWL 8,000 656 3,909 S-41-1220-002W & S-41-1224-002WR Main line route length (concrete thickness 100mm)
D-41-136A-001W
A3 Offshore (KP 4 - KP 6) Linepipe Pipeline Linepipe 914.4mm 22.2mm API 5L-X65 DSAWL 4,000 328 1,955 S-41-1220-002W & S-41-1224-002WR Main line route length (concrete thickness 130mm)
D-41-136A-001W
A4 Offshore (KP 6 - KP 7.5) Linepipe Pipeline Linepipe 914.4mm 22.2mm API 5L-X65 DSAWL 3,000 246 1,466 S-41-1220-002W & S-41-1224-002WR Main line route length (concrete thickness 150mm)
D-41-136A-001W
A5 Offshore (KP 7.5 - KP 7.524) Linepipe Pipeline Linepipe 914.4mm 22.2mm API 5L-X65 DSAWL 49 4 24 S-41-1220-002W & S-41-1224-002WR For transition purpose (concrete thickness 130mm)
D-41-136A-001W
A6 Offshore (KP 7.524 - KP 7.548) Linepipe Pipeline Linepipe 914.4mm 22.2mm API 5L-X65 DSAWL 49 4 24 S-41-1220-002W & S-41-1224-002WR For transition purpose (concrete thickness 100mm)
D-41-136A-001W
A9 Onshore Pipeline Section Spool Onshore Pipeline Spool 914.4mm 22.2mm API 5L-X65 DSAWL 61 5 30 S-41-1220-002W & S-41-1224-002WR Piping spool at onshore up to insulation joint
TOTAL REQUIRED LINEPIPE FOR OFFSHORE AND ONSHORE PIPELINE 2,827 16,846
Pipeline Tie-in D-41-133Z-001WR Pipeline spool next to PLEM, 1.5% joint spare, plus 2 Joints for
A1s Offshore Pipeline Spool 914.4mm 22.2mm API 5L-X65 DSAWL - 3 18 S-41-1220-002W & S-41-1224-002WR
Expansion Spool additional expansion spool spare for installation tolerances
D-41-136A-001W
A2s Offshore (KP 0 - KP 4) Linepipe Spare Pipeline Linepipe 914.4mm 22.2mm API 5L-X65 DSAWL - 10 60 S-41-1220-002W & S-41-1224-002WR Main line route length, 1.5%joint spare
D-41-136A-001W
A3s Offshore (KP 4 - KP 6) Linepipe Spare Pipeline Linepipe 914.4mm 22.2mm API 5L-X65 DSAWL - 5 30 S-41-1220-002W & S-41-1224-002WR Main line route length, 1.5%joint spare
D-41-136A-001W
A4s Offshore (KP 6 - KP 7.5) Linepipe Spare Pipeline Linepipe 914.4mm 22.2mm API 5L-X65 DSAWL - 4 24 S-41-1220-002W & S-41-1224-002WR Main line route length, 1.5% joint spare
D-41-136A-001W
A5s Offshore (KP 7.5 - KP 7.524) Linepipe Spare Pipeline Linepipe 914.4mm 22.2mm API 5L-X65 DSAWL - 1 6 S-41-1220-002W & S-41-1224-002WR For transition purpose, 1.5% joint spare
D-41-136A-001W
A6s Offshore (KP 7.524 - KP 7.548) Linepipe Spare Pipeline Linepipe 914.4mm 22.2mm API 5L-X65 DSAWL - 1 6 S-41-1220-002W & S-41-1224-002WR For transition purpose, 1.5% joint spare
D-41-136A-001W
A7s Offshore (KP 7.548 - KP 16.74) Linepipe Spare Pipeline Linepipe 914.4mm 22.2mm API 5L-X65 DSAWL - 23 137 S-41-1220-002W & S-41-1224-002WR Main line route length, up to shore crossing, 1.5% joint spare
Construction Spare Linepipe 50 298 (Approx. 1.8% from Total Required Linepipe for Offshore & Onshore Pipeline)
D-41-136A-001W
A10.1 Offshore Linepipe Route Contingency 914.4mm 22.2mm API 5L-X65 DSAWL - 11 66 S-41-1220-002W & S-41-1224-002WR Approx 1.5% joint spare. (concrete thickness 150mm)
D-41-136A-001W
A10.2 Offshore Linepipe Route Contingency 914.4mm 22.2mm API 5L-X65 DSAWL - 30 179 S-41-1220-002W & S-41-1224-002WR Approx 1.5% joint spare. (concrete thickness 100mm)
D-41-136A-001W
A12 Offshore Linepipe Coating PQT 914.4mm 22.2mm API 5L-X65 DSAWL - 5 30 S-41-1220-002W & S-41-1224-002WR Five joints assumed, for coating PQT
D-41-136A-001W
A14 Offshore Linepipe Construction Aids 914.4mm 22.2mm API 5L-X65 DSAWL - 5 30 S-41-1220-002W & S-41-1224-002WR Five joints assumed
D-41-136A-001W
A15 Offshore Linepipe Weld / test pipe 914.4mm 22.2mm API 5L-X65 DSAWL - 5 30 S-41-1220-002W & S-41-1224-002WR Five joints assumed, for welder and procedure qualification
Miscellaneous Spare Linepipe 95 566 (Approx. 3.5% from Total Required Linepipe for Offshore & Onshore Pipeline)
ATTACHMENT B
S-41-1224-001WR Rev. 1
14-0048-01-P-7-101R
SPECIFICATION FOR LINE PIPE MATERIAL
Project: Engineering Design & Bid Package For Replacement Of Submarine Pipeline for Crude SPM RU VI Balongan
Job No: 140048.01 Date: 03/06/10
Document Title: Specification for Line Pipe Material
Document Number: 14-0048-01-P-1-002
Issue / Revision: 4
S-41-1220-002W Rev. 4
14-0048-01-P-1-002
SPECIFICATION FOR LINE PIPE M ATERIAL
Table of Contents
1.0 INTRODUCTION 3
1.1 General 3
1.2 Scope 3
1.3 Definitions and Abbreviations 3
1.4 Units 4
1.5 Reference, Codes and Standards 4
2.0 MATERIAL REQUIREMENTS 5
2.1 General 5
2.2 Diameter 5
2.3 Wall Thickness 5
2.4 Straightness 5
2.5 Length 5
2.6 Pipe End Squareness 5
2.7 Pipe End Bevel 5
2.8 Weight 6
3.0 MANUFACTURING 6
4.0 PREQUALIFICATION AND QUALIFICATION 7
5.0 INSPECTION AND TESTING 7
5.1 Inspection 7
5.2 Testing 7
5.3 Rejection 12
6.0 REPAIR OF LINE PIPE 13
7.0 MARKINGS AND COATINGS 13
8.0 TRANSPORTATION AND HANDLING 14
8.1 Transportation Preparation 14
8.2 End Cap 14
9.0 DOCUMENTATION 14
9.1 General 14
9.2 Certification 14
9.3 Test Reports 15
ATTACHMENT
Attachment A MPS Minimum Requirement
Attachment B Qualification Test
1.0 INTRODUCTION
1.1 General
PT Pertamina Persero RU VI Balongan (Company), as operator plans to replace the existing SPM with
new SPM located further offshore at deeper water depth. The new SPM 250,000 DWT will be located
offshore off the North-East coast of West Java approximately 17 km of Balongan Refinery, Indonesia.
The new SPM will have 250,000 DWT capacities. The new SPM and its pipeline to onshore are
intended to unload crude oil from oil tanker to the storage tanks Balongan Refinery.
PT Wood Group Indonesia has been awarded the Contract for the Engineering Design and Bid
Package for Replacement of Submarine Pipeline for Crude SPM RU VI Balongan.
1.2 Scope
This specification covers the requirements for purchasing carbon steel line pipe to be used for
Submarine Pipeline for Crude SPM RU VI Balongan.
This Specification defines the minimum standards of quality and acceptability governing the
manufacture, inspection, testing, marking and shipment of carbon steel line pipe.
Line pipe shall be manufactured in accordance with the requirements of DNV–OS–F101 Submarine
Pipeline Systems with additional requirement from API 5L Specification for Line Pipe 2004, as
modified herein. Where not modified, the provisions of DNV–OS–F101 and API Specification 5L shall
apply.
1.3.1 Definitions
Company PT Pertamina (Persero) RU VI Balongan
Contractor The party which provides services to perform part of the Contract scope of
work on behalf of Company.
Manufacturer The party which manufacturers equipment/materials specified and ordered
by Contractor.
Contract EPC contract for replacement of Submarine Pipeline for Crude SPM RU VI
Balongan.
1.3.2 Abbreviations
API American Petroleum Institute
ASME American Society of Mechanical Engineers
ASTM American Society of Testing and Material
DNV Det Norske Veritas
EPC Engineering Procurement and Construction
HAZ Heat-affected Zone
ID Inside Diameter
MPI Magnetic Particle Inspection
MPS Manufacturing Procedure Specification
MPQT Manufacturing Procedure Qualification Test
OD Outside Diameter
1.4 Units
Unit of measurement used in this project is SI units with exception for tubular pipe using inch.
ASME B31.4 Pipeline Transportation Systems for Liquid Hydrocarbons and Other
Liquids
2.1 General
DNV OS-F101 January 2000 edition shall be the governing standard for linepipe. Material designation
shall be as per DNV OS-F101. Chemical composition shall refer to Section 6 of DNV OS-F101.
Nominal dimensions of outside diameter shall conform to standard dimensions found in API 5L. Pipe
wall thicknesses may be non-standard API 5L.
Pipe dimensions shall be in accordance with API 5L. Dimensional tolerance, except as otherwise
stated herein, shall be based on the requirement of DNV–OS–F101.
Any technical values or parameters of the pipeline not specified in this specification shall comply with
the “Data Sheet Line Pipe and Bends”, Doc. No. S-41-1224-002WR.
2.2 Diameter
The actual diameter of pipe ends and body shall be calculated based on circumferential
measurements taken within 100 mm from each pipe end and approximately in the middle of pipeline
for the pipe body. Unless otherwise agreed, the diameter tolerance shall relate to the inside diameter
for pipe ends and outside diameter for pipe body.
The standard dimensional requirement shall be as per Table 6.14 of DNV–OS–F101.
2.4 Straightness
Each pipe length shall have a straightness less than or equal to 0.15% of the pipe length as per Table
6.14 of DNV–OS–F101.
2.5 Length
Unless specified otherwise, pipe joints shall have the following length tolerances the length of pipes in
any one order shall average 12.2m with tolerance between 11.9m and 12.5m in length.
2.8 Weight
The weight of each pipe shall be in the range of +10/-3.5% of nominal weight per metre as per Table
6.14 of DNV–OS–F101.
3.0 MANUFACTURING
The Manufacturer shall be an approved API Line Pipe manufacturer and shall be responsible for the
manufacture, inspection, testing and supply of pipe in full compliance with the requirements of the
latest edition of DNV–OS–F101 and this specification.
Material for line pipe shall be made by the open-hearth, electric-furnace, or basic-oxygen process.
Fully killed, fine grained steel shall be used.
Welded pipe shall be manufactured from plate rolled from continuously cast slab.
Manufacturer shall specify pipe fabrication process used (UOE or UO), subjected to Company
approval. UO fabrication process is preferable for this project.
The line pipe chemical composition, grain structure and heat treatment shall be such that a selected
number of pipes may be suitable for induction bending without significant loss of mechanical
properties.
The pipe with wall thickness less than 50 mm shall be suitable for field welding without the necessity
for post weld treatment.
Rare earth additions are prohibited.
Throughout the manufacturing process, every reasonable effort shall be made to inhibit resultant
micro-segregation in the finished pipe. Any addition of inclusion shape control additives, such as
calcium, shall be approved in writing by Company as to the type and amount prior to use.
Pipe shall be suitable (where applicable) for use with internal line-up clamps of the type considered
standard in the industry.
Jointers will not be accepted.
The line pipe manufacturer shall provide and mark a sufficient number of joints (as specified in the
Purchase Order) which have a wall thickness greater than the nominal wall thickness to be used for
induction bends.
Pipe shall be cleaned of all dirt, debris, disassociated mill scale and other foreign matter.
The manufacturing procedure shall be submitted for approval and any subsequent modifications
during production shall be approved by Company.
All pipes shall be supplied in Thermo-mechanical control process (TMCP).
The chemical composition shall be controlled within more stringent limits than the maximum values in
the code.
Manufacturer shall perform an analysis of each heat of steel to determine the percentage of each
element specified or restricted by this specification.
A product analysis shall be performed at the first plate of each heat of steel or batch of 50 pipes
employed in the production of the pipe to this specification, whichever is least. The cross section of the
plate or pipe sample shall be used for analysis and not the surface.
The weld metal analysis shall be taken at the same frequency as the base metal analysis and shall
meet the composition recorded during manufacturing procedure qualifications.
5.1 Inspection
All Manufacturer’s facilities, materials and fabrication work shall be subjected to inspection by
Company. Company’s inspector is not to be constructed as the authorized inspector responsible for
performing code inspections. DNV or DNV certified inspector shall perform verification, inspection and
certification.
5.2 Testing
Table 5.1 summarize test requirements
TABLE 5.1
REQUIREMENT TEST AND ACCEPTANCE CRITERIA OF LINE PIPE MATERIAL
REQUIREMENT TEST ACCEPTANCE CRITERIA
Destructive Testing
Chemical Testing Table 6.1 and Section 6 of DNV–OS–F101
Burst Testing Section 6 E1000 of DNV-OS-F101
Mechanical Testing Table 6.3, 6.4, 6.11, and 6.12 of DNV–OS–F101
Tensile Test Table 6.3 of DNV–OS–F101
Charpy Impact Test Table 6.3 and 6.4 of DNV–OS–F101
Hardness Test Table 6.3 of DNV–OS–F101
Hydrostatic Test
Hydrostatic Testing Section 6 E1100 of DNV–OS–F101
TABLE 5.2
MECHANICAL AND CORROSION TESTING
REQUIREMENT TEST LOCATION C - Mn Steel
One longitudinal and one transverse tensile test shall be made on Type-E strip-type specimens.
The minimum elongation shall be as required by DNV–OS–F101 Table 6.3. A stress-strain curve
typical for the specified line pipe material is to be recorded. For each pipe to be accepted, all tests
must be successful.
Charpy Impact Test
For each Charpy test during production, a minimum of one set of six specimens shall be taken: three
from the mid-thickness location (unless otherwise specified) in the pipe wall, and three from both the
weld centreline and HAZ.
All tests are to be made in the final heat treatment condition.
Charpy V-notch tests shall be conducted at the temperature specified in Table 6.4 of DNV–OS–F101
and the minimum average absorbed energy in accordance with DNV–OS–F101 Appendix B Part A
600, and the requirements of this specification.
For both transverse and longitudinal specimens, the notched axis shall be perpendicular to the pipe
surface. Full size specimens according to DNV–OS–F101 requirement shall be used.
Charpy V notch absorbed energy impact acceptance criteria shall be in accordance with Table 6.3 of
DNV–OS–F101.
Flattening of the pipe prior for specimen preparation is not permitted.
Hardness Testing
Hardness testing shall be conducted in accordance with DNV–OS–F101 Appendix B Part A 1003-
1004.
As a minimum, transverse hardness tests shall be made on the inside, outside and approximate mid-
point of the wall thickness of the specimens, as well as coverage of the weld and heat affected zone.
Maximum hardness values throughout the pipe body for non-sour service shall be as per Table 6.3 of
DNV–OS–F101, Jan 2000.
Pipe weldment hardness shall conform to the requirements for welding qualification.
Inspection and testing of steel and pipe, manufactured in accordance with this Specification, shall
conform to the requirements stipulated in DNV–OS–F101. In addition to the required tests as
specified in DNV–OS–F101, Company shall have the right to conduct visual inspection.
The type and extent of Non-Destructive Testing for pipe shall be as per Table 6.13 of DNV–OS–F101
for C-Mn Steel and NDT Level II.
All non-destructive tests shall be performed after cold expansion, heat treating, cold sizing,
straightening and hydrostatic testing.
Non-destructive inspection procedures and equipment shall be subject to approval by Company prior
to manufacture of the pipe.
All test results shall be made available to Company for review.
All gauges, instruments and equipment used in processing, measuring and testing shall be
periodically calibrated to the satisfaction of Company. Company may require checking of instruments,
gauges and other equipment if in Company's sole judgement reasonable cause exists.
Measuring instruments shall be calibrated or verified at least once every operating shift. Verifying the
accuracy of measuring devices shall consist of inspection for wear and conformance to specified
dimensions.
b. Dimensional Inspection
The pipes shall be examined visually for dimensional tolerances and for surface defects in
accordance with Section 6 Part E1000 of DNV–OS–F101.
The ends of each pipe shall be tested for out of roundness using an internal ring gauge of diameter
5.0mm less than the nominal internal diameter. The gauge shall pass freely into each end of the pipe
when held normal to the pipe axis.
ID shall be measured with inside calipers, inside micrometers, a telescope gauge or a similar device.
The method of checking pipe end squareness shall be specified in the MPS.
Straightness measurement frequency shall be five pipes per shift provided that these are visually
determined to be the worst pipe. If any of these pipes are rejectable, then inspection frequency shall
be increased to ten pipes per shift with these ten being the worst deviations, obtained visually, after
physically rolling the pipe.
Pipe weight shall be determined by automatic weighing machine.
c. Radiographic Testing
Weld seams shall be radiographed as per DNV–OS–F101 Appendix D Part B200 and shall meet the
requirements of DNV–OS–F101 and the Project Welding Specification.
d. Ultrasonic Testing
UT shall be performed on the plate body and bevel edges as per DNV–OS–F101 Appendix D Part
B300 or Part D200 and Part F, before welding. If laminations exceed DNV–OS–F101 criteria the
section(s) shall be rejected.
Ultrasonic wall thickness testing of the pipe body and ends shall be performed by scanning along a
helical or straight pattern in such a way that at least 10% of the pipe surface is covered.
The body and ends of all pipes shall be 100% ultrasonically tested for inside and outside surface
defects as well as transverse, longitudinal and inclined embedded defects.
After bevelling, the complete circumference of the pipe end shall be tested ultrasonically from the
inside for laminations (this inspection shall cover a width which includes the entire bevel). Alternatively
the pipe may be tested from the outside prior to bevelling, in which case a band of at least 25mm
wide, to include the eventual bevelled area, shall be tested.
For pipes previously subjected to 100% rotary ultrasonic inspection, the above requirements shall not
apply
5.3 Rejection
Completed line pipe containing defects originating with the Manufacturer’s design, materials or
workmanship, or that are not in complete compliance with the requirements of this order shall be
rejected.
If the pipe rejection rate for defects exceeds 15%, Company shall be entitled to refuse acceptance of
all production until the cause(s) thereof is determined and positive action has been taken to rectify the
problem(s).
Rejectable flaws shall include cracks, leaks and laminations. Rejects due to non-destructive tests and
end laminations shall be in accordance with the relevant sections above.
Dents, bulges, gouges and other surface irregularities shall be considered poor workmanship.
Finished pipe shall be completely free of all debris and foreign matter and visually inspected.
Manufacturer shall prepare a rejection rate record and maintain a current record of all rejected pipes,
complete with reasons or causes for rejection. Production shall be halted if rejection rates become
unacceptable (greater than 3% after 10% of the pipe in the lot has been produced). Production shall
not be continued until after the causes of this rejection rate are determined, steps are taken to prevent
these from occurring during the rest of the production order, Company is notified, and written approval
by Company is given.
9.0 DOCUMENTATION
9.1 General
The Manufacturer shall provide an MDR, detailing test reports and certification in accordance with the
requirements of DNV–OS–F101 as modified by this Specification.
All test reports and certification shall be marked with sufficient information to enable full traceability to
the items they represent and the relevant specifications and procedures.
All reports and inspection certificates shall be signed by Manufacturer and Company representative to
signify compliance with the requirements of this Specification.
All test results and certificates, where possible, shall be in numerical form using SI units.
All reports and certificates shall be in the English language.
The complete MDR shall be submitted by Manufacturer in 3 copies and 1 PDF file.
9.2 Certification
Full certification of the results of inspection and testing shall be provided by Manufacturer according to
DNV OS F 101 Section 6 – G and shall be validated by Company. All shall be DNV certified
All certificates shall be available prior to pipe arrival.
All pipes shall be identified on the mill test certificates.
Certification shall cover all results required by this Specification. The following data are required as a
minimum on all mill certificates:
a. Purchase order number.
b. Line pipe outside diameter, wall thickness and grade.
c. Mill name and location.
d. Heat/lot identifying numbers.
e. Pipe identifying numbers.
f. Ladle analysis.
g. Product analysis.
h. Heat Treatment.
i. All required mechanical test results.
j. Specification limits.
k. Micrographic examination record where specified.
l. Dimensional report.
m. NDT results.
n. Signature of responsible official of Manufacturer signifying compliance with this Specification's
requirements.
Layout of certificate may be per Manufacturer's standard format.
ATTACHMENT A
MPS MINIMUM REQUIREMENT
The MPS requirement shall be in accordance with DNV OS F101 Section 6 – E 300. The MPS shall
include, but not be limited to, the following information where relevant:
• Plan(s) and process flow description/diagram.
• Project specific quality plan.
• Manufacturing process
• Manufacturer and manufacturing location of raw material and/or plate for welded pipes
• Raw material scrap content including allowable variation.
• Details of steel making, casting methods and alloying practice.
• Details of hot rolling practice.
• Material quality specification giving chemical composition and mechanical properties. Both nominal
values and ranges of these parameters shall be stated.
• Pipe manufacturing method including instrumentation to ensure proper control of processing
temperatures and other measures utilised to ensure consistency of both the mechanical properties
and dimensional tolerances of the line pipe.
• Pipe forming temperature range.
• Alignment and joint design for welding and production WPS.
• Weld seam post-weld heat treatment procedure.
• Method for cold expansion/ sizing/ finishing, target and maximum sizing ratio.
• Full details of pipe heat treatment, including heat treatment times and temperatures, heating and
cooling rates, cooling medium and furnace details and final heat treatment condition.
• Pressure Test procedure.
• Dimensional controls and measuring methods, including Squareness Verification Procedures.
• Full details of NDT testing, including visual inspection, equipment details, calibration methods and
frequency, scanning procedure and matrix, probe details, recording/reporting methods, alarm
system.
• Production mechanical testing – type and frequency.
• Pipe number allocation
• Pipe Tracking System.
• Marking, coating and protection procedures.
• Handling, Transport and Storage Procedures, including details of stacking and end cap.
• Reference to applicable supplementary requirements.
S-41-1220-004W Rev. 4
14-0048-01-P-1-004
SPECIFICATION FOR PIPELINE CORROSION
COATING
ATTACHMENT B
QUALIFICATION TEST
B.1 Introduction
Two completely finished pipes of the first day's production from two different heats, shall be selected at
random for testing to verify that the submitted Manufacturing Procedure Specification results in fully
acceptable pipe.
All NDT and destructive tests shall be performed for qualification as required by this specification for
production testing and the requirements of this attachment.
The above-noted first-day production tests shall be repeated upon any change in the manufacturing
procedure (essential variables).
The Manufacturer shall submit to Company a report giving the results of all tests mentioned in Table 6.11,
Table 6.12 and Table 6.13 (NDT Level II) of DNV OS F101, with following note:
a. Tensile Test
One transverse test shall be made on Type E strip-type specimens, taken across the weld.
The yield strength shall not exceed the SMYS.
c. Hardness Tests
Three specimens from one pipe shall be extracted from locations to be chosen by Company. These
specimens shall be cross-sectioned, polished and etched for macro-examination.
A series of Vickers hardness readings (10 kg load) shall be made on one of the above etched
specimens, selected by the Third Party Inspector. Three traverses shall be made: one near the outer
edge, the second across the centre, and the third near the inner edge. The traverse at the outer and
inner edges shall be spaced approximately 1 mm from the outer/inner edge. Readings shall be about 1
mm apart.
S-41-1220-004W Rev. 4
14-0048-01-P-1-004
REQUISITION – LINE PIPE
ATTACHMENT C
S-41-1224-001WR Rev. 1
14-0048-01-P-7-101R
Data Sheet: Line Pipe
Project : Replacement of Submarine Pipeline For Crude Doc. Number : S-41-1224-002WR
SPM RU VI Balongan Title : Data Sheet for Line Pipe
Client : Pertamina RU VI Balongan
Location : Balongan
1 GENERAL DESIGN DATA
Project Specification Required S-41-1220-002W
Design Standard API 5L Specification for Line Pipe
DnV OS F101 Offshore Standard - Submarine Pipeline Systems (2000)
Environment Offshore and Onshore
Design Pressure 2.265 MPa
Design Temperature 70ºC
Design Life 30 Years
Environmental Temperature Range Seawater : 28.2ºC to 31.5ºC
Air : 19ºC to 34ºC
Service Crude Oil, Flushing Fluid
Outside Diameter (OD) Length 914.4mm (crude oil pipeline) 17.24km (up to onshore tie-in)
914.4mm (flushing fluid pipeline) 17.24km (up to onshore tie-in)
Minimum Required Wall Thickness 22.2mm (crude oil pipeline)
22.2mm (flushing fluid pipeline)
Inside Diameter (ID) 870mm (crude oil pipeline)
870mm (flushing fluid pipeline)
Corrosion Allowance 7.0mm
End Finish API 5L Bevel 30º + 5° / -0°
Joint Length 12.2 m
Dimensional Tolerance In accordance with DnV OS F101 Table 6.14 and 6.15 and Section 2.0 of Project Specification S-41-1220-002W
2 MATERIALS
Steel Grade Carbon Steel API 5L Grade X65 PSL2 with DnV OS F101 requirement
Chemical Composition In accordance with Table 6.1 of DnV OS F101
Type Double Submerged Arc Welding Longitudinal (DSAWL)
3 TESTING
DESTRUCTIVE TEST
Chemical Composition Testing Yes, in accordance with DnV OS F101 Section 6 and Table 6.1 and Section 5.2 of Project Specification S-41-1220-002W
Burst Testing Yes, 1 pipe, in accordance with DnV OS F101
Mechanical Testing Yes, in accordance with DnV OS F101 Table 6.3, 6.4, 6.11 and 6.12 and Section 5.2 of Project Specification S-41-1220-002W
Qualification
Macro Examination Yes, in accordance with DnV OS F101 Table 6.11 and 6.12 and Appendix B and Section 5.2 of Project Specification
S-41-1220-002W
Fracture Toughness Testing Yes, in accordance with DnV OS F101 Table 6.11 and 6.12 and Appendix B and Section 5.2 of Project Specification
S-41-1220-002W
Weldability Testing Yes, in accordance with DnV OS F101 Table 6.11 and 6.12 and Appendix B and Section 5.2 of Project Specification
S-41-1220-002W
Strain Ageing Testing Yes, in accordance with DnV OS F101 Table 6.11 and 6.12 and Appendix B and Section 5.2 of Project Specification
S-41-1220-002W
M t ll
Metallographic
hi Examination
E i ti Yes, iin accordance
Y d with
ith DnV
D V OS F101 Table
T bl 6.11
6 11 and
d 6.12
6 12 and
d Appendix
A di B and
dSSection
ti 5 5.2
2 off P
Project
j tS Specification
ifi ti
S-41-1220-002W
Qualification and Production
Tensile Testing Yes, in accordance with DnV OS F101 Table 6.3 and Section 5.2 of Project Specification S-41-1220-002W
Bend Testing Yes, in accordance with DnV OS F101 Appendix B A500 and Section 5.2 of Project Specification S-41-1220-002W
Charpy Impact Test Yes, in accordance with DnV OS F101 Table 6.3 and 6.4 and Section 5.2 of Project Specification S-41-1220-002W
Hardness Testing Yes, in accordance with DnV OS F101 Table 6.3 and Section 5.2 of Project Specification S-41-1220-002W
HYDROSTATIC TEST Yes, in accordance with DnV OS F101 Section 6 E1100 and Section 5.2 of Project Specification S-41-1220-002W
NON DESTRUCTIVE TEST
Yes, in accordance with DnV OS F101 Appendix D Table D-3; Table 6.14 and 6.15; Section 6 E1200 and Section 5.2 of Project
Visual Examination and Dimensional Inspection
Specification S-41-1220-002-W
Radiographic Testing Yes, in accordance with DnV OS F101 Appendix D, Section D-4 and Section 5.2 of Project Specification S-41-1220-002W
Ultrasonic Testing Yes, in accordance with DnV OS F101 Appendix D, Section D-5 and Section 5.2 of Project Specification S-41-1220-002W
Magnetic Particle Inspection Yes, in accordance with DnV OS F101 Appendix D Section I205 and Section 5.2 of Project Specification S-41-1220-002W
Residual Magnetism Yes, in accordance with DnV OS F101 Table 6.13 and Appendix D G405 and Section 5.2 of Project Specification
S-41-1220-002W
TEST FREQUENCY Yes, in accordance with DnV OS F101 Appendix A B400
ACCEPTANCE CRITERIA Yes, in accordance with DnV OS F101 Appendix B, C, and D and Table 5.1 of Project Specification S-41-1220-002W
4 REPAIR
Repair In accordance with DnV OS F101 Section 10 and Section 6.0 of Project Specification S-41-1220-002W
5 CERTIFICATION
All Materials According to DnV OS F101 Section 6 - G and Section 9.2 of Project Specification S-41-1220-002W
7 TRACEABILITY
Traceability In accordance with Section 6.0 Part E607 of DnV OS F101 and API 5L Section 5.6, Section 9.8.4.9 and Appendix F SR15
2 MATERIALS
Mother Pipe Carbon Steel API 5L Grade X65 PSL 2 suitable for crude oil and flushing fluid service. The wall
thickness of the mother pipe before bending shall be at least +8% of the specified nominal wall
thickness.
Chemical Composition In accordance with Table 7.5 of DnV OS F101 (2000)
Type Double Submerged Arc Welding Longitudinal (DSAWL)
3 TESTING
DESTRUCTIVE TESTING
Tensile Test Yes, in accordance with DnV OS F101 Table 6.3 and Section 7.2.1.a and Table 7.1 Project Specification
S-41-1220-003W
Charpy Impact Test Yes, in accordance with DnV OS F101 Table 6.3 and Section 7.2.1.b and Table 7.1 Project Specification
S-41-1220-003W
Hardness Test Yes, in accordance with DnV OS F101 Section 6C and 6D and Section 7.2.1.c and Table 7.1 of Project
Specification S-41-1220-003W
TEST FREQUENCY Yes, in accordance with Section 7 G900 of DnV OS F101
NON DESTRUCTIVE TESTING
Yes, in accordance with DnV OS F101 Section 6 Part E and Section 7 Part G, and Section 7.2.2.a and
Visual Examination and Dimensional Inspection
Table 7.1 of Project Specification S-41-1220-003W
Radiographic Testing Yes, in accordance with DnV OS F101 Section 7 Part G and Section 7.2.2.b and Table 7.1 of Project
Specification S-41-1220-003W
Ultrasonic Testing Yes, in accordance with DnV OS F101 Section 7 Part G and Section 7.2.2.c and Table 7.1 of Project
Specification S-41-1220-003W
Magnetic Particle Inspection Yes, in accordance with DnV OS F101 Section 7 Part G and Section 7.2.2.d and Table 7.1 of Project
Specification S-41-1220-003W
Surface Hardening Testing Yes, in accordance with DnV OS F101 Section 7 Part G and Section 7.2.2.e and Table 7.1 of Project
Specification S-41-1220-003W
TEST FREQUENCY Yes, in accordance with Section 7 G800 of DnV OS F101
ACCEPTANCE CRITERIA Yes, in accordance with DnV OS F101 and Project Specification S-41-1220-003W
4 REPAIR
Repair In accordance with DnV OS F101 and Section 8.0 of Project Specification S-41-1220-003W
5 CERTIFICATION
All Materials According to ASME B16.49 Section 14, DnV OS F101 and Project Specification S-41-1220-003W