01 - Details Sequence of Work - TNB Manhole

This document outlines the sequence of works for the construction of 118 units of 2-storey terrace houses and associated works at Plot 12R2C in Putrajaya, Malaysia. It involves setting out the site using survey instruments, mobilizing workers and materials, excavating openings as per construction drawings using hydraulic excavators, installing precast manholes by sand-bedding the foundation and backfilling after installing iron covers.

Uploaded by

Ha Ho
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
753 views1 page

01 - Details Sequence of Work - TNB Manhole

This document outlines the sequence of works for the construction of 118 units of 2-storey terrace houses and associated works at Plot 12R2C in Putrajaya, Malaysia. It involves setting out the site using survey instruments, mobilizing workers and materials, excavating openings as per construction drawings using hydraulic excavators, installing precast manholes by sand-bedding the foundation and backfilling after installing iron covers.

Uploaded by

Ha Ho
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

SETARA PELANA SDN. BHD.

Revision No: 00
SEQUENCE OF WORKS Date: 25th June 2018

THE PROPOSED CONSTRUCTION AND COMPLETION OF 118 UNITS 2 STOREY TERRACE HOUSES AT
PLOT 12R2C AND ASSOCIATED WORKS AT PRESINT 12, PUTRAJAYA

Setting out & mobilization workers, machinery and materials


1. Setting out shall using suitable type of survey instruments and conducted by qualified
or experienced surveyor to ensure correct setting and position.
2. Assigned worker will gathered to the position of installation.
3. Before start work, toolbox talk will be given by the supervisor. All hazard and control
measured will be communicated among the worker.

Excavation
1. Excavate the opening are as per the construction drawing.
2. All excavation shall be by means of open excavation using hydraulic excavator.
3. Excavated material shall be stockpiled at the side for backfilling upon completion.

Manhole Installation
1. Sand-bedding the foundation of the manhole
2. Precast manhole installed into the excavated open cut area
3. Backfilled the excavation area after the iron cover installed.