Job Costing PDF
Job Costing PDF
LEARNING OBJECTIVES
When you have finished studying this chapter, you should be able to
• Understand the meaning and distinctive features of Job, Batch, Operating and
Contract Costing.
• Understand the accounting procedures to be applied in the above-mentioned different
methods of Costing.
6.1 Introduction
Today business and industry needs costing systems to meet their individual requirements.
Costing experts believe that it may not be possible to devise a single costing system to fulfill
everybody’s needs. They have developed different methods of costing for different industries
depending upon the type of manufacture and their nature. Mainly the industries can be
grouped into two basic types:
(1) Industries doing job work.
(2) Industries engaged in mass production of a single product or identical production.
A concern engaged in the execution of specification order is characterised as a firm producing
several items distinguishable from one another by respective specifications and other details.
Such a concern is thought of involved in performing job works.
Production under job work is strictly according to customer’s specifications and each lot, job or
production order is unique. Examples of jobs order type of production are : ships building,
roads, bridges, manufacture of heavy electrical machinery, machine tools, iron foundries,
wood working shops, etc. Here each job or unit of production is treated as a separate identity
for the purpose of costing. The methods of costing and for ascertaining cost of each job are
known as a job costing, contract costing and Batch costing.
segregation of materials cost by jobs or work orders is brought about by the use of separate
stores requisitions for each job or work order. Where a bill of material is prepared, it provides
the basis for the preparation of these stores requisitions. But when the entire quantity of
materials specified in the bill of materials is drawn in one lot or in instalments, the bill itself
could be made to serve as a substitute for the stores requisition.
After the materials have been issued and the stores requisitions have been priced, it is usual
to enter the value of the stores requisition in a material abstract or analysis book. It serves to
analyse and collect the cost of all direct materials according to job or work orders and
departmental standing orders or expense code numbers.
From the abstract book, the summary of materials cost of each job is posted to individual job
cost sheets or cards in the Work-in-Progress ledger. The postings are usually made weekly or
monthly. Similarly, at periodical intervals, from the material abstract books, summary cost of
indirect material is posted to different standing orders or expense code numbers in the
Overhead Expenses ledger. If any special material has been purchased for a particular job, it
is generally the practice to charge such special material direct to the job concerned without
passing it through the Stores Ledger, as soon as it is purchased.
If any surplus material is left over in the case of any job, unless it can be immediately and
economically used on some other job, the same is returned to the store room with a proper
supporting document/stores Debit Note or Shop Credit, and the relevant job account is
credited with the value of excess material returned to the store room.
If the surplus material is utilised on some other job, instead of being returned to the store room
first, a material transfer note is prepared. The transfer note would show the number of the
transfer to job as well as transferee job (or jobs) so that, on that basis, the cost thereof can be
adjusted in the Work-in-Progress Ledger.
Accounting for Labour: All direct labour cost must be analysed according to individual jobs
or work orders. Similarly, different types of indirect labour cost also must be collected and
accumulated under appropriate standing order or expenses code number.
The analysis of labour according to jobs or work orders is, usually, made by means of job time
cards or sheets. All direct labour is booked against specific jobs in the job time cards or
sheets. All the idle time also is booked against appropriate standing order expense code
number either in the job time card for each job or on a separate idle time card for each worker
(where the job time card is issued job-wise). The time booked or recorded in the job time and
idle time cards is valued at appropriate rates and entered in the labour abstract or analysis
book. All direct labour cost is accumulated under relevant job or work order numbers, and the
total or the periodical total of each job or work order is then posted to the appropriate job cost
card or sheet in Work-in-Progress ledger. The postings are usually made at the end of each
week or month.
The abstraction of idle time costs under suitable standing order or expenses code numbers is
likewise done and the amounts are posted to the relevant departmental standing order or
expense code number in the Overhead Expenses Ledger at periodical intervals. As regards
other items of indirect labour cost these are collected from the payrolls books for the purpose
of posting against standing order or expenses code numbers in the Overhead Expenses
ledger.
Accounting for Overhead: Manufacturing overheads are collected under suitable standing
order numbers and selling and distribution overheads against cost accounts numbers. Total
overhead expenses so collected are apportioned to service and production departments on
some suitable basis. The expenses of service departments are finally transferred to production
departments. The total overhead of production departments is then applied to products on
some realistic basis, e.g. machine hour; labour hour; percentage of direct wages; percentage
of direct materials; etc. It should be remembered that the use of different methods will lead to
a different amounts being computed for the works overhead charged to a job hence to
different total cost.
The problem of accurately absorbing, in each individual job or work order, the overhead cost
of different cost centres or departments involved in the manufacture is difficult under the job
costing method. It is because the cost or the expenses thereof cannot be traced to or
identified with any particular job or work order.
In such circumstances, the best that can be done is to apply a suitable overhead rate to each
individual article manufactured or to each production order. This is essentially an arbitrary
method.
Price of a job: Price of a job may be arrived by adding the desired percentage of profit to the total
cost of the job.
Treatment of spoiled and defective work: Spoiled work is the quantity of production that has
been totally rejected and cannot be rectified.
Defective work refers to production that is not as perfect as the saleable product but is
capable of being rectified and brought to the required degree of perfection provided some
additional expenditure is incurred.
Normally, all the manufacturing operations are not fully successful; they result in turning out a
certain amount of defective work. Nonetheless, over a period of time it is possible to work out
a normal rate of defectives for each manufacturing process which would represent the number
of defective articles which a process shall produce in spite of due care. Defects arise in the
following circumstances:
identified with jobs, the cost of rectification may be treated as factory overheads. Abnormal
defectives should be written off to the Costing Profit and Loss Account.
Illustration 2
A shop floor supervisor of a small factory presented the following cost for Job No. 303, to
determine the selling price.
Per Unit
`
Materials 70
Direct wages 18 hours @ ` 2.50 45
(Deptt. X 8 hours ; Deptt. Y 6 hours; Deptt. Z 4 hours)
Chargeable expenses 5
120
Add : 33-1/3 % for expenses cost 40
160
Analysis of the Profit/Loss Account
(for the year 2011)
` `
Materials used 1,50,000 Sales less returns 2,50,000
Direct wages:
Deptt. X 10,000
Deptt. Y 12,000
Deptt. Z 8,000 30,000
Special stores items 4,000
Overheads :
Deptt. X 5,000
Deptt. Y 9,000
Deptt. Z 2,000 16,000
Works cost 2,00,000
Gross profit c/d 50,000 _______
2,50,000 2,50,000
Selling expenses 20,000 Gross profit b/d 50,000
Net profit 30,000 ______
50,000 50,000
It is also noted that average hourly rates for the three Departments X, Y and Z are similar.
You are required to:
Draw up a job cost sheet.
Calculate the entire revised cost using 2011 actual figures as basis.
Add 20% to total cost to determine selling price.
Solution
Job Cost Sheet
Customer Details ——— Job No._________________
Date of commencement —— Date of completion _________
Particulars Amount
`
Direct materials 70
Direct wages :
Deptt. X ` 2.50 × 8 hrs. = ` 20.00
Deptt. Y ` 2.50 × 6 hrs. = ` 15.00
Deptt. Z ` 2.50 × 4 hrs. = ` 10.00 45
Chargeable expenses 5
Prime cost 120
Overheads:
` 5,000
Deptt. X = × 100 = 50% of ` 20 = ` 10.00
` 10,000
` 9,000
Deptt. Y = × 100 = 75% of ` 15 = ` 11.25
` 12,000
` 2,000
Deptt. Z = × 100 = 25% of ` 10 = ` 2.50 23.75
` 8,000
Works cost 143.75
` 20,000
Selling expenses = × 100 = 10% of work cost 14.38
` 2,00,000
Total cost 158.13
Profit (20% of total cost) 31.63
Selling price 189.76
6.3 Contract Costing
6.3.1 Introduction : A contract usually takes several years to get itself completed. If the profit
on such contracts is recorded only after their completion, then wide fluctuations may be noted
in the profit figures of contractors from year to year. To avoid these fluctuations in the reported
profits and to reflect the revenue in the accounting period during which the activity is
undertaken, the profit in respect of each contract in progress is transferred to the profit and
loss account of the year by calculating the notional profit. The portion of notional profit to be
transferred to the profit and loss account depends on the stage of completion of a contract. To
determine such a profit figure the knowledge of various concepts as discussed below is
essential in contract costing.
6.3.2 Meaning of Contract Costing: Contract or terminal costing, as it is termed, is one form
of application of the principles of job costing. In fact a bigger job is referred to as a contract.
Contract costing is usually adopted by building contractors engaged in the task of executing
Civil Contracts. Contract costing have the following distinct features:
1. The major part of the work in connection with each contract is ordinarily carried out at the
site of the contract.
2. The bulk of the expenses incurred by the contractor are considered as direct.
3. The indirect expenses, mostly consist of office expenses of the yards, stores and works.
4. A separate account is usually maintained for each contract.
5. The number of contracts undertaken by a contractor at a time is not usually very large.
6. The cost unit in contract costing is the contract itself.
6.3.3 Recording of contract costs
Material Cost: All materials supplied from the stores or purchased directly for the contract are
debited to the concerned contract account. In the case of transfer of excess material from one
contract to other contract, their costs would be adjusted on the basis of material transfer note,
signed both by the transferee and the transferor foreman. In case the return of surplus
material appears uneconomical on account of high cost of transportation, the same is sold and
the concerned contract account is credited with the sale price. Any loss or profit arising there-
from is transferred to the Profit and Loss Account. Any theft, or destruction of material by fire
represent a loss and as such, the same is transferred to the Profit and Loss Account. If any
stores items are used for manufacturing tools, the cost of such stores items are charged to the
work expenses account. If the contractee has supplied some materials without affecting the
contract price, no accounting entries will be made in the contract account, only a note may be
given about it.
Labour Cost: Labour actually employed on the site of the contract is regarded as direct
(irrespective of the nature of the task performed) and the wages paid to them are charged to
the concerned contract directly or on the basis of a wage analysis sheet (if concurrently a
number of contracts are carried on and labourers are required to devote their time on two or
more contracts).
Direct Expenses: Direct expenses (if any) are directly charged to the concerned contract.
Indirect Expenses: Indirect expenses (such as expenses of engineers, surveyors,
supervisors etc.) may be distributed over several contracts as a percentage of cost of
materials, or wages paid or of the prime cost. If however, the contracts are big, the labour hour
method may be used for the distribution of expenses.
Plant and Machinery : The value of the plant in a contract may be either debited to contract
account and the written down value thereof at the end of the year entered on the credit side
for closing the contract account, or only a charge (depreciation) for use of the plant may be
Work certified
(e) Notional Profit ×
Contract price
(This formula may be preferably used in the absence of estimated profit figure).
It is preferable to use formula (b) in the absence of specific instructions.
6.3.5 Cost plus Contract: Under Cost plus Contract, the contract price is ascertained by
adding a percentage of profit to the total cost of the work. Such type of contracts are entered
into when it is not possible to estimate the Contract Cost with reasonable accuracy due to
unstable condition of material, labour services, etc.
Cost plus contracts have the following advantages and disadvantages:
Advantages:
(i) The Contractor is assured of a fixed percentage of profit. There is no risk of incurring any
loss on the contract.
(ii) It is useful specially when the work to be done is not definitely fixed at the time of making
the estimate.
(iii) Contractee can ensure himself about ‘the cost of the contract’, as he is empowered to
examine the books and documents of the contractor to ascertain the veracity of the cost
of the contract.
Disadvantages - The contractor may not have any inducement to avoid wastages and effect
economy in production to reduce cost.
Escalation Clause - If during the period of execution of a contract, the prices of materials, or
labour etc., rise beyond a certain limit, the contract price will be increased by an agreed
amount. Inclusion of such a clause in a contract deed is called an “Escalation Clause”.
Illustration 4
The following expenses were incurred on a contract : `
Material purchased 6,00,000
Material drawn from stores 1,00,000
Wages 2,25,000
Plant issued 75,000
Chargeable expenses 75,000
Apportioned indirect expenses 25,000
The contract was for ` 20,00,000 and it commenced on January 1, 2011. The value of the work
completed and certified upto 30th November, 2011 was ` 13,00,000 of which ` 10,40,000 was
received in cash, the balance being held back as retention money by the contractee. The value of
work completed subsequent to the architect’s certificate but before 31st December, 2011 was
` 60,000. There were also lying on the site materials of the value of ` 40,000. It was estimated that
the value of plant as at 31st December, 2011 was ` 30,000.
Solution :
Dr. Contract Account Cr.
` `
To Material purchased 6,00,000 By Work-in-progress :
” Stores issued 1,00,000 Work certified 13,00,000
” Wages 2,25,000 Work uncertified 60,000
” Plant 75,000 Material unused 40,000
” Chargeable expenses 75,000 Plant less depreciation 30,000
” Indirect expenses 25,000
” Profit and Loss Account,
2/3rds of profit on cash basis 1,76,000*
” Work-in-progress
balance of profit c/d 1,54,000 ________
14,30,000 14,30,000
” Balance b/d: Work certified 13,00,000
Uncertified 60,000
Material at site 40,000
Plant at site 30,000
14,30,000
Less: Reserve 1,54,000
12,76,000
*Computation of Profit : `
Apparent profit 3,30,000
2/3rd of that since 65% of the work is complete 2,20,000
80% of that on cash basis 1,76,000
An alternative method of presentation can be to deduct the balance of profit to be carried
down (` 1,54,000 in the above case) from the work certified before it is entered in the contract
account. It will be ` 11,46,000 in the illustration given above. Of course, the reserve to be so
deducted from the work certified will have to be first ascertained by considering the value of
the work certified.
Illustration 5
A contractor prepares his accounts for the year ending 31st December each year. He
commenced a contract on 1st April, 2011.
The following information relates to the contract as on 31st December, 2011 :
`
Material issued 2,51,000
Labour charges 5,65,600
Salary to Foreman 81,300
A machine costing ` 2,60,000 has been on the site for 146 days, its working life is estimated
` 10,49,000
∴Cost of 100% " " " " × 100 = ` 15,73,500
66.67
∴Cost of 50% of the contract which has been certified by the architect is ` 7,86,750.
Also the cost of 16.67% of the contract, which has been completed but not certified by
the architect is ` 2,62,250.
Illustration 6
M/s. Bansals Construction Company Ltd. took a contract for ` 60,00,000 expected to be
completed in three years. The following particulars relating to the contract are available:
2009 2010 2011
` ` `
Materials 6,75,000 10,50,000 9,00,000
Wages 6,20,000 9,00,000 7,50,000
Cartage 30,000 90,000 75,000
Other expenses 30,000 75,000 24,000
Cumulative work certified 13,50,000 45,00,000 60,00,000
Cumulative work uncertified 15,000 75,000 —
Plant costing ` 3,00,000 was bought at the commencement of the contract. Depreciation was
to be charged at 25% per annum, on the written down value method. The contractee pays
75% of the value of work certified as and when certified, and makes the final payment on
completion of the contract.
You are required to make a contract account and contractee account as they would appear in
each of the three years. Also show how the work-in-progress and other items should appear in
the balance sheet.
Solution
Dr. Contract Account Cr.
` `
2009 2009
To Materials 6,75,000 By Plant at site c/d 2,25,000
To Wages 6,20,000 By work-in-progress c/d : `
To Cartage 30,000 Work certified 13,50,000
To Other expenses 30,000 Work uncertified 15,000 13,65,000
2010 ` 2010 `
To Work-in-progress b/d : By Work-in-progress c/d :
Contractee’s account
2009 ` 2009 `
To Balance c/d 10,12,500 By Bank 10,12,500
2010 2010
To Balance c/d 33,75,000 By Balance b/d 10,12,500
________ By Bank 23,62,500*
33,75,000 33,75,000
2011 2011
To Contract A/c 60,00,000 By Balance b/d 33,75,000
(Contract price) ________ By Bank 26,25,000
60,00,000 60,00,000
*The total value of work certified at the end of 2010 was ` 45,00,000 of that worth ` 13,50,000
was certified in 2009. Hence, the cash to be received in 2010 is 75% of ` 31,50,000 (`
45,00,000 − ` 13,50,000) i.e. ` 23,62,500.
Balance sheet (Extract) 2009
Liabilities ` Assets `
Capital − Plant at site 2,25,000
Less : Loss during the year 65,000
Work-in-progress : `
Work certified 13,50,000
Work uncertified 15,000
13,65,000
Less: Cash received 10,12,500 3,52,500
Balance sheet (Extract) 2010
Liabilities ` Assets `
Capital − Plant at site 1,68,750
Add: Profit during the year 5,19,375 Work-in-progress : `
Work certified 45,00,000
Work uncertified 75,000
45,75,000
Less: Profit in reserve 5,19,375
40,55,625
Less Cash received 33,75,000 6,80,625
Balance sheet (Extract) 2011
Liabilities ` Assets `
Capital − Plant at site 1,26,562
Add: Profit during the year 1,53,157
Illustration 7
Compute a conservative estimate of profit on a contract (which has been 90% complete) from
the following particulars. Calculate the proportion of profit to be taken to Profit & Loss Account
under various methods and give your recommendation.
`
Total expenditure to date 4,50,000
Estimated further expenditure to complete the contract (including contingencies) 25,000
Contract price 6,12,000
Work certified 5,50,800
Work uncertified 34,000
Cash received 4,40,640
Solution
Computation of notional profit `
Value of work certified 5,50,800
Less: Cost of work certified
(` 4,50,000 – ` 34,000) 4,16,000
Notional profit 1,34,800
Computation of estimated profit `
Contract price 6,12,000
Less: Cost of work to date 4,50,000
Estimated further expenditure to complete the contract 25,000
Estimated total cost 4,75,000
Estimated profit 1,37,000
Profit to be transferred under various methods
Work certified
(i) Notional profit ×
Contract price
` 5,50,800
= ` 1,34,800 × = ` 1,21,320
` 6,12,000
Work certified
(ii) Estimated profit ×
Contract price
` 5,50,800
= ` 1,37,000 × = ` 1,23,300
` 6,12,000
Work certified Cash received
(iii) Estimated profit × ×
Contract price Work certified
` 5,50,800 ` 4,40,640
= ` 1,37,000 × × = ` 98,640
` 6,12,000 ` 5,50,800
increase in costs which are caused by factors beyond the control of contractor and not for
increase in costs which are caused due to inefficiency or wrong estimation.
Illustration 9
AKP Builders Ltd. commenced a contract on April 1, 2010. The total contract was for
`5,00,000. Actual expenditure for the period April 1, 2010to March 31, 2011 and estimated
expenditure for April 1, 2011 to December 31, 2011 are given below :
Particulars 2010-11 2011-12
(actual) (9 months)
(estimated)
Materials issued 90,000 85,750
Labour : Paid 75,000 87,325
Outstanding at the end 6,250 8,300
Plant 25,000 -
Sundry expenses : Paid 7,250 6,875
Prepaid at the end 625 -
Establishment charges 14,625 -
A part of the material was unsuitable and was sold for `18,125 (cost being `15,000) and a
part of plant was scrapped and disposed of for `2,875. The value of plant at site on 31 March,
2011 was ` 7,750 and the value of material at site was ` 4,250. Cash received on account to
date was ` 1,75,000, representing 80% of the work certified. The cost of work uncertified was
valued at ` 27,375.
The contractor estimated further expenditure that would be incurred in completion of the contract :
¾ The contract would be completed by 31st December, 2012.
¾ A further sum of `31,250 would have to be spent on the plant and the residual value of
the plant on the completion of the contract would be `3,750.
¾ Establishment charges would cost the same amount per month as in the previous year.
¾ `10,800 would be sufficient to provide for contingencies.
Required: Prepare Contract Account and calculate estimated total profit on this contract. Profit
transferrable to Profit and Loss Account is to be calculated by reducing estimated profit in
proportion of work certified and contract price.
Solution: AKP Builders Ltd.
Contract Account (2010-11)
Particulars ` Particulars `
To Materials issued 90,000 By Material sold 18,125
To Labour 75,000 By Plant sold 2,875
Add: Outstanding 6,250 81,250 By Plant at site 7,750
To Plant 25,000 By Material at site 4,250
Illustration 10
RST Construction Ltd. commenced a contract on April 1, 2011. The total contract was for
`49,21,875. It was decided to estimate the total profit on the contract and to take to the credit of Profit
and Loss A/c that proportion of estimated profit on cash basis, which work completed bore to total
contract. Actual expenditure for the period April 1, 2011 to March 31, 2012 and estimated expenditure
for April 1, 2012 to September 30, 2012 are given below :
(`)
April 1, 2011 to April 1, 2012 to
March 31, 2012 Sept. 30, 2012
(Actuals) (Estimated)
Materials issued 7,76,250 12,99,375
Labour : Paid 5,17,500 6,18,750
Prepaid 37,500 -
Outstanding 12,500 5,750
Plant purchased 4,00,000 -
Expenses: Paid 2,25,000 3,75,000
Outstanding 25,000 10,000
Prepaid 15,000 -
Plant returns to store (historical cost) 1,00,000 3,00,000
The plant is subject to annual depreciation @ 25% on written down value method. The
contract is likely to be completed on September 30, 2012.
Required : Prepare the Contract A/c. Determine the profit on the contract for the year 2011-12 on
prudent basis, which has to be credited to Profit and Loss A/c.
Solution:
Calculation of written down value of plant as on 30-9-2012. (`)
10,000)
To Estimated profit 10,21,125 ________
52,48,750 52,48,750
Since the contract is nearing completion, the following formula is used for transfer of profit to Profit and
Loss Account.
Cash received
Estimated profit ×
Contract price
18,75,000
= 10,21,125 × = `3,89,000.
49,21,875
Illustration 11:
A contractor commenced a building contract on October 1, 2010. The contract price is
` 4,40,000. The following data pertaining to the contract for the year 2011-2012 has been
compiled from his books and is as under :
`
April 1, 2011 Work-in-progress not certified 55,000
Materials at site 2,000
2011–12 Expenses incurred :
Materials issued 1,12,000
Wages paid 1,08,000
Hire of plant 20,000
Other expenses 34,000
March 31, 2012 Materials at site 4,000
Work-in-progress : Not certified 8,000
Work-in-progress : Certified 4,05,000
The cash received represents 80% of work certified. It has been estimated that further costs to
complete the contract will be ` 23,000 including the materials at site as on March 31, 2012.
Required :
Determine the profit on the contract for the year 2011-12 on prudent basis, which has to be
credited to P/L A/c.
Solution
Contract Account
for the year 2011-12
Dr. Cr.
Particulars (`) Particulars (`)
1.4.11
To Work-in-progress 55,000 By Materials at site 4,000
(not certified)
To Materials at site 2,000
2011–12
To Materials issued 1,12,000 By Cost of contract c/d (to date) 3,27,000
To Wages paid 1,08,000
To Hire of plant 20,000
To Other expenses 34,000 _______
3,31,000 3,31,000
31.3.12
To Cost of contract b/d 3,27,000 By Work-certified 4,05,000
(to date) By Work-not certified 8,000
To Profit & loss A/c 66,273
To Profit in reserve 19,727 _______
4,13,000 4,13,000
Profit for the year 2011-12 = ` 4,13,000 – ` 3,27,000 = ` 86,000
Estimated profit (on the completion of the contract)
`
Cost of the contract (to date) 3,27,000
Further cost of completing the contract 23,000
Total cost: (A) 3,50,000
Contract price: (B) 4,40,000
Estimated profit on the completion of contract: {(A) – (B)} 90,000
⎛ Work certified ⎞ ` 4,05,000
Since ⎜⎜ ⎟⎟ × 100 = × 100 = 92.05%
⎝ Contract price ⎠ ` 4,40,000
Illustration 12
A construction company under-taking a number of contracts, furnished the following data
relating to its uncompleted contracts as on 31st March, 2012 :
(` in lacs)
Contract Numbers
723 726 729 731
Total Contract Price 23.20 14.40 10.08 28.80
Estimated Costs on completion of contract 20.50 11.52 12.60 21.60
Expenses for the year ended 31.3.12 :
Direct Materials 5.22 1.80 1.98 0.80
Direct Wages 2.32 4.32 3.90 2.16
Overheads (Excluding Depreciation) 1.06 2.60 2.62 1.05
Profit Reserve as on 1.4.11 1.50 — — —
Solution
MNP Construction Ltd.
Contract Account (1st April, 2010 to 31st March, 2011)
Dr. Cr.
Particulars Amount Particulars Amount
(`) (`)
Materials issued 3,00,000 By Plant returned to store 37,500
Labour : Paid 2,00,000 (Refer to working note 1)
Outstanding 20,000 2,20,000 By Materials at site 20,000
To Plant purchased 1,50,000 By Work certified 8,00,000
(Refer to working note 4) By Work uncertified 25,000
To Expenses 60,000 By Plant at site 75,000
To Notional profit c/d 2,27,500 (Refer to working note 2) ________
9,57,500 9,57,500
To Profit and Loss A/c 66,321,43 By Notional profit b/d 2,27,500,00
(Refer to working note 5)
To Work in Progress A/c 1,61,178,57
(Profit in reserve) ___________ ___________
2,27,500,00 2,27,500,00
MSP Construction Ltd.
Contract Account (1st April, 2010 to 31st December, 2011)
(For computing estimated profit)
Dr. Cr.
Particulars Amount Particulars Amount
(`) (`)
To Materials issued 8,50,000 By Materials at site 50,000
(` 3,00,000 + `5,50,000) By Plant returned to store on 37,500
To Labour (paid & outstanding) 4,80,000 31st March, 2011
(` 2,20,000 + ` 2,30,000 + ` 30,000) (Refer to working note 1)
To Plant purchased 1,50,000 By Plant returned to store 60,937.50
To Expenses 2,25,000 on 31st December, 2011
(` 60,000 + ` 1,65,000) (Refer to working note 3)
To Estimated profit 1,93,437.50 By Contractee’s A/c 17,50,000
18,98,437.50 18,98,437.50
Working Notes :
1. Value of the plant returned to store on 31st March, 2011 `
Historical cost of the plant returned 50,000
Less : Depreciation @ 25% of WDV cost for 1 year 12,500
Value of the plant returned to store on 31st March, 2011 37,500
each batch order and overall position of the order for 1,200 pieces.
Month Batch Material Direct Direct
Output cost wages labour hours
` `
January 210 650 120 240
February 200 640 140 280
March 220 680 150 280
April 180 630 140 270
May 200 700 150 300
June 220 720 160 320
The other details are :
Month Chargeable expenses Direct labour
` hours
January 12,000 4,800
February 10,560 4,400
March 12,000 5,000
April 10,580 4,600
May 13,000 5,000
June 12,000 4,800
Solution
Jan. Feb. March April May June Total
Batch output (in units) 210 200 220 180 200 220 1,230
Sale value ` 1,680 1,600 1,760 1,440 1,600 1,760 9,840
Material cost ` 650 640 680 630 700 720 4,020
Direct wages ` 120 140 150 140 150 160 860
Chargeable expenses* ` 600 672 672 621 780 800 4,145
Total cost ` 1,370 1,452 1,502 1,391 1,630 1,680 9,025
Profit per batch ` 310 148 258 49 –30 80 815
Total cost per unit ` 6.52 7.26 6.83 7.73 8.15 7.64 7.34
Profit per unit ` 1.48 0.74 1.17 0.27 –0.15 0.36 0.66
Overall position of the order for 1,200 units
Sales value of 1,200 units @ ` 8 per unit ` 9,600
Total cost of 1,200 units @ ` 7.34 per unit ` 8,808
Profit ` 792
Chargeable exp enses
× Direct labour hours for batch
Direct labour hour for the month
6.4.2 Economic Batch Quantity: In batch costing the most important problem is the
determination of optimum size of the batch (how much to produce) or Economic Batch
Quantity.
The determination of economic batch quantity involve two types of costs viz.,
(i) Set up cost (or preparation cost) and
(ii) Carrying cost.
With the increase in the batch size, there is an increase in the carrying cost but the set up cost
per unit of product is reduced; this situation is reversed when the batch size is reduced. Thus
there is one particular batch size for which both set up and carrying costs are minimum. This
size is known as economic or optimum batch quantity.
Economic batch quantity can be determined with the help of a table, graph or mathematical
formula. The mathematical formula usually used for its determination is as follows :
2 DS
EBQ =
C
Where, D = Annual demand for the product
S = Setting up cost per batch
C = Carrying cost per unit of production
Note : If the rate of interest (I) and unit cost of production (C) are given, the following formula
should be used for determining EBQ.
2 DS
EBQ =
C
Illustration 15
Monthly demand for a product 500 units
Setting-up cost per batch ` 60
Cost of manufacturing per unit ` 20
Rate of interest 10% p.a.
Determine economic batch quantity.
Solution
2DS 2 × 500 × 12 × 60
EBQ = = = 600 units.
C 0.1× 20
6.5 Operating Costing
6.5.1 Meaning of Operating Costing: It is a method of ascertaining costs of providing or
operating a service. This method of costing is applied by those undertakings which provide
services rather than production of commodities. The emphasis under operating costing is on
the ascertainment of cost of services rather than on the cost of manufacturing a product. This
costing method is usually made use of by transport companies, gas and water works depart-
ments, electricity supply companies, canteens, hospitals, theatres, schools etc.
For computing the operating cost, it is necessary to decide first, about the unit for which the
cost is to be computed, this may often require the study of some technical and operating data,
for finding out the factors which have a bearing on cost. The cost units usually used in the
following service undertakings are as below :
Transport service − Passenger km., quintal km., or tonne km.
Supply service − Kw hr., Cubic metre, per kg., per litre.
Hospital − Patient per day, room per day or per bed, per operation etc.
Canteen − Per item, per meal etc.
Cinema − Per ticket.
Composite units i.e. tonnes kms., quintal kms. etc. may be computed in two ways.
(i) Absolute (weighted average) tonnes-kms., quintal kms. etc.
(ii) Commercial (simple average) tonnes-kms., quintal kms. etc.
(i) Absolute (weighted average) tonnes-kms. Absolute tonnes-kms., are the sum total of
tonnes-kms., arrived at by multiplying various distances by respective load quantities
carried.
(ii) Commercial (simple average) tonnes-kms. Commercial tonnes-kms., are arrived at by
multiplying total distance kms., by average load quantity.
Note: To understand the concept of absolute tonnes-kms., and commercial tonnes-kms.,
students should refer to the following illustration.
Illustration 16
A lorry starts with a load of 20 tonnes of goods from station A. It unloads 8 tonnes at station B
and rest of goods at station C. It reaches back directly to station A after getting reloaded with
16 tonnes of goods at station C. The distance between A to B, B to C and then from C to A are
80 kms., 120 kms., and 160 kms., respectively. Compute ‘Absolute tonnes-kms.,’ and
‘Commercial tonnes-kms.
Solution
Absolute tonnes-kms. = 20 tonnes × 80 kms + 12 tonnes × 120 kms + 16 tonnes × 160 kms.
= 5,600 tonnes-kms.
Commercial tonnes-kms. = Average load × total kilometres travelled
⎛ 20 + 12 + 16 ⎞
= ⎜ ⎟ tonnes × 360 kms. = 5,760 tonnes-kms.
⎝ 3 ⎠
6.5.2 Preparation of Cost Sheet under Operating Costing: For preparing a cost sheet
under operating cost, costs are usually accumulated for a specified period viz., a month, a
quarter, or a year etc.
All of the accumulated costs should be classified under the following three heads:
1. Fixed costs or standing charges,
2. Variable costs or running charges,
3. Semi-variable costs or maintenance costs.
Note : In the absence of information about semi-variable costs, the costs may be shown under
two heads only, i.e., fixed and variable.
Under operating costing, the per unit cost of service may be calculated by dividing the total
cost for the period by the total units of service in the period.
Treatment of depreciation and interest - Depreciation if related to effluxion of time, may be
treated as fixed. If it is related to the activity level, it may be treated as variable.
If information about interest is explicitly given, it may be treated as fixed cost.
Illustration 17
You have been given a permit to run a bus on a route 20 Km. long. The bus costs you
` 90,000. It has to be insured @ 3% p.a. and the annual tax will be ` 1,000. Garage rent is
` 100 p.m. Annual repairs will be ` 1,000 and the bus is likely to last for 5 years at the end of
which the scrap value is likely to be ` 6,000.
The driver’s salary will be ` 150 p.m. and the conductor’s ` 100 together with 10% of the
takings as commission (to be shared equally by both). Stationery will cost ` 50 p.m. The
manager-cum-accountant’s salary will be ` 350 p.m.
Diesel and oil be ` 25 per hundred kilometres. The bus will make 3 round trips for carrying on the
average 40 passengers on each trip. Assuming 15% profit on takings, calculate the bus fare to be
charged from each passenger. The bus will work on the average 25 days in a month.
Solution
Operating Cost Statement
Bus No. : Per annum Per 100
Carrying capacity : 40 passenger km.
` P. ` P.
1 2 3
A. Standing Charges
Depreciation (90,000 – 6,000) ÷ 5 16,800
Tax 1,000
Insurance 2,700
Stationery 600
Manager’s salary 4,200 _____
Total 25,300 1.756
B. Maintenance charges
Garage rent 1,200
Repairs 1,000 _____
Total 2,200 0.152
C. Operating or running charges
Diesel and oil 9,000
Driver’s salary 1,800
Conductor’s salary 1,200 _____
Total 12,000 0.833
Grand Total (A+B+C) 2.741
Loading @ 25/75 0.91
Fare per passenger-km. 3.65
Notes :
(1) Number of kms. run in a month : 3 × 2 × 20 × 25 = 3,000
25
(2) Diesel & Oil : 3,000 × = ` 750
100
(3) Number of passenger-kms. per month : 3,000 × 40 = 1,20,000
per annum : 1,20,000 × 12 = 14,40,000
(4) Loading - If taking is ` 100, 10 will have to be given as commission and 15 must remain
as profit; the cost must therefore be 75. On 75 the loading must be 25 to make the taking
equal to 100.
Illustration 18
SMC is a public school having five buses each plying in different directions for the transport of
its school students. In view of a larger number of students availing of the bus service the
buses work two shifts daily both in the morning and in the afternoon. The buses are garaged in
the school. The work-load of the students has been so arranged that in the morning the first
trip picks up senior students and the second trip plying an hour later picks up the junior
students. Similarly in the afternoon the first trip takes the junior students and an hour later the
second trip takes the senior students home.
The distance travelled by each bus one way is 8 kms. The school works 25 days in a month
and remains closed for vacation in May, June and December. Bus fee, however, is payable by
the students for all 12 months in a year.
Annual fixed costs and maintenance charges are ` 60,000 and ` 12,000 respectively. Running
charges spent during January 2012 are ` 2,944.
You are required to find out the cost per absolute ton-kilometre and the profit for January, 2012.
Solution
Statement showing the Operating Cost per ton-km. and Profit for January, 2012.
(i) Costs incurred ` `
Fixed charges 60,000
Maintenance cost 12,000
72,000
Cost for the month (` 72,000 ÷ 12) 6,000
Monthly running charges 2,944
Total monthly running cost 8,944
Cost per absolute tons-km. ` 8,944 ÷ 44,720 absolute ton-km. = `0.20.
(ii) Statement of Profit ` `
Receipts 13,368
Less:Cost 8,944
Fine 1,200 10,144
Profit 3,224
Comments:
(i) Transporters often carry overloads, which attract fines and penalties. In this question
absolute cost per ton-kilometre is required. This can be arrived at by considering both the
entire receipts from the overloading as well as fines paid.
(ii) Normally fines will not form part of cost. It is to be debited to profit and loss account
directly.
Illustration 20
Mr. X owns a bus which runs according to the following schedule:
(i) Delhi to Chandigarh and back, the same day.
Distance covered: 150 kms. one way.
Number of days run each month : 8
Seating capacity occupied 90%.
(ii) Delhi to Agra and back, the same day.
Distance covered: 120 kms. one way.
Number of days run each month : 10
Seating capacity occupied 85%.
(iii) Delhi to Jaipur and back, the same day.
Solution
Alternative Proposals
I II III
Use of company’s car Use of own Use of
car hired car
` per annum ` per km. ` per km. ` per km.
Reimbursement (A) − 1.60 1.00 @
Fixed cost: (B)
Per car per annum
Insurance 1,200 0.06* −
Taxes 800 − 0.04**
Depreciation −
(` 1,00,000 – 20,000)/5 16,000
Total 18,000
Fixed cost per km
(` 18,000 ÷ 20,000 km.) 0.90
Running and Maintenance
Cost (C)
Per car per km.
Petrol 0.60 − 0.60
Repairs and Maintenance 0.20 − −
Tyre 0.12 − 0.12
Total cost per km. (A+B+C) 1.82 1.66 1.76
Cost for 20,000 km. ` 36,400 ` 33,200 ` 35,200
Ranking of alternative III I II
proposals
Decision : II alternative i.e., use of own car, is the best alternative from company’s point of
view. III alternative, i.e. hiring cars from outside agency is the second best alternative. I
alternative, i.e. maintaining the fleet is the costliest alternative.
* ` 1200/20000 Kms. = `0.06; ** ` 800 /20,000 Kms. = `0.04;
@ ` 20,000/20,000Kms = `1.
Illustration 23
From the following data pertaining to the year 2011-12 prepare a cost sheet showing the cost
of electricity generated per k.w.h. by Chambal Thermal Power Station.
reduced to ‘standard load’ by first calculating their weight and then the bulk of article
produced, the costs of distributing the product would be easily ascertained.
This principle also can be extended for associating cost with convenient units of service
rendered by an organisation so that management is able to judge whether the organisation is
running efficiently and in the manner in which the service requires to be improved or be made
more economical. The cost of generation of electricity on the same principle is correlated with
units generated and also with units sold; in hospitals the cost of their maintenance is co-
related to units of ‘available bed-days’.
6.6 Multiple Costing
It refers to the method of costing followed by a business wherein a large variety of articles are
produced, each differing from the other both in regard to material required and process of
manufacture. In such cases, cost of each article is computed separately by using, generally,
two or more methods of costing. For instance, for ascertaining the cost of a bicycle, cost of
each part will be ascertained by using batch or job costing method and, then the cost of
assembling the parts will be ascertained by following the method of single or output costing.
6.7 Summary
¾ JOB Costing : Production/work done as per customer specification
¾ Meaning of spoiled and decective work under job costing:-
♦ Spoiled :- Produced units can not be rectified.
♦ Defective:- Units can be rectified with some additional cost.
¾ Contract costing:-
♦ Accounts maintained as per contract wise.
♦ Some contract not complete with in the Financial year so computation of profit
are main point so profit computation is as follow:-.
the case of incomplete contracts, the following four situations may arise:
(i) Completion of contract is less than 25 per cent: No profit should be taken to
profit and loss account.
(ii) Completion of contract is upto 25 per cent or more than 25 per cent but less than
50 per cent:
1 Cash received
× Notional Pr ofit ×
3 Work certified
(iii) Completion of contract is upto 50 per cent or more than 50 per cent but less than
90 per cent:
2 Cash received
× Notional Pr ofit ×
3 Work certified
(iv) Completion of contract is upto 90 per cent or more than 90 per cent i.e. it is
nearing completion:
Work certified
(a) Estimated Profit ×
Contract price
Work certified Cash received
(b) Estimated Profit × Contract price × Work certified
OR
Cash received
Estimated Profit × Contract price
Cost of work to date
(c) Estimated Profit × Estimated total cost
Cost of work to date Cash received
(d) Estimated Profit × Estimated total cost × Work certified
Work certified
(e) Notional Profit × Contract price
¾ Batch Costing:- Articles are produced in a lot and cost are computed per unit in a batch.
Cost per unit in a batch= Total cost of a batch/Number of item produced.
EBQ = Points where Set up and carrying cost are minimum.
2DS
EBQ =
IC
¾ Operating Costing:-Use those undertaking which provide services rather than production
in commodities.
Cost units used in the following services undertaken as below:-
Transport service − Passenger km., quintal km., or tonne km.
Supply service − Kw hr., Cubic metre, per kg., per litre.
Hospital − Patient per day, room per day or per bed, per operation etc.
Canteen − Per item, per meal etc.
Cinema − Per ticket.