Distributed Generation on 11kV Feeders
Distributed Generation on 11kV Feeders
constrained feeders
Report produced by University of Strathclyde for the Accelerating Renewables
Connection Project
Authors:
Simon Gill: [email protected]
Milana Plecas: [email protected]
Ivana Kockar: [email protected]
Status: Final
Distributed generation on 11kV voltage constrained feeders
Contents
1 Executive Summary ..................................................................................................................................... 2
Existing Operating Principles ....................................................................................................................... 2
Actively managing generation against voltage constraints ......................................................................... 2
1.1 Modelling work to data ....................................................................................................................... 3
1.2 Additional Conclusions and Future Work ............................................................................................ 5
2 Task 1: Set up model of single 11kV feeder based on St. Andrews data .................................................... 6
2.1 FlexNet Data Overview ........................................................................................................................ 7
2.1.1 FlexNet Data – Uncertainties....................................................................................................... 7
3 Task 2: Business-as-usual design specifications: static ............................................................................. 11
3.1.1 Voltage at the Primary Substation ............................................................................................ 11
3.1.2 LV measurements at secondary substations ............................................................................. 12
3.1.3 Modelling Feeder Voltage levels ............................................................................................... 13
3.2 Generation capacity on Feeder 25 under existing operational rules ................................................ 14
3.3 Firm capacity estimates ..................................................................................................................... 16
3.4 The effect of multiple generators...................................................................................................... 18
4 Task 3: Managing constrain voltages ........................................................................................................ 21
4.1 The effect of raising the point-of-connection voltage limit .............................................................. 21
4.2 Increasing Demand – The ability of flexible demand to increase capacity for distributed generation
22
4.3 Other strategies for managing feeder voltages................................................................................. 24
5 Non-firm connection Agreements ............................................................................................................. 25
6 Task 5: Studying multiple feeders ............................................................................................................. 28
7 Conclusions and next steps ....................................................................................................................... 30
7.1 Further Work ..................................................................................................................................... 30
Appendix 1: Description of the models ............................................................................................................. 32
Appendix 2: Summary of scripts developed during modelling studies ............................................................. 38
Appendix 3: Modelling specification, April – July 2014 ..................................................................................... 54
Summary........................................................................................................................................................ 54
Outcomes ...................................................................................................................................................... 54
Modelling tasks.............................................................................................................................................. 54
Future Work .................................................................................................................................................. 56
Page 1 of 57
Distributed generation on 11kV voltage constrained feeders
1 Executive Summary
The connection of distributed generation at 11kV can create significant network management issues related
to thermal and voltage limits. The management of thermal constraints as part of Active Network
Management (ANM) schemes has been developed by a number of UK DNOs to manage constraints in the
33kV network. However, voltage management is a potentially more complex issue and one that has not
been tackled by UK ANM schemes to date.
This interim report details work carried out by the University of Strathclyde to develop methods for analysis
of the potential for ANM in managing voltage constraints along an 11kV feeder. The work uses Feeder 25
from St. Andrews Primary substation as a template for the methods; however the methods developed can
be applied to any radial 11kV feeder.
The determination of whether to award a firm connection to a generator at a particular location on an 11kV
feeder depends on studies into the voltage at the point-of-connection of the generator. Existing operating
principles state that this should be less than 11.25kV under all standard operation conditions. The
methodology for calculating the point-of-connection voltage is given in the SPEN Distributed Generation
Requirements1. The methodology involves carrying out a detailed power flow analysis using Power Factory,
and the following key points:
Where the point-of-connection voltage exceeds 11.25kV, the generator will not be allowed to connect. The
choice of 11.25kV has been developed through engineering experience from operating the network and is
used to provide confidence that voltages at Low Voltage (LV) level will remain within statutory limits across
the network. Voltages at both 11kV and LV levels are largely un-monitored, and secondary transformers
have limited controllability. For these reasons, robust mechanisms are needed to ensure voltage levels are
within required limits.
1
Distributed Generation Connection Requirements, SPEN, ESDD-01-005, Issue No 1.
Page 2 of 57
Distributed generation on 11kV voltage constrained feeders
Task 1: Set up model of single 11kV feeder based on St. Andrews data
A model of Feeder 25 out of St. Andrews Primary Substation has been created and modified in Power
Factory (See Appendix A1.1). The FlexNet project has installed a significant number of monitors on the St.
Andrews 11kV and LV networks over the past year and data from this project has been made available to
University of Strathclyde for the current work.
The existing Power Factory model used within SPEN has been checked against GIS based information and a
number of errors in cable types and capacities were identified. These have been corrected and detailed in
Appendix A1.1.
Verification against voltage measurements from the FlexNet project is currently proving difficult as the
original Power Factory model does not include models of the 11kV/433V transformers. Generic assumptions
about 11kV/433kV transformers have been made but the modelled and recorded voltage show significant
discrepancies. It is assumed here that the 11kV section of the model is correct and this issue is discussed in
more detail in the body of the report.
Data on power demands for Feeder 25 have been analysed, and half-hourly demand profiles for the months
of April – June 2014 have been created. These have been used as the basis for the initial testing of the
methodologies developed. A number of issues have been identified with the data.
Firstly, a significant fraction of demand is not monitored at secondary substation level. This is evident from
comparing measurements of power flow out of the primary with measurements of power flow at the
secondary substations. The modelling in this report adds additional demand at secondary substations to
bring the total measurements in-line with the values measured at the primary.
Secondly, to verify the Power Factory model, historic measurements of demand on the feeder and voltage at
the primary substation are used as inputs to the model which then simulates the LV voltages. The
comparison between the simulated LV voltages and those recorded by FlexNet currently show significant
inconstancies. There are currently two potential reasons for this: the use of generic 11kV/433V transformer
models and the distribution of unmonitored demand (particularly for reactive power) along the feeder. UoS
is continuing to work on understanding this issue.
In addition to understanding the data, a number of additions have been made to the original Power Factory
model to understand the sensitivity to various assumptions. In particular, a version of the model has been
created with the point at which the voltage is fixed (the infinite bus) moved from the 11kV primary busbar to
the 33kV primary busbar. A load, representative of demand on other feeders from St. Andrews primary, has
also been added (See Appendix A1.3).
2
See appendix 3.
Page 3 of 57
Distributed generation on 11kV voltage constrained feeders
drop off of DG capacity along the length of the feeder to be visualised for a particular time step, and for the
DG capacity at a particular secondary substation across time to be visualised.
The method also allows the identification of estimates of ‘Firm Capacity limits’ at each busbar based on
either the absolute minimum DG capacity at each secondary over the time-horizon investigated (April – June
2014 in this case) or the ‘99th Percentile’ DG capacity at each secondary. These results have been compared
with a heuristic relationship referred to here as ‘the rule of 4’ which suggested that the firm DG capacity will
be inversely related to the distance from the primary. The comparison confirms the Rule of 4 in broad terms.
A methodology has also been developed to investigate the interaction of two DGs on the feeder (See the
Power Factory model in Appendix A1.2). Studies have been run to show the effect of the location of a firm,
high capacity-factor generator on the remaining network capacity over time. The location of the firm
generator is shown to significantly affect the total capacity for generation on the feeder. Locating the
generator at the end of the feeder leads to significantly higher constraints on non-firm generation across the
feeder.
Firstly, the effect of relaxing the constraint on the voltage at the point-of-connection of DG from 11.25kV to
11.3kV was investigated. The methodology developed under Task 2 is repeated with the relaxed constraint,
and the DG capacities are compared. Results show that this can allow a significant increase in firm capacity.
At the end of the feeder, approximately 200kW additional capacity can be released, in the middle section
approximately 1MW. Close to the primary the effect depends on the exact method of defining ‘firm
capacity’. The increase in the voltage limit reduces the limiting effect of time-steps with primary voltage
levels at or above 11.25kV.
The second tool investigated to increase capacity is the use of flexible demand that can allow demand to be
increased to relieve curtailment. If demand and generation are on the same site this will give a 1:1
relationship with 1 unit of additional demand reliving curtailment by 1 unit. However, it is possible that the
flexible demand may be located elsewhere on the feeder. A methodology has therefore been developed
which identifies the increase in DG capacity created at a particular secondary substation if demand is
increased at a different secondary substation. The methodology increases demand by 100kW at different
locations on the feeder and calculates the increase in DG capacity at a particular secondary.
Results show that demand connected either at the same location as the DG or further away from the
primary has approximately a 1:1 relationship with between demand and additional DG capacity. However,
demand connected closer to the primary substation than DG is less effective; a unit of additional demand
increases DG capacity by less than 1 unit. The effectiveness of demand decreases the closer it is to the
primary.
Page 4 of 57
Distributed generation on 11kV voltage constrained feeders
An illustration of this method has been carried out using the historic network information for St. Andrews
Feeder 25 and historic output of a wind generator from the ARC region. These data are used to calculate the
capacity of non-firm generation that could connect at each secondary substation whilst experiencing a
curtailment of no more that 10% of available output across the time-horizon of the study.
Results suggest that the greatest potential for non-firm generation will be in the middle regions of the feeder
where the potential for firm capacity is relatively low but significant additional capacity is available during
most time-steps.
It should be noted that these conclusions are based on only three months of data and at least one full year
of data is required before these results can be confirmed.
To fully understand this work, a detailed understanding of the control systems of the primary On Load Tap
Changer is required, and the potential for operating the primary as an ‘exporting primary’. As such this work
has been left until the project team has reviewed the work on single-feeder modelling and Strathclyde have
the opportunity to meet with SPEN technical experts to identify the OLTC transformer work.
- There is significant variability in the 11kV voltage at measured at St. Andrews primary substation,
ranging from approximately 10.9kV – 11.3kV. (Task 1)
- The voltage constrained capacity at most secondary substations modelled depends more strongly on
the primary voltage than on the feeder load. (Task 1)
- The available firm capacity drops off exponentially as a function of distance from the primary. (Task
2)
- The greatest opportunity for non-firm connection agreements lies in the middle section of the
feeder where firm capacity is low due to voltage constraints during a small number of time-steps,
but significantly greater capacity during the majority of time steps. (Task 4)
- The capacity for DG on the feeder if more than one generator is connected depends on the locations
of both generators and the relatively priority given to output from those generators. (Task 3)
- The modelling of 11kv/433V transformers needs further investigation with input from SPEN on this
aspect of the Power Factory model.
- There are significant inconsistencies between power flow measurements at St. Andrews Primary and
the secondary substations. This is assumed to be because not all the secondary substations are
monitored. We suggest a meeting with the FlexNet team to discuss this aspect of the project.
- The effect on primary voltages of the changes to power injected to the feeder by Distributed
Generation needs further analysis. This is required to verify conclusions made in Tasks 3 and 4, and
should be agreed before significant progress can be made on Task 5.
Page 5 of 57
Distributed generation on 11kV voltage constrained feeders
2 Task 1: Set up model of single 11kV feeder based on St. Andrews data
The aim of Task 1 is to set up a usable model of an 11kV feeder to develop methodologies for analysis of the
connection of Distributed Generation (DG) and provide insight into the potential for operating a voltage
constrained feeder as part of the ARC project. SPEN have provided a Power Factory model of Feeder 25, an
11kV feeder from St. Andrews Primary substation. The FlexNet Project has carried out detailed monitoring of
this section of the network, and analysis of the data collected forms an important part of the work within
this task.
A Power Factory model of St. Andrews Feeder 25 has been provided by SPEN. The components of this model
have been checked against GIS based data held by SPEN. Several errors were identified in the original model
of the including incorrect cable types (for example copper instead of aluminium) and incorrect cable lengths.
A full list of the errors identified is given in Appendix 1.1.
The initial model also includes a number of distributed generation studies carried out by SPEN dated
between September 2013 and April 2014. These studies have been removed for the purposes of this work.
Figure 1 shows an overview of the feeder as modelled in Power Factory. More detailed information on the
Power Factory models used is included in Appendix 1.
The original Power Factory model does not include 11kV/433V transformers and load is connected directly
to the 11kV bus-bar at the secondary substation. The model used for this work has been extended to include
11kV to 433V transformers with impedances in line with the standard values used by SPEN. However, it
should be noted that the modelling of 11kV/433V transformers has not been verified, and significant
inconsistencies exist between historic measurements and Power Factory modelling results for LV voltages.
In addition to the base model, which begins at the 11kV busbar at St. Andrews Primary, a derivate model has
been created which includes 2 generic 33/11 kV transformers, the 33kV busbar and an additional load
representing demand on other feeders(See Appendix A1.3). This allows the effect of varying voltage drops
through the primary transformers to be modelled when varying the capacity of distributed generation and
load on the primary substation.
Page 6 of 57
Distributed generation on 11kV voltage constrained feeders
At each secondary substation the following data useful to this project is recorded on each phase:
At substations fitted with Subnet equipment values for V, I and pf are recorded to a greater number of
significant figures than P and Q which are often given to only 1 or 2 significant figures. As such all values of P
and Q used in these studies are derived from V, I and pf. Data is recorded at either 1 or 10 minute resolution.
This analysis reduced the data to half-hourly resolution.
Measurements at St. Andrews Primary include Line-to-Line voltages between phases A and B and phases B
and C (there is no recording of Voltage between Phase C and A). There are also measurements of P, Q made
with a two-power meter. Phase-by-Phase powers are not recorded but the total of the two measurements of
P and the two measurements of Q give the three phase values.
However, the secondary measurements do not account for all the demand. Summing primary power
measured across all phases and similarly aggregating all secondary measurements across all secondary
substations and all phases suggests that the secondary measurements account for approximately 50% of
total real power and 25% of total reactive power demand. The two time-series for primary and total
secondary real Power are shown in Figure 2. The primary measurement varies from 1.6 – 3.4 times the total
secondary powers at those times with an average of 2.2.
FlexNet measurements of the current at St. Andrews primary have been verified against PI records for the
same period and show close agreement as shown in Figure 3. As noted above, the current, voltage and
power factor readings have been used to calculate P and Q at the primary and it is these values of P and Q
which have been compared against secondary values calculated in a similar way.
Page 7 of 57
Distributed generation on 11kV voltage constrained feeders
Figure 2: Comparing primary and secondary power measurements for Feeder 25, April 2014
Figure 3: Comparison of FlexNet and Pi records of current flow on Feeder 25, April 2014
The most likely reason for the inconsistency between primary and secondary measurements power records
is that some secondary substations are unmonitored. In particular, the rural region of the feeder has a
number of unmonitored secondary substations. The magnitude of the difference between primary and
secondary measurements with respect to reactive powers is surprising even given the number of
unmonitored secondary substations.
To account for the inconsistencies we have assumed that the measurements of real power from the primary
are accurate and electrical losses are negligible compared with the inconsistencies in the data. To correct the
secondary power measurements two techniques have been used:
- The value of P and Q at each secondary substation is scaled up so that the aggregate real power
across the feeder is equal to the real power drawn from the primary. This spreads the missing
demand across the whole feeder. Demand profiles calculated using this method are referred to as
scaled profiles.
- Additional load is added in the rural section of the feeder. Specifically: ¼ of the missing load is added
at each of: East Grange Terminal Pole, St Andrews Bay WWTW, St. Andrews Bay Hotel and
Kingsbarns. The missing demand is equally spread across the three phases. This method assumes
that the missing demand is fully located in the rural region of the feeder. Demand profiles from this
method are referred to as extra rural demand profiles.
Throughout this report, unless otherwise stated, the second of these two methods is used to model demand
on the feeder.
Page 8 of 57
Distributed generation on 11kV voltage constrained feeders
The real and reactive power as measured by the secondary substations are both scaled by the same value
based on missing real power.
At this stage UoS suggested that, to agree on the most appropriate correction method for real and reactive
power, and to further understand the very large difference in reactive power measurements, we suggest
meeting with the FlexNet technical team.
Simulation of the LV voltage involves setting the primary 11kV voltage to the historically recorded value,
setting the LV loads to the historically recorded values of P and Q, running a load flow and recording the LV
voltages. A script has been created to automate this process for all half-hour time steps during April – June
2014 (see Appendix A2.1 for details).
Results for a particular time-step with intermediate demand are shown in Figure 4. The grey lines show the
values recorded by FlexNet and the coloured lines show the results simulated with Power Factory. The red
line uses the recorded values of P and Q at the secondary substations and as discussed above misses a
significant amount of demand as monitored by Primary. The blue lines use the scaled demand profile and
the green lines use the extra rural demand profiles. In all cases, simulated voltages are significantly higher
than the measured values at the majority of secondary substations.
Figure 4: LV voltages measured by FlexNet and Simulated on Power Factory. Simulation results include three demand distributions
representing the demand recorded by FlexNet secondary substation monitors and the addition of additional demand to match
measurements at the primary.
Two potential reasons for the inconsistency are the 11kV/433V transformer models and measurements of
reactive power demand. The components forming the 11kV cables and overhead lines have been carefully
checked against SPEN’s GIS based database of equipment and are assumed to be accurate.
The secondary transformer models currently used are taken from the ‘Library Distribution Design Manual’
provided with the Power Factory model with impedances checked against the standard values for
particularly sizes of transformer.
Page 9 of 57
Distributed generation on 11kV voltage constrained feeders
Given the significant differences between primary and secondary measurements of reactive power demand
there is the potential that the reactive powers used in the model are not correct. Reactive power drawn
through the 11kV/433V transformers can significantly affect the LV voltage levels. As such confirmation that
the reactive power measurements from FlexNet are accurate is important in verifying this model.
Despite the need to further verify the modelling of LV modelling, much of the analysis required by the ARC
project focuses on the 11kV level. As it is likely that the LV voltage errors are related to the 11kV/433V
transformers, UoS is continuing with the current model which requires only 11kV voltages. This allows the
development of methodologies and outline results. Simulation results for the 11kV voltage profiles for single
time-steps are shown in Figure 5 for the three distributions of demand. It is clear that verifying the quantity
of real power demand and its distribution along the feeder is important for identifying the voltage
constrained DG capacity towards the end of the feeder.
Figure 5: 11kV voltages in Per Unit values for a single times step with three distributions of demand.
An additional simulation carried out for sensitivity is to double the additional Q included in the extra rural
demand profile. This is shown by the dashed lines in Figure 5 and represents the case where P is increased
by 2.66 compared with the total monitored secondary demand, and Q is increased by 5.32. The significant
additional Q, connected at the end of the feeder makes only a relatively small difference to the 11kV voltage
(it should be noted that this makes a more significant difference to the simulated LV voltage).
Page 10 of 57
Distributed generation on 11kV voltage constrained feeders
- The On Load Tap Changers (OLTC) at the primary operate to maintain the voltage be close to 11.2kV.
The SPEN Design Manual suggests using 11.2kV as the primary voltage for distributed generation
studies if actual readings are not available3.
- The limit on DG connecting to a feeder such that “Typically, 11kV connections will be constrained to
an upper limit of 11.25kV at the Point of Common Coupling (POCC)”4
In addition, the following limits on the allowed voltage levels are identified:
- The 11kV network should be operated in the region 11kV + / - 6% corresponding to 10.34kV –
11.66kV.
- The LV network should be operated in the region 230V +10% - 6% corresponding to 216.2V – 253V.
One objective of studying the FlexNet data is to identify if these rules are obeyed in practice.
Figure 6: distribution of phase-to-phase voltages at St. Andrews Figure 7: Voltage imbalance at St. Andrews Primary during
Primary during April 2014 April 2014
3
Distributed Generation Connection Requirements, SPEN, ESDD-01-005, Issue No 1.
4
Distributed Generation Connection Requirements, SPEN, ESDD-01-005, Issue No 1.
Page 11 of 57
Distributed generation on 11kV voltage constrained feeders
Figure 8: No correlation is seen between Primary voltage and demand on the feeder, nor between Primary voltage and total Primary
demand.
The recorded data shows that the primary voltage is operating below 11.2kV for the majority of the time.
The voltage Va-b is less than 11.2kV for 99% of time-steps and voltage Vb-c is less than 11.2kV for 75% of the
time. The average of the voltage is 11.09kV and 11.16kV for Va-b and Vb-c respectively.
The value of Vb-c is also higher than 11.25kV during 186 time-steps meaning that during these periods there
would be no capacity for distributed generation close to the primary substation due to the voltage limit of
11.25kV at the point-of-connection of distributed generation.
The LV voltages recorded at the primary substations are well correlated with the primary voltage, for
example for Priestden Road, Phase A, the correlation between LV reading and average Primary voltage is
shown in Figure 9 (a). The LV voltages are also correlated with total feeder demand, and Figure 9 (b) shows
this for Priestden Road Phase A. The conclusion is that, as expected, overvoltage at Priestden Road will occur
when primary voltage is high and total feeder demand is low. The data shows only low correlation between
voltages and demand at Priestden Road itself, any local effect being swamped by primary voltage and overall
feeder demand.
Page 12 of 57
Distributed generation on 11kV voltage constrained feeders
(a) (b)
Figure 9: Correlation between (a) primary voltage and LV voltage at Priestden Road on phase A, and (b) total Feeder demand and
LV voltage at Priestden Road phase A.
Simulations have been carried out to model the 11kV voltage profile along the feeder for each time-step
during April-June 2014. The modelling has used the adjusted extra rural demand profiles. Figure 10 Shows
two typical voltage profiles, where the horizontal axis represents distance along the feeder. The primary
voltage (shown at zero distance) is the average recorded voltage across the two measured phases at the
primary. Two time steps are show: the high demand time step shows the greatest voltage drop along the
feeder.
Figure 10: Example 11kV voltage profiles simulated by Power Factory representing high and low demand time-steps
Figure 11 shows the distribution of voltages at each secondary throughout April – June as modelled by
Power Factory. The dashed central line shows the median value of voltage at each substation. To either side
of this are lines representing confidence bounds, for example the light grey lines shows the range within
which voltage at that location is in for 99% of the time – the 99th percentile limit. The red and blue lines
show the absolute maximum and minimum values modelled at each time-step.
Page 13 of 57
Distributed generation on 11kV voltage constrained feeders
Figure 11: Statistical properties of voltage variation along the feeder. The central line represents the median value of voltage at each
substation while moving progressively away from the centre shows higher percentile values. The bounding lines, top and bottom
represent the absolute maximum and minimum values simulated at each substation.
The results suggest that the voltage on the 11kV network is operating within bounds for the 11kV system.
- At periods of low demand a distributed generator must not be capable of overloading the thermal
limits of the feeder.
- Under all standard operating conditions, from minimum to maximum demand, voltage limits across
the feeder must be maintained.
The second of these is currently met by limiting the voltage at the point-of-connection to a maximum of
11.25kV. Both of these constraints are traditionally met by only setting a Firm Capacity limit; the use of non-
firm contracts however allows greater capacities to connect on condition that they respond to curtailment
signals and reduce their demand when required to maintain the two conditions.
To investigate the capacity available for distributed generation at each of the secondary substations Power
Factory studies have been run for each half hour in April 2014. For each time-step the maximum capacity
that maintains the thermal and voltage limits is calculated at each secondary substation under the
assumption that there is only one distributed generator connecting.
To carry out this study a Power Factory script has been developed which loads the historic conditions for a
particular time-step and then finds the maximum capacity of distributed generation that maintains the
thermal and voltage limits for that time step. The result is a time-series of capacity limits for each secondary
substation. More detail on the methodology and script developed are given in Appendix A2.1.
The methodology developed is applied to the period April – June 2014 using the adjusted demand profile
with addition demand in the rural section. Figure 12 shows three examples of the available DG capacity
along the length of the feeder. In all three cases the capacity at the first two secondary substations (Forrest
St. and Hamilton Ave.) are constrained by the thermal limit on export form the feeder. The limiting power
flow along the feeder is approximately 4.3MVA, and the maximum thermally constrained DG capacity is
therefore approximately 4.3MW plus current demand on the feeder.
Page 14 of 57
Distributed generation on 11kV voltage constrained feeders
For the cases of low demand, DG at all substations from 3 - 13 are voltage constrained with the limit of
11.25kV at the point-of-connection reached before the thermal limit of the feeder. With high demand,
substation 3 is thermally constrained and 4 – 13 are voltage constrained. However, with the intermediate
demand level, substations 1-10 are thermally constrained and the voltage constraint is only binding between
substations 11 and 13.
Figure 12: Capacity profile along feeder for three demand scenarios during April – June 2014.
The lack of voltage constraints in the central section of the feeder for the intermediate demand case is due
to a low primary voltage. The primary voltage for this time step is 10.97kV compared with 11.17kV for the
low demand case and 11.13kV for high demand. The low primary voltage creates significant voltage
headroom even out to several km along the feeder. This shows the importance of primary voltage on the
available capacity for DG on the feeder.
Figure 13 shows the distribution of available capacity at several secondary substations in the form of a
‘capacity availability curve’. This shows the fraction of time that the available capacity is greater than a given
quantity and can be interpreted as the fraction of time the network can accept full output from a given
capacity of generation at that location. Capacity availability curves move towards the left for substations
further along the feeder showing the reduction in available capacity. Where the capacity availability curve is
close to 1, the network can almost always accept that capacity of generation. Where it is close to zero the
network can almost never accept that capacity of generation.
Figure 13: Capacity duration curve showing network capacity available at 5 secondary substations. For a given network capacity, the
figure shows the fraction of time that at least that level of network capacity is available.
Page 15 of 57
Distributed generation on 11kV voltage constrained feeders
The capacity availability curve for Forrest St. which is close to the primary shows that 5MW of network
capacity is almost always available. This reflects the fact that Forrest St. is thermally constrained the majority
of the time with a limit set by the feeder thermal limit and the current demand.
Figure 14 shows how these availability duration curves relate to the associated time-series. At Forrest St. the
thermal limit leads to a relatively small variation in capacity during most time-steps, with occasional
downward spikes when particularly high primary voltages lead to voltage constraints becoming binding. At
St. Nicolas Street, the thermal constraint defines the upper edge of the envelope of available capacity,
however voltage constrains are binding during significantly more time-steps than is the case for Forrest St.
Finally, at Kingsbarns at the end of the feeder, all time-steps are voltage constrained, and the significantly
lower available capacity is shown by plotting the results on the same scale as for Forrest St. and St. Nicolas
St.
Figure 14: Time series of available network capacity at three substations for April – June 2014.
A point of comparison for either method of determining the firm capacity limit is to compare with heuristic a
rule of thumb used by SPEN referred to here as the ‘rule of 4’. This heuristic estimate of available capacity
states that the firm capacity multiplied by the distance from the primary should be less than or equal to 4:
Figure 15 plots the 99th Percentile capacity, the Rule of 4 and the absolute minimum capacity along the
feeder. Close to the primary the rule of 4 and the 99th Percentile give similar estimates of firm capacity,
whilst the absolute minimum gives a very low estimate. Further along the feeder both the absolute
minimum and 99th Percentile give estimates slightly higher than the rules of 4. As with other results in this
Page 16 of 57
Distributed generation on 11kV voltage constrained feeders
report it should be remembered that the modelled estimates of firm capacity are based on only three
months of data. Table 1 gives the values calculated for each substation.
Table 1: Maximum and Minimum DG capacities at each secondary substation during April 2014
th
Substation Distance Max DG Min DG 99 Percentile DG ‘Rule of 4’
from Primary capacity (MW) Capacity (MW) Capacity (MW) Capacity (MW)
Forrest St 0.83 7.14 0.00 3.57 4.80
Hamilton Ave 1.13 7.14 0.00 2.78 3.54
St Nicholas Street 2.49 7.16 0.31 1.95 1.61
Abbey Walk 2.92 7.16 0.51 1.89 1.37
Harbour Pumping
Station 3.13 7.10 0.60 1.85 1.28
Gatty Marine 3.56 7.06 0.73 1.76 1.12
St Andrews
Swimming Pool 4.08 6.93 0.83 1.67 0.98
St Nicholas WWTW 4.18 6.85 0.84 1.64 0.96
Priestden Road 4.72 6.71 0.90 1.54 0.85
East Grange 5.54 5.37 0.96 1.35 0.72
St Andrews WWTW 7.65 5.04 0.95 1.19 0.52
St. Andrews Bay
Hotel 11.24 3.71 0.71 0.92 0.36
Kingsbarns 18.03 2.66 0.54 0.68 0.22
Figure 15: Comparison between the 99th Percentile Capacity and the 'Rule of 4' capcaity for substations along Feeder 25 derived from
data for April 2014.
Page 17 of 57
Distributed generation on 11kV voltage constrained feeders
As a simple example, if a DG injects the power at Substation 6 raising the voltage here close to 11.24kV,
which is close to the limiting value, voltages at Substation 5 and 7 will also rise meaning very limited capacity
at either of these locations.
To investigate the effect of the interaction of two DGs, the method of Section 3.2 is adjusted to consider the
remaining capacity for DG after the connection of a 0.5MW firm generator with a capacity factor of 1. The
remaining capacity will be less than that calculated in Section 3.2, but it is interesting to identify the
magnitude of the decrease, and the effect of the location at which the 0.5MW firm generator is connected.
To model this, an adapted version of the Power Factory feeder model has been created with the extra
generator added to represent the firm generator. The resulting model is explained in Appendix A1.2. The
methodology of Section 3.2 which was used to calculate the maximum DG capacity at each secondary
substation and at each time step, described in Appendix A2.1, is also modified. In the new script, described
in Appendix A2.2, the firm generator is first dispatched along with the historical demand, then the remaining
capacity at each secondary substation is calculated. This script requires checking that the voltage remains
within limits at both the point-of-connection of both the Firm and Non-Firm generators.
The method is carried out with the 0.5MW firm generator connected at 3 locations:
The effect on the remaining capacity for DG across the feeder is illustrated for three time-steps in Figure 16.
The time-steps represent High, Intermediate and Low demand, respectively. In each case the capacity for DG
without firm generation (as calculated in Section 3.2) is compared with the remaining capacity with the firm
generator connected at each of the three potential locations.
Substations which are thermally constrained see a reduction in the remaining capacity for DG of
approximately 0.5MW if they remain thermally constrained after the addition of the firm generator. The firm
Page 18 of 57
Distributed generation on 11kV voltage constrained feeders
generator effectively reduces the feeder demand by 0.5MW therefore reducing the available thermal
capacity by 0.5MW. However, when a substation is constrained by voltage, it is not only the size of the firm
generator but its location which affects the remaining capacity.
Figure 16 (c) shows the case of the low demand and relatively high Primary voltage, with substations 3 – 13
constrained by voltage with no Firm generator and substations 1 and 2 thermally constrained. The addition
of the firm generator at either Substation 1 or 7 reduced the DG capacity at Substations 1 and 2 by
approximately 0.5MW as expected. However the connection of the firm generator at Substation 13 reduces
the DG capacity at Substations 1 and 2 by significantly more. This is because the voltage at Substation 13 is
now close to 11.25V and only a small DG capacity can be accommodated elsewhere on the feeder before the
voltage at Substation 13 reaches the limit. During some time-steps, this effect can reduce the available
capacity elsewhere on the feeder to zero. In all three cases shown in Figure 16, locating the firm generator at
Substation 13 leads to the greatest reduction in remaining network capacity elsewhere.
Whilst locating the firm generator at Substation 13 reduces DG capacity significantly, locating the firm
generator at Substation 1 has an almost negligible effect on capacity at voltage constrained buses. In Figure
16 (a) the connection of the 0.5MW firm generator at Substation 1 can be seen to reduce the remaining
capacity at thermally constrained Substations (1 to 4) by 0.5MW as expected. However, from substations 5 –
13 the addition of the firm generator does not reduce the remaining capacity. This means the feeder can
support the original DG capacity at these locations and the 0.5MW firm generator. The reason is that the
firm generator is close to the primary where the voltage is fixed. Injection of 0.5MW at Substation 1
therefore doesn’t significantly affect the voltage profile across the feeder.
A useful way to visualise the competing effects is to consider the reduction in total capacity as a fraction of
generation from the firm generator. During 1 half hour time-step the firm generator will inject 0.25MWh of
electrical energy onto the network, or 1.08GWh over three months. The reduction of capacity available for
other generators can then be benchmarked against this value.
Figure 17 plots the capacity reduction in this way for the three firm generator locations. A value of 1 reflects
the situation where the reduction in network capacity exactly balances the output of the firm generator. This
represent a neutral condition: the firm generator is efficiently using network capacity. If the value is greater
than 1, the reduction in network capacity is greater than generation from the firm generator and conversely
if less than 1 the reduction in network capacity is less than the energy injected by the firm generator. For
values less than 1 the results is an overall greater capacity for DG than may have been expected from the
results in Section 3.2.
By definition the fractional capacity reduction will be exactly 1 at the substation where the firm generator is
connected. For example with the firm generator connected at Substation 7, network capacity reduction at
Substation 7 is exactly 1. However, it is interesting to note that when the firm generator is at Substation 1,
the reduction in network capacity is always less than 1 at substations 2 – 13, dropping to close to zero at the
end of the feeder: connecting a generator at Bus 1 has a negligible impact on the capacity for DG at the end
of the feeder. This therefore represents a highly efficient use of the network.
By contrast, connecting the firm generator at Bus 13 leads to a situation where the network capacity
reduction at Substations 1 – 12 is greater than 1, rising to nearly 3 in the middle section. This highlights the
inefficiency of connecting generation at the end of the feeder on the overall ability to connect more
generation to the feeder.
Page 19 of 57
Distributed generation on 11kV voltage constrained feeders
Figure 17: Reduction in network capacity due to a firm generator, where reduction in capacity is expressed as a fraction of the energy
injected from the firm generator.
The conclusion from Figure 13 is that DG should be connected as high up the network as possible to
maintain additional capacity. In an ANM situation the findings suggest that non-firm generation closer to the
primary should have a higher priority. The connection of a DG can be thought of as imposing an ‘opportunity
cost’ equal to the reduction in remaining capacity for DG. The connection of DG near the primary therefore
has a small opportunity cost, whilst the connection of DG near the end of the feeder has a high opportunity
cost.
Further understanding the interaction of multiple generators, and investigating the interaction of non-firm
generators with various principles of access will form an important aspect of further work.
Page 20 of 57
Distributed generation on 11kV voltage constrained feeders
Two specific examples are given. Firstly, the effect of increasing the limit on the point-of-connection voltage
is investigated. Secondly, the use of demand flexibility or new electrical to raise demand at different point on
the feeder. The objective of this section is to highlight the potential increases in DG capacity that these two
interventions can create.
Figure 18 shows the effect during the High and Low demand time-step illustrated earlier in Figure 12. The
thermally constrained capacities at the first two substations remain unchanged. In the middle regions of the
feeder at Substation 6 the capacity increases by 1.02MW for the High Demand case and 1.19MW for the low
demand case. At the extremities of the feeder, the increase is relatively small with an increases of 200kW
280kW respectively for the High and Low Demand.
Figure 18: Comparing the capacity along the feeder with a point-of-connection voltage limit of 11.25kV and 11.3kV.
Figure 19: Methods of Estimating the Firm Capacity when the point-of-connection is raised to 11.3kV
Page 21 of 57
Distributed generation on 11kV voltage constrained feeders
The increase in firm capacity as estimated by either the 99th Percentile of available capacity and the absolute
minimum capacity are shown in Figure 19 and Table 2. Raising the voltage limit removes the effect of very
high primary voltages on firm capacity at substations close to the primary. The greatest increases are seen in
the first half of the feeder with the additional capacity created greater than 1MW as far out as Substation 6,
Gatty Marine, which is 3.56km from the primary.
Table 2: Increase in the Firm Capacity when raising the point-of-connection voltage limit from 11.25kV to 11.3kV as estimated by the
th
absolute minimum capacity and the 99 Percentile capacity. All values are in MW
Substation 1 2 3 4 5 6 7 8 9 10 11 12 13
Increase (Absolute Min) 2.78 2.40 1.71 1.50 1.38 1.17 1.00 0.97 0.83 0.61 0.43 0.28 0.18
th
Increase (99 Percentile) 1.66 2.45 1.72 1.51 1.38 1.18 1.00 0.97 0.83 0.61 0.43 0.28 0.19
Increasing the allowed 11kV voltage level has the potential to impact on LV voltages. At locations where LV
voltages are close to the upper bound of 253V per phase, increases 11kV voltages may create more cases of
overvoltage. As discussed in Section 2, the only substation with significant instances of overvoltage is
currently Priestden Road where 25% of voltages on Phase A are over 253V. Over the whole feeder only 0.6%
of all LV voltage measurements collected by FlexNet for this period are overvoltage. Another 3% of voltages
were recorded in the range 250V – 253V representing voltages that are close to the upper limit and in
danger of being pushed over by increased 11kV voltages.
4.2 Increasing Demand – The ability of flexible demand to increase capacity for distributed
generation
A second way to increase capacity for DG is to increase demand. This can either be through the development
of new electrical demand, for example converting a non-electrical energy demand such as oil-heating, to
electricity and aiming to supply it with renewable electricity from distributed generation. A second potential
demand-side involvement is the use of flexible demand that can change the timing of electrical demand to
relieve curtailment.
If demand and generation are on the same site, an increase in demand during a particular time-step will give
a 1:1 relationship with capacity for DG: 1kW of additional demand reliving curtailment by 1kW. However, it is
possible that the flexible demand may be located elsewhere on the feeder, for example if demand is
distributed through a village and spread across multiple secondary substations. A methodology has
therefore been developed which identifies the increase in DG capacity created at a particular secondary
substation if demand is increased at a different secondary substation. The methodology increases demand
by 100kW at different locations on the feeder and calculates the increase in DG capacity at a particular
secondary. Details of the methodology can be found in Appendix A2.3 which describe the Power Factory
script developed for this activity.
Page 22 of 57
Distributed generation on 11kV voltage constrained feeders
Figure 20: Additional DG capacity creased due to increase in demand during a single time step. Each line represents DG capacity
increase at a particular feeder location when demand is added at different substations.
Figure 20 shows the results for a single time-step and for DG capacity at four secondary substations. The line
for Substation 1 shows the additional DG capacity created when 100kW of demand is added at each
secondary substation. The conclusion from this line for substation 1, the addition of 100kW of demand at
any substation will allow an additional 100kW of DG capacity during that time-step. If a constrained
generator were presented at Substation 1, the additional demand would therefore have the potential to
reduce curtailment on a 1:1 basis no matter what the location of the demand. During this time-step
Substation 1 is thermally constrained and any therefore additional demand would reduce reverse power
flow from the feeder to the primary substation on a 1:1 basis5.
For the other DG locations shown in Figure 20, the binding constraint is due to voltage. In these cases, the
effectiveness of additional demand at creating further headroom for DG depends on its location. For DG
located at Substation 13 that is at the end of the feeder additional demand located closer to the primary has
a small than 1:1 effective: 100kW of additional demand leads to less than 100kW of extra DG capacity.
The results shown in Figure 20, which are replicated at all time-steps can be summarised as follows:
- Additional demand at the same secondary substation as a DG will raise capacity for that DG on a 1:1
basis.
- For substations where DG is thermally constrained, the addition of additional demand leads to
approximately a 1:1 increase in DG capacity regardless of the location of the DG.
- Where DG capacity is voltage constrained, additional demand located closer to the primary than the
DG unit will have a small than 1:1 effect on DG capacity, so every unit of additional demand creates
less than 1 unit of extra DG capacity.
- Where DG capacity is voltage constrained and the additional demand is located further from the
primary than the DG unit, the demand creates approximately a 1:1 increase in DG capacity.
These conclusions suggest that the efficient use of flexible demand to relieve voltage constraint requires that
demand flexibility is used to manage voltages between the demand and the primary rather than between
the demand and the extreme of the feeder.
5
As with other conclusions relating to thermal constraints, changes in the electrical losses mean that there will be small
variations away from the exact results, however these variations will be small compared with the level of precision that
the power system is operated to.
Page 23 of 57
Distributed generation on 11kV voltage constrained feeders
Many of these are being tested in other projects around the UK. The majority of them are beyond the scope
of the ARC project. One further intervention which may be used within ARC to increase voltage-constrained
DG capacity is to change the control settings at primary transformers. Specifically it may be possible to lower
the primary voltage as long as this can still be guaranteed to keep the network, out to the extremes of the LV
network above the minimum voltage threshold.
Modelling and analysis of such a scheme will require a UoS to develop greater understanding of the existing
and proposed control systems for LV models. This will include verifying a model of the 33/11kV transformer
and understanding the set-points, dead band, and delays associated with the OLCT control system. One
useful observation of the FlexNet data is that the lowest LV voltage recorded over Feeder 25 is 218, just
above the lower statutory limit of 216V (based on a -10% limit). The number of instances of voltage records
less than 227V which would form the lower bound if limits were tightened to a -6% limit is 21 out of more
than 200,000. The FlexNet readings are made at the Secondary Substation, and it is important to ensure that
LV voltages are above the minimum limit at the end of the LV feeders. SPEN operate the LV network with a
maximum voltage drop along the feeder. This maximum voltage drop can therefore be applied to LV voltage
measurements, and this analysis can form part of future work.
Page 24 of 57
Distributed generation on 11kV voltage constrained feeders
For a given size of DG wishing to connect at a particular secondary substation, the expectation of curtailment
can be estimated using historical times-series. Such a calculation requires (a) a time-series of the expected
available generation and (b) a time-series of the available network capacity at that location. The network
capacity time-series is an output of Task 2 as discussed in Section 3.2. The available generation time-series
depends on the generation technology. For a wind generator, an existing method is to scale the historic
output time-series for a nearby wind generator to the installed capacity of the non-firm generator in
question. This assumes that the same wind resource is seen by both generators.
To illustrate this method, the network data for April – June 2014 is used to calculate the capacity of non-firm
generation that can connect and should expect to have 10% of its potential output curtailed. This is referred
to as , meaning the DG capacity available for non-firm wind with 10% curtailment. It must be
remembered that the results are only valid for 3 month of data and are included to show the methodology.
Figure 21 shows the normalised available wind profile used in the study. The data is taken from a wind farm
in the ARC region for the period January – March 2012. This is neither close to St. Andrews nor for the same
time-period for which network data is available. As such it is strictly an illustration of the methodology.
However, some of the results of the study are likely to be qualitatively useful in directing further studies of
these effects.
Figure 21: Normalised available wind generation for a wind generator with an uncurtailed capacity factor of 0.36.
Figure 22: Comparing network capacity against available wind generation for a 10 day period. Where the available generation (black)
is greater than the network capacity (red) the generator is curtailed to the red line.
Page 25 of 57
Distributed generation on 11kV voltage constrained feeders
Figure 22 shows an example of the calculation that should be carried out for a given capacity of generation
connecting at a given network location. The red line shows the capacity of generation that the network can
accommodate within thermal and voltage limits, and the black line shows the available generation. Where
the black line is greater than the red line, curtailment is required. Ideally this calculation should be carried
out for at least one full year of co-incident network and generation data before drawing firm conclusions.
To calculate the non-firm capacity at each secondary substation that will experience a 10% curtailment the
following method is used:
6. Calculate how much curtailment is required for each time step to stay within the network limits
7. Calculate the fraction of available non-firm generation curtailment across the study
8. If the fraction of curtailed non-firm generation is less than 10% increase by
0.1MW and repeat steps 5 – 8.
9. Repeat Steps 2 – 8 for each secondary substation
The methodology has been developed as an excel spread sheet model. It connects firm capacity up to the
99th percentile limit, and then continues to connect non-firm capacity to the point at which the non-firm
capacity experiences 10% curtailment.
Page 26 of 57
Distributed generation on 11kV voltage constrained feeders
Substation Firm Capacity (MW) Non-Firm Capacity (MW) Total Capacity (MW)
Forrest St 3.57 4.2 7.77
Hamilton Ave 2.78 5.2 7.98
St Nicholas Street 1.95 5.3 7.25
Abbey Walk 1.89 5 6.89
Harbour Pumping Station 1.85 4.6 6.45
Gatty Marine 1.76 4.2 5.96
St Andrews Swimming Pool 1.67 3.7 5.37
St Nicholas WWTW 1.64 3.6 5.24
Priestden Road 1.54 3.1 4.64
East Grange 1.35 2.4 3.75
St Andrews WWTW 1.19 1.8 2.99
St Andrews Bay Hotel 0.92 1.3 2.22
Kingsbarns 0.68 0.8 1.48
Figure 23 and Table 3 show the illustrative estimates of capacity that can connect at each bus based on the
three months analysis. As already noted these results are illustrative of the method rather than providing
firm conclusions to draw for this network.
Whilst studies need to be carried out with at least one year of coincident data, the form of the results is
sensible. Close to the primary substation, the firm capacity is large which itself limits the opportunity for
non-firm capacity. However, in the middle region of the feeder firm capacity is limited by voltage constraints
during a relatively few number of time-steps. For example substations 2 – 6 in the example are likely to
provide the greatest opportunity for non-firm generators.
Page 27 of 57
Distributed generation on 11kV voltage constrained feeders
The work presented so far fixes the 11kV primary substation voltage to the historically recorded value.
Whilst this allows the correct modelling of the historic network conditions including real and reactive power
loading, the addition of distributed generation will lead to a change in the voltage at the primary substation.
When only single DG or a single feeder is being investigated this change is held to a small value by the large
load on other feeders. However, for the studies of the full distribution network with multiple generators
added at different locations, the additional modelling is required.
This modelling will seek to understand the control of voltage at the primary by the transformers and
associated on load tap changers, and the effect on demand drawn from the primary substation on the 33kV
voltage level. In a simple example, a reduction of demand (or equivalently an increase in DG output) will
initially lead to a rise in the voltage on the 11kV busbar as voltage drop on the 33kV system and through the
primary transformers is reduced. However, at some point when the 11kV primary voltage reaches a
predefined level for a predefined period, the on load tap changer will operate to reduce the voltage by
changing the tap position.
Two types of modelling may be required. Firstly, a full dynamic analysis of situations where demand and DG
output changes over time and the corresponding response of the on load tap changer. Secondly the ability to
calculate the eventual steady state primary voltage from a more detailed Power Factory model, rather than
relying on historically recorded values.
It is envisaged that this work will create an additional level of complexity which is beyond that already
carried out. Before embarking on this stage of the modelling, UoS would like to engage with the wider ARC
team to identify the further direction of this work.
As an example of the likely effect of removing the modelling requirement that the 11kV primary busbar is
held at constant voltage, Figure 24 compares the DG capacity calculated for Feeder 25 in two cases: firstly
with the 11kV voltage held constant and secondly with the 33kV voltage held constant but the 11kV voltage
allowed to fluctuate. In the second case, the load associated with other feeders from St. Andrews Primary is
included through a separate load of the 11kV primary busbar.
When the 11kV voltage is allowed to vary, the DG capacity calculated at all buses that are voltage
constrained is reduced slightly. This is because the injection of power by the DG raises the 11kV voltage
compared with the historic situation, therefore the remaining voltage head-room at the point-of-connection
of the DG is reduced. The effect is greatest at locations closest to the primary where voltage is the binding
constraint. When DG capacity is limited by thermal effects there is no difference between the two results,
and at the far end of the feeder, the difference between the two results approaches zero. It is this effect,
and where it begins to interact with the OLTC that needs further investigation.
Page 28 of 57
Distributed generation on 11kV voltage constrained feeders
Figure 24: Comparing DG capacity calculated with the 11kV voltage head constant against holding the 33kV voltage constant for an
example time-step.
Page 29 of 57
Distributed generation on 11kV voltage constrained feeders
The work also presents tentative results from 3 months of data from the period April – June 2013. The
overall results and conclusions are listed below:
- FlexNet data: The FlexNet data provides a useful bank of historic data for 11kV feeders. However
there are a number of questions which require further information. Most importantly, the mismatch
Page 30 of 57
Distributed generation on 11kV voltage constrained feeders
between monitored and simulated LV voltages should be understood. Secondly, the exact reason for
the missing demand should be identified and particularly the reason for the significant quantity of
‘missing’ reactive power when secondary substation measurements are compared with those from
the primary should be understood.
- Power Factory model: further study of the 11kV/433V transformers is needed to ensure that this
section of the power factory model is correct. In addition, the model should be extended to include
at least some of the 33kV network. This would allow the point at which voltage is held constant in
the simulations to be varied and allow the 11kV to vary. Understanding the best way to do this, and
how to model the OLTC requires both Strathclyde Analysts and SPEN engineers.
- The effect of lowering the Primary voltage should be investigated.
It is expected that further work will aim towards defining and justifying new operating principles in terms of
the maximum DG capacity to connect at different locations on the 11kV feeder when non-firm contracts are
used. This may involve analysing the situation where DG is curtailed or controlled based on local
measurements of voltage but without an overarching coordinated control system. In this case, the expected
capacity may be increased beyond the ‘rule of 4’ to a higher capacity, but at each capacity and each
combination of multiple generators connected at different locations, a new rule should be devised and
justified.
In addition to this extra work, a further area to explore is the applicability of learning from another relevant
LCNF project: LV templates6. This project, carried out by Western Power Distribution, monitored the LV
feeders and attempts to classify secondary substations into ‘templates’ which can then predict important
aspects of its operation including daily demand profiles and daily voltage profiles. Initial analysis of the St.
Andrews Feeder 25 substations suggests a large variation in the shape of demand profiles at secondary
substation on a day-by-day basis. This highlights the need to test the applicability of conclusions from LV
Templates.
It is proposed that further work will attempt to apply the LV templates model to the FlexNet data, and later
ARC data to determine if the use of templates can be beneficial to understanding the DG capacity, and likely
curtailment of non-firm voltage constrained generation.
6
http://www.westernpowerinnovation.co.uk/LV-Templates.aspx
Page 31 of 57
Distributed generation on 11kV voltage constrained feeders
The original model includes the feeder itself, secondary subsations with three-phase loads taken directly off
the 11kV busbars, external grid acting as the swing bus connected to 11kV primary busbar, and some
distributed generation. After comparing the components of the original model against SPEN’s GIS based
database, some of the components were adjusted to the required project types. A list of component
modifications of the original model is given in Table 4 with changes highlighted.
The initial model also includes a number of distributed generation studies carried out by SPEN dated
between December 2013 and April 2014. These were not necessary for the purpose of this work and such
they have been removed from the model (red circles in Figure 25).
Page 32 of 57
Original Power Factory Model Corrected Power Factory Model
Substation Line Order PF component Name PF component Type Length (km) Substation Line Order PF component Name PF component Type Length (km)
Pirmary 1 CABLE Cable 11kV Al 185mm Coral.TypLne 0.145 Primary 1 CABLE Cable 11kV Cu 0.15in.TypLne 0.2
2 CABLE(6) Cable 11kV Al 0.30in.TypLne 0.044 2 CABLE(6) Cable 11kV Al 0.30in.TypLne 0.044
3 CABLE(7) Cable 11kV Al 0.15in.TypLne 0.194 3 cablePinchPoint Cable 11kV Al 185mm Coral.TypLne 0.194
Forrest St 4 CABLE(8) Cable 11kV Al 185mm Coral.TypLne 0.226 Forrest St. 4 CABLE(8) Cable 11kV Al 185mm Coral.TypLne 0.226
5 CABLE(9) Cable 11kV Al 0.30in.TypLne 0.07 5 CABLE(9) Cable 11kV Al 0.30in.TypLne 0.07
Hamilton Ave. 6 CABLE(10) Cable 11kV Al 185mm Coral.TypLne 0.007 Hamilton Av 6 CABLE(10) Cable 11kV Al 0.30in.TypLne 0.115
7 CABLE(11) Cable 11kV Al 0.30in.TypLne 1.247 7 CABLE(11) Cable 11kV Al 0.30in.TypLne 1.247
St. Nicolas St 8 CABLE(1) Cable 11kV Al 185mm Coral.TypLne 0.006 St. Nicolas St. 8 CABLE(1) Cable 11kV Cu 0.30in.TypLne 0.06
9 CABLE(2) Cable 11kV Cu 0.25in.TypLne 0.355 9 CABLE(2) Cable 11kV Cu 0.25in.TypLne 0.225
10 CABLE(3) Cable 11kV Cu 0.25in.TypLne 0.68 10 CABLE(3) Cable 11kV Cu 0.25in.TypLne 0.14
Abby Walk 11 CABLE(4) Cable 11kV Al 185mm Coral.TypLne 0.213 Abbey Walk 11 CABLE(4) Cable 11kV Al 185mm Coral.TypLne 0.213
Harbour Pumping St 12 CABLE(5) Cable 11kV Al 185mm Coral.TypLne 0.408 Harbour Pumping St. 12 Line Cable 11kV Al 185mm Coral.TypLne 0.14
13 Line(2) Cable 11kV Al 185mm Coral.TypLne 0.29
Gatty Marine 13 CABLE(12) Cable 11kV Al 185mm Coral.TypLne 0.532 Gatty Marine 14 CABLE(12) Cable 11kV Al 185mm Coral.TypLne 0.52
St Andrews Swimming Pool 14 CABLE(13) Cable 11kV Al 185mm Coral.TypLne 0.097 St. Andrews Swimming Pool 15 CABLE(13) Cable 11kV Al 185mm Coral.TypLne 0.097
St Nicolas WWTW 15 CABLE(14) Cable 11kV Al 185mm Coral.TypLne 0.095 St Nicolas WWTW 16 CABLE(14) Cable 11kV Al 185mm Coral.TypLne 0.04
16 CABLE(15) Cable 11kV Al 0.25in.TypLne 0.53 17 CABLE(15) Cable 11kV Al 0.25in.TypLne 0.5
Page 33 of 57
Priestden Rd 17 CABLE(16) Cable 11kV Al 185mm Coral.TypLne 0.014 Priestden Rd. 18 CABLE(16) Cable 11kV Al 95mm Coral.TypLne 0.1
18 CABLE(17) Cable 11kV Al 0.25in.TypLne 0.724 19 CABLE(17) Cable 11kV Al 95mm Coral.TypLne 0.724
East Grange Term Pole 19 O/H/L OHL 11kV SCA 150mm.TypLne 1.337 East Grange Term Pole 20 O/H/L OHL 11kV SCA 150mm.TypLne 1.337
20 CABLE(19) Cable 11kV Al 185mm Coral.TypLne 0.793 21 CABLE(19) Cable 11kV Al 185mm Coral.TypLne 0.77
St Andrews WWTW 21 CABLE(18) Cable 11kV Al 185mm XLPE 3c.TypLne 0.091 St. Andrews WWTW 22 CABLE(18) Cable 11kV Al 185mm XLPE 3c.TypLne 0.091
No7 Sheds 22 CABLE(20) Cable 11kV Al 185mm XLPE 3c.TypLne 0.79 No7. Sheds 23 CABLE(20) Cable 11kV Al 185mm XLPE 3c.TypLne 0.33
23 CABLE(22) Cable 11kV Al 185mm XLPE 3c.TypLne 0.381 24 CABLE(22) Cable 11kV Al 185mm XLPE 3c.TypLne 0.381
24 CABLE(21) Cable 11kV Al 185mm Coral.TypLne 0.644 25 CABLE(21) Cable 11kV Al 185mm Coral.TypLne 0.644
25 O/H/L(1) OHL 11kV SCA 150mm.TypLne 0.797 26 O/H/L(1) OHL 11kV SCA 150mm.TypLne 0.797
26 O/H/L(9) OHL 11kV SCA 150mm.TypLne 0.587 27 O/H/L(9) OHL 11kV SCA 150mm.TypLne 0.587
27 CABLE(23) Cable 11kV Al 185mm XLPE 3c.TypLne 0.014 28 CABLE(23) Cable 11kV Al 185mm XLPE 3c.TypLne 0.014
28 CABLE(24) Cable 11kV Al 185mm Coral.TypLne 1.049 29 CABLE(24) Cable 11kV Al 185mm Coral.TypLne 1.049
ST Andrews Bay Hotell 29 CABLE(25) Cable 11kV Al 185mm Coral.TypLne 1.065 St Andrews Bay Hotel 30 CABLE(25) Cable 11kV Al 185mm Coral.TypLne 1.065
30 O/H/L(2) OHL 11kV SCA 150mm.TypLne 1.665 31 O/H/L(2) OHL 11kV SCA 150mm.TypLne 1.665
31 O/H/L(6) OHL 11kV SCA 150mm.TypLne 2.394 32 O/H/L(6) OHL 11kV SCA 150mm.TypLne 1.6
32 O/H/L(11) OHL 11kV SCA 150mm.TypLne 1.446 33 O/H/L(11) OHL 11kV SCA 150mm.TypLne 1.15
33 O/H/L(3) OHL 11kV SCA 150mm.TypLne 1.446 34 O/H/L(3) OHL 11kV SCA 150mm.TypLne 0.96
Kingsbarn Kingsbarns
Table 4: Modifications to original Power Factory model to correct errors identified from GIS data. Changes are highlighted in Red.
Distributed generation on 11kV voltage constrained feeders
Distributed generation on 11kV voltage constrained feeders
Each secondary substation is extended to include an 11kV/433V transfomer, LV busbar and LV load (the
11kV load is moved to the LV busbar). The size and impedence of the transformer at each secondary
substation is set in line with information provided by SPEN (04/06/2014). An example of an extended
secondary substation model is shown in Figure 26.
Since the FlexNet Data used as an input data for the purpose of this work included demand data for 3
substations that are not provided in the original PF model, additional loads have been added. These are: The
Shore, Allanhill, Kinkell Caravan Park, Borwnhills and Seagate. The Shore has been added as a second load at
the Harbour Pumping Station Substation. Allanhill, Kinkell and Brownhills have been added to an extra
secondary substation connected to the East Grange Terminal Pole. Seagate has been added as an extra load
at Kingsbarns School substation. On the other hand, two secondary substations: No7 Sheds and No7
Clubhouse, have been removed from the original PF model since they did not correspond to the readings
from Flexible Networks. Additionaly, for the purpose of modelling and writing scripts, all substation were
renamed in the Power Factory model and Table 5 summarrizes all substation name changes with their loads.
Page 34 of 57
Distributed generation on 11kV voltage constrained feeders
Number Original substation name Power Factory substation name Substation load name
Primary St. Andrews 186-25
1. Forrest Street 001 Forrest Street S/S 001 Forrest St Load
2. Hamilton Avenue 002 Hamilton Avenue St A S/S 002 Hamilton Ave Load
3. St. Nicholas Street 003 St. Nicholas Street S/S 003 St. Nicholas Street Load
4. Abby Walk 004 Abby Walk S/S 004 Abbey Walk Load
5. Harbour Pumping Station 005 Harbour Pumping Stn S/S 005 Harbour Pumping station Load
006 The Shore Load
6. Gatty Marine 007 Gatty Marine S/S 007 Gatty Marine Load
7. St. Andrews Swimming Pool 008 St. Andrews Swimming Pool S/S 008 St. Andrews Swimming Pool Load
8. St. Nicholas WWTW 009 St. Nicholas WWTW S/S 009 St. Nicholas WWTW Load
9. Priestden Road 010 Priestden Road S/S 010 Priestden Road Load
10. East Grange Term Pole 011 East Grange Term Pole S/S 011 Allanhill
012 Kinkell
013 Brownhills
11. St. Andrews WWTW 014 St. Andrews WWTW S/S 014 St. Andrews WWTW Load
No7 Sheds
Links No 7 Clubhouse
12. St. Andrews Bay Hotel 015 St. Andrews Bay Hotel S/S 015 St. Andrews Bay Hotel Load
13. Kingbarns School 016 Kingbarns School S/S 016 Kingbarns School Load
017 SeaGate Load
Finally, as this model was used to study various DG scenarios, a ‘shadow DG generator’ is added to each
secondary substation on the 11kV side with generation (P and Q) set to zero. These shadow DG generators
were named in the model as 001 DG, 002 DG up to 016 DG with the reference number the same as the
reference number of the secondary substation to which it connects. The final feeder model used in the study
is shown in Figure 27 with red squares showing added ‘shadow DG generators’.
008 ST ANDREWS SWIMMING POOL S/S
DIgSILENT
MIN CCT LOAD=36.6A(698KVA)
011 EAST GRANGE TERM POLE S/S
002 HAMILTON AVENUE ST A S/S
CABLE(18)
Line Line(2)
cablePinchPoint CABLE(19)
External Grid
CABLE CABLE(6) CABLE(8) CABLE(9) CABLE(10) CABLE(11) CABLE(1) CABLE(2) CABLE(3) CABLE(4) CABLE(12) CABLE(13) CABLE(14) CABLE(15) CABLE(16) CABLE(17) O/H/L
008 St Andrews Swimming Pool ..
005 Harbour Pumping Station..
2-Winding..
2-Winding..
2-Winding..
2-Winding..
2-Winding..
2-Winding..
2-Winding..
2-Winding..
009 St Nicholas WWTW L..
2-Winding..
2-Winding..
014 St Amdrews WWTW LV
002 Hamilton Avenue..
004 Abbey Walk Load 005 Harbour Pum.. 006 The Shore Load 007 Gatty Marina Load 010 Priestden Road Load 011 Alla.. 012 Ki.. 013 Brownhills
003 St Nicolas Street Load 008 St Andrews Swimming Pool Load 009 St Nicolas WWTW load
001 Forrest St Load 002 Hamilton Ave Load 014 St Andrews WWTW load
001 DG
002 DG
003 DG
004 DG
005 DG
007 DG
008 DG
009 DG
010 DG
011 DG
014 DG
TEE-OFF TO BOGHALL KINGSBARNS SPUR
NO7 SHEDS
O/H/L(8) O/H/L(3) O/H/L(11) O/H/L(6) O/H/L(2) CABLE(25) CABLE(24) CABLE(23) O/H/L(9) O/H/L(1) CABLE(21) CABLE(22) CABLE(20)
2-Winding..
2-Winding..
017 SeaGate Load 016 Kingsbarns School Load 015 St Andrews Bay Hotel Load
Project:
016 DG
Date: 9/1/2014
PowerFactory 14.1.6 Annex:
Page 35 of 57
Distributed generation on 11kV voltage constrained feeders
DIgSILENT
MIN CCT LOAD=36.6A(698KVA)
CABLE(18)
Line Line(2)
cablePinchPoint CABLE(19)
External Grid
CABLE CABLE(6) CABLE(8) CABLE(9) CABLE(10) CABLE(11) CABLE(1) CABLE(2) CABLE(3) CABLE(4) CABLE(12) CABLE(13) CABLE(14) CABLE(15) CABLE(16) CABLE(17) O/H/L
2-Winding..
2-Winding..
2-Winding..
2-Winding..
2-Winding..
2-Winding..
2-Winding..
2-Winding..
009 St Nicholas WWTW L..
2-Winding..
2-Winding..
014 St Amdrews WWTW LV
002 Hamilton Avenue..
004 Abbey Walk Load 005 Harbour Pum.. 006 The Shore Load 007 Gatty Marina Load 010 Priestden Road Load 011 Alla.. 012 Ki.. 013 Brownhills
003 St Nicolas Street Load 008 St Andrews Swimming Pool Load 009 St Nicolas WWTW load
001 Forrest St Load 002 Hamilton Ave Load 014 St Andrews WWTW load
001 DG
002 DG
003 DG
004 DG
005 DG
007 DG
008 DG
009 DG
010 DG
011 DG
014 DG
TEE-OFF TO BOGHALL KINGSBARNS SPUR
NO7 SHEDS
O/H/L(8) O/H/L(3) O/H/L(11) O/H/L(6) O/H/L(2) CABLE(25) CABLE(24) CABLE(23) O/H/L(9) O/H/L(1) CABLE(21) CABLE(22) CABLE(20)
2-Winding..
2-Winding..
017 SeaGate Load 016 Kingsbarns School Load 015 St Andrews Bay Hotel Load
Project:
016 DG
Date: 9/1/2014
PowerFactory 14.1.6 Annex:
Page 36 of 57
Distributed generation on 11kV voltage constrained feeders
A1.3 Model with the additional HV section and the extra load to represent other feeders
This model is an extension of the basic model described above. The basic model was extended at the start of
the feeder (red circle in Figure 29) in order to include the 33kV busbar at St. Andrews Primary.
DIgSILENT
MIN CCT LOAD=36.6A(698KVA)
CABLE(18)
External Grid
Line Line(2)
cablePinchPoint CABLE(19)
2-Winding..
CABLE CABLE(6) CABLE(8) CABLE(9) CABLE(10) CABLE(11) CABLE(1) CABLE(2) CABLE(3) CABLE(4) CABLE(12) CABLE(13) CABLE(14) CABLE(15) CABLE(16) CABLE(17) O/H/L
2-Winding..
2-Winding..
2-Winding..
2-Winding..
2-Winding..
2-Winding..
2-Winding..
2-Winding..
009 St Nicholas WWTW L..
2-Winding..
2-Winding..
014 St Amdrews WWTW LV
002 Hamilton Avenue..
002 DG
003 DG
004 DG
005 DG
007 DG
008 DG
009 DG
010 DG
011 DG
014 DG
TEE-OFF TO BOGHALL KINGSBARNS SPUR
NO7 SHEDS
O/H/L(3) O/H/L(11) O/H/L(6) O/H/L(2) CABLE(25) CABLE(24) CABLE(23) O/H/L(9) O/H/L(1) CABLE(21) CABLE(22) CABLE(20)
2-Winding..
015 DG
017 SeaGate Load 016 Kingsbarns School Load 015 St Andrews Bay Hotel Load
Project:
016 DG
The adjusted section of the model is shown in Figure 30. The 33kV bus becomes the point of fixed voltage
with the ‘External Grid’ feeding to this busbar. Two generic 2-winding 33kV/11kV transformers linking the
33kV and 11kV bars at the Primary are added at the start of the Feeder 25. Also, an extra load (named 020
Other Feeders) is used to represent demand on other feeders fed from St. Andrews Primary. This extra load
is set to the total historically recorded demand on all other feeders from the primary.
Page 37 of 57
Distributed generation on 11kV voltage constrained feeders
Page 38 of 57
Distributed generation on 11kV voltage constrained feeders
Page 39 of 57
Distributed generation on 11kV voltage constrained feeders
The script uses a binary search algorithm to find the maximum DG that maintains the local voltage limit of
11.25kV at the point-of-connection, and the thermal limit of all cables in the model. The load flow is
calculated by executing the script LoadFlow (see A2.1.3) and the thermal loading of all cables by executing
the script checkCableLoading (see A2.1.4). Assumed maximum DG capacity is in the range (0 – 10MW at each
location). The starting point of the binary search is 5MW. From the existing guess, the DG capacity is either
decreased or increased depending on whether constraints are breached or not. The initial step size for the
increase/decrease is 2.5MW, i.e. half the initial capacity. Step size is reduced by 2 in each subsequent
iteration. The convergence condition is that the difference between the upper and lower bounds on capacity
(that is the lowest DG capacity that breaches the constraints and the highest DG capacity that does not
breach the constraints) is less than 0.01MW.
Input parameters are: the load flow related to the active study case; set of all secondary substations in the
model; set of all wind generators in the model; and an index of the output file in which the results will be
written. The search returns the final lower bound, which is therefore guaranteed not to breach limits and to
be within 0.01 of the actual limit.
Page 40 of 57
Distributed generation on 11kV voltage constrained feeders
Page 41 of 57
Distributed generation on 11kV voltage constrained feeders
Input parameters are: the load flow related to the active study case; and type of the load flow – 0 for
balanced and 1 for unbalanced load flow.
Page 42 of 57
Distributed generation on 11kV voltage constrained feeders
The input parameter is the set of all cables in the model, and the output parameter is the maximum loading
of all cables as a percentage of rated capacity.
Page 43 of 57
Distributed generation on 11kV voltage constrained feeders
It opens a ‘csv’ input file with historical measurements of primary voltage and historical demand readings of
three phase loads of each secondary substation for Feeder 25. It then sets the primary voltage and load
values, the active and reactive power, to represent conditions at a particular time-step. The number of time-
steps is equal to the number of days multiplied by 48, since we are using half hourly time-steps. The script
dispatches the chosen firm generator at full capacity (0.5MW) and then calls DG_capacityWithMultipleGen
script (see A2.2.2) to estimate the remaining capacity at each secondary substation for non-firm DG. The
possible locations of added firm generator are the following three secondary substations: 001 – Forrest
Street S/S; 008 – St. Andrews Swimming Pool S/S; and 016 – Kingsbarns School S/S. Finally, the script prints a
number of completed time-step and closes input and output files.
The flowchart of the script is shown in Figure 35 with blue boxes presenting modifications of the script in
Figure 31.
Page 44 of 57
Distributed generation on 11kV voltage constrained feeders
Page 45 of 57
Distributed generation on 11kV voltage constrained feeders
The script calculates the maximum power injections available for a single DG at each secondary substation
for the current demand conditions and with one firm generator enabled and generating at full capacity. It
maintains thermal limits across the feeder and checks voltage limits of both firm generator and non-firm DG
connection points. The script loops around each bus in order to find the maximum DG capacity that can
connect at each secondary substation. Calculated capacity at each bus assumes one firm generator
connected at the chosen bus in the system and no non-firm DG connected at any other bus.
The script uses a binary search algorithm to find the maximum DG that maintains the local voltage limit of
11.25kV at the point of both firm generator and non-firm DG connection, and the maximum thermal limit of
all cables in the model. The load flow is calculated by executing the script LoadFlow shown in Figure 33 and
the thermal loading of all cables by executing the script checkCableLoading shown in Figure 34. Assumed
maximum DG capacity is in the range (0 – 10MW at each location). The binary search starting point for DG
capacity is 5MW. From the existing guess, the DG capacity is either decreased or increased depending on
whether constraints are breached or not. The initial step size for the increases/decrease is 2.5MW, i.e. half
the initial capacity. Step size is reduced by 2 in each subsequent iteration. The convergence condition is that
the difference between the upper and lower bounds on capacity (that is the lowest DG capacity that
breaches the constraints and the highest DG capacity that does not breach the constraints) is less than
0.01MW.
Input parameters are: the load flow related to the active study case; the set of all secondary substations in
the model; the set of all wind generators in the model; the bus with firm generation connected; and an index
of the output file in which the results will be written. The search returns the final lower bound, which is
therefore guaranteed not to breach limits and to be within 0.01 of the actual limit.
The flowchart of the script is shown in Figure 36 with blue boxes presenting modifications of the script in
Figure 32.
Page 46 of 57
Distributed generation on 11kV voltage constrained feeders
Page 47 of 57
Distributed generation on 11kV voltage constrained feeders
The script is the main script in this case study. The script opens two ‘csv’ input files. The first contains
historical measurements of the primary voltage and historical demand readings at each secondary
substation for three phase loads for Feeder 25 and the second contains the maximum DG capacity as
calculated without demand response by the script threePhaseTimeStep. The script then sets the primary
voltage and load values, the active and reactive power, to represent conditions at a particular time-step. The
number of time-steps is equal to the number of days multiplied by 48, since we are using half hourly time-
steps. Within the time-step loop, the script opens the second ‘csv’ file calls LoadFlow (shown in Figure 33),
checkCableLoading (shown in Figure 34) and newDGgen scripts (see A2.3.2) to calculate the effect of
demand increase to the maximum power injections at a particular bus. Finally, the script prints a number of
completed time-step and closes input and output files.
The flowchart of the script is shown in Figure 37 with blue boxes presenting modifications of the script in
Figure 31.
Page 48 of 57
Distributed generation on 11kV voltage constrained feeders
Page 49 of 57
Distributed generation on 11kV voltage constrained feeders
Input parameters are: the set of all LV loads in the model; the maximum DG capacity as calculated without
demand response; an object representation of wind generator; an object representation of secondary
substation; the set of all cables in the model; an index of the output file in which the results will be written;
and the load flow related to the active study case. The script returns the new maximum DG capacity and
increase over the original demand level.
Page 50 of 57
Distributed generation on 11kV voltage constrained feeders
Page 51 of 57
Distributed generation on 11kV voltage constrained feeders
Before running it,the ‘External Grid’ should be edited in the Power Factory model by navigating to the Load
Flow tab and ensuring that the ‘setpoint’ is set to ‘bus target voltage’. Also, it should be ensured that the
reference busbar is set to ‘St. Andrews 186-25.
The script is the main script in this case study. The script opens a ‘csv’ input file with historical
measurements of primary voltage and historical demand readings of three phase loads for each secondary
substation on Feeder 25 with extra loads added to represent other feeders. It then sets the primary voltage
and load values, the active and reactive power, to represent conditions at a particular time-step. The
number of time-steps is equal to the number of days multiplied by 48, since we are using half hourly time-
steps. At the end of each time-step, the script calculates the load flow by executing the script LoadFlow
shown in Figure 33 and records the voltage level at the end of a 33kV extension.
The calculated 33kV voltages are stored in a ‘csv’ output file, and can be used as inputs to further studies
which adjust the historically recorded conditions, for example by adding DG to the feeder.
The flowchart of the script is shown in Figure 39 with blue boxes presenting modifications of the script in
Figure 31.
Page 52 of 57
Distributed generation on 11kV voltage constrained feeders
Page 53 of 57
Distributed generation on 11kV voltage constrained feeders
Summary
The work will make use of the data collected as part of Strathclyde’s previous work: WP5.2, milestone
‘Collation of data from ARC case studies to produce data sets for evaluation’. Data collected and to be used
in this modelling is as follows:
1. Detailed monitoring data for 11kV feeder from St. Andrews area collected as part of the Flexible
Networks project.
2. Historic measurements of output for Dunbar connected wind farms.
The work will fulfil Strathclyde’s milestone under WP5.2 ‘Production of evaluation models of ARC case
studies and smart solutions’ to be delivered by 31st July 2014.
Strathclyde will liaise with SPEN and Smarter Grid Solutions (SGS) throughout to exchange models and
results with when appropriate.
Outcomes
Strathclyde will produce the following:
- A short technical report detailing the set-up and outcomes of each of the modelling tasks.
- Full modelling results provided in a suitable format (excel spreadsheet or csv files).
- A half-day workshop to present and discuss the results with the wider ARC team.
The time-scale for this work is 3.5 months with completion on 31st July 2014.
Modelling tasks
Task 1: Set up model of single 11kV feeder based on St. Andrews data
Activities 1. Load and verify Power Factory model of feeder as supplied by SPEN.
2. Adjust model tap-settings for secondary transformers based on
information provided by SPEN.
3. Ensure historical measurements of power flows and voltage etc. can be
reproduced using the models.
Additional - Tap-settings for secondary substations.
Information - Measurements of voltage at primary substations.
required
Outcomes: i. Operational model of feeder verified against monitoring data.
ii. Internal documentation capturing Strathclyde’s understanding of the
feeder.
Page 54 of 57
Distributed generation on 11kV voltage constrained feeders
Page 55 of 57
Distributed generation on 11kV voltage constrained feeders
Future Work
It is expected that the outcomes of the modelling tasks detailed here will form the basis for the further
development of ANM based management of 11kV voltage constraints
- Interaction between 11kV voltage constraints and wider (33kV and GSP based) thermal constraints.
- The need to develop smart tap-changing at primary substations as part of 11kV voltage management.
- The need to investigate under voltage effects on the Low Voltage network if changes are implemented
to design standards for voltage levels at primary substations.
- Application of learning to case-studies in the ARC area.
Page 56 of 57